CN108196139A - 一种小型发电机组并网核相方法 - Google Patents
一种小型发电机组并网核相方法 Download PDFInfo
- Publication number
- CN108196139A CN108196139A CN201810053251.4A CN201810053251A CN108196139A CN 108196139 A CN108196139 A CN 108196139A CN 201810053251 A CN201810053251 A CN 201810053251A CN 108196139 A CN108196139 A CN 108196139A
- Authority
- CN
- China
- Prior art keywords
- phase
- phases
- pointer
- nuclear
- phasing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R29/00—Arrangements for measuring or indicating electric quantities not covered by groups G01R19/00 - G01R27/00
- G01R29/18—Indicating phase sequence; Indicating synchronism
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Monitoring And Testing Of Nuclear Reactors (AREA)
Abstract
本发明涉及一种小型发电机组并网核相方法,准备两套10kV电压等级指针式核相器,步骤一、将一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静止触头上,将另一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上;步骤二与步骤一同样的方法测A相、C相;步骤三与步骤一同样的方法测B相、C相;步骤四、前三个步骤中的电压升降一致,可以判断相序正确,发电机可以并网。采用该并网核相方法,能准确判断小型发电机组一次电压相序与系统电压相序是否一致,能直观、快速判断小型发电机组具备并网条件。
Description
技术领域
本发明涉及发电机组并网技术领域,具体涉及一种小型发电机组并网核相方法。
背景技术
目前两个不同电压核相只采用一组核相,对于全部是系统电压的情况适用,但对于发电机并网核相不适用。
发明内容
为克服所述不足,本发明的目的在于提一种小型发电机组并网核相方法,能直观、快速判断小型发电机组具备并网条件。
本发明解决其技术问题所采用的技术方案是:一种小型发电机组并网核相方法,包括:
步骤一、准备两套10kV电压等级指针式核相器,将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静止触头上,能观察到指针从0kV-10kV之间来回波动,将另一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤二、将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤三、一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;接着将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤四、经步骤一、步骤二、步骤三核相后,电压的升降一致,可以判断相序正确,发电机可以并网。
本发明具有以下有益效果:采用该并网核相方法,能准确判断小型发电机组一次电压相序与系统电压相序是否一致,能直观、快速判断小型发电机组具备并网条件。
具体实施方式
现在对本发明作进一步详细的说明。
一种小型发电机组并网核相方法,包括:
步骤一、准备两套10kV电压等级指针式核相器,将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静止触头上,能观察到指针从0kV-10kV之间来回波动,将另一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤二、将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤三、一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;接着将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,仔细观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤四、步骤一、步骤二、步骤三核相后,电压的升降一致,可以判断相序正确,发电机可以并网。
本发明不局限于所述实施方式,任何人应得知在本发明的启示下作出的结构变化,凡是与本发明具有相同或相近的技术方案,均落入本发明的保护范围之内。
本发明未详细描述的技术、形状、构造部分均为公知技术。
Claims (1)
1.一种小型发电机组并网核相方法,其特征在于:包括:
步骤一、准备两套10kV电压等级指针式核相器,将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静止触头上,能观察到指针从0kV-10kV之间来回波动,将另一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤二、将其中一套核相器的两根核相杆分别放置在发电机侧的A相和系统侧的A相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤三、一套核相器的两根核相杆分别放置在发电机侧的B相和系统侧的B相断路器静触头上,能观察到指针从0kV-10kV之间来回波动;接着将另一套核相器的两根核相杆分别放置在发电机侧的C相和系统侧的C相断路器静触头上,能观察到指针从0kV-10kV之间来回波动,观察两套核相器的指针同时从0kV-10kV波动,到达10kV时,又同时从10kV-0kV波动;
步骤四、经步骤一、步骤二、步骤三核相后,电压的升降一致,可以判断相序正确,发电机可以并网。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810053251.4A CN108196139A (zh) | 2018-01-19 | 2018-01-19 | 一种小型发电机组并网核相方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810053251.4A CN108196139A (zh) | 2018-01-19 | 2018-01-19 | 一种小型发电机组并网核相方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108196139A true CN108196139A (zh) | 2018-06-22 |
Family
ID=62590328
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810053251.4A Pending CN108196139A (zh) | 2018-01-19 | 2018-01-19 | 一种小型发电机组并网核相方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108196139A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109932601A (zh) * | 2019-03-31 | 2019-06-25 | 上海二十冶建设有限公司 | 用反送电对星型定子发电机组并网回路检测的方法 |
CN112290599A (zh) * | 2020-10-10 | 2021-01-29 | 上海二十冶建设有限公司 | 一种发电并网核相保护装置及其使用方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130027992A1 (en) * | 2010-04-16 | 2013-01-31 | Kenersys Gmbh | Method for inputting power and power input system |
CN104062513A (zh) * | 2014-05-20 | 2014-09-24 | 东南大学 | 二次核相仪及核相方法 |
CN105242122A (zh) * | 2015-11-05 | 2016-01-13 | 国网黄石供电公司运维检修部(检修分公司) | 一种停电线路无线核相测试装置 |
CN105676009A (zh) * | 2016-03-24 | 2016-06-15 | 国网山东省电力公司济南供电公司 | 一种三相式环网柜二次核相器及其核相方法 |
CN106571645A (zh) * | 2016-10-31 | 2017-04-19 | 内蒙古包钢钢联股份有限公司 | 发电机一次系统核相方法 |
-
2018
- 2018-01-19 CN CN201810053251.4A patent/CN108196139A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130027992A1 (en) * | 2010-04-16 | 2013-01-31 | Kenersys Gmbh | Method for inputting power and power input system |
CN104062513A (zh) * | 2014-05-20 | 2014-09-24 | 东南大学 | 二次核相仪及核相方法 |
CN105242122A (zh) * | 2015-11-05 | 2016-01-13 | 国网黄石供电公司运维检修部(检修分公司) | 一种停电线路无线核相测试装置 |
CN105676009A (zh) * | 2016-03-24 | 2016-06-15 | 国网山东省电力公司济南供电公司 | 一种三相式环网柜二次核相器及其核相方法 |
CN106571645A (zh) * | 2016-10-31 | 2017-04-19 | 内蒙古包钢钢联股份有限公司 | 发电机一次系统核相方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109932601A (zh) * | 2019-03-31 | 2019-06-25 | 上海二十冶建设有限公司 | 用反送电对星型定子发电机组并网回路检测的方法 |
CN112290599A (zh) * | 2020-10-10 | 2021-01-29 | 上海二十冶建设有限公司 | 一种发电并网核相保护装置及其使用方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Rietveld et al. | Measurement infrastructure to support the reliable operation of smart electrical grids | |
Saleh et al. | Implementing and testing $ d $–$ q $ WPT-based digital protection for microgrid systems | |
Hu et al. | Synchronous online diagnosis of multiple cable intermittent faults based on chaotic spread spectrum sequence | |
JP7006237B2 (ja) | 電力供給システムの保護装置を備えたシステム | |
Madtharad et al. | An optimal measurement placement method for power system harmonic state estimation | |
CN109031177A (zh) | 兼顾逆变器电流传感器故障和功率管开路故障的诊断方法 | |
Wu et al. | Three-phase instrument transformer calibration with synchronized phasor measurements | |
Kamwa et al. | Optimal integration of disparate C37. 118 PMUs in wide-area PSS with electromagnetic transients | |
CN108196139A (zh) | 一种小型发电机组并网核相方法 | |
Saleh et al. | Antiislanding protection based on signatures extracted from the instantaneous apparent power | |
CN106291258A (zh) | 一种微电网中线路故障的定位方法 | |
CN106571645A (zh) | 发电机一次系统核相方法 | |
CN108345706B (zh) | 一种电源快切的仿真方法及模型 | |
Kumar et al. | A passive islanding detection approach for distributed generation using rate of change of negative sequence voltage and current | |
CN106684927B (zh) | 一种孤网系统中大型发电机组并网系统及并网方法 | |
DE112011102451T5 (de) | Kalibrierungssteuerung für einen Generatorsatz | |
CN203799008U (zh) | 支柱式电子式电流互感器一次振动试验的数据采集装置 | |
Yuan et al. | Power system low frequency oscillation monitoring and analysis based on multi-signal online identification | |
CN109596931B (zh) | 中性点非有效接地系统的故障选线方法 | |
Lira et al. | PMU performance requirements and validation for closed loop applications | |
Esreraig et al. | An observer-based protection system for microgrids | |
CN110927551B (zh) | 晶闸管换流阀组件短路电流试验回路 | |
Chen et al. | Locating sub-cycle faults in distribution network applying half-cycle DFT method | |
US20190368856A1 (en) | Central point positioning determination device and central point positioning method thereof for rotor coil of large-scale steam turbine generator | |
US10088509B2 (en) | Checking a multi-pole electrical circuit breaker |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180622 |
|
RJ01 | Rejection of invention patent application after publication |