CN108228984A - Fit up project management system, its method, electronic equipment and computer program product - Google Patents

Fit up project management system, its method, electronic equipment and computer program product Download PDF

Info

Publication number
CN108228984A
CN108228984A CN201711386337.0A CN201711386337A CN108228984A CN 108228984 A CN108228984 A CN 108228984A CN 201711386337 A CN201711386337 A CN 201711386337A CN 108228984 A CN108228984 A CN 108228984A
Authority
CN
China
Prior art keywords
finishing
project
finishing project
user
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201711386337.0A
Other languages
Chinese (zh)
Inventor
陈成华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seize Heavenly Palace (shenzhen) Technology Co Ltd
Original Assignee
Seize Heavenly Palace (shenzhen) Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seize Heavenly Palace (shenzhen) Technology Co Ltd filed Critical Seize Heavenly Palace (shenzhen) Technology Co Ltd
Priority to CN201711386337.0A priority Critical patent/CN108228984A/en
Publication of CN108228984A publication Critical patent/CN108228984A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention discloses a kind of finishing project management system, its method, electronic equipment and computer program products.The finishing project management system includes:Database, the database fit up project data for storing several;Interactive interface, for showing the finishing project data to user;Item setup module for obtaining the setting of user instruction, determines the finishing project data of user setting;Data statistics module, for the finishing project data according to the user setting, in the corresponding tree-shaped graphic layer structure of automatic input.It provides the project management operating function to match with fitting-up engineering.User easily can be managed each project in fitting-up engineering, and automatically imported into corresponding tree data structure, be convenient for the layer management of fitting-up engineering.

Description

Fit up project management system, its method, electronic equipment and computer program product
Technical field
The present invention relates to design tool software technology field more particularly to a kind of finishing project management system, its method, electricity Sub- equipment and computer program product.
Background technology
With digitlization and the continuous propulsion of IT application process, in existing detail design, designer usually can apply The design tool software of existing building decoration area is designed, and is accordingly generated and finally presented in the form of electronic data Design result.
And in numerous Three-dimensional Design Software tools, Sketchup is a set of to be directly facing designing scheme production process Design tool.The production process of the design tool can give full expression to the thought of designer and fully meet and be handed over immediately with client The needs of stream so that designer directly very can intuitively be conceived on computers, be the creation of three-dimensional building designing scheme Excellent tool.
In process of the present invention is realized, inventor has found that the relevant technologies have the following problems:Existing BIM softwares setting, All kinds of work posts and the corresponding management function module of process offer that fitting-up construction industry is covered are provided.Cause to design Teacher or user can not carry out each subdivisional work Classifying Sum and and guide construction, can not also collect related data and summary information, The application being not easy in fitting-up engineering.
Invention content
For above-mentioned technical problem, an embodiment of the present invention provides a kind of finishing project management system, its method, electronics to set Standby and computer program product can not provide data pipe for fitting-up engineering to solve existing Sketchup design softwares Reason service, is not easy to the problem of user uses.
The first aspect of the embodiment of the present invention provides a kind of finishing project management system.The finishing project management system packet It includes:Database, the database fit up project data for storing several;Interactive interface, for showing the dress to user Repair project data;Item setup module, for obtain the setting of user instruction, determine user setting finishing project data and Data statistics module, for the finishing project data according to the user setting, in the corresponding tree-shaped graphic layer structure of automatic input.
Optionally, the finishing project data includes:Layer properties, work post classification and process adjustment.
Optionally, the interactive interface includes the first display area, the second display area and third display area;Institute The first display area is stated for show layers attribute;For showing that work post is classified, the third is shown for second display area Region is used to show that process adjusts.
Optionally, the item setup module includes:Project name setting unit, attributive classification setting unit, addition are pressed Key, delete button and mobile button;The project name setting unit is used to set the title of finishing project;The attribute point Class setting unit is used to set the attributive classification of finishing project;The addition button, delete button and mobile button are used to set Put the corresponding classification of group under the finishing project.
The second aspect of the embodiment of the present invention provides a kind of finishing project management method.The method includes walking as follows Suddenly:
It presets several finishing project datas and stores in the database;
The finishing project data is shown to user;
The setting instruction of user is obtained, determines the finishing project data of user setting;
According to the finishing project data of the user setting, in the corresponding tree-shaped graphic layer structure of automatic input.
Optionally, the finishing project data includes:Layer properties, work post classification and process adjustment.
Optionally, it is described to show the finishing project data to user, it specifically includes:In the first display area show layers Attribute shows work post classification in the second display area and process adjustment is shown in third display area.
Optionally, the setting instruction for obtaining user, determines the finishing project data of user setting, specifically includes:If Put the corresponding classification of group under the title of finishing project and attributive classification and the setting finishing project.
Third aspect present invention provides a kind of electronic equipment.The electronic equipment includes:At least one processor;And The memory being connect at least one processor communication.
Wherein, the memory is stored with the instruction repertorie that can be performed by least one processor, described instruction journey Sequence is performed by least one processor, so that at least one processor is able to carry out fitting up project pipe as described above Reason method.
Fourth aspect present invention provides a kind of computer program product fitted up and used in project management system.The meter Calculation machine program product includes finishing project management system as described above.
In technical solution provided in an embodiment of the present invention, filled for existing Sketchup design softwares tool towards finishing The problem of when adoring engineering, without targetedly function management module, making user inconvenient for use, can not realizing rapid data management, Provide the finishing project management system based on the design software tool.It provides and fits up in the finishing project management system The project management operating function that decorative engineering matches.User can easily carry out each project in fitting-up engineering Management, and automatically imported into corresponding tree data structure, it is convenient for the layer management of fitting-up engineering.
Description of the drawings
Fig. 1 is one embodiment schematic diagram of the finishing project management system of the embodiment of the present invention;
Fig. 2 is one embodiment schematic diagram of the item setup module of the finishing project management system of the embodiment of the present invention;
Fig. 3 is interactive interface one embodiment schematic diagram of the finishing project management system of the embodiment of the present invention;
Fig. 4 is one embodiment schematic diagram of the tree data structure of the embodiment of the present invention;
Fig. 5 is one embodiment schematic diagram of the finishing project management method of the embodiment of the present invention;
Fig. 6 is one embodiment schematic diagram of the electronic equipment of the embodiment of the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, the every other implementation that those skilled in the art are obtained without creative efforts Example, shall fall within the protection scope of the present invention.
It should be noted that when element is expressed " being fixed on " another element, it can directly on another element, Or there may be one or more elements placed in the middle therebetween.When an element is expressed " connection " another element, it can be with It is directly to another element or there may be one or more elements placed in the middle therebetween.Used in this specification The orientation or position of the instructions such as term " vertical ", " horizontal ", "left", "right", " on ", " under ", " interior ", " outer ", " bottom " Relationship is based on orientation shown in the drawings or position relationship, is for only for ease of the description present invention and simplifies description, without referring to Show or imply that the device of meaning or element there must be specific orientation, with specific azimuth configuration and operation, therefore cannot manage It solves as limitation of the present invention.In addition, term " first ", " second " etc. be only used for description purpose, and it is not intended that instruction or Imply relative importance.
Unless otherwise defined, technical and scientific term all used in this specification is led with belonging to the technology of the present invention The normally understood meaning of technical staff in domain is identical.Used term is only in the description of the invention in this specification The purpose of description specific embodiment is not intended to the limitation present invention.Term "and/or" includes used in this specification The arbitrary and all combination of one or more relevant Listed Items.In addition, invention described below difference is implemented Involved technical characteristic can be combined with each other as long as they do not conflict with each other in mode.
Sketchup softwares are a very common, the very extensive 3D design tools of application range.But towards finishing When decorative engineering designs, due to lacking the setting of corresponding specific aim, inconvenience that can be certain caused by the use of designer.
For example, in fitting-up engineering design process is carried out, existing design software tool cannot support fitting-up The relevant engineering classification of engineering.Therefore, it is impossible to the classification of these engineering projects is integrated into tree-shaped figure layer data knot automatically very well In structure, during the management of subsequent fitting-out work, it is not easy to quickly to call or find oneself desired figure layer and is led Go out or change operation.
It, can be soft in Sketchup in order to which Sketchup softwares is further made preferably to be suitable for fitting-up engineering On the basis of part, using finishing project management system provided in an embodiment of the present invention, realize and add corresponding classification of the items function, Consequently facilitating effective management to fitting-up engineering.
BIM, that is, Building Information Model is the numeral expression of some specific facility (construction project) physics and functional characteristic, Based on the platform that BIM is provided, each side such as designer or user can just participate in corresponding project in the design phase, pass through Three-dimensional stereo model intuitively determines or the every building function of simulation, preferably completes the design and construction of finishing project.
In general, the data of three-dimensional stereo model are in a manner of multiple figure layers, preserved using inverted tree 's.User is when needing to change or export a certain partial data, it may be convenient to be looked for according to the index of tree data structure To oneself target figure layer and modify accordingly.
Fig. 1 is a kind of finishing project management system provided in an embodiment of the present invention.The finishing project management system can be made For a complete software application, run in corresponding system platform.The finishing project management system can also set logical Cross conventional function module addition manner, be integrated into existing Sketchup softwares, as one of function module or Feature card uses, and with the application function of the expansion Sketchup softwares of adaptability, provides corresponding function to the user, is convenient for User realizes the data management for fitting-up engineering.
In the present embodiment, finishing project management system mainly in fitting-up engineering about each finishing project Classification is managed.Each finishing project can have different class objects or list, be carried out under tree data structure Sort out, user is facilitated to search or call by way of index.
As shown in Figure 1, the finishing project management system can specifically include following function module:Database 110, interaction Interface 120, item setup module 130 and data export module 140.
Wherein, database 110 can be any suitable, can store data with certain rule, support to carry out data The data acquisition system of retrieval.Databases contain preset finishing project data.
The finishing project data refers to be defined and manage in a manner of project management so that virtual graph image can With the relevant classification column for being defined, decompose, classifying and summarizing according to true project management theory and construction method.
Specifically, for each finishing project, following several dresses can be specifically divided into according to practical project management mode Repair project data:Layer properties, work post classification and process adjustment.
Wherein, layer properties is corresponding with specific finishing project, such as the finishing project of metope, the category of figure layer Property can include metope base and metope face layer two kinds.Metope base refers to the base layer structure of metope, and metope face layer refers to metope The apparent design of outer layer, such as decorative pattern of metope etc..
Work post classification refers to for each specific finishing project, according to the classification of work post progress.For example, the finishing item Mesh can be specifically the different work post project such as bricklayer's, carpenter, coating work and erector.Specific partitioning standards are by finishing item Purpose Specific construction work post is determined.
Process adjustment refers to the precedence relationship between each finishing project between working procedure.It is specific to finishing project And determine the order of various processes.
Interactive interface 120 is one for Exhibition Design system related information and acquires relevant control information, with user The function interface interacted.By the interactive interface, user can be selected according to the needs of oneself on software design tool Each finishing project is managed.Interactive interface 120 can specifically be carried out using any suitable element according to actual needs Setting, such as multiple and different regions is divided into show different finishing project datas by multiple rectangle frames, it realizes to dress Repair the management of project.
Specifically, can be set on the interactive interface 120, there are three the region independently divided, respectively the first viewing areas Domain, the second display area and third display area.
Wherein, first display area is used for show layers attribute;Second display area is used to show work post point Class, the third display area are used to show that process adjusts.
Item setup module 130 is that the finishing project data of user setting is determined for obtaining the setting of user instruction Function module.It realizes the corresponding setting instruction of user's input by the relevant control button shown on interactive interface 120 To fitting up the setting of project data.
In the present embodiment, which is the calculating core in design system, can be corresponding by calling The relevant function module of three-dimensional software tool and the data being stored in advance in database, be automatically generated after calculating and Determine the setting for some specific finishing project.
In some embodiments, as shown in Fig. 2, the item setup module 130 can specifically include:Project name is set Unit 131, attributive classification setting unit 132, addition button 133, delete button 134 and mobile button 135.
Wherein, the project name setting unit 131 is used to set the title of finishing project, and the attributive classification setting is single Member 132 is used to set the attributive classification of finishing project.Interactive interface 120 can be shown corresponding according to selected attributive classification Fit up project data.
The addition button 133, delete button 134 and mobile button 135 form complete control button combination, are used for The corresponding classification of group under the finishing project is set, can realize movement, addition and the operation deleted.
In the present embodiment, a complete fitting-up engineering is represented with the project of fitting up.It is wrapped under a finishing project The group of multiple and different subitem compositions, such as Mian Ceng groups or keel group etc. are contained.User can lead to when managing data Control button combination is crossed, group is added under corresponding finishing classification of the items, determines that it fits up classification of the items.
Data statistics module 140 is used for the finishing project data according to the user setting, and automatic input is corresponding tree-shaped In graphic layer structure.The data statistics module 140 is the data established between an existing software design tool and management system connection It is the function module of channel.The classification information that management system increases newly can be integrated into corresponding software design tool by it, with Corresponding tree data structure is presented, and is realized in software design tool to the finishing project of fitting-up engineering convenient for user Sort out and manage.
The finishing project management system provided through the embodiment of the present invention, by prestoring corresponding finishing project data Mode, the perfect fitting-out work project definition function of BIM softwares of supplement.And it can be carried in the interactive interface of offer The preceding specific Classifying Sum of project to difference work posts a large amount of in fitting-out work and process ensure that effective management for figure layer. Such mode convenient for acquiring the specific assortment data information of each fitting-out work project, and for formulate corresponding arrangement and method for construction and Estimation cost provides great convenience.
Fig. 3 is the schematic diagram of interactive interface provided in an embodiment of the present invention.After Fig. 4 is data export module export The schematic diagram of tree data structure.Each figure layer group belongs under corresponding project, can easily be managed.
Below in conjunction with interactive interface shown in Fig. 3, the tool of the finishing project management method of the embodiment of the present invention is described in detail Body application example.
First, needs are filled in project name and attributive classification to be managed, sort out the finishing project summarized.These dresses The project of repairing can include:Metope, ground, furred ceiling etc..After project name and attributive classification is had selected, system can add automatically It carries, by under finishing project, the group classified is respectively displayed in selective listing.
Wherein, as shown in figure 3, having corresponding selective listing in each display area, be respectively used to show layers attribute, Work post is classified and process adjusts three and needs the finishing project data being configured.
Then, according to practical project situation, by the combination of control button, the group that can will occur in selective listing It is moved to accordingly under different classification items.For example, by under the classification of wooden splint group mobility to metope base.
Finally, after all groups are all finished by rule and confirm errorless, user can click determining button accordingly Determine the setting for carrying out fitting up project data.Set later finishing project data that can be formed by data import modul 140 Final tree data structure is preserved, and can intuitively be presented in the manner illustrated in fig. 4 to user.
The embodiment of the present invention additionally provides a kind of finishing project management method.Fig. 5 is one kind provided in an embodiment of the present invention Fit up the method flow diagram of project management method.As shown in figure 5, the finishing project management method includes the following steps:
510th, several finishing project datas are preset and are stored in the database.
520th, the finishing project data is shown to user.
Specifically, the finishing project data includes:Layer properties, work post classification and process adjust three big classifications. There is corresponding classification under each classification.
530th, the setting instruction of user is obtained, determines the finishing project data of user setting.
Wherein, the component setting instruction includes:The selected instruction of component layout points and tensile member arrangement area are set The extension of domain to predetermined length instructs.
540th, according to the finishing project data of the user setting, in the corresponding tree-shaped graphic layer structure of automatic input.Wherein, The component layout area has the selected instruction and the extension instruction to determine.
In some embodiments, it is described to show the finishing project data to user, it specifically includes:In the first display area Show layers attribute shows work post classification in the second display area and process adjustment is shown in third display area.It also that is, will Three big classification is shown that user can be respectively in the control of these display area independences using different display areas respectively Or adjust the classification information of these groups.
In further embodiments, the setting instruction for obtaining user determines the finishing project data of user setting, tool Body includes:The corresponding classification of group under the title of finishing project and attributive classification and the setting finishing project is set.
It should be noted that the finishing project management method provided in above-described embodiment and finishing project management system are Based on identical inventive concept.Therefore, the step of fitting up each specific embodiment in project management method can be by corresponding Performed by function module, specific function can also have corresponding method in project management adding method is fitted up in function module Step, details are not described herein.
Fig. 6 is the hardware architecture diagram of electronic equipment provided by the embodiments of the present application.As shown in fig. 6, the equipment 60 is wrapped It includes:One or more processors 601 and memory 602.
In Fig. 6 for one.Wherein, processor 601 and memory 602 can be connected by bus or other modes It connects, in Fig. 6 for being connected by bus.
Memory 602 is used as a kind of non-volatile computer readable storage medium storing program for executing, available for storing non-volatile software journey Sequence, non-volatile computer executable program and module, as the finishing project management method in the embodiment of the present invention is corresponding Program instruction/module (for example, database 110, interactive interface 120, item setup module 130 and data statistics module 140). Processor 601 is by running non-volatile software program, instruction and the module of storage in the memory 602, so as to perform clothes The various function application of device of being engaged in and the finishing project management method method of data processing, i.e. realization above method embodiment.
Memory 602 can include storing program area and storage data field, wherein, storing program area can store operation system System, the required application program of at least one function;Storage data field can be stored uses institute according to finishing project management system Data of establishment etc..In addition, memory 602 can include high-speed random access memory, non-volatile memories can also be included Device, for example, at least a disk memory, flush memory device or other non-volatile solid state memory parts.In some embodiments In, memory 602 is optional including relative to the remotely located memory of processor 601, these remote memories can pass through net Network is connected to finishing project management system.The example of above-mentioned network include but not limited to internet, intranet, LAN, Mobile radio communication and combinations thereof.
One or more of modules are stored in the memory 602, when by one or more of processors During 601 execution, the finishing project management system in above-mentioned any means embodiment is performed.
The said goods can perform the method that the embodiment of the present application is provided, and has the corresponding function module of execution method and has Beneficial effect.The not technical detail of detailed description in the present embodiment, reference can be made to the method that the embodiment of the present application is provided.
The apparatus embodiments described above are merely exemplary, wherein the unit illustrated as separating component can To be or may not be physically separate, the component shown as unit may or may not be physics list Member, you can be located at a place or can also be distributed in multiple network element.It can be selected according to the actual needs In some or all of module realize the purpose of this embodiment scheme.
Through the above description of the embodiments, those of ordinary skill in the art can be understood that each embodiment The mode of general hardware platform can be added to realize by software, naturally it is also possible to pass through hardware.Those of ordinary skill in the art can With understand all or part of flow realized in above-described embodiment method be can be instructed by computer program it is relevant hard Part is completed, and the program can be stored in a computer read/write memory medium, the program is when being executed, it may include as above State the flow of the embodiment of each method.Wherein, the storage medium can be magnetic disc, CD, read-only memory (Read- Only Memory, ROM) or random access memory (Random Access Memory, RAM) etc..
It, can according to the technique and scheme of the present invention and this hair it is understood that for those of ordinary skills Bright design is subject to equivalent substitution or change, and all these changes or replacement should all belong to the guarantor of appended claims of the invention Protect range.

Claims (10)

1. a kind of finishing project management system, which is characterized in that including:
Database, the database fit up project data for storing several;
Interactive interface, for showing the finishing project data to user;
Item setup module for obtaining the setting of user instruction, determines the finishing project data of user setting;
Data statistics module, for the finishing project data according to the user setting, the corresponding tree-shaped figure layer knot of automatic input In structure.
2. finishing project management system according to claim 1, which is characterized in that the finishing project data includes:Figure Layer attribute, work post classification and process adjustment.
3. finishing project management system according to claim 2, which is characterized in that it is aobvious that the interactive interface includes first Show region, the second display area and third display area;
First display area is used for show layers attribute;Second display area is for showing that work post is classified, described the Three display areas are used to show that process adjusts.
4. finishing project management system according to claim 3, which is characterized in that the item setup module includes: Mesh title setting unit, attributive classification setting unit, addition button, delete button and mobile button;
The project name setting unit is used to set the title of finishing project;The attributive classification setting unit fills for setting Repair the attributive classification of project;The addition button, delete button and mobile button are used to set the group under the finishing project The corresponding classification of group.
5. a kind of finishing project management method, which is characterized in that the method includes:
It presets several finishing project datas and stores in the database;
The finishing project data is shown to user;
The setting instruction of user is obtained, determines the finishing project data of user setting;
According to the finishing project data of the user setting, in the corresponding tree-shaped graphic layer structure of automatic input.
6. finishing project management method according to claim 5, which is characterized in that the finishing project data includes:Figure Layer attribute, work post classification and process adjustment.
7. finishing project management method according to claim 6, which is characterized in that described to show the finishing item to user Mesh number evidence, specifically includes:
In the first display area show layers attribute, work post classification is shown in the second display area and is shown in third display area Show that process adjusts.
8. finishing project management method according to claim 7, which is characterized in that the setting instruction for obtaining user, It determines the finishing project data of user setting, specifically includes:
The title and attributive classification of finishing project are set;
The corresponding classification of group under the finishing project is set.
9. a kind of electronic equipment, which is characterized in that including at least one processor;
And the memory being connect at least one processor communication;
Wherein, the memory is stored with the instruction repertorie that can be performed by least one processor, described instruction program quilt At least one processor performs, so that at least one processor is able to carry out as described in claim 5-8 is any Fit up project management method.
10. a kind of fit up the computer program product used in project management system, which is characterized in that the computer program production Product include the finishing project management system as described in claim 1-4 is any.
CN201711386337.0A 2017-12-20 2017-12-20 Fit up project management system, its method, electronic equipment and computer program product Withdrawn CN108228984A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711386337.0A CN108228984A (en) 2017-12-20 2017-12-20 Fit up project management system, its method, electronic equipment and computer program product

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711386337.0A CN108228984A (en) 2017-12-20 2017-12-20 Fit up project management system, its method, electronic equipment and computer program product

Publications (1)

Publication Number Publication Date
CN108228984A true CN108228984A (en) 2018-06-29

Family

ID=62650024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711386337.0A Withdrawn CN108228984A (en) 2017-12-20 2017-12-20 Fit up project management system, its method, electronic equipment and computer program product

Country Status (1)

Country Link
CN (1) CN108228984A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110400077A (en) * 2019-07-25 2019-11-01 北京数字岛科技有限公司 Decoration Design method and Decoration Design system
CN110414126A (en) * 2019-07-25 2019-11-05 北京数字岛科技有限公司 Decoration Design method and Decoration Design system
CN112862511A (en) * 2019-11-28 2021-05-28 贝壳技术有限公司 Engineering cost calculation method and system
CN113065726A (en) * 2020-01-02 2021-07-02 宁波余慈一家电子商务有限公司 Decoration management system and management method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110400077A (en) * 2019-07-25 2019-11-01 北京数字岛科技有限公司 Decoration Design method and Decoration Design system
CN110414126A (en) * 2019-07-25 2019-11-05 北京数字岛科技有限公司 Decoration Design method and Decoration Design system
CN112862511A (en) * 2019-11-28 2021-05-28 贝壳技术有限公司 Engineering cost calculation method and system
CN113065726A (en) * 2020-01-02 2021-07-02 宁波余慈一家电子商务有限公司 Decoration management system and management method thereof

Similar Documents

Publication Publication Date Title
CN108228984A (en) Fit up project management system, its method, electronic equipment and computer program product
Shang et al. Social manufacturing cloud service platform for the mass customization in apparel industry
CN107590355A (en) Architectural design method, design system and electronic equipment based on BIM
CN104183023B (en) The construction method of many scene graph in a kind of distributed virtual environment
CN106780770B (en) Real community three-dimensional scene editing system based on PC (personal computer) terminal
CN103971416B (en) It is the multiple regions handled by computing resource by 3D scene cuts
CN104463957A (en) Three-dimensional scene generation tool integration method based on materials
CN107577887A (en) Wall surfacing design system, design method, electronic equipment and computer program product
CN107577888A (en) Fire-fighting spraying head design system, design method, electronic equipment and computer program product
CN108573112A (en) Aerospace test based on digitalized artificial emits two dimensional topology analysis method
CN108022296A (en) A kind of BIM interior decorations current floor and region design system and method
CN112651711B (en) Construction system of collaborative design management platform based on XDB file under BS architecture
CN106447786A (en) Parallel space establishing and sharing system based on virtual reality technologies
CN107153744A (en) Subsurface three-dimensional pipeline decision system
CN107918689A (en) Ground surface finishing design system, design method, electronic equipment and computer program product
CN107807980A (en) Report automatic generatioin system and its generation method
US20190304006A1 (en) System and method for web-based map generation
CN107832539A (en) A kind of stretching adjustment system, method of adjustment and electronic equipment based on suspension rod
CN114332439A (en) Three-dimensional data editing and generating system
CN107729616A (en) Fire protection pipeline design system, design method, electronic equipment and computer program product based on Sketchup
CN108009332A (en) Suspended ceiling member adding set, its method, electronic equipment and computer program
CN109783596B (en) ArcGIS map configuration preview method based on Angular component
WO2017061954A1 (en) Method and system for an online space planning tool
Yuan et al. An exploration of digital tourism design based on virtual reality
CN108009333A (en) Interior decoration level sets system, method, equipment and computer program product

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180629

WW01 Invention patent application withdrawn after publication