CN108251582A - A kind of hot vanadium slag treatment method - Google Patents

A kind of hot vanadium slag treatment method Download PDF

Info

Publication number
CN108251582A
CN108251582A CN201810115614.2A CN201810115614A CN108251582A CN 108251582 A CN108251582 A CN 108251582A CN 201810115614 A CN201810115614 A CN 201810115614A CN 108251582 A CN108251582 A CN 108251582A
Authority
CN
China
Prior art keywords
vanadium slag
flue gas
vanadium
treatment method
hot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810115614.2A
Other languages
Chinese (zh)
Inventor
李钰
董丽萍
赵连琦
毕德方
赵潮洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xuedilong Environmental Engineering Technology Co Ltd
Original Assignee
Beijing Xuedilong Environmental Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Xuedilong Environmental Engineering Technology Co Ltd filed Critical Beijing Xuedilong Environmental Engineering Technology Co Ltd
Priority to CN201810115614.2A priority Critical patent/CN108251582A/en
Publication of CN108251582A publication Critical patent/CN108251582A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B3/00General features in the manufacture of pig-iron
    • C21B3/04Recovery of by-products, e.g. slag
    • C21B3/06Treatment of liquid slag
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B3/00General features in the manufacture of pig-iron
    • C21B3/04Recovery of by-products, e.g. slag
    • C21B3/06Treatment of liquid slag
    • C21B3/08Cooling slag
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22BPRODUCTION AND REFINING OF METALS; PRETREATMENT OF RAW MATERIALS
    • C22B1/00Preliminary treatment of ores or scrap
    • C22B1/005Preliminary treatment of scrap
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22BPRODUCTION AND REFINING OF METALS; PRETREATMENT OF RAW MATERIALS
    • C22B34/00Obtaining refractory metals
    • C22B34/20Obtaining niobium, tantalum or vanadium
    • C22B34/22Obtaining vanadium
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22BPRODUCTION AND REFINING OF METALS; PRETREATMENT OF RAW MATERIALS
    • C22B7/00Working up raw materials other than ores, e.g. scrap, to produce non-ferrous metals and compounds thereof; Methods of a general interest or applied to the winning of more than two metals
    • C22B7/04Working-up slag
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies

Abstract

The present invention relates to industrial waste residue disposal fields, and in particular to a kind of hot vanadium slag treatment method.Mainly include step:It by hot vanadium slag slow cooling 6h~12h, walks and rolls repeatedly, be cooled to≤900 DEG C, granularity is in below 200mm;Vanadium slag secondary cooling is sent after carrying out crushing-magnetic selection again to vanadium extraction processing.The method of the present invention accurately controls vanadium slag temperature retention time, ensure vanadium slag in the case where follow-up vanadium extraction reaches maximum vanadium conversion ratio but also with certain mobility, to avoid the generation that bulk slag sticks together, conducive to follow-up break process.Deslagging and crushing operation are carried out, and set dust removal installation between the vanadium slag processing of closing, avoid pollution of the airborne dust to power house environment.

Description

A kind of hot vanadium slag treatment method
Technical field
The present invention relates to industrial waste residue disposal fields, and in particular to a kind of hot vanadium slag treatment method.
Background technology
The processing mode of vanadium slag is usually the vanadium slag first slow cooling in slag ladle at present, then transports to vanadium slag Treatment stations and carries out heat It sprinkles, then is pounded by water-spraying control, drop weight rammer and vanadium slag to be made to be fragmented into after fritter carry out crushing-magnetic selection processing again.Topple over and drop weight rammer is pounded During can generate a large amount of dust and noise and long processing period, inefficiency occupies a large amount of place.
Research at present about vanadium slag processing is seldom, and the present invention has found that vanadium slag treatment process is improper, meeting in the course of the research Leading to treated, vanadium slag is difficult to be directly entered follow-up process for extracting vanadium, for example it is difficult to take into account vanadium recovery rate and ball milling energy consumption problem. In addition, the slow cooling of vanadium slag makes vanadic spinel particle constantly grow up, and the growing state of vanadic spinel particle directly affects vanadium conversion Rate, slow cooling need suitable temperature and time, and the time is too short to reduce vanadium conversion ratio, and overlong time temperature is too low to cause vanadium slag Crust, topples over difficulty, and forms bulk slag after toppling over and stick together, and needs processing of dropping hammer.
Existing vanadium slag processing mode temperature retention time span is very big, does not carry out accurate time and temperature control, follow-up vanadium The effect of Slag treatment and vanadium conversion ratio is all unstable.
Invention content
The defects of for vanadium slag treatment method, this application provides a kind of efficient hot vanadium slag treatment methods.
The object of the present invention is to provide a kind of hot vanadium slag treatment methods.
The method according to the present invention that hot vanadium slag is handled before converter extracting vanadium, mainly includes the following steps that:
(1) the hot vanadium slag slow cooling that will be come out of the stove, temperature retention time are controlled in 6h~12h;
(2) vanadium slag after slow cooling is shakeout, carries out walking repeatedly and roll;
(3) water-spraying control is carried out to the vanadium slag after rolling, is cooled to≤900 DEG C, granularity is in 200mm hereinafter, selecting slag steel;
(4) by vanadium slag secondary cooling, water-spraying control is within 80 DEG C;
(5) vanadium slag after secondary cooling is crushed to≤50mm, and is sent after selecting bulk slag steel to vanadium extraction processing.
Efficient hot vanadium slag treatment method according to the present invention, wherein, in the step (1), temperature retention time control In 8h~10h.
Efficient hot vanadium slag treatment method according to the present invention, wherein, in the step (3), be cooled to 200 DEG C~ 800℃。
Efficient hot vanadium slag treatment method according to the present invention, wherein, in the step (3), be cooled to 300 DEG C~ 400℃。
Efficient hot vanadium slag treatment method according to the present invention, wherein, in the step (4), pass through rotary type Water cover carries out water-spraying control.
Efficient hot vanadium slag treatment method according to the present invention, in the envelope for being mounted with dry flue gas pipeline and wet flue gas pipeline It closes and implements hot vanadium slag processing procedure in space.
Efficient hot vanadium slag treatment method according to the present invention, dry flue gas and wet flue gas pipe pass through dry flue gas pipeline respectively It is discharged with wet flue gas pipeline, the different phase generated between the dry flue gas pipeline and wet flue gas pipeline according to dry, wet flue gas Carry out automation switching.
Efficient hot vanadium slag treatment method according to the present invention, wherein, the rotary type water cover rotating range is 0~90 °, the row's of setting steam pipe line in rotary cover is discharged by wind turbine auxiliary exhaust from chimney.
Efficient hot vanadium slag treatment method according to the present invention, wherein, it is secondary cold the vanadium slag after rolling is transported to But it during, deslagging and pushes away the dry flue gas of slag generation and is collected by bag filter, the wet cigarette generated during water-spraying control Gas is dusted by acoustic agglomeration facility, and dry and wet flue gas ash removal facility is switched over by automation control.
Specific embodiment according to the present invention can implement the efficient hot vanadium slag processing side in enclosure space Method is equipped with the dedusting pipeline of dry flue gas and wet flue gas in space, has conversion valve between dry flue gas and wet flue gas pipeline, according to place The different phase that dry and wet flue gas generates in reason flow carries out automation switching.
The efficient hot vanadium slag treatment method of the present invention has following technical advantage:
(1) take up little area, can be arranged before the converter extracting vanadium of spaces compact, slag tap, slow cooling, roll broken and secondary cooling it Between Connection between Processes it is close, accurately control the time of each flow.
(2) vanadium slag temperature retention time is accurately controlled, ensures vanadium slag in the case where follow-up vanadium extraction reaches maximum vanadium conversion ratio again Has certain mobility, to avoid the generation that bulk slag sticks together, conducive to follow-up break process.
(3) deslagging and crushing operation are carried out, and set dust removal installation between the processing of the vanadium slag of closing, avoids airborne dust to workshop The pollution of environment.
(4) dry and wet flue gas can be alternately produced in vanadium slag processing procedure, the characteristics of dry flue gas is dust content height (about 3g/ m3), but easily handled by bag filter;The characteristics of wet flue gas is low (the about 100mg/m of dust content3), but bag filter It can not handle.As two kinds of flue gas mixed processings can be brought, line clogging, dust removal installation investment is big, occupation of land is big and a large amount of mud can not The problem of processing.The time point that monitoring dry and wet flue gas of the invention accurate generates, using automation control to dry and wet dust removal installation into Row switching solves the problems, such as mixed flue gas processing and ensures that final smoke emissioning concentration is respectively less than 20mg/m3
(5) vanadium slag roll by the way of mechanization broken, treatment effeciency is high, solves because temperature retention time is long And being formed needs the problem of inefficiency, dust and the noise pollution for handling and bringing are serious and occupation of land is big of dropping hammer after slag sticks together.
(6) broken vanadium slag temperature is rolled at 300~400 DEG C, and setting rotary type water cover had carried out secondary cooling both Can complete vanadium slag be quickly cooled down and fragmentation, and steam can be made to discharge in a organized way.
Description of the drawings
Fig. 1 shows the flow chart of according to embodiments of the present invention 1 hot vanadium slag treatment method.
Fig. 2 shows the vanadium slag roasting conversion rate of different temperature retention times (6h, 8h, 10h, 12h).
Specific embodiment
As shown in Figure 1, the method according to the present invention that hot vanadium slag is handled before converter extracting vanadium, mainly including following step Suddenly:
(1) vanadium slag tank is hung in into slag ladle slow cooling area by overhead traveling crane after converter extracting vanadium slag and carries out slow cooling, temperature retention time point It does not control in 6h, 8h, 10h, 12h;
(2) the vanadium slag tank after slow cooling by overhead traveling crane be hung to vanadium slag processing between, vanadium slag treatment bench is poured onto by ladle tunbler, is passed through It pushes away slag device to shakeout vanadium slag, carries out walking repeatedly to the vanadium slag on treatment bench by rail mounted breaker and roll;
(3) spray equipment between vanadium slag processing carries out water-spraying control to the vanadium slag after rolling, and is cooled to 200 DEG C respectively, 300,400 DEG C, 800 DEG C, 900 DEG C, granularity is in 200mm hereinafter, selecting slag steel;
(4) vanadium slag slot is hoisted to secondary cooling zone, water-spraying control is carried out within 80 DEG C by rotary type water cover;
(5) vanadium slag after secondary cooling is crushed to 50mm hereinafter, and select bulk slag steel send to vanadium extraction handle.
The method according to the present invention that hot vanadium slag is handled before converter extracting vanadium, by pushing away slag device by vanadium slag from treatment bench It is pushed into vanadium slag slot, deslagging and pushes away the dry flue gas generated during slag and collected by bag filter, generated during water-spraying control Wet flue gas be dusted by acoustic agglomeration facility, dry or wet flue gas dust removal installation is switched over by automation control.
Efficient hot vanadium slag treatment method according to the present invention, wherein, the hot vanadium slag slow cooling in tank come out of the stove, to not It is sampled with the vanadium slag under temperature retention time and carries out viscosity test, vanadic spinel particle electron-microscope scanning and roasting vanadium conversion ratio experiment, Result of study shows:It is vanadic spinel granule growth stage within temperature retention time 8h, 8h changes unobvious later;Within slow cooling 8h Slag specimen with temperature retention time extend roasting conversion rate become larger, slow cooling 8h more than vanadium slags roasting conversion rate variation unobvious;It is slow The slag specimen of cold more than 12h is greatly reduced under flowing, viscosity significantly increases, and is easily formed slag and is sticked together, so it is slow to take slow cooling 8h~10h The Best Times of cooling working procedure.
As shown in Fig. 2, vanadium slag roasting conversion rate is obtained when changing over time trend based on the following conditions:
(1) vanadium slag of different temperature retention times is taken.
(2) by vanadium slag sample crushing grinding into -160 mesh powder, magnetic separation terminates until MFe contents are no more than 5%.
(3) according to Na/V (mol)=2 with addition of industrial sodium carbonate, then vanadium slag/residue (butt)=1 is pressed:1 respectively with addition of residual Slag is uniformly mixed.
(4) sample is placed in oxidizing roasting in Muffle furnace, control time:Room temperature to 800 DEG C (30 minutes), 800 DEG C (150 ~170 minutes), 800 DEG C to 600 DEG C (30 minutes).
(5) quick tapping is air-cooled when roasting material and cool to 600 DEG C, to room temperature after be ground to granularity by hand and be no more than 100 mesh.

Claims (9)

1. a kind of hot vanadium slag treatment method, which is characterized in that the described method comprises the following steps:
(1) the hot vanadium slag slow cooling that will be come out of the stove, temperature retention time are controlled in 6h~12h;
(2) vanadium slag after slow cooling is shakeout, carries out walking repeatedly and roll;
(3) water-spraying control is carried out to the vanadium slag after rolling, is cooled to≤900 DEG C, granularity≤200mm selects slag steel;
(4) by vanadium slag secondary cooling, water-spraying control is to≤80 DEG C;
(5) vanadium slag after secondary cooling is crushed to≤50mm, and is sent after selecting bulk slag steel to vanadium extraction processing.
2. hot vanadium slag treatment method according to claim 1, which is characterized in that in the step (1), temperature retention time Control is in 8h~10h.
3. hot vanadium slag treatment method according to claim 1, which is characterized in that in the step (3), be cooled to 200 DEG C~800 DEG C.
4. hot vanadium slag treatment method according to claim 3, which is characterized in that in the step (3), be cooled to 300 DEG C~400 DEG C.
5. hot vanadium slag treatment method according to claim 1, which is characterized in that in the step (4), by that can revolve Rotatable water cover carries out water-spraying control.
6. hot vanadium slag treatment method according to claim 5, which is characterized in that the rotary type water cover rotates model It is 0~90 ° to enclose, the row's of setting steam pipe line in rotary cover.
7. hot vanadium slag treatment method according to claim 1, which is characterized in that be mounted with dry flue gas pipeline and wet cigarette Implement hot vanadium slag processing procedure in the enclosure space of feed channel.
8. hot vanadium slag treatment method according to claim 7, which is characterized in that dry flue gas and wet flue gas pipe pass through respectively Dry flue gas pipeline and wet flue gas pipeline are discharged, and are generated between the dry flue gas pipeline and wet flue gas pipeline according to dry, wet flue gas Different phase carry out automation switching.
9. hot vanadium slag treatment method according to claim 7, which is characterized in that the vanadium slag after rolling is being transported to two It during secondary cooling, deslagging and pushes away the dry flue gas of slag generation and is collected by bag filter, generate during water-spraying control Wet flue gas is dusted by acoustic agglomeration facility.
CN201810115614.2A 2018-02-06 2018-02-06 A kind of hot vanadium slag treatment method Pending CN108251582A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810115614.2A CN108251582A (en) 2018-02-06 2018-02-06 A kind of hot vanadium slag treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810115614.2A CN108251582A (en) 2018-02-06 2018-02-06 A kind of hot vanadium slag treatment method

Publications (1)

Publication Number Publication Date
CN108251582A true CN108251582A (en) 2018-07-06

Family

ID=62744428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810115614.2A Pending CN108251582A (en) 2018-02-06 2018-02-06 A kind of hot vanadium slag treatment method

Country Status (1)

Country Link
CN (1) CN108251582A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109395514A (en) * 2018-10-11 2019-03-01 广州华鑫工程技术有限公司 For handling the device and method for the dust that hot slag generates
CN112458298A (en) * 2020-10-27 2021-03-09 攀钢集团攀枝花钢铁研究院有限公司 Method for extracting vanadium by direct sodium treatment of thermal vanadium slag
CN113198607A (en) * 2021-04-28 2021-08-03 河南省煜晟镍业有限责任公司 Low nickel matte comprehensive treatment method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU881032A1 (en) * 1980-02-20 1981-11-15 Уральский научно-исследовательский институт черных металлов Method of processing blast furnace slag
JPS6017003A (en) * 1983-07-05 1985-01-28 Sumitomo Metal Ind Ltd Treatment of blast furnace slag
JP2005256083A (en) * 2004-03-11 2005-09-22 Nippon Steel Corp Method for cooling iron-making slag
CN102191343A (en) * 2010-03-08 2011-09-21 中冶建筑研究总院有限公司 Aircooled crushing device and method of molten steel slag
CN102676712A (en) * 2012-05-07 2012-09-19 宝钢发展有限公司 Process for cooling stainless steel slag by wet method
CN105838831A (en) * 2016-04-15 2016-08-10 中冶节能环保有限责任公司 Casting residual slag online treatment device and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU881032A1 (en) * 1980-02-20 1981-11-15 Уральский научно-исследовательский институт черных металлов Method of processing blast furnace slag
JPS6017003A (en) * 1983-07-05 1985-01-28 Sumitomo Metal Ind Ltd Treatment of blast furnace slag
JP2005256083A (en) * 2004-03-11 2005-09-22 Nippon Steel Corp Method for cooling iron-making slag
CN102191343A (en) * 2010-03-08 2011-09-21 中冶建筑研究总院有限公司 Aircooled crushing device and method of molten steel slag
CN102676712A (en) * 2012-05-07 2012-09-19 宝钢发展有限公司 Process for cooling stainless steel slag by wet method
CN105838831A (en) * 2016-04-15 2016-08-10 中冶节能环保有限责任公司 Casting residual slag online treatment device and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
戈文荪等: "钒渣余热缓冷试验研究", 《第七届全国能源与热工学术年会》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109395514A (en) * 2018-10-11 2019-03-01 广州华鑫工程技术有限公司 For handling the device and method for the dust that hot slag generates
CN112458298A (en) * 2020-10-27 2021-03-09 攀钢集团攀枝花钢铁研究院有限公司 Method for extracting vanadium by direct sodium treatment of thermal vanadium slag
CN113198607A (en) * 2021-04-28 2021-08-03 河南省煜晟镍业有限责任公司 Low nickel matte comprehensive treatment method

Similar Documents

Publication Publication Date Title
CN101074457B (en) Method for smelting and separating refuse-combustion fly-ash heavy metal
CN108251582A (en) A kind of hot vanadium slag treatment method
CN111826486B (en) High-temperature soft molten steel slag accurate control efficient clean crushing treatment device and method
CN111850194A (en) High-temperature steel slag bottom blowing air cooling crushing waste heat recovery device and method
CN108220610B (en) A kind of processing method of the dedusting ash containing heavy metal
CN112760434A (en) Steel slag treatment process method
CN212426080U (en) Broken waste heat recovery device of forced air cooling is blown at bottom to high temperature slag
CN201852476U (en) Wet dust removal device of Kaldo furnace
CN108130422A (en) A kind of method that valuable metal is extracted in steel plant's flue dust
CN105032890B (en) Barium slag disposal system and processing method
CN105671329A (en) Rotary hearth furnace and method for treating lead-zinc smelting slag
CN102674649A (en) Chemical engineering sludge processing system
CN212560326U (en) High-temperature soft molten steel slag accurate control efficient cleaning and crushing treatment device
CN101352636B (en) Technique for purifying converter gas and removing dust
CN109357268A (en) The process of waste and old paint kettle is handled using the oxygen-enriched natural gas shaft furnace of hot wind
CN216947078U (en) Short-flow thermal state steel slag treatment system
CN209307235U (en) The process units of flyash for concrete blend composition
CN203798180U (en) Calcium carbide furnace calcium carbide sensible heat recovery device
CN215713243U (en) System for improving medium-temperature denitration effect of chain grate machine rotary kiln pellets
CN214666098U (en) Closed full-dry type non-emission waste heat recovery smelting slag treatment system
CN211133498U (en) Equipment for treating waste gas generated by carbonizing blast furnace gas ash and electric furnace ash
CN210242455U (en) Recovery device for smelting production line
CN210085290U (en) Device for granulating molten smelting slag glass and recovering waste heat
CN112797804A (en) Closed full-dry type non-emission waste heat recovery smelting slag treatment system and process
CN204690031U (en) A kind of converter steelmaking electrostatic precipitation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180706

RJ01 Rejection of invention patent application after publication