CN108265716A - One kind can tuning multifunction vibration plant stake device and its construction method - Google Patents

One kind can tuning multifunction vibration plant stake device and its construction method Download PDF

Info

Publication number
CN108265716A
CN108265716A CN201611259455.0A CN201611259455A CN108265716A CN 108265716 A CN108265716 A CN 108265716A CN 201611259455 A CN201611259455 A CN 201611259455A CN 108265716 A CN108265716 A CN 108265716A
Authority
CN
China
Prior art keywords
mast
steel pipe
vibration
tuning
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611259455.0A
Other languages
Chinese (zh)
Inventor
谢晓东
周玉石
张群
谢曙东
谢益飞
赵伟明
黄立伟
鲍国强
汤武
刘泽海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai City Ground Ground Design Co Ltd
SHANGHAI CHENGDI CONSTRUCTION CO Ltd
Original Assignee
Shanghai City Ground Ground Design Co Ltd
SHANGHAI CHENGDI CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City Ground Ground Design Co Ltd, SHANGHAI CHENGDI CONSTRUCTION CO Ltd filed Critical Shanghai City Ground Ground Design Co Ltd
Priority to CN201611259455.0A priority Critical patent/CN108265716A/en
Publication of CN108265716A publication Critical patent/CN108265716A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/18Placing by vibrating

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

One kind can tuning multifunction vibration plant stake device, described device include aircraft nose, mast, vibration hammer, steel pipe and prefabricated pile, fore-stock, Auxiliary support, crawler type host, after-poppet, counterweight, main winch, adjustable intermediate support, driver's cabin, inclinometer.The aircraft nose is mounted on mast top, it is connected by master winch system with crawler type host, the mast is connected by adjustable intermediate support system with crawler type host, and it is arranged at an angle, the vibration hammer is mounted on mast, the pulley on aircraft nose top is connected by steel wire rope, steel wire rope drives vibration hammer to be moved on the sliding rail of mast, and the steel pipe and prefabricated pile are clamped on vibration hammer.It is an advantage of the invention that:Easy construction, flow is simple, at low cost;Pile body construction length is deep, and effect is fast;Swivel base and adjustable intermediate support design can meet planar 360 degree, oblique 15 °~90 ° random angle constructions, wide adaptation range.

Description

One kind can tuning multifunction vibration plant stake device and its construction method
Technical field
The invention belongs to base pit engineering technical fields, and in particular to one kind can tuning multifunction vibration plant and stake device and its apply Work method.
Background technology
The beaer that steel pipe combination soil cement is formed is widely used in building engineering field, and construction method is usually Steel pipe is first inserted by soil body predetermined depth using slotting steel pipe mechanical, is then injected using grouting equipment to steel pipe bottom a certain amount of Cement mortar makes it form soil cement enlarged body in steel pipe bottom a certain range, and then forms the steel pipe with certain bearing capacity Soil cement beaer.When soil strength is excessively high, and steel pipe is inserted into difficult, need to first carry out that drilling power traction hole is used to rub to reduce the soil body Resistance is wiped, steel pipe is then inserted into soil body predetermined depth with slotting steel pipe mechanical, is then injected using grouting equipment to steel pipe bottom A certain amount of cement mortar makes it form soil cement enlarged body in steel pipe bottom a certain range, and then is formed to have and centainly carry energy The steel pipe soil cement beaer of power.It can be seen that the construction process of conventional method is cumbersome, it is related to a variety of construction equipments, construction efficiency Low, of high cost, bearing capacity ability is small.
Invention content
According to the deficiencies of the prior art described above, It is an object of the present invention to provide one kind can the plant stake of tuning multifunction vibration Device and its construction method, easy construction, flow is simple, and it is few to be related to construction equipment, at low cost;Pile body construction length is deep, effect Soon;Swivel base and adjustable intermediate support design can meet planar 360 degree, and oblique 15 °~90 ° random angle constructions adapt to model It encloses wide.
The object of the invention realization is completed by following technical scheme:
One kind can tuning multifunction vibration plant stake device, described device includes aircraft nose, mast, vibration hammer, steel pipe and pre- Stake processed, fore-stock, Auxiliary support, crawler type host, after-poppet, counterweight, main winch, adjustable intermediate support, driver's cabin, angle Instrument etc., the aircraft nose are mounted on mast top, are connected by main winch with crawler type host, and the mast is by can Intermediate supports is adjusted to be connected with crawler type host, and be arranged at an angle, the vibration hammer is mounted on mast, passes through steel wire rope The pulley on aircraft nose top is connected, steel wire rope drives vibration hammer to be moved on the sliding rail of mast, the steel pipe and prefabricated pile holder It holds on vibration hammer, the fore-stock, after-poppet are separately mounted on crawler type host on front and back position, and the counterweight is placed on On crawler type host, play the role of balancing drilling machine.
The vibration hammer clamping steel pipe and the size of prefabricated pile are in 300~1200mm.
There is sliding rail on the mast, sliding rail is round rod iron.
There is pulley on the aircraft nose.
The mast is connected, and be arranged at an angle by adjustable intermediate support system with crawler body, angle for 15 °~ 90°。
Inclinometer is installed on the mast.
The device is adapted to construction steel pipe, pile pile, steel pipe composite pile, precast construction engineering pile.
For described device when being constructed, the vibration hammer holds steel pipe and prefabricated pile, in vibration hammer hydraulic pressurization Under impact, the steel pipe and prefabricated pile sink to the soil body, and its step are as follows:
1) smooth construction site releases real sample according to construction drawing;
2) start can tuning multifunction vibration plant stake device, device moves to the foundation pit enclosure structure region constructed;
3) jet grouting pile driving machine is in place, and turn on the power device, according to a real sample piece cement mixing method of oblique construction;
4) can tuning multifunction vibration plant stake device it is in place, according to construction drawing require adjust mast angle, and will auxiliary Support is opened, it is made to be tight contacted between with construction surface, stiffening device balance quality makes it meet construction requirement;
5) pedrail crane is in place, and steel pipe and prefabricated pile are sling and are placed on device mast, and vibration hammer adjusts clamper will Steel pipe and prefabricated pile clamp;
6) start Power Component, steel pipe and prefabricated pile are pressed into predeterminated position by vibration hammer pressurization and vibration by construction requirement;
7) after steel pipe and prefabricated pile sink to predetermined depth, the connection of vibration hammer and steel pipe is disengaged, vibration hammer is in master file Under the pulling for raising machine steel wire rope, resetted along mast guide rail;
8) can tuning multifunction vibration plant stake device and move to next group of construction, repeat step 3~step 7 and construct next steel Pipe and prefabricated pile.
It is an advantage of the invention that:
It is 2 times of conventional piles machine speed of application, construction efficiency is high, at low cost 1. pile sinking speed is fast.
2. swivel base and adjustable intermediate support design can meet planar 360 degree, oblique 15 °~90 ° random angles are constructed, Wide adaptation range.
3. vibration hammer clamping range adapts to the various steel pipes of 300~1200mm, the precast constructions stake such as pile pile, bamboo joint pile.
Description of the drawings
Fig. 1 is can tuning multifunction vibration plant stake schematic device
Behind 1 aircraft nose, 2 masts, 3 vibration hammers, 4 steel pipes and prefabricated pile, 5 fore-stocks, 6 Auxiliary supports, 7 crawler type hosts, 8 Stent, 9 counterweights, 10 main winch, 11 adjustable intermediate supports, 12 driver's cabins, 13 inclinometers, 14 sliding rails, 15 guide rails
Fig. 2 is can the oblique steel pipe schematic diagram of tuning multifunction vibration plant stake device construction
16 can tuning multifunction vibration plant stake device, 17 foundation pit enclosure structures, 18 cement mixing methods
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to Following embodiments.
Embodiment
As shown in Figure 1, one kind can tuning multifunction vibration plant stake device 16, described device includes aircraft nose 1, mast 2, shakes Dynamic hammer 3, steel pipe and prefabricated pile 4, fore-stock 5, Auxiliary support 6, crawler type host 7, after-poppet 8, counterweight 9, main winch 10, can Adjust intermediate supports 11, driver's cabin 12, inclinometer 13, the aircraft nose 1 be mounted on 2 top of mast, by main winch 10 with Crawler type host 7 is connected, and the mast 2 is connected, and angled cloth by adjustable intermediate support 11 with crawler type host 10 It puts, the vibration hammer 3 is mounted on mast 2, and the pulley 15 on 1 top of aircraft nose is connected by steel wire rope, and steel wire rope drive is shaken Dynamic hammer moves on the sliding rail of mast, and the steel pipe and prefabricated pile are clamped on vibration hammer, the fore-stock, after-poppet difference On front and back position on crawler type host, the counterweight is placed on crawler type host, plays the role of balancing drilling machine.
It is according to the present invention it is a kind of can tuning multifunction vibration plant the construction method of stake device 16, its step are as follows:
1) smooth construction site releases real sample according to construction drawing;
2) start can tuning multifunction vibration plant stake device 16, device moves to 17th area of foundation pit enclosure structure to have constructed Domain;
3) jet grouting pile driving machine is in place, and turn on the power device, according to a real sample piece cement mixing method 18 of oblique construction;
4) can tuning multifunction vibration to plant stake device 16 in place, required to adjust mast angle, and will be auxiliary according to construction drawing Support 6 is helped to open, it is made to be tight contacted between with construction surface, stiffening device balance quality makes it meet construction requirement;
5) pedrail crane is in place, and steel pipe and prefabricated pile 4 are sling and are placed on device mast 2, and vibration hammer 3 adjusts clamper Steel pipe and prefabricated pile 4 are clamped;
6) start Power Component, steel pipe and prefabricated pile 4 are pressed into predeterminated position by 3 pressurization and vibration of vibration hammer by construction requirement;
7) after steel pipe and prefabricated pile 4 sink to predetermined depth, the connection of vibration hammer 3 and steel pipe and prefabricated pile 4 is disengaged, is shaken Dynamic hammer 3 resets under the pulling of 10 steel wire rope of main winch system along 2 guide rail of mast;
8) can tuning multifunction vibration plant stake device 16 and move to next group of construction, repeat step 3~step 7 and construct next Steel pipe and prefabricated pile 4.

Claims (8)

1. one kind can tuning multifunction vibration plant stake device, described device includes aircraft nose, mast, vibration hammer, steel pipe and prefabricated Stake, fore-stock, Auxiliary support, crawler type host, after-poppet, counterweight, main winch, adjustable intermediate support, driver's cabin, angle Instrument, the aircraft nose are mounted on mast top, are connected by main winch with crawler type host, the mast passes through adjustable Intermediate supports are connected with crawler type host, and are arranged at an angle, and the vibration hammer is mounted on mast, is connected by steel wire rope The pulley on aircraft nose top is connect, steel wire rope drives vibration hammer to be moved on the sliding rail of mast, the steel pipe and prefabricated holder for pile On vibration hammer, the fore-stock, after-poppet are separately mounted on crawler type host on front and back position, and the counterweight is placed on shoe On belt host, play the role of balancing drilling machine.
2. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that the vibration hammer The size of steel pipe and prefabricated pile is clamped in 300~1200mm.
3. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that have on the mast Sliding rail, sliding rail are round rod iron.
4. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that on the aircraft nose There is pulley.
5. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that the mast passes through Adjustable intermediate support system is connected with crawler body, and is arranged at an angle, and angle is 15 °~90 °.
6. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that on the mast Inclinometer is installed.
7. one kind according to claim 1 can tuning multifunction vibration plant stake device, which is characterized in that the device It is adapted to construction steel pipe, pile pile, steel pipe composite pile, precast construction engineering pile.
8. it is piece according to claim 1 it is a kind of can tuning multifunction vibration plant the construction method of stake device, which is characterized in that For described device when being constructed, the vibration hammer holds steel pipe and prefabricated pile, under the impact of vibration hammer hydraulic pressurization, institute It states steel pipe and prefabricated pile sinks to the soil body, its step are as follows:
1) smooth construction site releases real sample according to construction drawing;
2) start can tuning multifunction vibration plant stake device, device moves to the foundation pit enclosure structure region constructed;
3) jet grouting pile driving machine is in place, and turn on the power device, according to a real sample piece cement mixing method of oblique construction;
4) can tuning multifunction vibration to plant stake device in place, required to adjust mast angle, and by Auxiliary support according to construction drawing It opens, it is made to be tight contacted between with construction surface, stiffening device balance quality makes it meet construction requirement;
5) pedrail crane is in place, and steel pipe and prefabricated pile are sling and are placed on device mast, and vibration hammer adjusts clamper by steel pipe And prefabricated pile clamps;
6) start Power Component, steel pipe and prefabricated pile are pressed into predeterminated position by vibration hammer pressurization and vibration by construction requirement;
7) after steel pipe and prefabricated pile sink to predetermined depth, the connection of vibration hammer and steel pipe is disengaged, vibration hammer is in main winch Under the pulling of steel wire rope, resetted along mast guide rail;
8) can tuning multifunction vibration plant stake device and move to next group of construction, repeat step 3~step 7 construct next steel pipe and Prefabricated pile.
CN201611259455.0A 2016-12-30 2016-12-30 One kind can tuning multifunction vibration plant stake device and its construction method Pending CN108265716A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611259455.0A CN108265716A (en) 2016-12-30 2016-12-30 One kind can tuning multifunction vibration plant stake device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611259455.0A CN108265716A (en) 2016-12-30 2016-12-30 One kind can tuning multifunction vibration plant stake device and its construction method

Publications (1)

Publication Number Publication Date
CN108265716A true CN108265716A (en) 2018-07-10

Family

ID=62753630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611259455.0A Pending CN108265716A (en) 2016-12-30 2016-12-30 One kind can tuning multifunction vibration plant stake device and its construction method

Country Status (1)

Country Link
CN (1) CN108265716A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344414A (en) * 2019-07-12 2019-10-18 刘建军 A kind of pilot hole plant stake piling all-in-one machine
CN112323796A (en) * 2020-11-13 2021-02-05 中建三局集团有限公司 Inclined precast pile construction device and construction method thereof
CN114277800A (en) * 2021-12-29 2022-04-05 胡晓琳 Auxiliary device for placing in steel reinforcement cage hole of rotary digging pile for building construction
CN114438999A (en) * 2022-03-01 2022-05-06 江苏建院营造股份有限公司 Intelligent composite supporting method and system for deep foundation pit with strong support
CN114790738A (en) * 2022-04-24 2022-07-26 广州市建筑科学研究院集团有限公司 Foundation pit supporting construction device and method based on assembled large-diameter tubular piles

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205728A (en) * 2007-12-15 2008-06-25 徐州鹏达科技有限公司 Endless-tracked multifunctional rotary excavating driller
CN101581097A (en) * 2009-05-22 2009-11-18 中交第一航务工程局有限公司 Vibration sinking technology method of large-sized combined steel plate pile
CN102383431A (en) * 2011-04-21 2012-03-21 上海城地建设发展有限公司 Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN102561349A (en) * 2012-02-09 2012-07-11 安徽力达实业股份有限公司 Multifunctional static pile press
CN102644269A (en) * 2012-05-04 2012-08-22 朱建新 Non-earth-borrowing composite pile and construction method thereof
CN203904996U (en) * 2014-04-09 2014-10-29 河南工业大学 Multifunctional hydraulic crawler-type pile driver
CN206512718U (en) * 2016-12-30 2017-09-22 上海城地建设股份有限公司 One kind can tuning multifunction vibration plant stake device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205728A (en) * 2007-12-15 2008-06-25 徐州鹏达科技有限公司 Endless-tracked multifunctional rotary excavating driller
CN101581097A (en) * 2009-05-22 2009-11-18 中交第一航务工程局有限公司 Vibration sinking technology method of large-sized combined steel plate pile
CN102383431A (en) * 2011-04-21 2012-03-21 上海城地建设发展有限公司 Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN102561349A (en) * 2012-02-09 2012-07-11 安徽力达实业股份有限公司 Multifunctional static pile press
CN102644269A (en) * 2012-05-04 2012-08-22 朱建新 Non-earth-borrowing composite pile and construction method thereof
CN203904996U (en) * 2014-04-09 2014-10-29 河南工业大学 Multifunctional hydraulic crawler-type pile driver
CN206512718U (en) * 2016-12-30 2017-09-22 上海城地建设股份有限公司 One kind can tuning multifunction vibration plant stake device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344414A (en) * 2019-07-12 2019-10-18 刘建军 A kind of pilot hole plant stake piling all-in-one machine
CN112323796A (en) * 2020-11-13 2021-02-05 中建三局集团有限公司 Inclined precast pile construction device and construction method thereof
CN114277800A (en) * 2021-12-29 2022-04-05 胡晓琳 Auxiliary device for placing in steel reinforcement cage hole of rotary digging pile for building construction
CN114277800B (en) * 2021-12-29 2023-10-20 浙江培华建设集团有限公司 Auxiliary equipment for placing in rotary pile reinforcement cage hole for building construction
CN114438999A (en) * 2022-03-01 2022-05-06 江苏建院营造股份有限公司 Intelligent composite supporting method and system for deep foundation pit with strong support
CN114790738A (en) * 2022-04-24 2022-07-26 广州市建筑科学研究院集团有限公司 Foundation pit supporting construction device and method based on assembled large-diameter tubular piles

Similar Documents

Publication Publication Date Title
CN108265716A (en) One kind can tuning multifunction vibration plant stake device and its construction method
CN206512718U (en) One kind can tuning multifunction vibration plant stake device
CN101429768B (en) Pre-stress high-strength concrete pipe pile static-pressure construction method
CN108797587A (en) A kind of novel sinking construction technology of static pressed pile
CN103821141B (en) Helical burr ram construction technology
CN102653945A (en) Foundation reinforcing and replacing structure and construction method thereof
CN1963044A (en) Construction method for withdrawal of waste pile
CN109252521A (en) Steel-pipe pile extracts equipment and its construction method in confined space water under girder steel
CN104196015B (en) A kind of construction method of long auger guncreting pile emptying aperture
CN101624825B (en) Static drawing machine
CN104120723A (en) Jetting and drawing-out pile jacking-in method
CN108266122A (en) One kind can the multi-functional middle pick agitation driller of tuning and its construction method
CN204780836U (en) Fixed drilling platform of adjustable floating
CN105604061B (en) A kind of surface unit and its construction method entering rock installation for steel-pipe pile in water
CN102926382A (en) Construction method of soil mixing wall (SMW) engineering method
CN203113332U (en) Anchor rod construction structure device after construction
CN203546793U (en) Cast-in-place pile hole digging and earth taking device
CN108265707A (en) One kind can the multi-functional middle pick of tuning fetch earth and plant stake device and its construction method
CN109339044A (en) A kind of concrete pipe pile construction equipment
CN206512706U (en) One kind can tuning it is multi-functional it is middle pick fetch earth plant stake device
CN205296177U (en) Dado bearing structure suitable for hole friction pile stake hole is dug in manual work
CN105604479B (en) A kind of power construction multifunctional hole-drilling machine
CN104005411A (en) Tubular pile construction method and pile tube structure of tubular pile
CN206769796U (en) One kind can the multi-functional middle pick agitation driller of tuning
CN103866763B (en) Method for making pile by performing pile pressure irrigation through immersed tube and special device and application

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination