CN108316637A - A kind of Rapid Combination locking-type connection system for guide rail - Google Patents

A kind of Rapid Combination locking-type connection system for guide rail Download PDF

Info

Publication number
CN108316637A
CN108316637A CN201810109205.1A CN201810109205A CN108316637A CN 108316637 A CN108316637 A CN 108316637A CN 201810109205 A CN201810109205 A CN 201810109205A CN 108316637 A CN108316637 A CN 108316637A
Authority
CN
China
Prior art keywords
upright bar
tapered end
brace
pin
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810109205.1A
Other languages
Chinese (zh)
Inventor
张鸿翎
李明生
祖继宏
齐小龙
江华
周波
任长伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Junying Equipment Technology Co Ltd
Original Assignee
Qingdao Junying Equipment Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Junying Equipment Technology Co Ltd filed Critical Qingdao Junying Equipment Technology Co Ltd
Priority to CN201810109205.1A priority Critical patent/CN108316637A/en
Publication of CN108316637A publication Critical patent/CN108316637A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The invention discloses a kind of Rapid Combination locking-type connection system for guide rail; mainly it is made of the structural members such as upright bar, horizon bar, brace and piece attachments; wherein upright bar is equipped with porous terminal pad and connection locking docking system; to be assembled into from mating horizon bar, brace etc., space structure is stable and can meet different load requirements builds system; and these base components there are structures interrelated, interdependent relationship; possessive construction part is all made of standard component series; it is produced on a large scale, is really achieved safe, reliable, efficient, practical.

Description

A kind of Rapid Combination locking-type connection system for guide rail
Technical field
The invention belongs to building fields, and in particular to what architectural engineering used combines with safe locking structure Fast Installation Formula scaffold builds system.
Background technology
Common scaffold for building includes pipe thread formula, gate-type, bowl fastening type and disk button etc. both at home and abroad at present, no matter which kind of There are many defects in use, include mainly in scaffold:
1, the locking of its tube clamps of pipe buckle type scaffold is carried by frictional force, easy to fall off to cause safety accident, and existing developed country is all It has eliminated;
2, door-type scaffold bearing capacity is small, and overlap height is limited;Total sub-semigroup supports by short distance cross bar right angle and uses steel Amount is very big, and side bearing capacity difference easily large area is caved in;
3, disk buckle type scaffold because of wedge cotter because no locking mechanism is made in horizontal loading, dynamic load, the factors such as expand with heat and contract with cold It is failed with lower self-locking, node is caused to loosen, frame body will shake and deform, it cannot be guaranteed that the overall stability of frame body, exists tight The security risk of weight.
Therefore designing novel Rapid Combination installation and preventing structural member from loosening the scaffold to fall apart becomes skill urgently to be resolved hurrily Art project.
Invention content
The purpose of the present invention is to provide safe and reliable, multipurpose, can combine, connecting portion is locking structure foot hand Frame builds system.
To reach above-mentioned technical purpose, the technical scheme is that:
A kind of Rapid Combination locking-type connection system for guide rail is built, the knot by upright bar 1 and several structural members and accessory kit Component includes horizon bar 2, brace 3, and the terminal pad 4 for being provided with mounting hole is spaced in the upright bar 1,
Further include horizontal lock 2-1, oblique tapered end 3-1, lock pin 6, the wedge pin being used cooperatively with horizontal lock 2-1, oblique tapered end 3-1 5;
Auxiliary catch 7 is arranged in the tapered end top of the oblique tapered end 3-1 of horizontal lock 2-1/, and relieving ring 5-1 is equipped on wedge pin 5, Relieving ring 5-1 is inserted in locking of the realization of auxiliary catch 7 of tapered end to 5 displacement of wedge pin;
The horizontal lock 2-1 front openings are simultaneously sticked in the terminal pad 4 of upright bar 1, and rear end is fixedly connected with horizon bar 2;It is logical Cross the connection that horizontal lock 2-1 realizes horizon bar 2 and upright bar 1 with the cooperation of wedge pin 5;
Lock pin 6 is fixed on oblique tapered end 3-1 or lock pin 6 is fixed on 1/ horizon bar 2 of upright bar;
Oblique tapered end 3-1 front openings are simultaneously sticked in the terminal pad 4 of upright bar 1, and rear end is provided with lock pin 6;3 front end of brace, which is fixed, to be connected Tape splicing has the brace connector 3-2 of casing;The casing of the brace connector 3-2 is inserted into lock pin 6, realizes the company of brace 3 and upright bar 1 It connects;
Or the brace connector 3-2 of brace 3 is directly sleeved on the lock pin 6 of 1/ horizon bar 2 of upright bar and realizes that brace 3 is horizontal with upright bar 1/ The connection of bar 2.
Further, the horizontal lock 2-1, oblique tapered end 3-1 be made of tapered end top and tapered end lower part " [" shape structure, The tapered end top, tapered end lower interior portion offer the flat connecting hole being inserted into for wedge pin 5, wedge pin 5 be inserted into tapered end top, The oblique tapered end 3-1 of horizontal lock 2-1/ and 4 wedging of terminal pad of upright bar 1 are connected to one by the mounting hole of terminal pad 4 and tapered end lower part It rises.
Further, the upright bar 1 is equipped with upper casing 1-7 close to top position, and setting of casing 1-2 is arranged in bottom;Upper casing 1-7 Upper setting installation is to just using lug 1-6;Setting of casing 1-2 is equipped with U-nut 1-3 and connection through-hole corresponding with U-nut 1-3, Bottom setting is to just using groove piece 1-5;1 upper and lower plug-in type of upright bar connects, and by bolt or is inserted into pin locking;Upper casing 1-7 installations are to just using lug 1-6, when setting of casing 1-2 is inserted in lower upright bar 1-8 and groove piece and lug to timing, at the top of lower upright bar The mounting hole of mounting hole and setting of casing 1-2 are also to just, bolt is connect across the concentric connecting hole of upper and lower upright bar with U-nut 1-3 Or it is inserted into pin locking.
Further, the brace connector 3-2 is provided with several casings of different location, the set that brace 3 passes through different location Pipe connect with lock pin 6, and realization brace 3 and horizon bar 2 or 1 link position of upright bar are adaptively adjusted, completion multiple combinations.
Further, setting " u "-shaped in 6 front end of the lock pin is open, the setting pin vertical with opening direction in " u "-shaped is open Locating part 6-2 is installed on axis 6-1, axis pin 6-1.
Further, the locating part 6-2 is spring stop piece, bolt or locking plate;It is equipped in the spring stop piece or locating part Annular space, which is simultaneously inserted on axis pin 6-1, to be realized rotation and moves up and down, brace connector 3-2 sets when ensureing axial consistent with lock pin 6 Pipe can be inserted in, and can prevent brace connector 3-2 casings from falling off when standing position.It can also be inserted into bolt in U-shaped mouth on the inside of axis pin 6-1 Complete locking.
Further, the outer cornice setting of 4 mounting hole of slotting disk installed in the upright bar 1 is fluted.
Compared with the prior art, the present invention has the following advantages and good effect:
The first, the present invention devises unique tapered end and connect dish structure, by horizon bar, brace, etc. with the porous company in upright bar The mating connection of disk is connect, and devises wedge pin and matched relieving ring, auxiliary catch by tapered end and terminal pad locking, is built into Space structure that is convenient, stablizing;
The second, a variety of of brace are devised and build mode, by brace connector and lock pin, allow brace directly with upright bar, water Flat bar connects and composes oblique rock-steady structure, and the position of tie point can realize multiple combinations by the brace connector of different location.
Third, upright bar use modularized design, easy to assembly between different units module, and devise locking mechanism, pacify Quan Xinggao.
4th, possessive construction part be all made of standard component series, be produced on a large scale, be really achieved it is safe, reliable, efficient, It is practical.
Description of the drawings
Fig. 1 is a kind of local attachment structure schematic diagram of Rapid Combination locking-type connection system for guide rail of the present invention;
Fig. 2 is location A enlarged structure schematic diagram in Fig. 1;
Fig. 3 is location A brace coupling part enlarged structure schematic diagram in Fig. 1;
Fig. 4 is B location enlarged structure schematic diagram in Fig. 1;
Fig. 5 is the attachment structure schematic diagram of horizon bar/upright bar and lock pin;
Fig. 6 is locking plate detent configuration schematic diagram at vertical position in embodiment 3;
Fig. 7 is locking plate detent configuration schematic diagram in cis-position in embodiment 3;
Fig. 8 is spring stop piece detent configuration schematic diagram in cis-position in embodiment 4;
Fig. 9 is spring stop piece detent configuration schematic diagram at vertical position in embodiment 4;
Figure 10 is upright bar base unit connecting portion structural schematic diagram.
Symbol and its explanation in figure:
Upright bar 1;Upper pright stanchion 1-1;Setting of casing 1-2;U-nut 1-3;Groove piece 1-5;Lug 1-6;Upper casing 1-7;Lower upright bar 1- 8;Horizon bar 2;Horizontal lock 2-1;Brace 3;Oblique tapered end 3-1;Brace connector 3-2;Terminal pad 4;Mounting hole 4-1;Wedge pin 5; Relieving ring 5-1;Lock pin 6;Axis pin 6-1;Locating part 6-2;Auxiliary catch 7.
Specific implementation mode
Below in conjunction with the accompanying drawings and the embodiment of the present invention to the present invention a kind of Rapid Combination locking-type connection system for guide rail make into One step is described in detail.
A kind of Rapid Combination locking-type connection system for guide rail is built, institute by upright bar 1 and several structural members and accessory kit It includes horizon bar 2, brace 3 to state structural member, and the terminal pad 4 for being provided with mounting hole, a preferred side are spaced in the upright bar 1 In case, the outer cornice setting of mounting hole is fluted, is designed by groove, helps to prevent from rotating when 5 lateral force of wedge pin, The torque resistant ability for helping to improve horizon bar, to ensure the stability of horizontal direction structure.
In order to realize that building for the structural members such as horizon bar, upright bar, brace, the present invention devise horizontal lock 2-1, oblique tapered end 3-1, lock pin 6, the wedge pin 5 being used cooperatively with horizontal lock 2-1, oblique tapered end 3-1.The front ends horizontal lock 2-1/ oblique tapered end 3-1 It is open and is sticked in the terminal pad 4 of upright bar 1, rear end is fixedly connected with 2/ brace 2 of horizon bar;It is described in one preferred embodiment Horizontal lock 2-1, oblique tapered end 3-1 are made of " [" shape structure, under the tapered end top, tapered end tapered end top and tapered end lower part Offer the flat connecting hole being inserted into for wedge pin 5 inside portion, wedge pin 5 be inserted into tapered end top, terminal pad 4 mounting hole and lock Head lower part, the oblique tapered end 3-1 of horizontal lock 2-1/ and 4 wedging of terminal pad of upright bar 1 are linked together.
In order to realize the locking to connection, stability is improved, the tapered end top of the oblique tapered end 3-1 of horizontal lock 2-1/ is set Auxiliary catch 7 is set, relieving ring 5-1 is installed on wedge pin 5, the auxiliary catch 7 that relieving ring 5-1 is inserted in tapered end is realized to wedge pin 5 The locking of displacement;
Connection type that there are many braces and upright bar, brace and horizon bar,
Embodiment 1:Brace 3 realizes the connection with upright bar 1 by oblique tapered end 3-1 cooperations,
Oblique tapered end 3-1 front openings are simultaneously sticked in the terminal pad 4 of upright bar 1, and the connection that rear end is provided with disjunctor lock pin 6 is flat Platform;3 front end of brace is fixedly connected with the brace connector 3-2 with casing;The casing of the brace connector 3-2 is inserted into and disjunctor lock pin With locating part 6-2 lockings after 6, the connection of brace 3 and upright bar 1 is realized;In one preferred scheme, brace connector 3-2 is provided with Several casings, with reference to Fig. 4, brace 3 can be connect by different location casing with lock pin 6, realize brace 3 and horizon bar 2 or upright bar 1 The adaptability of link position selects, and can complete various structures combination.
Embodiment 2:Brace 3 is directly connect with 1/ horizon bar 2 of upright bar by lock pin 6,
Lock pin 6 is fixed on 1/ horizon bar 2 of upright bar, is convenient to be inserted in the casing of brace connector 3-2, realize brace 3 with The connection of 1/ horizon bar 2 of upright bar.
6 front end of the lock pin is arranged " u "-shaped and is open, the setting axis pin 6-1 vertical with opening direction in " u "-shaped is open, Locating part 6-2 is installed on axis pin 6-1.The locating part 6-2 is spring stop piece, bolt or locking plate;
Embodiment 3
As shown in Figure 6, Figure 7, the locating part 6-2 is locking plate, and annular space is equipped in the locking plate and is inserted on axis pin 6-1 real It now rotates and moves up and down, ensure that brace connector 3-2 casings can be inserted in when consistent i.e. cis-position axial with lock pin 6, can prevent when standing position Only brace connector 3-2 casings fall off;
Embodiment 4
As shown in Figure 8, Figure 9, the locating part 6-2 is spring stop piece, and the spring stop piece is by elastic component around making annular space And be inserted in realization rotation on axis pin 6-1 and move up and down, ensure brace connector 3-2 casings when consistent i.e. cis-position axial with lock pin 6 Can be inserted in, stand position when elastic component will lock pin 6 compress, can prevent brace connector 3-2 casings from falling off;
Embodiment 5
It can also be inserted into and be locked with bolt in U-shaped mouth on the inside of axis pin 6-1.
Connection relation between upright bar is as shown in Figure 10:
Upright bar 1 is equipped with upper casing 1-7 close to top position, and setting of casing 1-2 is arranged in bottom;Setting installation is to just on upper casing 1-7 With lug 1-6;Setting of casing 1-2 is equipped with U-nut 1-3 and connection through-hole corresponding with U-nut 1-3, and bottom is arranged to just using Groove piece 1-5;1 upper and lower plug-in type of upright bar connects, and by bolt or is inserted into pin locking;Upper casing 1-7 installations are to just with convex Piece 1-6, when setting of casing 1-2 is inserted in lower upright bar 1-8 and groove piece with lug to timing, lower upright bar top mounting holes and setting of casing 1- 2 mounting hole also to just, pin being connect or being inserted into U-nut 1-3 across the concentric connecting hole of upper and lower upright bar by bolt, this Sample then realizes longitudinal anticreep locking connection of upright bar, while also improving the ability of upright bar torque resistant.
The above described is only a preferred embodiment of the present invention, being not that the invention has other forms of limitations, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. Imitate embodiment.But it is every without departing from technical solution of the present invention content, according to the technical essence of the invention to above example institute Any simple modification, equivalent variations and the remodeling made, still fall within the protection domain of technical solution of the present invention.

Claims (7)

1. a kind of Rapid Combination locking-type connection system for guide rail, by upright bar(1)And several structural members and accessory kit are built, institute It includes horizon bar to state structural member(2), brace(3), the upright bar(1)It is upper to be spaced the terminal pad for being provided with mounting hole(4), special Sign is:
It further include horizontal lock(2-1), oblique tapered end(3-1), lock pin(6)With horizontal lock(2-1), oblique tapered end(3-1)Cooperation makes Wedge pin(5);
The horizontal lock(2-1)/ oblique tapered end(3-1)Tapered end top be arranged auxiliary catch(7), wedge pin(5)On guarantor is installed Dangerous ring(5-1), by relieving ring(5-1)It is inserted in the auxiliary catch of tapered end(7)It realizes to wedge pin(5)The locking of displacement;
The horizontal lock(2-1)Front opening is simultaneously sticked in upright bar(1)Terminal pad(4)On, rear end and horizon bar(2)It is fixed Connection;Pass through horizontal lock 2-1 and wedge pin(5)Horizon bar is realized in cooperation(2)With upright bar(1)Connection;
Lock pin(6)It is fixed on oblique tapered end(3-1)Upper or lock pin(6)It is fixed on upright bar(1)/ horizon bar(2)On;
Oblique tapered end 3-1 front openings are simultaneously sticked in upright bar(1)Terminal pad(4)On, rear end is provided with lock pin 6;Brace(3)Front end It is fixedly connected with the brace connector with casing(3-2);The brace connector(3-2)Casing be inserted into lock pin 6, realize brace 3 with Upright bar(1)Connection;
Or brace(3)Brace connector(3-2)It is directly sleeved on upright bar(1)/ horizon bar(2)Lock pin 6 on realize brace(3)With Upright bar(1)/ horizon bar(2)Connection.
2. assembly scaffold according to claim 1 builds system, it is characterised in that:The horizontal lock(2-1), tiltedly Tapered end(3-1)It is made of that " [" shape structure, the tapered end top, tapered end lower interior portion are offered tapered end top and tapered end lower part For wedge pin(5)The flat connecting hole of insertion, wedge pin(5)It is inserted into tapered end top, terminal pad(4)Mounting hole and tapered end under Portion, by horizontal lock(2-1)/ oblique tapered end(3-1)With upright bar(1)Terminal pad(4)Wedging links together.
3. assembly scaffold according to claim 1 builds system, it is characterised in that:The upright bar(1)Close to top Position is equipped with upper casing(1-7), setting of casing is arranged in bottom(1-2);Upper casing(1-7)Upper setting installation is to just using lug(1-6); Setting of casing(1-2)Equipped with U-nut(1-3)And and U-nut(1-3)Corresponding connection through-hole, bottom are arranged to just using groove Piece(1-5);Upright bar(1)Upper and lower plug-in type connection, and by bolt or it is inserted into pin locking;Upper casing(1-7)Installation is to just using Lug(1-6), work as setting of casing(1-2)It is inserted in lower upright bar(1-8)And groove piece and lug be to timing, lower upright bar top mounting holes with Setting of casing(1-2)Mounting hole also to just, bolt is passed through into the concentric connecting hole of upper and lower upright bar and U-nut(1-3)Connection is inserted Enter pin locking.
4. assembly scaffold according to claim 1 builds system, it is characterised in that:The brace connector(3-2)If It is equipped with several casings of different location, brace(3)Pass through the casing and lock pin of different location(6)Brace is realized in connection(3)With water Flat bar(2)Or upright bar(1)Link position is adaptively adjusted, and completes multiple combinations.
5. assembly scaffold according to claim 1 builds system, it is characterised in that:The lock pin(6)Front end is arranged " u "-shaped is open, the setting axis pin vertical with opening direction in " u "-shaped is open(6-1), axis pin(6-1)Upper installation locating part(6- 2).
6. assembly scaffold according to claim 5 builds system, it is characterised in that:The locating part(6-2)It is bullet Spring catch, bolt or locking plate;It is equipped with annular space in the spring stop piece or locating part and is inserted in axis pin(6-1)Upper realization rotation With move up and down, ensure and lock pin(6)Brace connector when axial consistent(3-2)Casing can be inserted in, and can prevent brace from connecing when standing position Head(3-2)Casing falls off.
7. disc locking type scaffold according to claim 1 builds system, it is characterised in that:The upright bar(1)Middle installation Insert disk(4)The outer cornice setting of mounting hole is fluted.
CN201810109205.1A 2018-02-05 2018-02-05 A kind of Rapid Combination locking-type connection system for guide rail Pending CN108316637A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810109205.1A CN108316637A (en) 2018-02-05 2018-02-05 A kind of Rapid Combination locking-type connection system for guide rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810109205.1A CN108316637A (en) 2018-02-05 2018-02-05 A kind of Rapid Combination locking-type connection system for guide rail

Publications (1)

Publication Number Publication Date
CN108316637A true CN108316637A (en) 2018-07-24

Family

ID=62903283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810109205.1A Pending CN108316637A (en) 2018-02-05 2018-02-05 A kind of Rapid Combination locking-type connection system for guide rail

Country Status (1)

Country Link
CN (1) CN108316637A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025243A (en) * 2018-08-03 2018-12-18 江苏国舜速接架有限公司 A kind of novel socket joint type disk button quick access frame
CN109025221A (en) * 2018-09-13 2018-12-18 北京城建十六建筑工程有限责任公司 A kind of two times transfer frame
CN110453906A (en) * 2019-07-12 2019-11-15 邱萍 A kind of means for fastening scaffolding for construction
CN111236645A (en) * 2020-03-17 2020-06-05 陕西省建筑科学研究院有限公司 Steel pipe support and occlusion type node connecting device thereof
CN112065012A (en) * 2020-08-31 2020-12-11 中国建筑第二工程局有限公司 Hospital construction scaffold and use method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT8348151A0 (en) * 1983-04-22 1983-04-22 Rocco Palamara JOINTS WITH SLIDING AXIS CONNECTION, FOR SHELVING AND/OR SCAFFOLDING WITH SQUARE OR ROUND RODS
CN201314115Y (en) * 2008-11-17 2009-09-23 无锡速捷脚手架工程有限公司 Combined scaffold
CN201802058U (en) * 2010-08-19 2011-04-20 周继忠 Novel insertion disk fastener scaffold
CN205206267U (en) * 2015-11-03 2016-05-04 青岛军英装备科技有限公司 Safe multi -functional scaffold
CN105544962A (en) * 2015-12-10 2016-05-04 山东拉立克建材科技有限公司 Disk buckle type steel pipe support joint in high torsional rigidity
CN107246143A (en) * 2017-06-06 2017-10-13 青岛军英装备科技有限公司 Disc locking type scaffold builds system
CN208586889U (en) * 2018-02-05 2019-03-08 青岛军英装备科技有限公司 A kind of Rapid Combination locking-type connection system for guide rail

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT8348151A0 (en) * 1983-04-22 1983-04-22 Rocco Palamara JOINTS WITH SLIDING AXIS CONNECTION, FOR SHELVING AND/OR SCAFFOLDING WITH SQUARE OR ROUND RODS
CN201314115Y (en) * 2008-11-17 2009-09-23 无锡速捷脚手架工程有限公司 Combined scaffold
CN201802058U (en) * 2010-08-19 2011-04-20 周继忠 Novel insertion disk fastener scaffold
CN205206267U (en) * 2015-11-03 2016-05-04 青岛军英装备科技有限公司 Safe multi -functional scaffold
CN105544962A (en) * 2015-12-10 2016-05-04 山东拉立克建材科技有限公司 Disk buckle type steel pipe support joint in high torsional rigidity
CN107246143A (en) * 2017-06-06 2017-10-13 青岛军英装备科技有限公司 Disc locking type scaffold builds system
CN208586889U (en) * 2018-02-05 2019-03-08 青岛军英装备科技有限公司 A kind of Rapid Combination locking-type connection system for guide rail

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025243A (en) * 2018-08-03 2018-12-18 江苏国舜速接架有限公司 A kind of novel socket joint type disk button quick access frame
CN109025221A (en) * 2018-09-13 2018-12-18 北京城建十六建筑工程有限责任公司 A kind of two times transfer frame
CN109025221B (en) * 2018-09-13 2024-01-16 北京城建十六建筑工程有限责任公司 Secondary conversion frame
CN110453906A (en) * 2019-07-12 2019-11-15 邱萍 A kind of means for fastening scaffolding for construction
CN110453906B (en) * 2019-07-12 2021-05-11 重庆工程职业技术学院 Scaffold connecting device for building construction
CN111236645A (en) * 2020-03-17 2020-06-05 陕西省建筑科学研究院有限公司 Steel pipe support and occlusion type node connecting device thereof
CN112065012A (en) * 2020-08-31 2020-12-11 中国建筑第二工程局有限公司 Hospital construction scaffold and use method thereof

Similar Documents

Publication Publication Date Title
CN108316637A (en) A kind of Rapid Combination locking-type connection system for guide rail
CN208586889U (en) A kind of Rapid Combination locking-type connection system for guide rail
CN106939690B (en) The anti-load-bearing scaffold that inclines of one kind
CN107246143A (en) Disc locking type scaffold builds system
US20080283336A1 (en) Fittings for Builders' Trestles
CN102535832A (en) Novel scaffold connecting piece
CN116118631A (en) Plug-in type spiral joint pavement guardrail device
CN208347291U (en) A kind of aluminium joist structure for socket joint type disk button steel pipe support
CN206448512U (en) Multiplex roles drag link, simple drag link, hound and pylon
CN208347296U (en) A kind of belt lacing rod piece
CN201343864Y (en) Butterfly clip component for connection of combined scaffold
CN203230170U (en) Scaffold diagonal bar
CN108868112B (en) Wheel buckle type scaffold combined connection fixing device
CN205557823U (en) Connection structure of whole bathroom steel frame and steel column
CN210031629U (en) Road construction rail guard
WO2013150439A1 (en) Modular scaffold
CN219619003U (en) Plug-in type spiral joint pavement guardrail device
CN202882397U (en) Pitch point connecting structure of scaffold
CN106760474A (en) A kind of multiplex roles drag link, simple drag link, hound and pylon
CA2742051C (en) Scaffold post sleeve
CN208457896U (en) A kind of safety device for hanging stage lamp
CN216196539U (en) Plug-in self-locking scaffold
CN205276855U (en) A fastener for connecting steel pipe
CN220811668U (en) Assembled guardrail of building tower machine
CN216430735U (en) Side longitudinal anti-seismic support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination