CN108163715A - Hanging in a kind of day walks axis cable and climbs fixed frame - Google Patents

Hanging in a kind of day walks axis cable and climbs fixed frame Download PDF

Info

Publication number
CN108163715A
CN108163715A CN201810130691.5A CN201810130691A CN108163715A CN 108163715 A CN108163715 A CN 108163715A CN 201810130691 A CN201810130691 A CN 201810130691A CN 108163715 A CN108163715 A CN 108163715A
Authority
CN
China
Prior art keywords
wire casing
cable
day
fixed frame
housing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810130691.5A
Other languages
Chinese (zh)
Other versions
CN108163715B (en
Inventor
董洋洋
李修武
何忠挺
张成梁
李生龙
孙冬炜
单齐勇
董德权
陈竞新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Fanuc Robotics Co Ltd
Original Assignee
Shanghai Fanuc Robotics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Fanuc Robotics Co Ltd filed Critical Shanghai Fanuc Robotics Co Ltd
Priority to CN201810130691.5A priority Critical patent/CN108163715B/en
Publication of CN108163715A publication Critical patent/CN108163715A/en
Application granted granted Critical
Publication of CN108163715B publication Critical patent/CN108163715B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/12Arrangements of means for transmitting pneumatic, hydraulic, or electric power to movable parts of devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

Axis cable is walked the invention discloses hanging in a kind of day to climb fixed frame, including:Wire casing fixed part includes wire casing fixed frame, left socle and right support;The upper end of wire casing fixed frame is connected to the lower face for hanging guide rail in day by left socle and right support;Wire casing housing is fixed on wire casing fixed part;Several cable fixing portions are in left-right direction through wire casing housing, and several cable fixing portions are from top to bottom set in turn in wire casing housing;Cable is hung by day and hung down on the drag chain on guide rail to wire casing housing, and the lower end of cable is extended by the lower end of wire casing housing.When present invention design is so that cable hangs guide rail down from day, cable is fixed in wire casing, will not be shaken;Meanwhile cable is built in wire casing, cable is not pullled and is worn.

