Invention content
The present invention is directed at least solve the technical problems existing in the prior art, especially innovatively proposes one kind and be based on
The two side-wall pilot tunnel tunnel excavation dividing elements method of BIM technology.
In order to realize the above-mentioned purpose of the present invention, the present invention provides a kind of two side-wall pilot tunnel tunnel based on BIM technology
Road excavates dividing elements method, includes the following steps:
S1 is designed importing to tunnel model, configured tunneling technique parameter attribute, the characteristics of according to tunnel excavation engineering method, builds
The vertical constraints for excavating section, generates and excavates cross section profile, and excavation face is generated according to tunnel center line, then with engineering design
Results model carries out Boolean calculation, obtains and excavates results model;
S2, split cells is generated according to these hierarchical modes, and cell attribute configuration and expansion are carried out to these hierarchical modes,
Obtain the BIM models of excavation model construction.
The two side-wall pilot tunnel tunnel excavation dividing elements method based on BIM technology, it is preferred that the S1 packets
It includes:
S1-1 calculates the normal vector vSecNormal in section according to the tunnel section of selection;
S1-2 calculates projection of this on tunnel center line according to any point A on tunnel center line and tunnel section
A1, to obtain tunnel center line A1 points normal plane and tangential direction;The tangent line of normal vector and A1 points in conjunction with section
Direction vector, the cosine value by calculating its angle determine whether the tangential direction vector of A1 is reversed with expection, finally calculates
Normal vector vProNormal of the tunnel center line in A1 normal planes;
S1-3 calculates H direction vectors, then ask with the tangential direction of A1, it is specified that with tunnel benchmark excavation line direction for the directions H
Tunnel excavation the directions V, calculation formula V=vProNormal*H, i.e. vector V be perspective plane normal vector vProNormal and
The multiplication cross of direction vector H;
S1-4 obtains the minimum of object model section in construction work data and surrounds according to the tunnel cross section profile of selection
Box L and bounding box long axis maximum point MaxP and smallest point MinP;
S1-5 calculates kernel of section point minPos according to bounding box the long axis MaxP and MinP acquired in conjunction with perspective plane.
The two side-wall pilot tunnel tunnel excavation dividing elements method based on BIM technology, it is preferred that the S2 packets
It includes:
S2-1 carries out attribute configuration to each excavation result entity, including:Color, transparency, construction type, personnel, when
Between carry out assignment;
S2-2 calculates separately out the width and height in tunnel section, calculation formula according to the directions H and V and bounding box long axis length
For:
Projection vector of the bounding box long axis in the directions H:
VHProLen=((((MaxP-MinP) %H)/(H.x*H.x+H.y*H.y+H.z*H.z)) * H);
Tunnel cross-sectional width:
HLen=sqrt (vHProLen.x*vHProLen.x+vHProLen.y*vHProLen.y+vHProLen.z*
vHProLen.z);
Wherein H is the direction vector that S1-3 is acquired, and H.x/H.y/H.z is respectively the x/y/z coordinates of vector H,
VHProLen.x/vHProLen.y/vHProLen.z is respectively the x/y/z coordinates of vector v HProLen, and sqrt is extraction of square root;
S2-3 combines according to the cross section parameter of input, calculates tunnel section outline excavation;By way of sweeping along
Tunnel center line by tunnel section outline excavation sweeping at excavation face, then by excavation face with excavate body according to first left and right sides base tunnel after
Upper and lower sequence carries out Boolean calculation, obtains and excavates results model.
In conclusion by adopting the above-described technical solution, the beneficial effects of the invention are as follows:
Unit in charge of construction's high-precision easy to use is converted to disclosure address how designing a model of obtaining from designing institute to apply
Work model that is, by industry set rule or constraints, and is managed BIM attribute informations, and automatic divide is convenient for
The construction organization unit of implementation realizes the BIM auto-building models of Project Construction Organization, improves the essence of construction management of project
Degree and accuracy, by two side-wall pilot tunnel tunnel excavation dividing elements method of this method based on BIM technology, raising project is held
Line efficiency.
The additional aspect and advantage of the present invention will be set forth in part in the description, and will partly become from the following description
Obviously, or practice through the invention is recognized.
Specific implementation mode
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end
Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached
The embodiment of figure description is exemplary, and is only used for explaining the present invention, and is not considered as limiting the invention.
In the description of the present invention, it is to be understood that, term " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear",
The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" is based on attached drawing institute
The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, and does not indicate or imply the indicated dress
It sets or element must have a particular orientation, with specific azimuth configuration and operation, therefore should not be understood as the limit to the present invention
System.
Wherein BIM (Building Information Modeling) technologies model for architecture information.
Wherein when tunneling data model imported into BIM systems, need to execute following steps:
I, engineering design model is directly read, and translation resolution is carried out to its model data institutional framework;According to construction work
Journey construction requirements form design and construction engineering master data information, according to construction requirements, read and import different-format design result
Model;According to the mode of different designs tool design results model, translation resolution design result model data institutional framework
Product Structure;According to construction characteristic and positioning, each different modelling tool design result moulds are directly read
Type, independent of different modelling tools.
II, according to model data institutional framework feature, classify to each model data institutional framework, according to point
Class obtains the data of each of which classification, wherein comprising the graph data in model institutional framework, the attribute in model institutional framework
Data;It is required according to construction work model data institutional framework, according to the model data institutional framework after I translation resolution
Product Structure features classify to each model data institutional framework, and classification form is assembly Product,
Part Part, body Body;It is required according to construction work model data institutional framework, to sorted model data institutional framework,
Its attribute data and graph data are obtained respectively;The requirement of construction work model data institutional framework:Assemble the child node of Product
Can only be assembly Product and part Part nodes, the child node of part Part can only be body Body, wherein assembling
Product and part Part nodes only represent construction work model tree institutional framework, and body Body represents the construction work mould
A geometry data under type data;
III, it is woven according to the model data institutional framework got, and the new model data institutional framework of needs, group
The model institutional framework of new needs;
IV, according to the model data institutional framework got, and got after classifying to model data institutional framework
Corresponding model attributes data and model graph data, according to being loaded directly into and quickly loading both of which, respectively to model geometric
Topological Skew Field carries out respective handling;
According to construction work model data institutional framework require, and to design result model data institutional framework classify after
The correspondence model attributes data and model graph data obtained respectively, for construction work model data import two ways,
It is loaded directly into and quickly loads, handle respectively;
It is required according to construction work model data, the mode of being loaded directly into requires the geometry entity number of designing load results model
According to, the geometry entity data of design result model are made of model geometric model and constructive geometry construction two parts,
Wherein model geometric refers to the class that topological class is directed toward, and does not include specific shape information, constructive geometry refers in model geometric
Statement, including actual shape information;Model geometric is also known as the topological structure of model, and constructive geometry is also known as solution to model and releases knot
Structure, the geometry entity expression of a square, 1:Wherein model geometric topology refers to how many block in this square geometry
(square only there are one block), how many face (there are six faces for square) in block, on face how many boundary edge (12 boundaries
Side), how how many point (eight points) in boundary edge connects, 2 between point and side:Wherein constructive geometry refers to, specific face, face
Upper specific side (being made of which point), specific side, specific point coordinates, constructive geometry is that specific explanations model geometric is opened up
It flutters.The difference of model geometric model in model entity data and constructive geometry construction with the former does not include tool
The shape data information of body, and the latter includes actual shape data information.
It is required according to construction work model data, is loaded directly into design result model data and needs to carry out precision and Model Space
Between control, the precision and the model space of designing load results model data control formula are as follows:
Set A:Bare minimum (10e-6)
B:Minimum value of standardizing (10e-10)
C:The approximation accuracy (10e-3) of curve and surface
D:It is considered as zero maximum value (10e-11)
Model space computational algorithm:
Model space=A/B=10e-6/10e-10=10e4;
It is required according to construction work model data, quick load mode requires the figure number of quick designing load results model
According to the graph data of design result model refers to that, not comprising the pure graph data for having topology, pictorial data representaton method is as follows:
Set point:P1, P2, P3, P4, P5, P6
Wherein P1=P4, P3=P6,
Point list:PList=P1x, P1y, P1z, P2x, P2y, P2z, P3x, P3y, P3z, P4x, P4y, P4z, P5x,
P5y, P5z, P6x, P6y, P6z }
Face table data collection:FList={ Pn1, P1, P2, P3, Pn2, P5, P4, P6 }
Face Face=PList+FList
Pn:Point quantity
Original discrete graphics data, expression figure be Fig. 3:
The figure is a rectangle, becomes two triangles after discrete, abides by the right-hand rule, and normal direction is all outside, optimization
Process is:
Point duplicate removal:PList={ P1x, P1y, P1z, P2x, P2y, P2z, P3x, P3y, P3z, P5x, P5y, P5z },
Face duplicate removal data set:FList={ Pn1, P1, P2, P3, Pn2, P5, P1, P3 }
Reduce dough sheet quantity:Such as two quadrangles constitute a big quadrangle, are four triangle griddings before optimization, it is excellent
It is two triangle griddings after change, triangle gridding is that computer hardware rendering is needed data, and triangle gridding quantity is lower, can carry
Rise rendering efficiency.
The engineering design model introduction method based on BIM technology, it is preferred that the S5 includes:
It is required according to construction work model data, the graph data and attribute for having been subjected to processing that will be got in S4
Data are tied to respectively in the corresponding node of the construction work model data institutional framework recombinated in S3.
V, according to being loaded directly into and quickly loading both of which, add respectively into each classification of model data institutional framework
The model graphical information that adds that treated.
As illustrated in fig. 1 and 2, the present invention provides a kind of, and the two side-wall pilot tunnel tunnel excavation unit based on BIM technology is drawn
Divide method, includes the following steps:
S1 is designed importing, configured tunneling technique parameter attribute to tunnel model, and the demand according to user to tunneling obtains
Corresponding parameters for tunnel is taken, is preconditioned according to the characteristics of tunnel excavation engineering method, the constraints for excavating section is established, it is raw
At tunnel model profile is split, the fractionation cross section profile of excavation is scanned, excavation face is generated according to tunnel center line, then
Boolean calculation is carried out with engineering design results model, obtains the result of the fractionation tunnel model of excavation;
S2, split cells is generated according to these hierarchical modes, and cell attribute configuration and expansion are carried out to these hierarchical modes,
Obtain the BIM models of excavation model construction.
Preferably, the S1 includes:
S1-1 calculates the normal vector vSecNormal in section according to the tunnel section of selection;
S1-2 calculates projection of this on tunnel center line according to any point A on tunnel center line and tunnel section
A1, to obtain tunnel center line A1 points normal plane and tangential direction;The tangent line of normal vector and A1 points in conjunction with section
Direction vector, the cosine value by calculating its angle determine whether the tangential direction vector of A1 is reversed with expection, finally calculates
Normal vector vProNormal of the tunnel center line in A1 normal planes;
S1-3 calculates H direction vectors, it is specified that split by the directions horizontal axis H of tunnel benchmark excavation line direction, then with A1
Tangential direction acquire the directions longitudinal axis V of tunnel excavation and split, calculation formula V=vProNormal*H, i.e. vector V are
The multiplication cross of perspective plane normal vector vProNormal and direction vector H;
S1-4 obtains the minimum of object model section in construction work data and surrounds according to the tunnel cross section profile of selection
Box L and bounding box long axis maximum point MaxP and bounding box long axis smallest point MinP;
S1-5, according to the bounding box long axis maximum point MaxP and bounding box long axis smallest point MinP acquired, in conjunction with projection
Face calculates kernel of section point minPos.
As shown in Figure 3, it is preferred that the S2 includes:
S2-1 carries out attribute configuration to each excavation result entity, including:Color, transparency, construction type, personnel, when
Between carry out assignment;
S2-2 calculates separately out the width and height in tunnel section, calculation formula according to the directions H and V and bounding box long axis length
For:
Projection vector of the bounding box long axis in the directions horizontal axis H:
VHProLen=((((MaxP-MinP) %H)/(H.x*H.x+H.y*H.y+H.z*H.z)) * H);
Tunnel cross-sectional width:
HLen=sqrt (vHProLen.x*vHProLen.x+vHProLen.y*vHProLen.y+vHProLen.z*
vHProLen.z);
Wherein H is the direction vector that S1-3 is acquired, and H.x/H.y/H.z is respectively the x/y/z coordinates of vector H,
VHProLen.x/vHProLen.y/vHProLen.z is respectively the x/y/z coordinates of vector v HProLen, and sqrt is extraction of square root;
According to fig. 3, from the point of view of the specific embodiment of Fig. 4 and Fig. 5 is analyzed, vertical data H is acquired first, then acquires lateral data W,
Acquisition hence for data can be carried out orderly, make project data more rich in conditioning, certainly, according to the specific of engineering construction
It needs, can also be played very for other actual conditions using lateral data W, the method for then acquiring vertical data H is first acquired
Good technique effect, is adjusted flexibly in practical operation according to demand data.
As shown in fig. 6, in architecture information manages BIM technology, particularly with the data model construction of constructing tunnel engineering
Certification is mutually distinguishable for construction work data and machine in order to realize in the process, hence for needing for tunneling data mould
Type carries out the import operation of model, is handled to imported among BIM systems, tunnel model is actually applied according to different
Work condition carries out the fractionation and planning of model, the programming project for different tunnel models is formed, to improve constructing tunnel work
After finishing tunnel model division, by the automatic hooking method of PBS structures, construction is carried out to tunneling data model for journey efficiency
Plan as a whole to arrange with data name, construction and data name are planned as a whole to the tunneling data model after arranging and carry out export operation, it is above-mentioned
Description presents working links of the PBS in whole BIM, and the tunnel model in construction is divided, and there is important guidance to anticipate
Justice.
S2-3 combines according to the cross section parameter of input, calculates tunnel section outline excavation;By way of sweeping along
Tunnel center line by tunnel section outline excavation sweeping at excavation face, then by excavation face with excavate body according to first left and right sides base tunnel after
Upper and lower sequence carries out Boolean calculation, obtains and excavates results model.
As shown in figure 3, the step of using S2-3 for conventional tunnel shape carries out constructing operation, tunneling data mould is drawn
Type;
After tunneling data model is divided, is mounted, be as follows automatically by PBS:
1. reading in PBS data;According to PBS codings, the data row of PBS descriptions, PBS classification, to PBS data in Excel
It carries out tissue and reads in system;The PBS data of importing include column heading, and wherein PBS codings are prerequisite data row;If leading
Enter PBS data other than PBS codings, description, classification, includes also the information such as attribute or quantities, correspondence need to be added to
PBS after;Without any requirement for the sequence of data row tissue, random order data row tissue is all supported to import and identify;
It supports single PBS to import, also PBS quantities is supported to import simultaneously.
2. mapping data row;The PBS data of importing are arranged the data of PBS codings, PBS descriptions, PBS classification,
Carry out one-to-one mapping;
3. structured coding samples of the typing PBS per level-one;PBS encodes sample and supports:Engineering project, construction unit, branch
6 engineering, subdivisional work, element project, construction cell ranks;
Arbitrary rank number is carried out for PBS codings to import,
Actual coding rank 1=engineering projects+construction unit;
Actual coding rank 2=engineering projects+construction unit+partitioned project;
Actual coding rank 3=engineering projects+construction unit+partitioned project+subdivisional work;
Actual coding rank 4=engineering projects+construction unit+partitioned project+subdivisional work+element project;
Actual coding rank 5=engineering projects+construction unit+partitioned project+subdivisional work+element project+construction cell;
Wherein engineering project does not insert coding sample, to generate an interim root node, in preview function, to the root
Node is automatically corrected, and sets engineering project to root node.
4. being mounted automatically;Automatically each level structure is calculated, organizes sub- father node relationship automatically;
Specified data row are extracted from PBS data pools, are put into valid data pond;
Six engineering project, construction unit, partitioned project, subdivisional work, element project, construction cell ranks are obtained successively
Sample encodes;According to coding sample parsing coding placeholder, algorithm is:
If being encoded to Cur_Code before PBS coding broomrapes, PBS coding row are next to be encoded to Next_Code;
So traversal PBS codings row, if Cur_Code_Len!Then placeholder ReplaceChar is=Next_Code_Len
Null character string, at this moment the digit in PBS codings per level encoder is all different, and wherein Cur_Code_Len is previous volume
Code character string length, Next_Code_Len are the latter code character string length;
It is equipotential PBS codings if Cur_Code_Len==Next_Code_Len, at this moment PBS encodes each rank
Number of encoding bits are the same, for the insufficient digit of each rank, use some specific placeholder for supplement, such as 0;It is right at this time
Each character of PBS codings is traversed:If:It is Cur_Code_C, Next_ in the character of the same position J, Cur_Code
The character of Code is Next_Code_C;If Cur_Code_C!=Next_Code_C, Next_Code_C are placeholder
ReplaceChar;Parse the number of encoding bits of the PBS coding each ranks of sample;According to coding sample parsing coding placeholder, calculate
Method is:If placeholder ReplaceChar is empty string, every grade of number of encoding bits are actual coding sample digit;If placeholder
ReplaceChar is not empty string, then needs the digit that placeholder is weeded out to every grade of coding sample;According to placeholder, each level
Several searched successively from top to bottom PBS codings matches, and first searches father node fNode, the attribute of tissue father node fNode and
Other data, and the attribute of father node fNode and other data are bound with PBS codings;Search the next stage node of father node
Set vChildren, and vChildren is articulated under fNode;Until the subclass vChildren of lookup is that empty end is looked into
Look for matching;
5. PBS structure previews;Preview function is provided to the PBS structures mounted.
The tunneling data model that PBS mountings are completed is subjected to export operation, steps are as follows for specific execution:
(i), selection engineering construction model export format and the corresponding version of engineering construction model export format;
(ii), according to the engineering construction model of selection, its engineering construction model data institutional framework is traversed, and apply to this engineering
Work model data institutional framework is classified, and mode classification assembles for Product, Part parts, Body bodies;
(iii), according to the engineering construction model data institutional framework got, and the new model data knot of tissue of needs
Structure, group weave the model institutional framework of new needs;
(iv), according to the model data institutional framework got, and got after classifying to model data institutional framework
Corresponding model attributes data and model figure entity B-Rep data, fill out corresponding engineering construction model data knot of tissue respectively
In structure;It is required according to construction work model data institutional framework, and divided after classifying to design result model data institutional framework
The correspondence model attributes data and model figure B-Rep data not obtained, are filled into corresponding engineering construction model data group respectively
Knit each class node of structure;It is required according to construction work model data, engineering construction model, the geometry entity of design result model
Data are made of model geometric model and constructive geometry construction two parts, and wherein model geometric refers to that topological class refers to
To class, do not include specific shape information, constructive geometry refers to the statement in model geometric, including actual shape information,
The relationship of model geometric and constructive geometry is as follows:Wherein abstract geometry corresponds to model geometric, and specific geometry corresponds to constructive geometry;Root
According to the requirement of construction work model data, the export of engineering construction model data needs to carry out precision and model space control, and engineering is applied
Precision derived from work model data and model space control formula are as follows:
Set A:Bare minimum (10e-6)
B:Minimum value of standardizing (10e-10)
C:The approximation accuracy (10e-3) of curve and surface
D:It is considered as zero maximum value (10e-11)
Model space computational algorithm:
Model space=A/B=10e-6/10e-10=10e4.
(v), format is exported according to the engineering construction model of selection and export format corresponds to version, the engineering that will be got
Engineering construction model attributes data and figure B-Rep data in construction model data organizational structure and each taxonomic structure are led
Go out.
As shown in Figures 4 and 5, wherein also being emulated in specific execution operation for rectangular tunnel or prismatic tunnel
Experiment equally uses the step of S3-4 new-type tunnel model and carries out execution operation, and the double side wall of the tangible present invention is led
In the implementation procedure of hole method tunnel excavation dividing elements, the process split is completely the same, finally can also realize corresponding effect
Fruit is converted tunnel-shaped according to different arrangement and method for construction for future, is drawn using the two side-wall pilot tunnel tunnel excavation unit
Timesharing is equally realized and quickly splits model, to play significant directive significance to actual constructing tunnel engineering.
The data that above-mentioned steps use need to carry out the acquisition operation of data successively, can be accurately obtained construction in this way
The engineering material data that each stage needs, can ensure project estimates precision.And for its configuration of different data
Content simultaneously differs, this needs just access above-mentioned working method according to continuous experiment.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that:Not
In the case of being detached from the principle of the present invention and objective a variety of change, modification, replacement and modification can be carried out to these embodiments, this
The range of invention is limited by claim and its equivalent.