CN108166509A - A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage - Google Patents

A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage Download PDF

Info

Publication number
CN108166509A
CN108166509A CN201711364613.3A CN201711364613A CN108166509A CN 108166509 A CN108166509 A CN 108166509A CN 201711364613 A CN201711364613 A CN 201711364613A CN 108166509 A CN108166509 A CN 108166509A
Authority
CN
China
Prior art keywords
slope
protection
excavation
stage
side slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711364613.3A
Other languages
Chinese (zh)
Inventor
赵之仲
苏芸华
崔峰
杨振宇
柳泓哲
刘桂强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jiaotong University
Original Assignee
Shandong Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jiaotong University filed Critical Shandong Jiaotong University
Priority to CN201711364613.3A priority Critical patent/CN108166509A/en
Publication of CN108166509A publication Critical patent/CN108166509A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses the longitudinally spaced excavations and protection construction method stage by stage of a kind of slope construction, sequentially follow the steps below:1) it along the longitudinally spaced excavation of roadbed, forms reserved part soil body A and excavates the spaced apart pattern in part;2) part is excavated to carry out according to top-down sequence;3) rapid after the completion of excavating to carry out protection works construction, protection should excavate primary protection level-one, 4) will leave and take the part top-down sequences of soil body A carries out classification excavation;5) protection works construction is carried out immediately after the completion of every grade of excavation, seam crossing does not process.Side slope of the present invention longitudinally excavates reserved soil body A and is used for back-pressure slope foot, by back-pressure slope foot and the mutual embedding sliding force for being constructed for bearing the soil body of the soil body so that a kind of passive force type retaining structure that deformable body is stabilized.

Description

A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage
Technical field
The invention belongs to slope excavatings and protection technology field, and in particular to a kind of excavation construction method of side slope is applicable in In the high slope of soft soil-slope, plaster rock side slope, area of heavy rainfull by the variation of rainwater effect soil property greatly.
Background technology
The destruction of side slope:Refer to slopes and occur larger displacement with certain speed, slope rock mass, the soil body generate whole sliding Dynamic, rolling or rotation.
For slope project, consequence of failure caused by damage is possible has very much, such as:Jeopardize the life of people, make Into economic loss, social harmful effect is generated.
The excavation of side slope and the major issue that protection is mountain highway, railway construction, water conservancy and hydropower exploitation and urban construction. Although country and place all put into huge manpower and materials to administer every year, the traffic because caused by having an accident side slope is obstructed in Disconnected, river blocks, to Reservoir region and city, rural area bring harm be still it is huge, caused by lose it is still very huge Greatly.
Current general digging mode has lateral excavation, longitudinal direction excavation and ground settlement and tunnel, the foundation of selection only to consider excavation area The length and depth in domain, are not involved with sequence of excavation impact on slope stability.And different sequence of excavation, road can be caused The difference of counter-pressure changing rule at moat side slope slope foot, so as to bury the security risk on landslide.During construction about protection works Machine and sequence are also very big to the stability influence of side slope during excavation.
In road engineering in a mountainous area construction, it is often necessary to original (natural) ground is constructing roadbed or road surface by excavating, this Kind roadbed is known as cutting, and the side slope that excavating cut slope is formed is known as cut slope.Cut slope is through excavating the artificial side formed Slope, that excavates Unloading Deformation lasts dynamic and the dynamic change of rule and side slope environmental background factor, to stable slope State has obvious action and influence, and embodies specific Aging Characteristic.
Cut slope is the important component of road engineering, and the unstable failure of side slope directly endangers and threatens traffic operation Unimpeded and public safety.
The expressway construction in mountain area inevitably meets with a large amount of deeply-excavated cuts and high-filled embankment slope project, Side slope fails with landslide accident as one of focus in Highway Construction in Mountainous Area and difficult point.In addition, railway, the energy, mine, Water conservancy construction engineering field all inevitably meets with a large amount of high gradient slope and deep concave edge slope, and the success or failure of these slope projects are One of factor of entire engineering construction success or failure is restricted through becoming.
Landslide is considered always endangering together with earthquake, flood, disease four big disasters of human survival and development.Landslide Be sufficiently complex dynamic process, relate in one aspect to mechanics and the material internal factor of ground composition, on the other hand by Topography and geomorphology, geologic structure type compositing characteristic, and influenced with complicated external factor such as the influences of environment.Rainfall is especially Heavy showers, the influence of heavy rain directly influence the stability of side slope.
During construction and excavation, due to no special protection, and influenced by rain factor, be easy to cause rain The generation for the large area that comes down when season excavates.Side slope slump when especially rainy season excavates in digging process in order to prevent, it is proposed that Compartment digging mode, remaining soils back-pressure slope foot form counter-pressure.
Just there are ratio of slope method and loss of weight design, height and slope by the control side slope of reasonable design in the design of side slope Degree, so as to ensure the slope stability after construction;It is preloading with the corresponding another technology of off-load in Landslide Treatment technology Anti-skid technology, it be by anti-skid section of (generally in the lower part on the landslide) preloading on landslide improving the anti-skid power on landslide so that Landslide is in stable method.The patented method improves the anti-skid power on landslide so that landslide is in steady similar to slope foot preloading It is fixed.
For a natural slopes before excavation Unloading Effect is not affected by, crustal stress is certain value, is made by off-load is excavated With rear, slopes will generate stress release and adjustment.Cutting Excavation of Expressway causes slopes to be in unloading condition.During Slope excavation, Slopes internal stress is readjusted in a certain range during rebuilding new mechanical balance system, and forming new slopes should The field of force.There is stresses re-distribution and stress concentration effect phenomenon near the lateral free face of slopes in new stress field, and is excavating Expanding rebound on free face direction, the stresses re-distribution and the expansion springback process of slopes free face in slopes are wanted to contact, Slopes undergo digging process, and stress state is adjusted by natural strain condition to new stress field.Slope excavating, which belongs to, laterally to be unloaded Lotus acts on, and stress release, which generates relaxation deformation, causes slope instability to destroy.
Invention content
The problem of for background technology, excavation and protection the purpose of the present invention is to provide a kind of slope construction Method, the longitudinally spaced excavation of side slope of the application is safe and reliable with means of defence stage by stage, and clear principle, construction technology is simple, Operating method is ripe, and safety and economic benefit are huge, the problem of for efficiently against background technology.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of longitudinally spaced excavation of side slope and protection construction method stage by stage, which is characterized in that sequentially follow the steps below:
1) it along the longitudinally spaced excavation of roadbed, leaves and takes part soil body A and does not excavate, form reserved part soil body A and excavate part Spaced apart pattern;
2) part is excavated to carry out according to top-down sequence, if slope height is equal to or more than 20m, classification is excavated, Classification height is 8m to 10m according to every grade of step height of specification, and step width is 2m to 3m, if slope height is more than the side of 30m The step of 4m to 6m is stayed on slope at middle part, and digging process side slope ratio of slope m is controlled, and slope gradient m meets soil-slope:1: 1~1:1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~1:1;Weak-weathered rock side slope:1:0.5~ 1:0.75;
3) rapid after the completion of excavating to carry out protection works construction, protection should excavate primary protection level-one,
4) the part top-down sequences of soil body A will be left and taken and carry out classification excavation, if slope height is equal to or more than 20m When, classification is excavated, and classification height is 8m~10m according to every grade of step height of specification, and step width is 2m~3m, is highly more than The side slope of 30m stays the step of 4~6m at middle part, and digging process side slope ratio of slope m is controlled, and slope gradient m meets soil property side Slope:1:1~1:1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~1:1;Weak-weathered rock side slope:1: 0.5~1:0.75;
5) protection works construction is carried out immediately after the completion of every grade of excavation, seam crossing does not process.
The construction of gravity cover can be used in protection works construction, plant growing protection slope is squirted in Anchored frame beam or for rack plating zinc A method of selecting in the protection of iron wire grass planting on net or friction pile, grouting and anchor pole protection is constructed.
The gravity cover work progress is as follows, removes side slope slumping block first, then according to design side slope backfill rubble Dank materials are waited, and are fully compacted, on the slope step excavation, step reaches 3m width as far as possible, step tendency roadbed Horizontal slope is 4%, is then laid with anti-filter geotextiles in bottom surface, and longitudinal direction is also wanted step excavation and is laid with anti-at gravity cover terminus Geotextiles are filtered, then by spreading 15cm thickness plain concrete layers in two level Slope foot plate surface, charge for remittance in slopes is drained into side slope and is put down Platform semi-circular tube, then filler backfill to form gravity cover.
The beneficial effects of the invention are as follows:
Side slope longitudinally excavates reserved soil body A and is used for back-pressure slope foot, is used by mutual embedding make of back-pressure slope foot and the soil body To bear the sliding force of the soil body so that a kind of passive force type retaining structure that deformable body is stabilized.Remaining soils soil layer knot Structure is not destroyed like stake bottom is embedded in soil layer.
Description of the drawings
One of longitudinally spaced excavation construction processes of Fig. 1.
The two of the longitudinally spaced excavation construction processes of Fig. 2.
The three of the longitudinally spaced excavation construction processes of Fig. 3.
The four of the longitudinally spaced excavation construction processes of Fig. 4.
Fig. 5 is Taylor analysis method chart one.
Fig. 6 is Taylor analysis method chart two.
Fig. 7 is the cross-section diagram of gravity cover.
Specific embodiment
The present invention technical solution be:A kind of longitudinally spaced excavation of side slope and protection construction method stage by stage, it is special Sign is to include the following steps:
1) (side slope can also be excavated level-one using longitudinally spaced excavate from top to bottom before alternation excavation, such as schemed 1st, 2) mode excavates the soil body and is excavated to design position, leave and take part soil body A and do not excavate (reservation), for back-pressure slope foot (side slope Having in the control measure of deformation failure reduces sliding force, increases skid resistance;It chops off the head the principle of presser feet).
Soil body alternation excavation length, that is, slope toe excavation length a is up to nxH,nxValue can be according to ndAnd α is checked in by Fig. 5, Fig. 6, Wherein, Fig. 5 and Fig. 6, comes from《Soil Mechanics and Soil Science》Chapter 8, the Stability of Earth Slopes of slope stability analysis third section cohesive soil The Monolithic Stability Analysis in the circular slip of earth slope face of analysis -- the analysis method of Taylor.
Top of the slope excavation length 2Hm+nx(m is equal to the M in Fig. 5, case-insensitive to H.Excavation can also be classified, according to Unloading plat width adjustment top of the slope excavation length).
2) part being excavated to carry out according to top-down sequence, when slope height is equal to or more than 20m, classification is excavated, point Grade height is 8m to 10m according to every grade of step height of specification, and step (unloading plat) width is 2m to 3m, highly more than 30m's Side slope, stays the Wide Worktable of 4m to 6m at middle part, and when excavation should strictly control slope gradient m, soil-slope:1:1~1: 1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~1:1;Weak-weathered rock side slope:1:0.5~1: 0.75。
3) rapid after the completion of excavating to carry out protection works construction, protection should excavate primary protection level-one.Gravity cover can be used Surface construction (can also be carried out squirting in Anchored frame beam according to requirement of engineering plant growing protection slope or for hang the protection of galvanized wire mesh grass planting, Or friction pile, grouting and anchor pole protection), gravity cover work progress is as follows:
1. removing side slope slumping block first, then according to dank materials such as design side slope backfill rubbles, and fully it is compacted, Side slope stability is kept using the gravity of backfilling material itself, with reference to figure 7.It 2. should step excavation on the slope before backfill 001, step reaches 3m width as far as possible, and the horizontal slope of step tendency roadbed is 4%, anti-filter geotextiles is laid in bottom surface, in gravity Longitudinal direction also wants step excavation and is laid with anti-filter geotextiles 002 at cover terminus, to meet lateral stability of slope and drainage requirement. 3. by spreading 15cm thickness plain concrete layer 003 in two level Slope foot plate surface, charge for remittance in slopes is drained into plain stage of slope semi-circular tube 004.4. filler backfills, maximum particle diameter≤30cm of 005 backfilling material of gravity cover is formed, and maximum particle diameter is no more than layering and presses The 2/3 of real thickness.
All constructions for excavating part are completed stage by stage.
4) with it is all excavation part complete after, by it is remaining leave and take the part top-down sequences of soil body A carry out classification open Dig, if slope height be equal to or more than 20m, classification height according to every grade of step height of specification be 8m~10m, step (off-load Platform) width is 2m~3m, the highly side slope more than 30m, stays the Wide Worktable of 4~6m at middle part, when excavation, copes with slope gradient M is strictly controlled, soil-slope:1:1~1:1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~ 1:1;Weak-weathered rock side slope:1:0.5~1:0.75.
5) progress gravity cover construction immediately is excavated after the completion for every grade, gravity cover constructs section with reference to figure 7.Gravity cover Seam crossing does not process, in case side slope destroys gravity cover when generating differential settlement.1. side slope slumping block is removed first, then It according to dank materials such as design side slope backfill rubbles, and is fully compacted, side is kept using the gravity of backfilling material itself Slope stability.2. step excavation 001, step should reach 3m width as far as possible on the slope before backfill, step 001 is inclined to road The horizontal slope of base is 4%, is laid with anti-filter geotextiles 002 in bottom surface, step excavation and paving are also wanted in longitudinal direction at gravity cover terminus If anti-filter geotextiles 002, to meet lateral stability of slope and drainage requirement.It is 3. thick by spreading 15cm in two level Slope foot plate surface Charge for remittance in slopes is drained into plain stage of slope semi-circular tube 004 by plain concrete layer 003.4. filler backfills, gravity cover 005 is formed, Maximum particle diameter≤30cm of backfilling material, and maximum particle diameter is no more than the 2/3 of compaction in layers thickness.
The above-described embodiments are merely illustrative of preferred embodiments of the present invention, not to the model of the present invention It encloses and is defined, under the premise of design spirit of the present invention is not departed from, various changes of the relevant technical staff in the field to the present invention Shape and improvement should all expand as determined by claims of the present invention in protection domain.

Claims (3)

1. a kind of longitudinally spaced excavation of side slope and protection construction method stage by stage, which is characterized in that sequentially follow the steps below:
1) it along the longitudinally spaced excavation of roadbed, leaves and takes part soil body A and does not excavate, form reserved part soil body A and excavate part interval The pattern of arrangement;
2) it excavates part to carry out according to top-down sequence, if slope height is equal to or more than 20m, classification is excavated, classification Height is 8m to 10m according to every grade of step height of specification, and step width is 2m to 3m, if slope height is more than the side slope of 30m, The step of 4m to 6m is stayed at middle part, and digging process side slope ratio of slope m is controlled, and slope gradient m meets soil-slope:1:1~1: 1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~1:1;Weak-weathered rock side slope:1:0.5~1: 0.75;
3) rapid after the completion of excavating to carry out protection works construction, protection should excavate primary protection level-one,
4) the part top-down sequences of soil body A will be left and taken and carry out classification excavation, if slope height is equal to or more than 20m, point Grade is excavated, and classification height is 8m~10m according to every grade of step height of specification, and step width is 2m~3m, the highly side more than 30m The step of 4~6m is stayed on slope at middle part, and digging process side slope ratio of slope m is controlled, and slope gradient m meets soil-slope:1:1 ~1:1.5;Soil-like material slope:1:1~1:1.5;Strong-weathered rock side slope:1:0.75~1:1;Weak-weathered rock side slope:1:0.5~1: 0.75;
5) protection works construction is carried out immediately after the completion of every grade of excavation, seam crossing does not process.
2. the longitudinally spaced excavation of a kind of side slope according to claim 1 and protection construction method stage by stage, which is characterized in that The protection works construction uses gravity cover to construct, plant growing protection slope is squirted in Anchored frame beam or to hang galvanized wire mesh grass planting A method of selecting in protection or friction pile, grouting and anchor pole protection is constructed.
3. the longitudinally spaced excavation of a kind of side slope according to claim 2 and protection construction method stage by stage, which is characterized in that The gravity cover work progress is as follows, removes side slope slumping block first, then according to water penetrations such as design side slope backfill rubbles Material, and be fully compacted, step excavation, step reach 3m width as far as possible on the slope, and the horizontal slope of step tendency roadbed is 4%, anti-filter geotextiles then are laid in bottom surface, longitudinal direction also wants step excavation and is laid with anti-filter geotechnique at gravity cover terminus Charge for remittance in slopes then by spreading 15cm thickness plain concrete layers in two level Slope foot plate surface, is drained into plain stage of slope semicircle by cloth Pipe, then filler backfills to form gravity cover.
CN201711364613.3A 2017-12-18 2017-12-18 A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage Pending CN108166509A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711364613.3A CN108166509A (en) 2017-12-18 2017-12-18 A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711364613.3A CN108166509A (en) 2017-12-18 2017-12-18 A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage

Publications (1)

Publication Number Publication Date
CN108166509A true CN108166509A (en) 2018-06-15

Family

ID=62522333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711364613.3A Pending CN108166509A (en) 2017-12-18 2017-12-18 A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage

Country Status (1)

Country Link
CN (1) CN108166509A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110222944A (en) * 2019-05-15 2019-09-10 长江勘测规划设计研究有限责任公司 A kind of ground matter slope excavating method based on rainfall intensity
CN113174956A (en) * 2021-04-29 2021-07-27 中交路桥建设有限公司 Method for reinforcing wind-blown sand high-steep slope construction platform and wind-blown sand high-steep slope structure
CN114658079A (en) * 2022-04-06 2022-06-24 长江勘测规划设计研究有限责任公司 Dumping yard waste soil stacking method based on rain intensity
CN115094907A (en) * 2022-07-13 2022-09-23 上海勘察设计研究院(集团)有限公司 Layered sectional type upright self-stabilizing enclosure structure and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
CN103850257A (en) * 2014-03-21 2014-06-11 中国水电顾问集团成都勘测设计研究院有限公司 Digging slope body structure used for rock side slope and digging construction method of digging slope body structure
CN104500079A (en) * 2014-11-26 2015-04-08 中国电建集团成都勘测设计研究院有限公司 Tunnel excavation method in shallow-buried bias-pressure toppling-deformation bulk solid and strong-unloading rock structure
CN106245481A (en) * 2016-08-26 2016-12-21 中铁四局集团有限公司 Construction method for maintaining integrity and stability of roadbed under complex geological condition

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
CN103850257A (en) * 2014-03-21 2014-06-11 中国水电顾问集团成都勘测设计研究院有限公司 Digging slope body structure used for rock side slope and digging construction method of digging slope body structure
CN104500079A (en) * 2014-11-26 2015-04-08 中国电建集团成都勘测设计研究院有限公司 Tunnel excavation method in shallow-buried bias-pressure toppling-deformation bulk solid and strong-unloading rock structure
CN106245481A (en) * 2016-08-26 2016-12-21 中铁四局集团有限公司 Construction method for maintaining integrity and stability of roadbed under complex geological condition

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110222944A (en) * 2019-05-15 2019-09-10 长江勘测规划设计研究有限责任公司 A kind of ground matter slope excavating method based on rainfall intensity
CN110222944B (en) * 2019-05-15 2023-09-19 长江勘测规划设计研究有限责任公司 Rock-soil slope excavation method based on rainfall intensity
CN113174956A (en) * 2021-04-29 2021-07-27 中交路桥建设有限公司 Method for reinforcing wind-blown sand high-steep slope construction platform and wind-blown sand high-steep slope structure
CN114658079A (en) * 2022-04-06 2022-06-24 长江勘测规划设计研究有限责任公司 Dumping yard waste soil stacking method based on rain intensity
CN114658079B (en) * 2022-04-06 2023-08-29 长江勘测规划设计研究有限责任公司 Method for stacking waste soil in dumping site based on rain intensity
CN115094907A (en) * 2022-07-13 2022-09-23 上海勘察设计研究院(集团)有限公司 Layered sectional type upright self-stabilizing enclosure structure and construction method

Similar Documents

Publication Publication Date Title
Zaruba et al. Landslides and their control
Song et al. A large-scale colluvial landslide caused by multiple factors: mechanism analysis and phased stabilization
CN102493303B (en) Road bed embedding and broadening method
CN108166509A (en) A kind of longitudinally spaced excavation of slope construction and protection construction method stage by stage
CN101598028A (en) Lining structure for super large section water-rich loess tunnel of high-speed railroad
Youd et al. Liquefaction and secondary ground failure
Chen et al. Failure Analysis of a Highway Cut Slope with Anti‐Slide Piles
CN107700514B (en) Processing method for selecting structural style of soft foundation
Gu et al. Analysis and prevention of sinkhole collapses during the reconstruction and extension of Guang-Qing freeway, china
CN113863076B (en) Sinking road construction method under sand bridge
Tao et al. Study on Deformation Mechanism and Control Measures of Tanziyan Landslide
CN110528539A (en) A kind of Construction of Civil Engineering method quickly handling mud-rock flow, landslide collapsing using weatherability woven bag
CN110219248A (en) Antidumping expedient bridge pier construction method and antidumping expedient bridge construction method
Si-yi et al. Characteristics and mechanism of loess landslide induced by drill vibration
Yang et al. High fill embankment of collapsible loess settlement observation and research
Yang Geotechnical design of bridge foundations and approaches in hilly granite formation
Liu Force Analysis of Anti-slip Pile Bodies on Soil Mudstone Slopes Under Heavy Rainfall
Skuodis et al. Vibrations measurement of the funicular generated vibrations on Gediminas Hill north part slope
Zeng et al. Study on water damage mechanism and emergency restore of fill subgrade upon squashy slope foundation in mountain area
Yang et al. Geological Characteristics of the Tangjiashan Barrier Lake Area
Lv et al. Distribution Characteristics of Geological Disasters and Main Control Measures in Shandong Province
Rahmadania et al. Case study of the causes of failure of combination of gabion and geotextile construction to handle landslides on the slope of kariangau substation, balikpapan, east borneo
Jelisavac et al. Geotechnical investigations of the landslide “Lapisnica” aimed at the repair of main road M-5 in the vicinity of Sarajevo
Hunt et al. Stability of Slopes
Hardiman et al. Stability Analysis Of Embankment Above Soft Soil Slopes At Former Coal Mining Pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180615