Description

Hanging in a kind of day walks axis cable and climbs fixed frame
Technical field
Axis cable is walked the present invention relates to the technical field of fixed frame more particularly to hanging in a kind of day to climb the technology of fixed frame Field.
Background technology
In intelligence manufacture industry, day hangs the walking axle of form with more and more extensive.It is hung in day in form walking axle, generally Cable directly will hang the drag chain end of guide rail down from being fixed on day after drag chain, and cable is not fixed, directly swing it is lower after point Toward each process equipment and control device.The drag chain end that cable directly hangs guide rail from day down, is not fixed, and is easily shaken, long The suspension of time uses, and cable there is a possibility that drawing is bad, easy to wear and unsightly simultaneously because cable does not protect.
Invention content
Against the above deficiency, axis cable is walked the object of the present invention is to provide hanging in a kind of day to climb fixed frame.
In order to achieve the above object, the present invention uses following technical scheme:
Hanging in a kind of day walks axis cable and climbs fixed frame, wherein, including:
Wire casing fixed part, the wire casing fixed part include wire casing fixed frame, left socle and right support;The wire casing is consolidated The upper end for determining frame is connected to the lower face for hanging guide rail in day by the left socle and the right support;
Wire casing housing, the wire casing housing are fixed on the wire casing fixed part;
Several cable fixing portions, several cable fixing portions run through the wire casing housing in left-right direction, and Several cable fixing portions are from top to bottom set in turn in the wire casing housing;
Cable, the cable is hung by the day to hang down on the drag chain on guide rail to the wire casing housing, the cable Extended by the lower end of the wire casing housing lower end.
Above-mentioned hanging in a kind of day walks axis cable and climbs fixed frame, wherein, the wire casing fixed frame for one " [" template, and It is described that " trailing flank that guide rail is hung in the front of [" template with the day is concordant.
Above-mentioned hanging in a kind of day walks axis cable and climbs fixed frame, wherein, the left socle is consistent with the right support structure, The left socle and the right support include a crossbeam and a floor;The crossbeam forms L-type structure with the floor;It is described The crossbeam of left socle is fixed on the lower face that the day hangs guide rail, and the floor of the left socle is fixed on the wire casing The left side of fixed frame;The crossbeam of the right support is fixed on the lower face that the day hangs guide rail, the right support it is described Floor is fixed on the right side of the wire casing fixed frame.
Above-mentioned hanging in a kind of day walks axis cable and climbs fixed frame, wherein, the wire casing housing includes housing parts and cover Part;The end face of the housing parts is fixedly connected on the front of the wire casing fixed frame, the housing section by several screws The rear side cover divided has the cap portion;The wire casing housing is a L-type housing, and the right angle of the wire casing housing is set as oblique Face.
Above-mentioned hanging in a kind of day walks axis cable and climbs fixed frame, wherein, each cable fixing portion includes nut, fixed spiral shell Bar and binding band;The standing screw runs through the both side plate of the housing parts, and described in the standing screw perforative one One end of side plate is cased with the nut;The cable is tied by band in the standing screw.
With above technical scheme, following advantageous effect can be reached:
When present invention design is so that cable hangs guide rail down from day, cable is fixed in wire casing, will not be shaken;Meanwhile line Cable is built in wire casing, and cable is not pullled and worn.
Description of the drawings
Fig. 1 be the present invention hanging in a kind of day walk axis cable climb fixed frame an angle stereogram;
Fig. 2 be the present invention hanging in a kind of day walk axis cable climb fixed frame include wire casing housing an angle solid Figure;
Fig. 3 be the present invention hanging in a kind of day walk axis cable climb fixed frame do not include wire casing housing another angle it is vertical Body figure;
Fig. 4 is that the hanging in a kind of day of the present invention walks axis cable and climbs the side view of fixed frame;
Fig. 5 be the present invention hanging in a kind of day walk axis cable climb fixed frame cable fixing portion schematic diagram;
Fig. 6 is that the hanging in a kind of day of the present invention walks axis cable and climbs the rearview of fixed frame;
Fig. 7 be the present invention hanging in a kind of day walk axis cable climb fixed frame wire casing fixed part scheme of installation.
In attached drawing:1st, wire casing fixed part;11st, wire casing fixed frame;12nd, left socle;13rd, right support;141st, crossbeam;142、 Floor;2nd, wire casing housing;21st, housing parts;22nd, cap portion;23rd, screw;24th, inclined-plane;3rd, cable fixing portion;31st, spiral shell It is female;32nd, standing screw;33rd, binding band;4th, cable;5th, day hangs guide rail;51st, drag chain.
Specific embodiment
The invention will be further described in the following with reference to the drawings and specific embodiments, but not as limiting to the invention.
Fig. 1 be the present invention hanging in a kind of day walk axis cable climb fixed frame an angle stereogram;Fig. 2 is the present invention Hanging in a kind of day walk axis cable climb fixed frame include wire casing housing an angle stereogram;Fig. 3 is the one of the present invention Kind of day hanging walk axis cable climb fixed frame do not include wire casing housing another angle stereogram;Fig. 4 is one kind of the present invention Its hanging walks axis cable and climbs the side view of fixed frame;Fig. 5 is that the hanging in a kind of day of the present invention walks axis cable and climbs fixed frame The schematic diagram of cable fixing portion;Fig. 6 is that the hanging in a kind of day of the present invention walks axis cable and climbs the rearview of fixed frame;Fig. 7 is The present invention hanging in a kind of day walk axis cable climb fixed frame wire casing fixed part scheme of installation.
It refers to shown in Fig. 1 to Fig. 6, in a kind of preferred embodiment, hanging in a kind of day walks axis cable and climbs fixed frame, Wherein, including:
Wire casing fixed part 1, wire casing fixed part 1 include wire casing fixed frame 11, left socle 12 and right support 13;Wire casing is consolidated The upper end for determining frame 11 is connected to the lower face for hanging guide rail 5 in day by left socle 12 and right support 13.
Wire casing housing 2, wire casing housing 2 are fixed on wire casing fixed part 1.
Several cable fixing portions 3, several cable fixing portions 3 are in left-right direction through wire casing housing 2, and if main line Cable fixed part 3 is from top to bottom set in turn in wire casing housing 2.
Cable 4, the drag chain 51 that cable 4 is hung by day on guide rail 5 hang down to wire casing housing 2, and the lower end of cable 4 is by wire casing shell Extend the lower end of body 2.
It these are only preferred embodiments of the present invention, not thereby limit embodiments of the present invention and protection domain.
Further, in a kind of preferred embodiment, the upper surface that day hangs guide rail 5 sets a drag chain 51, and cable 4 passes through drag chain It will be set in wire casing housing 2, and extended away by the lower end of wire casing housing 2 directly from 51 end of drag chain down after 51.
Further, in a kind of preferred embodiment, wire casing fixed frame 11 for one " [" template, and " front of [" template with The trailing flank that it hangs guide rail 5 is concordant.
Further, in a kind of preferred embodiment, left socle 12 is consistent with 13 structure of right support, left socle 12 and right support 13 include a crossbeam 141 and a floor 142;Crossbeam 141 forms L-type structure with floor 142;The crossbeam 141 of left socle 12 is solid The lower face of guide rail 5 is hung due to day, the floor 142 of left socle 12 is fixed on the left side of wire casing fixed frame 11;The horizontal stroke of right support 13 Beam 141 is fixed on the lower face that day hangs guide rail 5, and the floor 142 of right support 13 is fixed on the right side of wire casing fixed frame 11.
Further, in a kind of preferred embodiment, wire casing housing 2 includes housing parts 21 and cap portion 22;Housing section Points 21 end face is fixedly connected on the front of wire casing fixed frame 11 by several screws 23, and the rear side of housing parts 21 is stamped cover Part 22;Wire casing housing 2 is a L-type housing, and the right angle of wire casing housing 2 is set as inclined-plane 24 so that cable 4 is in right angle turn There is larger leeway.
Further, in a kind of preferred embodiment, each cable fixing portion 3 includes nut 31, standing screw 32 and pricks Tape 33;Standing screw 32 runs through the both side plate of housing parts 21, and one end of 32 perforative side plate of standing screw is cased with Nut 31;Cable 4 is tied by binding band 33 in standing screw 32.
It these are only preferred embodiments of the present invention, not thereby limit embodiments of the present invention and protection domain, it is right For those skilled in the art, it should can appreciate that and all be replaced with being equal made by description of the invention and diagramatic content It changes and obviously changes obtained scheme, should all include within the scope of the present invention.

Claims (5)

1. hanging in a kind of day walks axis cable and climbs fixed frame, which is characterized in that including:
Wire casing fixed part, the wire casing fixed part include wire casing fixed frame, left socle and right support;The wire casing fixed frame Upper end the lower face for hanging guide rail in day is connected to by the left socle and the right support;
Wire casing housing, the wire casing housing are fixed on the wire casing fixed part;
Several cable fixing portions, several cable fixing portions run through the wire casing housing, and several in left-right direction The cable fixing portion is from top to bottom set in turn in the wire casing housing;
Cable, the cable is hung by the day to hang down on the drag chain on guide rail to the wire casing housing, the lower end of the cable Extended by the lower end of the wire casing housing.
2. hanging in a kind of day walks axis cable and climbs fixed frame according to claim 1, which is characterized in that the wire casing fixed frame For one " [" template, and described " trailing flank that guide rail is hung in the front of [" template with the day is concordant.
3. hanging in a kind of day walks axis cable and climbs fixed frame according to claim 2, which is characterized in that the left socle and institute It is consistent to state right support structure, the left socle and the right support include a crossbeam and a floor;The crossbeam and the rib Plate forms L-type structure;The crossbeam of the left socle is fixed on the lower face that the day hangs guide rail, the left socle it is described Floor is fixed on the left side of the wire casing fixed frame;The crossbeam of the right support is fixed on the lower end that the day hangs guide rail Face, the floor of the right support are fixed on the right side of the wire casing fixed frame.
4. hanging in a kind of day walks axis cable and climbs fixed frame according to claim 2, which is characterized in that the wire casing housing packet Include housing parts and cap portion;The end face of the housing parts is fixedly connected on the wire casing fixed frame by several screws Front, the rear side cover of the housing parts have the cap portion;The wire casing housing be a L-type housing, the wire casing housing Right angle be set as inclined-plane.
5. hanging in a kind of day walks axis cable and climbs fixed frame according to claim 2, which is characterized in that each cable fixed part Divide and include nut, standing screw and binding band;The standing screw runs through the both side plate of the housing parts, and the fixation One end of perforative one side plate of screw rod is cased with the nut;The cable is tied by band in the standing screw.
CN201810130691.5A 2018-02-08 2018-02-08 Lifting and traveling axial cable climbing fixing frame Active CN108163715B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810130691.5A CN108163715B (en) 2018-02-08 2018-02-08 Lifting and traveling axial cable climbing fixing frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810130691.5A CN108163715B (en) 2018-02-08 2018-02-08 Lifting and traveling axial cable climbing fixing frame

Publications (2)

Publication Number Publication Date
CN108163715A true CN108163715A (en) 2018-06-15
CN108163715B CN108163715B (en) 2024-01-23

Family

ID=62513864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810130691.5A Active CN108163715B (en) 2018-02-08 2018-02-08 Lifting and traveling axial cable climbing fixing frame

Country Status (1)

Country Link
CN (1) CN108163715B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB759894A (en) * 1954-11-09 1956-10-24 William E Cary Ltd Cable trunking
KR960041032A (en) * 1996-07-30 1996-12-17 홍경호 Elevator hoistway cable connection branching method and apparatus
KR100984124B1 (en) * 2009-12-02 2010-09-28 (주)홍주산업 Cable trench for crane
CN104753005A (en) * 2015-03-26 2015-07-01 南车南京浦镇车辆有限公司 Mounting method of railway vehicle roof line slot
CN104917118A (en) * 2015-05-14 2015-09-16 江苏有能新能源有限公司 Combined fireproof cable tray for power supply system cable and installation method of combined fireproof cable tray
CN206865040U (en) * 2017-06-05 2018-01-09 上海西电高压开关有限公司 One kind can adjust moveable Cubicle Gas-Insulated Switchgear wiring slot way
CN208166399U (en) * 2018-02-08 2018-11-30 上海发那科机器人有限公司 Hanging in a kind of day walks axis cable and climbs fixed frame

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB759894A (en) * 1954-11-09 1956-10-24 William E Cary Ltd Cable trunking
KR960041032A (en) * 1996-07-30 1996-12-17 홍경호 Elevator hoistway cable connection branching method and apparatus
KR100984124B1 (en) * 2009-12-02 2010-09-28 (주)홍주산업 Cable trench for crane
CN104753005A (en) * 2015-03-26 2015-07-01 南车南京浦镇车辆有限公司 Mounting method of railway vehicle roof line slot
CN104917118A (en) * 2015-05-14 2015-09-16 江苏有能新能源有限公司 Combined fireproof cable tray for power supply system cable and installation method of combined fireproof cable tray
CN206865040U (en) * 2017-06-05 2018-01-09 上海西电高压开关有限公司 One kind can adjust moveable Cubicle Gas-Insulated Switchgear wiring slot way
CN208166399U (en) * 2018-02-08 2018-11-30 上海发那科机器人有限公司 Hanging in a kind of day walks axis cable and climbs fixed frame

Also Published As

Publication number Publication date
CN108163715B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN206718961U (en) A kind of band terraced fuel tank to pedal
CN108163715A (en) Hanging in a kind of day walks axis cable and climbs fixed frame
CN208166399U (en) Hanging in a kind of day walks axis cable and climbs fixed frame
CN106555501A (en) A kind of cat-head transmission tower suitable for single time overhead transmission line cable T joint
CN208216622U (en) Intelligent driving road condition analyzing equipment and its mounting structure
CN201636499U (en) Gimbal capable of completely hiding wiring harness
CN206646291U (en) A kind of clothes hanger device of security protection
CN205840099U (en) Metal batten Os Draconis ceiling structure
CN204457068U (en) Municipal engineering safety guard net
CN108245848A (en) A kind of telescopic climbers of pedal
CN209013300U (en) A kind of oil-net structure
CN203290486U (en) Cabinet hanger
CN206020051U (en) A kind of Novel car suspension system intelligent pressure monitoring alarm device
CN107542201A (en) Lightgage steel joist aluminium grid ceiling
CN206128798U (en) Cat head tower suitable for single time overhead line cable T connects
CN206667937U (en) A kind of fence of horse racing runway with defencive function
CN205742869U (en) A kind of combined floor
CN204915553U (en) Pencil fixed mounting support
CN203898983U (en) Human body falling prevention safety device of pole
CN204520060U (en) Photo frame buckles
CN205637290U (en) Furred ceiling aluminium alloy
CN205001257U (en) Balancing piece structure for compressor
CN206128848U (en) Transmission tower safety protective guard
CN208982441U (en) The fastening bolt that automobile uses
CN211428772U (en) Wire jumping prevention device of paying-off tackle

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant