CN108266209A - A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part - Google Patents

A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part Download PDF

Info

Publication number
CN108266209A
CN108266209A CN201711480958.5A CN201711480958A CN108266209A CN 108266209 A CN108266209 A CN 108266209A CN 201711480958 A CN201711480958 A CN 201711480958A CN 108266209 A CN108266209 A CN 108266209A
Authority
CN
China
Prior art keywords
layer
excavates
construction
ledge
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711480958.5A
Other languages
Chinese (zh)
Inventor
方涛
黄朝根
刘橙
朱黎理
陶旭
林苏义
吴德海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ranken Railway Construction Group Co Ltd
Original Assignee
Ranken Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ranken Railway Construction Group Co Ltd filed Critical Ranken Railway Construction Group Co Ltd
Priority to CN201711480958.5A priority Critical patent/CN108266209A/en
Publication of CN108266209A publication Critical patent/CN108266209A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses the rapid constructing method that a kind of big ledge method in large section subway station excavates lower part, do after ledge two serves as a contrast, middle and lower part is constructed using the suitable digging formula mode of layer and section, excavation by troughs AT STATION, construct the specific steps are:(1), station is divided into multistage according to station length, and is multilayer by station lower middle portion according to height;(2), the first layer of first segment draws first layer bracket groove, open the first Ma Kou job-hoppings, then the soil at both sides of first layer bracket groove is excavated, it performs preliminary bracing and side wall two serves as a contrast, and erection bracing members are carried out to first layer, other layers under first layer carry out the construction such as first layer, bottomed until digging first segment;(3), such as step (2) carries out remaining section of construction.Present invention segmentation excavation by troughs, multiple work surfaces are constructed simultaneously, accelerate construction speed while construction safety is ensured, while reduce against construction joint is done, waterproof quality preferably ensures at structure construction seam.

Description

A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part
Technical field
The present invention relates to underground structrue engineering technical fields, and in particular to a kind of big ledge method in large section subway station is opened Dig down the rapid constructing method in portion.
Background technology
Contrary sequence method or the construction of PBA engineering methods in the generally use ledge hole of large section tunneling subway station.This two methods is applied Work safety coefficient is high, and sedimentation and deformation is small, but construction speed is slow, and construction period can not be met in duration anxiety.And substep is opened It is larger to two lining structures (waterproof, the reinforcing bar, concrete etc.) destruction constructed during digging, quality requirement can not be met, be later stage matter Measuring defect processing increases difficulty.
Patent application CN201210129678.0, which is disclosed, builds super Shallow Large Span tunneling subway in a kind of rocky stratum The joist ledge method at station, joist and two lining phase separations in this method, the whole stressed effect of joist is poor in construction work, and Joist construction is carried out at the same time with excavation supporting operation, and construction interference is larger, and construction quality hardly results in guarantee, therefore this method is simultaneously Suitable for the construction of large section tunnel.
Invention content
Present invention aims at the rapid constructing method for providing a kind of big ledge method in large section subway station and excavating lower part, Solve the problems, such as that joist is integrally difficult to ensure that by force difference, construction quality.
The present invention is achieved through the following technical solutions:
A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part, after doing the lining of ledge two, in vehicle Stand middle and lower part using layer and section, excavation by troughs suitable digging formula mode construct, construct the specific steps are:
(1), station is divided into multistage according to station length, and is multilayer by station lower middle portion according to height;
(2), the first layer of first segment draws first layer bracket groove, opens the first Ma Kou job-hoppings, then excavates the two of first layer bracket groove The side soil body, performs preliminary bracing and side wall two serves as a contrast, and carries out erection bracing members to first layer, other under first layer Layer carries out the construction such as first layer, until digging first segment is bottomed, does inverted arch, side wall and middle plate;
(3), such as step (2) carries out the excavation construction of remaining section, does station internal structure after the completion.
Before the lining construction of ledge two is done, ledge excavation is carried out:It is constructed using two side-wall pilot tunnel, first excavates left and right pilot tunnel, Intercalated nucleus cubsoil part is excavated again.
Height between first layer and the second layer is equal.The setting of layer height can facilitate field operation, ensure construction Quality.
From top to bottom, the gradient of each layering increases with the increase of depth.
The gradient of first Ma Kou job-hoppings is 45 degree.
When excavating the second layer, the gradient of the second Ma Kou job-hoppings is 60 °.In the present invention, both first layer and the second layer slope Degree setting can ensure well width in meeting, it is ensured that construction quality is effectively controlled
When excavating undermost bracket groove, the kerve construction undermost bracket groove of section:It is symmetrically set between slot bottom and side wall It is equipped with grouting rock bolt, the angle of grouting rock bolt and slot bottom is 70 °.
Excavation by troughs section width is unsuitable long for the first time, long to avoid the lining overhanging of ledge two, increases the risk of side wall unstability, Its length should also meet driving harden structure construction length more than one across (9.12m) simultaneously, and meet related specifications and construct to beam, plate It stitches the requirement of indwelling and job-hopping Duan Yuwei excavates intersegmental working space requirement;Therefore job-hopping segment length control for the first time is in 18m~24m It is advisable, residue job-hopping segment length can slightly be grown, and in addition job-hopping section avoids openings position as possible for the first time.
Station big ledge of the invention of first constructing, then station middle and lower part layer and section excavation by troughs, first performs first layer side Wall two serves as a contrast, to set up bracing members.Re-segmenting excavates remainder, performs excavation segment structure using along the practice, middle plate has performed Inner support is shaped as, remaining paragraph is finally excavated, performs two lining structures and internal structure.It can ensure entire tunnel in work progress The globality stressed effect in road, the interference by each step in extraneous and construction is minimum in the construction process, rhythm of constructing It can ensure construction quality while fast.
To ensure the density of side wall horizontal construction joint concrete, it is close to the pre-buried Full-face pouring pipe of construction joint.Side wall mould Plate oblique notches in construction joint position, and skewed slot is risen when horizontal construction joint 30cm, casting concrete, and concrete needs superfilled 30cm Height, in the process vibration compacting.
The present invention is compared with CN201210129678.0, and longeron is set in two linings in the present invention, is served as a contrast together with arch two It performs, globality stressed effect is good, and construction interference is small, and construction quality is effectively ensured.
Difficult point in the present invention is:1st, the Forming Quality of big ledge arch springing basal plane is controlled;2nd, middle and lower part side wall excavates When, it is necessary to out break is controlled, reduces country rock disturbance, ensures the integrality of country rock as possible;And it is exactly based on the construction of the present invention Way:The first construction big ledge in station, then station middle and lower part layer and section excavation by troughs, first performs first layer side wall two and serves as a contrast, with Just bracing members are set up.Re-segmenting excavates remainder, performs excavation segment structure using along the practice, middle plate performs completion and forms interior prop up Support finally excavates remaining paragraph, performs two lining structures and internal structure, just overcome above-mentioned difficult point.
Compared with prior art, the present invention it has the following advantages and advantages:
Present invention segmentation excavation by troughs, multiple work surfaces are constructed simultaneously, and construction is accelerated while construction safety is ensured Progress, Multi-working-surface independently working influence each other small, and small, guarantee construction quality is influenced on molding structure.
Description of the drawings
Attached drawing described herein is used for providing further understanding the embodiment of the present invention, forms one of the application Point, do not form the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is vertical structure schematic diagram in station of the present invention.
Fig. 2 is the vertical layered excavation schematic diagram in station of the present invention;
Fig. 3~Figure 12 is that each step in the embodiment of the present invention corresponds to schematic diagram.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation are only used for explaining the present invention, do not make For limitation of the invention.
In embodiment, the number of plies and hop count are only as illustrating that technical scheme of the present invention carries out
Embodiment 1
As shown in Figure 1 and Figure 2,
Step 1, the big ledge in station is excavated, construction ledge two serves as a contrast;
Step 2 draws bracket groove to excavate A1 areas shown in Fig. 3;
Step 3, shown in Fig. 4, left and right sides A2 areas in the middle part of excavation by troughs section are constructed from top to down with digging with branch;
Step 4 shown in Fig. 5, performs A2 areas abutment wall two and serves as a contrast, and excavates B1 areas;Height phase between first layer and the second layer Deng.
From top to bottom, the gradient of each layering increases with the increase of depth.
The gradient of first Ma Kou job-hoppings is 45 degree.
When excavating the second layer, the gradient of the second Ma Kou job-hoppings is 60 °.
Step 5, shown in Fig. 6, at left and right sides of excavation by troughs section middle and lower part B2 areas, are constructed from top to down with digging with branch;It opens When digging undermost bracket groove, the kerve construction undermost bracket groove of section:Mortar anchor is symmetrically arranged between slot bottom and side wall The angle of bar, grouting rock bolt and slot bottom is 70 °.
Step 6 shown in Fig. 7, sets up bracing members;
Step 7, shown in Fig. 8, kerve construction section bracket groove C1 areas;
Step 8, shown in Fig. 9, at left and right sides of excavated section lower part C2 areas, are constructed from top to down with digging with branch;
Step 9 shown in Figure 10, performs inverted arch;
Step 10, shown in Figure 11, apply station B2, C2 area side wall and minus two floor driving harden structure (beam, plate, column, rail are against the wind Road).Then remove bracing members.
Step 11 shown in Figure 12, performs station internal structure.
In this implementation, before the lining construction of ledge two is made in, ledge excavation is carried out:It is constructed using two side-wall pilot tunnel, first Left and right sides pilot tunnel is excavated, then excavates mid-board part, when carrying out left and right sides pilot tunnel lower part excavation, need to be drilled with along side wall excavation line One row's shock relieve vent, the spacing between shock relieve vent is 2~3 times of shock relieve vent aperture two-by-two.
To ensure the density of side wall horizontal construction joint concrete, it is close to the pre-buried Full-face pouring pipe of construction joint.Side wall mould Plate oblique notches in construction joint position, and skewed slot is risen when horizontal construction joint 30cm, casting concrete, and concrete needs superfilled 30cm Height, in the process vibration compacting.
Above-described specific embodiment has carried out the purpose of the present invention, technical solution and advantageous effect further It is described in detail, it should be understood that the foregoing is merely the specific embodiment of the present invention, is not intended to limit the present invention Protection domain, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (9)

1. a kind of big ledge method in large section subway station excavates the rapid constructing method of lower part, which is characterized in that does ledge two After lining, AT STATION middle and lower part using layer and section, excavation by troughs suitable digging formula mode construct, construct the specific steps are:
(1), station is divided into multistage according to station length, and is multilayer by station lower middle portion according to height;
(2), the first layer of first segment draws first layer bracket groove, opens the first Ma Kou job-hoppings, then excavates the both sides soil of first layer bracket groove Body, performs preliminary bracing and side wall two serves as a contrast, and carries out erection bracing members to first layer, other layers under first layer, into The construction of row such as first layer, until digging first segment is bottomed, does inverted arch, side wall and middle plate;
(3), such as step (2) carries out the excavation construction of remaining section, does station internal structure after the completion.
2. the big ledge method in large section subway station according to claim 1 excavates the rapid constructing method of lower part, special Sign is, before the lining construction of ledge two is done, carries out ledge excavation:It is constructed using two side-wall pilot tunnel, first excavates left and right sides pilot tunnel, Mid-board part is excavated again.
3. the big ledge method in large section subway station according to claim 1 excavates the rapid constructing method of lower part, special Sign is that the height between first layer and the second layer is equal.
4. the big ledge method in large section subway station according to claim 1 excavates the rapid constructing method of lower part, special Sign is that from top to bottom, the gradient of each layering increases with the increase of depth.
5. the big ledge method in large section subway station according to claim 4 excavates the rapid constructing method of lower part, special Sign is that the gradient of the first Ma Kou job-hoppings is 45 degree.
6. the big ledge method in large section subway station according to claim 4 excavates the rapid constructing method of lower part, special Sign is, when excavating the second layer, the gradient of the second Ma Kou job-hoppings is 60 °.
7. the big ledge method in large section subway station according to claim 1 excavates the rapid constructing method of lower part, special Sign is, when excavating to undermost bracket groove, the kerve construction undermost bracket groove of section:It is symmetrical arranged between slot bottom and side wall There is a grouting rock bolt, the angle of grouting rock bolt and slot bottom is 70 °.
8. the big ledge method in large section subway station according to claim 1 excavates the rapid constructing method of lower part, special Sign is that station longitudinal divisions job-hop segment length control in 9~24m for the first time.
9. the big ledge method in large section subway station according to claim 2 excavates the rapid constructing method of lower part, special Sign is, when carrying out left and right sides pilot tunnel lower part excavation, row's shock relieve vent need to be drilled with along side wall excavation line, two-by-two between shock relieve vent Spacing be 2~3 times of shock relieve vent aperture.
CN201711480958.5A 2017-12-29 2017-12-29 A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part Pending CN108266209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711480958.5A CN108266209A (en) 2017-12-29 2017-12-29 A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711480958.5A CN108266209A (en) 2017-12-29 2017-12-29 A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part

Publications (1)

Publication Number Publication Date
CN108266209A true CN108266209A (en) 2018-07-10

Family

ID=62773125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711480958.5A Pending CN108266209A (en) 2017-12-29 2017-12-29 A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part

Country Status (1)

Country Link
CN (1) CN108266209A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441478A (en) * 2018-10-09 2019-03-08 黄河勘测规划设计有限公司 The advanced leverage of IV class of tunnel, V class surrounding rock encircles damping reinforcement method
CN109854280A (en) * 2019-03-05 2019-06-07 中铁工程设计咨询集团有限公司 Core Soil bearing-type support system and its construction method for tunneling subway station
CN110159323A (en) * 2019-05-09 2019-08-23 中国葛洲坝集团第一工程有限公司 The construction method fixed with steel arch-shelf is excavated suitable for extra-large cross-section underground chamber
CN110486036A (en) * 2019-08-26 2019-11-22 中建隧道建设有限公司 A kind of first branch ledge method construction method of expansion arch springing
CN110735656A (en) * 2019-09-26 2020-01-31 重庆市轨道交通设计研究院有限责任公司 Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN110939472A (en) * 2019-12-24 2020-03-31 中矿金业股份有限公司 Construction method of large-section ultrahigh chamber
CN111577325A (en) * 2020-04-20 2020-08-25 中铁十二局集团有限公司 Construction method for arch bridge type arc middle plate of underground excavation station
CN112065470A (en) * 2020-09-23 2020-12-11 中铁四局集团有限公司 Cave depot tank body excavation method
CN114109450A (en) * 2021-10-20 2022-03-01 中铁十局集团第一工程有限公司 Construction method of arch cover type subway station arch springing

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11223099A (en) * 1998-02-09 1999-08-17 Ohbayashi Corp Construction method for large-scale cave structure
CN101440708A (en) * 2008-12-19 2009-05-27 中建国际建设有限公司 PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN102644466A (en) * 2012-04-27 2012-08-22 北京城建设计研究总院有限责任公司 Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN106761778A (en) * 2017-01-24 2017-05-31 山东大学 A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11223099A (en) * 1998-02-09 1999-08-17 Ohbayashi Corp Construction method for large-scale cave structure
CN101440708A (en) * 2008-12-19 2009-05-27 中建国际建设有限公司 PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN102644466A (en) * 2012-04-27 2012-08-22 北京城建设计研究总院有限责任公司 Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN106761778A (en) * 2017-01-24 2017-05-31 山东大学 A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
游水涛: "重叠换乘大拱脚暗挖地铁车站施工方案优化研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441478B (en) * 2018-10-09 2020-04-28 黄河勘测规划设计研究院有限公司 Method for damping and reinforcing IV-type and V-type surrounding rock advanced rod system arch of tunnel
CN109441478A (en) * 2018-10-09 2019-03-08 黄河勘测规划设计有限公司 The advanced leverage of IV class of tunnel, V class surrounding rock encircles damping reinforcement method
CN109854280A (en) * 2019-03-05 2019-06-07 中铁工程设计咨询集团有限公司 Core Soil bearing-type support system and its construction method for tunneling subway station
CN109854280B (en) * 2019-03-05 2023-09-15 中铁工程设计咨询集团有限公司 Core soil bearing type supporting system for underground excavation of subway station and construction method thereof
CN110159323A (en) * 2019-05-09 2019-08-23 中国葛洲坝集团第一工程有限公司 The construction method fixed with steel arch-shelf is excavated suitable for extra-large cross-section underground chamber
CN110486036A (en) * 2019-08-26 2019-11-22 中建隧道建设有限公司 A kind of first branch ledge method construction method of expansion arch springing
CN110486036B (en) * 2019-08-26 2021-08-03 中建隧道建设有限公司 Construction method for expanding arch foot primary support arch cover method
CN110735656B (en) * 2019-09-26 2021-12-24 重庆市轨道交通设计研究院有限责任公司 Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN110735656A (en) * 2019-09-26 2020-01-31 重庆市轨道交通设计研究院有限责任公司 Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN110939472A (en) * 2019-12-24 2020-03-31 中矿金业股份有限公司 Construction method of large-section ultrahigh chamber
CN111577325A (en) * 2020-04-20 2020-08-25 中铁十二局集团有限公司 Construction method for arch bridge type arc middle plate of underground excavation station
CN112065470A (en) * 2020-09-23 2020-12-11 中铁四局集团有限公司 Cave depot tank body excavation method
CN114109450A (en) * 2021-10-20 2022-03-01 中铁十局集团第一工程有限公司 Construction method of arch cover type subway station arch springing
CN114109450B (en) * 2021-10-20 2023-05-16 中铁十局集团第一工程有限公司 Construction method of arch cover type subway station arch foot

Similar Documents

Publication Publication Date Title
CN108266209A (en) A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN205742213U (en) Foundation pit supporting construction
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN102758632A (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN104632227B (en) Subway station excavation technology of single-layer beam arch structure
CN110130927A (en) A kind of carbonaceous slate serious deformation control construction method
CN110439571A (en) Flat pilot tunnel leads to the adit construction method and transverse passage-way of main tunnel
CN107905814B (en) Large span loess tunnel top bar CD construction method
CN105781582A (en) Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN102287194B (en) Construction method of multi-span gently arc tunnel
CN106968691A (en) Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel
CN107288642A (en) PBA construction technologies
CN105545323A (en) Construction method for open cut tunnel lining
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN108266191A (en) A kind of multiple-arch tunnel optimized construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180710

RJ01 Rejection of invention patent application after publication