CN108203991A - A kind of method using load-carrying air bag rectification gutter retaining wall - Google Patents

A kind of method using load-carrying air bag rectification gutter retaining wall Download PDF

Info

Publication number
CN108203991A
CN108203991A CN201810138356.XA CN201810138356A CN108203991A CN 108203991 A CN108203991 A CN 108203991A CN 201810138356 A CN201810138356 A CN 201810138356A CN 108203991 A CN108203991 A CN 108203991A
Authority
CN
China
Prior art keywords
air bag
barricade
rectification
retaining wall
gutter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810138356.XA
Other languages
Chinese (zh)
Inventor
高志勇
顾浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Anjie Geotechnical Engineering Co Ltd
Original Assignee
Jiangsu Anjie Geotechnical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Anjie Geotechnical Engineering Co Ltd filed Critical Jiangsu Anjie Geotechnical Engineering Co Ltd
Priority to CN201810138356.XA priority Critical patent/CN108203991A/en
Publication of CN108203991A publication Critical patent/CN108203991A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The present invention discloses a kind of method using load-carrying air bag rectification gutter retaining wall, and the method implementation steps are as follows:Construction ditch depth and width are first measured, according to measurement data, the design section area of air bag is the 1.5 2 of gutter area of section times of the air bag corrected;A small amount of water is passed through in gutter, air bag is put into ditch, a small amount of gas is first filled with and causes, air bag spread apart floats on the water surface;Air bag, which is pushed into, needs the barricade of rectification to topple over side, and fix;Continue to be inflated air bag, while observe barricade and return positive situation, when barricade angle is returned just to 80 degree, stop inflation;Using two hydraulic jacks by barricade slowly support to 90 degree of vertical states, the limiting device that installed additional at the top of barricade be fixed;Air bag can deflate, and be repeated above-mentioned steps, carry out the rectification work of next section of barricade.

Description

A kind of method using load-carrying air bag rectification gutter retaining wall
Technical field
The present invention relates to geotechnical engineering field more particularly to a kind of sides using load-carrying air bag rectification gutter retaining wall Method.
Background technology
In highway, railway, municipal works, many slope retainings are required for using retaining wall, such as one in China at present The retaining wall by a large amount of bank protection, retaining wall, especially gutter is needed in a little excavation of foundation pit, due to being invaded for a long time by liquid Erosion, causes wall to be more prone to topple over, and causes draining difficult or even generates security hidden trouble, anxious to be resolved, while requires work Journey has many advantages, such as that easy to operate, at low cost, speed of application is fast.
Invention content
It is more prone to topple over for solution more than wall, causes draining difficulty or even generation security hidden trouble etc. are existing to ask Topic, the present invention provide a kind of method using load-carrying air bag rectification gutter retaining wall.
A kind of method using load-carrying air bag rectification gutter retaining wall,
The method implementation steps are as follows:
A. construction ditch depth and width are first measured, according to measurement data, the design section area of air bag is that correction is good 1.5-2 times of air bag of gutter area of section;;
B. a small amount of water is passed through in gutter, air bag is put into ditch, a small amount of gas is first filled with and causes, air bag spread apart, Float on the water surface;
C. air bag is pushed into needs the barricade of rectification to topple over side, and fix;
D. continue to be inflated air bag, while observe barricade and return positive situation, when barricade angle is returned just to 80 degree, stop Inflation;
E. using two hydraulic jacks by barricade slowly support to 90 degree vertical states, install additional and limit at the top of barricade Position device is fixed;
F. air bag can deflate, and be repeated above-mentioned steps, carry out the rectification work of next section of barricade.
Preferably, pressure gauge is added at the airbag aeration mouth.
Preferably, it is 2 times of the lateral pressure of barricade according to bearing capacity during the airbag design and designs above.
Preferably, the design section area of air bag is 1.5-2 times of air bag of the gutter area of section corrected;
Preferably, two " F " shapes that 120 channel steel that the limiting device uses is welded into, length slightly compare retaining wall Generous width little by little, is just stuck on barricade, it is ensured that barricade is in plumbness.
The present invention is in order to achieve the above object, using following scheme:
The advantageous effect that the present invention generates:
1. not destroying the original structure of retaining wall, the original state rectification righting for keeping tilting structure can reach;It is led with traditional , can not be in the narrow space of operation in people when drawing method, incremental launching method, it can low cost, efficient rectification with the method Righting;
2. guarantee is not destroyed by the barricade integrality of rectification;Short time limit, speed are fast;Safety and environmental protection is pollution-free, noiseless;
3. operation does not need to take special measure under dark moist environment, it is ensured that construction safety;Construction cost is low, effect Rate is high, and the people of input, material, machine are fewer.
Specific embodiment
Technical scheme of the present invention is made below specifically, complete explanation.
When specifically coming into operation,
A kind of method using load-carrying air bag rectification gutter retaining wall,
The method implementation steps are as follows:
A. construction ditch depth and width are first measured, according to measurement data, the design section area of air bag is that correction is good 1.5-2 times of air bag of gutter area of section, the bearing capacity of air bag are the 2 times or more of the lateral pressure of barricade;
B. a small amount of water is passed through in gutter, air bag is put into ditch, a small amount of gas is first filled with and causes, air bag spread apart, Float on the water surface;
C. air bag is pushed into needs the barricade of rectification to topple over side, and fix,;
D. continue to be inflated air bag, while observe barricade and return positive situation, when barricade angle is returned just to 80 degree, stop Inflation;
E. using two hydraulic jacks by barricade slowly support to 90 degree vertical states, install additional and limit at the top of barricade Position device is fixed;
F. air bag can deflate, and be repeated above-mentioned steps, carry out the rectification work of next section of barricade.
Obviously, described embodiment is only the part of the embodiment rather than whole embodiments of the present invention.Based on this The embodiment of invention, all other reality that those of ordinary skill in the art are obtained without making creative work It applies, belongs to protection scope of the present invention.

Claims (4)

  1. A kind of 1. method using load-carrying air bag rectification gutter retaining wall, which is characterized in that
    The method implementation steps are as follows:
    A. construction ditch depth and width are first measured, according to measurement data, design section area is the gutter section corrected 1.5-2 times of air bag of area;
    B. a small amount of water is passed through in gutter, air bag is put into ditch, a small amount of gas is first filled with and causes, air bag spread apart, floating In the water surface;
    C. air bag is pushed into needs the barricade of rectification to topple over side, and fix,;
    D. continue to be inflated air bag, while observe barricade and return positive situation, when barricade angle is returned just to 80 degree, stop filling Gas;
    E. using two hydraulic jacks by barricade slowly support to 90 degree vertical states, limiting of being installed additional at the top of barricade fill It puts and is fixed;
    F. air bag can deflate, and be repeated above-mentioned steps, carry out the rectification work of next section of barricade.
  2. 2. a kind of method using load-carrying air bag rectification gutter retaining wall according to claim 1, which is characterized in that described Pressure gauge is added at airbag aeration mouth.
  3. 3. a kind of method using load-carrying air bag rectification gutter retaining wall according to claim 1 or claim 2, which is characterized in that It is 2 times of the lateral pressure of barricade according to bearing capacity during the airbag design and designs above.
  4. 4. a kind of method using load-carrying air bag rectification gutter retaining wall according to claim 1, which is characterized in that described Two " F " shapes being welded into of 120 channel steel that limiting device uses, length slightly it is generouser than retaining wall it is wide little by little, just block On barricade, it is ensured that barricade is in plumbness.
CN201810138356.XA 2018-02-10 2018-02-10 A kind of method using load-carrying air bag rectification gutter retaining wall Pending CN108203991A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810138356.XA CN108203991A (en) 2018-02-10 2018-02-10 A kind of method using load-carrying air bag rectification gutter retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810138356.XA CN108203991A (en) 2018-02-10 2018-02-10 A kind of method using load-carrying air bag rectification gutter retaining wall

Publications (1)

Publication Number Publication Date
CN108203991A true CN108203991A (en) 2018-06-26

Family

ID=62606319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810138356.XA Pending CN108203991A (en) 2018-02-10 2018-02-10 A kind of method using load-carrying air bag rectification gutter retaining wall

Country Status (1)

Country Link
CN (1) CN108203991A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111206631A (en) * 2020-01-17 2020-05-29 河南文博建设工程有限公司 Deviation rectifying method for water bag integral lifting building

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101086158A (en) * 2006-06-05 2007-12-12 尤利泰克全球公司 Method and arrangement for improving soil and/or for lifting structures
CN107059777A (en) * 2017-05-24 2017-08-18 杨斌 A kind of air pressure turnover panel is taken precautions against natural calamities continuous wall system
CN107178219A (en) * 2016-03-09 2017-09-19 青岛天力建筑加固工程有限公司 Help formula building Deviation Correction method
CN206545235U (en) * 2017-03-04 2017-10-10 叶长青 Reinforcing pile stake top stress bringing device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101086158A (en) * 2006-06-05 2007-12-12 尤利泰克全球公司 Method and arrangement for improving soil and/or for lifting structures
CN107178219A (en) * 2016-03-09 2017-09-19 青岛天力建筑加固工程有限公司 Help formula building Deviation Correction method
CN206545235U (en) * 2017-03-04 2017-10-10 叶长青 Reinforcing pile stake top stress bringing device
CN107059777A (en) * 2017-05-24 2017-08-18 杨斌 A kind of air pressure turnover panel is taken precautions against natural calamities continuous wall system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111206631A (en) * 2020-01-17 2020-05-29 河南文博建设工程有限公司 Deviation rectifying method for water bag integral lifting building

Similar Documents

Publication Publication Date Title
CN1023722C (en) Overflow spillway for dams, weirs and similar structures
CN104032770A (en) Water sealing device for underwater connection between precast bearing platform and cast-in place pile
CN107401118A (en) A kind of suspension bridge pier-stage type prestressing force anchorage
CN108203991A (en) A kind of method using load-carrying air bag rectification gutter retaining wall
CN103089298A (en) Structure and method for building side direction multicolumn gob-side entry retaining filling wall body
CN201962689U (en) Building foundation adapting to foundation deformation of worked-out area
CN209468652U (en) A kind of mountain area subgrade river side subgrade protection structure
CN205329631U (en) Utilize geotechnique to fill and irritate a bag and a provisional flood control barrier that shaped steel frame was built
CN213204210U (en) Linear float-type suspension tunnel slide rail device
CN212358208U (en) High pile cap wharf revetment structure
CN205035780U (en) Wet tailing of piling accelerates drainage consolidation device and tailing storehouse drainage system step by step
CN101205711A (en) Three-cavity water/gas filling expansion dam and cofferdam construction method
CN201560420U (en) Geomembrane
CN209099304U (en) A kind of hydraulic engineering protection river levee
CN206944885U (en) A kind of asphalt concrete face slab defect range-measurement system
CN206667185U (en) Approach channel shore protection repairs structure
CN208280151U (en) Profundal zone antiseepage cofferdam structure
CN101603299B (en) Broken line type dam joint structure and construction method thereof
CN104912084B (en) Building dense district deep basal pit external sealing type static press piling construction method
CN112323853A (en) Self-adaptive linear underground engineering structure and transverse deformation control method thereof
CN208309759U (en) A kind of swelling rock cutting deep layer discharge structure
CN210315500U (en) Steel sheet pile cofferdam structure
CN220377196U (en) Warehouse entry structure suitable for geomembrane surrounding dam
CN211228384U (en) Impact-proof stainless steel plate rubber dam bag body
CN215976661U (en) Road water retaining structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180626

RJ01 Rejection of invention patent application after publication