CN108330807A CN201810107841.0A CN201810107841A CN108330807A CN 108330807 A CN108330807 A CN 108330807A CN 201810107841 A CN201810107841 A CN 201810107841A CN 108330807 A CN108330807 A CN 108330807A
Authority
CN
China
Prior art keywords
box beam
template
arc
mould
forming method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810107841.0A
Other languages
Chinese (zh)
Other versions
CN108330807B (en
Inventor
郑昕
郭飞
胡继生
黄毅
李熙浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou City No2 Municipal Engineering Co Ltd
Original Assignee
Guangzhou City No2 Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou City No2 Municipal Engineering Co Ltd filed Critical Guangzhou City No2 Municipal Engineering Co Ltd
Priority to CN201810107841.0A priority Critical patent/CN108330807B/en
Publication of CN108330807A publication Critical patent/CN108330807A/en
Application granted granted Critical
Publication of CN108330807B publication Critical patent/CN108330807B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses arc box beam template forming methods, include the following steps:1) surveying and locating:Determine coordinate, live setting-out on the spot, 2) mould material is than choosing:Mould material including glass steel formwork, set shaped steel formwork, film plate+stainless steel double shuttering, bridge aerated core, aluminum alloy mould plate, double-wall corrugated pipe, plastic formwork is than choosing, 3) mould material is selected:Selected including box beam external mold and box girder inner formwork mould material, in conjunction with the characteristics of arc box beam, box beam external mold uses film plate+stainless steel double shuttering, box girder inner formwork use double-wall corrugated pipe, 4) bed die be laid with, 5) side form installation, 6) internal model is installed, and 7) reinforcing of side mould.Speed of application of the present invention is fast, significantly improves arc box beam overall appearance quality and geometric accuracy, while having ensured construction safety, has saved construction cost.

Description

Arc box beam template forming method
Technical field
The present invention relates to a kind of arc box beam template more particularly to arc box beam template forming methods.
Background technology
With advances in technology, traditional concrete box girder construction has been applied to Longspan Bridge engineering, subway station vehicle It stands engineering, single layer and multi storied industrial factory building column, high level and high-rise building engineering etc..Its construction method be also it is with rapid changepl. never-ending changes and improvements, such as Integral Steel template construction, rigid backbone assembled plank sheathing, rubber internal model etc., but occur some in actual application Problem:
1, steel form cost itself is higher, for special-shaped box beam, can not reuse, and when design drawing part exists When conflicting with each other, scene adjustment is difficult.
2, pouring in concrete box girder belongs to concealed work, the pouring quality of concrete can not macroscopic examination, work as use When manually pouring and vibrate, it can only ensure construction quality in sense of responsibility and strict construction and management by operating personnel, Simultaneously check it is cumbersome, it is time-consuming.
When 3, there is the special-shaped box beam of variation for box beam height and width, while there was only 1m at box beam height minimum, When local clear height only has 60cm, manually removes internal model and conveniently cannot achieve.
4, rigid backbone assembled plank sheathing and combined steel internal model widely used in construction at present, when mounted, one As need 10h or so, it is time-consuming.
5, rigid backbone assembled plank sheathing and combined steel internal model be during form removal, need personnel enter in box beam into Row is removed, and is expended time 5h or so, and need internally to dry in the process, is prevented personnel's anoxia asphyxia in box beam.Therefore Its form removal expends the time and cost increases.
6, the geometry of common rubber internal model is molded by rubber mandrel, and shape is not easy to control, the geometric form with design Shape difference is larger.
7, rubber internal model needs special messenger to keep an eye in concreting process, pays attention to that air pressure is replenished in time, prevents rubber bag tank Interior air pressure declines, and influences box beam concrete roof thickness, labor intensive.
8, rubber internal model striking time is not easy to control, to avoid concrete roof from caving in, it is easy to when artificial postponement form removal Between, occur internal model with concrete binding together the phenomenon that, the general number that recycles is less, and external capsule is easy to wear, if Abrasion, just will produce bulging to influence concrete formation.
Invention content
In view of the deficiencies of the prior art, the present invention intends to provide a kind of safe and reliable, practical, construction The arc box beam template forming method that speed is fast, Mass accuracy is high.
To achieve the above object, the present invention can be achieved by the following technical programs:
Arc box beam template forming method, includes the following steps:
1) surveying and locating:Before box girder construction, determine that arc box beam key controls pile No. in advance, then flat by arc box beam Face figure axis circular curve determines coordinate of mid-peg, and bottom plate, the seat of the stake of the top plate left side and the right stake are calculated according further to sectional view Mark, finally carries out setting-out on the spot at the scene, and respectively increase by one is carried out across the span of longitudinal horizontal rod with lime on both sides on the outside of top plate Label;
2) mould material is than choosing:Mould material includes glass steel formwork, set shaped steel formwork, film plate+stainless steel double molding Plate, bridge aerated core, aluminum alloy mould plate, double-wall corrugated pipe, plastic formwork;
3) mould material is selected:It is selected including box beam external mold and box girder inner formwork mould material, in conjunction with the characteristics of arc box beam, Box beam external mold uses film plate+stainless steel double shuttering, box girder inner formwork to use double-wall corrugated pipe;
4) bed die is laid with:Bed die plate material homonymy mould is all made of film plate, along box beam bottom plate boundary one batten of tailor's tack, Line style is consistent with box beam bottom plate both sides, carries out plane setting-out to bed die, measures bottom plate vertically and horizontally absolute altitude, according to measurement result the bottom of by Template is adjusted to designed elevation, detects absolute altitude again;
5) side form is installed:On already installed bed die, side template installation is carried out;A lumps of wood is followed closely at template back, often The lumps of wood for reinforcing support is arranged in constant spacing, withstands the lumps of wood at side template back on one side, is close to Template nail in joint It connects, other end is then followed closely on the lumps of wood being connect with shore frame;
6) internal model is installed:It is circular hollow structure inside box beam, it, highly can be with angle in order to reach arc effect Box beam is integrally adjusted, using the extendable double-wall corrugated pipe in part;
7) side mould is reinforced:Screw arbor with nut at both-ends is being worn apart from the position of the high 25-30cm in box beam bottom, apart from top 25-30cm It sets and wears Screw arbor with nut at both-ends.
Further, film plate+stainless steel double shuttering in step 2) is a kind of self-control gang form.
Further, film plate+stainless steel double shuttering in step 3), can be used in turn using composite shuttering.
Further, the double-wall corrugated pipe surface in step 3) is to be more conducive to install with ripple to manage, and is had simultaneously Certain ductility can be bent according to arc.
Further, hemline of the end template beyond both sides side form is more than 20cm in step 4), while at the bottom completed Anti-skidding batten is followed closely on mould, batten size length × width x thickness is the plank of 50cm × 20cm × 2cm, and spacing 25-35cm is used for the later stage Side mould installation.
Further, step 5) side template uses 18mm thickness film plates, side template back to follow closely a 2m long, 10cm × 10cm's The lumps of wood for reinforcing support is arranged per 60cm by the lumps of wood, spacing 15cm mono-.
Further, step 5) box beam top circular arc needs first to follow closely plank on top, highly exceeds design structure height 10-15cm, then the radius that design drawing needs is followed closely out with 2mm Stainless Molding Boards in circular arc.
Further, step 6) is to ensure the mounting height of bellows, and the not deviation in later stage casting concrete is moved It is dynamic, it is fixed using reinforcing bar, fixed steel bars need to effectively be welded with bottom main reinforcement.
Further, the reinforcing bar and homonymy spiral shell for larger section of radian using φ 14 after Screw arbor with nut at both-ends have been worn in step 7) both sides Bar be connected it is integral reinforced, radian is connect using steel pipe with screw rod compared with segment, box beam is reinforced, at the same in order to Reinforce template overall stability, increases per 3m and support together.
Advantageous effect of the present invention:The present invention is designed and implements for arc box beam template system.In template selection side Face:Domestic common template material is compared, from template density;Template is equipped with situation;Turnover rate;Processing, installation quality and difficulty Easy degree;Mechanical property, installation personnel requirement;Concrete formation quality;It is compared and analyzed in terms of cost, determines film plate + stainless steel double shuttering is best suited for arc box beam external mold, and double-wall corrugated pipe is most suitable for box girder inner formwork.In reinforcement system design side Face establishes arc box beam BIM models using rhinoceros (Rhino) software, scene is instructed to carry out template piecemeal, makes, positioning and peace Dress.Outboard template is reinforced using purlin system, is attached for Screw arbor with nut at both-ends between template, and piece is close, and it is firm to reinforce, after guarantee The safety of phase concreting;Internal model is fixed using reinforcing bar, and skeleton is formed with box beam bottom layer of the reinforcing steel, avoids internal model floating and position Offset.This series of measures significantly improves arc box beam overall appearance quality and geometric accuracy, while having ensured construction peace Entirely, construction cost has been saved.
Description of the drawings
Fig. 1 is arc box beam template forming method schematic diagram of the present invention;
Fig. 2 be the present invention become deck-molding, etc. deck-sidings, Variable-curvature-box Girder BIM models;
Fig. 3 is formwork reinforcement design drawing of the present invention;
Fig. 4 is arc box beam reinforcing bar diagrammatic cross-section of the present invention.
Wherein:1- reinforces the lumps of wood, and 2- reinforces steel pipe/reinforcing bar, and 3- line type control battens, 4- cheek boards, 5- is to wearing screw rod, 6- Slope variation, 7- design axis, 8- reinforcing bars, 9- reinforcing bars.
Specific implementation mode
Below in conjunction with attached drawing and specific implementation mode, the present invention is described further:
Such as Fig. 1, arc box beam template forming method of the present invention includes the following steps:
1, surveying and locating:Before box girder construction, determine that arc box beam key controls pile No. in advance, then flat by arc box beam Face figure axis circular curve determines coordinate of mid-peg, and bottom plate, the seat of the stake of the top plate left side and the right stake are calculated according further to sectional view Mark.Finally carry out setting-out on the spot at the scene, on the outside of top plate both sides respectively increase by one across longitudinal horizontal rod span, through calculating, Arc box beam longitudinal horizontal rod one is 600mm across span.It is further added by the walkways setting-out 800mm wide.Markings are sprinkled with lime, The center line that box beam is made further according to projection line, is equally marked with lime.
2, mould material is than choosing:Selection for arc box beam mould material, box beam in the bridge of Primary Reference domestic city Main mould material when construction.Including glass steel formwork, set shaped steel formwork, film plate+stainless steel double shuttering, bridge inflation Core model, aluminum alloy mould plate, double-wall corrugated pipe, plastic formwork etc..The characteristics of for arc box beam, respectively from template density;Template It is equipped with situation;Turnover rate;Processing, installation quality and complexity;Mechanical property, installation personnel requirement;Concrete formation quality; It is compared and analyzed successively in terms of Cost comparisons.
(1) glass steel formwork:Density 3.55-4.0kg/ ㎡;Turnover rate:Different level, different cross section need to be equipped with, Opposite turnover rate is high;Complexity is installed:Because processing technology limitation quality is relatively low, processing is easier to, and installs required personnel It is more;Mechanical property:Tensile strength >=200Mpa;Hardness Barcol >=48;To operating personnel:It is high;Concrete formation quality:Local column Cross sectional shape is yielding, and faulting of slab ends, husky line easily occurs in edge joint position;Cost comparisons:Mei ㎡ costs are higher, composite cost It is relatively high.
(2) set shaped steel formwork:Density 7.85g/cm3;Turnover rate:For special-shape arc box beam, prefabricated steel-template need to be distinguished, Only equal height and positions are generally applicable, and turnover rate is low;Complexity is installed:Processing quality is higher, and difficulty is big, and personnel are few needed for installation, Need mechanical-assisted;Mechanical property:Tensile strength >=235MPa;To operating personnel:It is higher;Concrete formation quality:Template itself Be afraid of acid, fearnesss afraid of water humidity, perishable rust, it is smooth to pour rear concrete surface, but uneven color easily occurs;Cost comparisons:Template is pacified It is few to fill process, but mechanical-assisted , Mei ㎡ costs need to be used high.
(3) bridge aerated core:Density:Rubber thickness 0.1m, air bag are 1.2-1.6kN/ ㎡;Turnover rate:It is only capable of conduct Internal model, same inner diameter is generally applicable, and core model turnover rate is higher;Complexity is installed:Materials processing limitation is few, and installation procedure is more, institute Need personnel more, curved section cracky;Mechanical property:Bilateral vulcanization adhesive plaster breaking strength (N/25mm):Radial > 1000, broadwise More than 800;Glue and cloth adhesion strength (N/25mm):More than 15;To operating personnel:It is high;Concrete formation quality:Striking time is not It is easy to control, too early easy collapse hole, form removal difficulty rapid wear core model too late.It requires height, core model easily to float worker when vibrating, leads to coagulation There is deviation in native size;Cost comparisons:Core model installation procedure is more, requires high , Mei ㎡ costs higher worker.
(4) aluminum alloy mould plate:Density:2.8g/cm3;Turnover rate:Flatness, verticality are good, high as external mold turnover rate; Complexity is installed:Materials processing limitation is more, and quality is high, and height is required to worker, and template is from heavy and light;Mechanical property:Tensile strength 95-125Mpa;It forms integral mold plate system bearing capacity and reaches 50kN/ ㎡;To operating personnel:It is high;Concrete formation quality:Tear coagulation open Native forming quality preferably controls, and is applicable in external mold, internal model installation is fixed and removes not easy to operate;Cost comparisons:Material cost is higher, , can not be general due to being abnormal formwork, overall cost is high.
(5) double-wall corrugated pipe:Density:DN600-12.5kg/m;Turnover rate:It being only capable of as internal model, same inner diameter is generally applicable, Core model turnover rate is higher;Complexity is installed:Outer wall wave structure in a ring, greatly strengthens the ring stiffness of tubing, to Enhance its resistance to concrete load;Mechanical property:Tensile break strength 37-39MPa;Tensile yield strength MPa25.8- 26.8;Ring stiffness ring stiffness >=8kN/m2;To operating personnel:It is higher;Concrete formation quality:Template band groove itself, it is fixed Convenient, lighter weight, built-in template itself increases the less concrete size of additional load and quality easily ensures;Cost comparisons:Material Material cost itself is relatively low, while simple installation, and quality easily ensures that overall cost is low.
(6) plastic formwork:Density:1.55-1.80g/cm3;Turnover rate:Only turnover rate plane mould >=30, column beam form >=40; Complexity is installed:Technological adaptability is strong, can saw, digs, bores, follow closely, and can arbitrarily form any geometry;Mechanical property:Table Surface hardness (shore) >=58;Bending strength >=45;To operating personnel:It is high;Concrete formation quality:If as internal model, surface mistake In smooth, it is not fixed easily, concrete size is not easy to ensure;Cost comparisons:Material cost is high, and internal model installation is fixed difficult, comprehensive It is of high cost.
(7) film plate+stainless steel double shuttering:Density 0.9g/cm3;Turnover rate:It need to be to different level, different cross section point It is not equipped with, template not warpage, surface is smooth, does not crack, and water resistance is good, and boiling is not come unglued for 24 hours, and turnover rate is high;Peace Fill complexity:Drawing materials, processing limitation is few, and quality is high, and personnel are more needed for installation, without machinery;Mechanical property:Static bending strength Rift grain direction 44.3MPa, band direction 50.9MPa;To operating personnel:It is low;Concrete formation quality:Demoulding is easy, concrete Apparent mass mores easily guarantee;Cost comparisons:The demoulding time used is steel form 1/7, and installation procedure is more, but without mechanical-assisted, Mei ㎡ costs are low.
3, mould material is than choosing:
(1) it is directed to arc box beam side form, mainly can be from glass steel formwork, set shaped steel formwork, film plate+stainless steel is compound Template, aluminum alloy mould plate, plastic formwork these types are compared.For set shaped steel formwork since its dead weight is larger, when assembling and disassembling, is equal Mechanical-assisted is needed, while being directed to arc box beam, generally applicable segment is less, and cost is higher, does not use.It is existing for glass steel formwork Stage is more for circular-sectioned pier and power pipe, and since it is polymerized for glass fibre, tensile resistance is strong, and side form is whole Difficulty is reinforced, height is required to worker, material cost itself is higher, does not use.Aluminum alloy mould plate and plastic formwork all have corrosion resistant, Anti-corrosion, from heavy and light the advantages of, but be required to carry out factory it is customized, for arc box beam use after, turnover rate is low, while to scene Installation exercise personnel requirement is high, and material itself is of high cost, does not use.Film plate+stainless steel double shuttering has taken into account the film simultaneously Plate convenient material drawing, properties are excellent, at low cost, low to on-site personnel requirement, and Stainless Molding Board is easy to process, can model Good advantage is combined, while being directed to arc box beam feature itself, can be used in turn using composite shuttering, determines to use.
(2) it is directed to box girder inner formwork, each class template can be used as box girder inner formwork, but the characteristics of combination arc box beam, height It is smaller, personnel's operating difficulties, therefore set shaped steel formwork, aluminum alloy mould plate, the film plate+stainless steel double shuttering are not applicable, it is contemplated that The general surface of glass steel formwork, plastic formwork is smooth, and difficulty is fixed when as internal model, therefore is not used.It is main for aerated core In view of it is in radian angular position cracky, installation procedure is complicated, and when concreting easily floats so that concrete size is not It meets the requirements, when form removal requires the features such as high to worker, therefore does not use.For double-wall corrugated pipe, convenient material drawing, due to its appearance Face itself has ripple and is more conducive to install fixation, while material itself has certain ductility, can be according to arc box beam radian It is bent, relatively low to in-site installation personnel requirement, overall cost is low, therefore uses.
4, bed die plate material homonymy mould is all made of film plate, and end template is more than 20cm beyond both sides side template hemline, Anti-skidding batten is followed closely on the bed die completed, batten size length × width x thickness is the plank of 50cm × 20cm × 2cm thickness, spacing 25- 35cm is installed for later stage side mould.Along box beam bottom plate boundary one wide 10cm of tailor's tack, the batten of thick 18mm, line style and box beam Bottom plate both sides are consistent.Plane setting-out is carried out to bed die, bottom plate vertically and horizontally absolute altitude is measured, is adjusted to end template according to measurement result Designed elevation detects absolute altitude again.
5, on already installed bed die, side template installation is carried out.Side template uses 18mm thickness film plates.Template back Follow closely the lumps of wood of a 2m long 10cm × 10cm, spacing 15cm mono-.One lumps of wood for reinforcing support is set per 60cm, is withstood on one side The lumps of wood at side template back, is close to Template nail in joint and is connect, and other end is then followed closely on the lumps of wood being connect with shore frame.For Arc box beam top circular arc highly exceeds design structure height 10-15cm, then in circular arc 2mm first in top nailing template Stainless Molding Board follows closely out the radius of design drawing needs, width 10cm.
6, it is circular hollow structure inside box beam, it, highly can be with box beam entirety with angle in order to reach arc effect It is adjusted, using the extendable double-wall corrugated pipe in part.In order to ensure the mounting height of bellows, in later stage casting concrete When not deviation, it is mobile, it is fixed using the reinforcing bar of 16 diameters of φ, spacing 80cm.Fixed steel bars need to have with bottom main reinforcement Effect welding.One circle screw-thread steel can be installed simultaneously along bellows, diameter 10mm ensures itself and other steel such as No. 8 reinforcing bars in Fig. 4 Muscle effectively connects.Increase longitudinal reinforcement on the outside of spiral bar, such as No. 9 reinforcing bars in Fig. 4.
7, Screw arbor with nut at both-ends is being worn apart from the position of the high 25-30cm in box beam bottom, is being worn apart from the top positions 25-30cm to drawing spiral shell Bar.Both sides are connected integral add for the reinforcing bar of larger section of use φ 14 of radian with homonymy screw rod after having worn Screw arbor with nut at both-ends Box beam is reinforced Gu being connect with screw rod using steel pipe compared with segment for radian.Simultaneously in order to reinforce template overall stability, Increase per 3m and supports together.
For those skilled in the art, it is various corresponding that other can be made according to above technical scheme and design Change and deformation, and all these change and distortions should all belong within the protection domain of the claims in the present invention.

Claims (9)

1. arc box beam template forming method, includes the following steps:
1) surveying and locating:Before box girder construction, determine that arc box beam key controls pile No. in advance, then pass through arc box beam plan view Axis circular curve determines coordinate of mid-peg, and bottom plate is calculated according further to sectional view, the coordinate of the stake of the top plate left side and the right stake, most Carry out setting-out on the spot at the scene afterwards, respectively increase by one is marked across the span of longitudinal horizontal rod with lime on both sides on the outside of top plate;
2) mould material is than choosing:Mould material includes glass steel formwork, set shaped steel formwork, film plate+stainless steel double shuttering, bridge Beam aerated core, aluminum alloy mould plate, double-wall corrugated pipe, plastic formwork;
3) mould material is selected:It is selected including box beam external mold and box girder inner formwork mould material, in conjunction with the characteristics of arc box beam, box beam External mold uses film plate+stainless steel double shuttering, box girder inner formwork to use double-wall corrugated pipe;
4) bed die is laid with:Bed die plate material homonymy mould is all made of film plate, along box beam bottom plate boundary one batten of tailor's tack, line style It is consistent with box beam bottom plate both sides, plane setting-out is carried out to bed die, measures bottom plate vertically and horizontally absolute altitude, according to measurement result by end template It is adjusted to designed elevation, detects absolute altitude again;
5) side form is installed:On already installed bed die, side template installation is carried out;A lumps of wood is followed closely at template back, is often fixed The lumps of wood for reinforcing support is arranged in spacing, withstands the lumps of wood at side template back on one side, is close to and is connect with Template nail in joint, separately One is then followed closely on the lumps of wood being connect with shore frame;
6) internal model is installed:It highly can be with box beam with angle in order to reach arc effect for circular hollow structure inside box beam Entirety is adjusted, using the extendable double-wall corrugated pipe in part;
7) side mould is reinforced:Screw arbor with nut at both-ends is being worn apart from the position of the high 25-30cm in box beam bottom, is being worn apart from the top positions 25-30cm Screw arbor with nut at both-ends.
2. arc box beam template forming method according to claim 1, it is characterised in that:Film plate in step 2)+no The steel composite shuttering that becomes rusty is a kind of self-control gang form.
3. arc box beam template forming method according to claim 1, it is characterised in that:Film plate in step 3)+no Become rusty steel composite shuttering, can be used in turn using composite shuttering.
4. arc box beam template forming method according to claim 1, it is characterised in that:Double-wall corrugated pipe in step 3) Surface is to be more conducive to install with ripple to manage, while having certain ductility, can be bent according to arc.
5. arc box beam template forming method according to claim 1, it is characterised in that:End template exceeds two in step 4) The hemline of avris mould is more than 20cm, while anti-skidding batten is followed closely on the bed die completed, and batten size length × width x thickness is The plank of 50cm × 20cm × 2cm, spacing 25-35cm are installed for later stage side mould.
6. arc box beam template forming method according to claim 1, it is characterised in that:Step 5) side template uses 18mm A 2m long, the lumps of wood of 10cm × 10cm are followed closely in thick film plate, side template back, and one is arranged per 60cm and adds by spacing 15cm mono- The lumps of wood of clamped support.
7. arc box beam template forming method according to claim 5, it is characterised in that:Step 5) box beam top circular arc Place needs first to follow closely plank on top, highly exceeds design structure height 10-15cm, then follow closely in circular arc 2mm Stainless Molding Boards Go out the radius of design drawing needs.
8. arc box beam template forming method according to claim 1, it is characterised in that:Step 6) is in order to ensure bellows Mounting height, the not deviation in later stage casting concrete is mobile, it is fixed using reinforcing bar, fixed steel bars need to be the bottom of with Portion's main reinforcement is effectively welded.
9. arc box beam template forming method according to claim 1, it is characterised in that:It has worn to drawing spiral shell on step 7) both sides Be connected with homonymy screw rod using the reinforcing bar of φ 14 for larger section of radian after bar it is integral reinforce, radian is adopted compared with segment It is connect with screw rod with steel pipe and box beam is reinforced, while in order to reinforce template overall stability, increased per 3m and support together.
CN201810107841.0A 2018-02-02 2018-02-02 Arc box beam template forming method Active CN108330807B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810107841.0A CN108330807B (en) 2018-02-02 2018-02-02 Arc box beam template forming method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810107841.0A CN108330807B (en) 2018-02-02 2018-02-02 Arc box beam template forming method

Publications (2)

Publication Number Publication Date
CN108330807A true CN108330807A (en) 2018-07-27
CN108330807B CN108330807B (en) 2019-10-25

Family

ID=62927905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810107841.0A Active CN108330807B (en) 2018-02-02 2018-02-02 Arc box beam template forming method

Country Status (1)

Country Link
CN (1) CN108330807B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172924A (en) * 2019-06-17 2019-08-27 中交第三公路工程局有限公司 Integral hydraulic box girder formwork construction method
CN110348142A (en) * 2019-07-16 2019-10-18 龙元建设集团股份有限公司 Based on the BIM method of gang form bracket technique molding curve bridge
CN111469252A (en) * 2020-04-17 2020-07-31 罗智 Double-layer inflatable membrane concrete formwork system and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104999772A (en) * 2015-08-03 2015-10-28 宁波柯乐芙家具股份有限公司 Manufacturing technology for arc slab
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN205502566U (en) * 2016-04-07 2016-08-24 山东方圆建筑材料有限公司 Arc formwork with adjustable
CN206299120U (en) * 2016-12-19 2017-07-04 保定鼎阳电力工程有限公司 A kind of arch formwork for placing
CN206604940U (en) * 2017-01-20 2017-11-03 山东省调水工程技术研究中心有限公司 Socket full circle is molded arc formwork

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN104999772A (en) * 2015-08-03 2015-10-28 宁波柯乐芙家具股份有限公司 Manufacturing technology for arc slab
CN205502566U (en) * 2016-04-07 2016-08-24 山东方圆建筑材料有限公司 Arc formwork with adjustable
CN206299120U (en) * 2016-12-19 2017-07-04 保定鼎阳电力工程有限公司 A kind of arch formwork for placing
CN206604940U (en) * 2017-01-20 2017-11-03 山东省调水工程技术研究中心有限公司 Socket full circle is molded arc formwork

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172924A (en) * 2019-06-17 2019-08-27 中交第三公路工程局有限公司 Integral hydraulic box girder formwork construction method
CN110172924B (en) * 2019-06-17 2020-09-08 中交第三公路工程局有限公司 Integral hydraulic box girder template construction method
CN110348142A (en) * 2019-07-16 2019-10-18 龙元建设集团股份有限公司 Based on the BIM method of gang form bracket technique molding curve bridge
CN110348142B (en) * 2019-07-16 2023-01-17 龙元建设集团股份有限公司 Method for forming curve bridge based on BIM combined template support process
CN111469252A (en) * 2020-04-17 2020-07-31 罗智 Double-layer inflatable membrane concrete formwork system and construction method thereof
CN111469252B (en) * 2020-04-17 2022-03-01 罗智 Double-layer inflatable membrane concrete formwork system and construction method thereof

Also Published As

Publication number Publication date
CN108330807B (en) 2019-10-25

Similar Documents

Publication Publication Date Title
CN108330807B (en) Arc box beam template forming method
CN105569331B (en) A kind of simple support method of concrete cylindrical template
CN104674945A (en) Tree-shaped steel pipe column structure and construction method thereof
CN206513379U (en) Lining construction reserves the Tunnel Second Lining formwork jumbo of V-groove structure
CN108385980A (en) Deformation joint shear wall set shaped steel formwork installs unidirectional fastening screw construction method
CN101440667A (en) Mounting method for wide span single layer rain shed reticulated shell structure
CN206873730U (en) A kind of steel bar truss floor structure
CN108894488A (en) A kind of construction method of Novel section steel keel steel and wood composite template
CN109208790A (en) Circular arc shear wall single side formwork construction method
CN108756291B (en) Large-tonnage concrete column replacement reinforcement structure and reinforcement method
CN106480983A (en) A kind of assembled beam-column hinged joint and its assembling mode
CN106760502A (en) Shear wall end cylinder construction method
CN104818849B (en) Construction method for space curved rib girder steel structure
CN106835992B (en) A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
CN204209803U (en) A kind of prefabricated box girder inner formwork aluminum alloy mould plate
CN110397268A (en) Ring beam template and board support integrated design and construction method are poured after fabricated shear wall
CN209854572U (en) Section beam prestressed pipeline positioning device adopting stub matching method
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN206928426U (en) A kind of prefabricated composite wallboard formula underground installation
CN110616839A (en) Preparation method of concrete laminated slab bottom plate based on light steel keels and cement boards
CN109469324A (en) The construction method of abnormal curved surface column
CN214498388U (en) Assembled overhanging formwork support bent
CN114718236A (en) Oversized GRC unit type construction process
CN212295619U (en) Combined glass fiber reinforced plastic concrete template
CN213358913U (en) Ornamental bowl-shaped structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant