CN108149852A - A kind of double wave ribbon skylight node upper end connecting structure and its installation method - Google Patents
A kind of double wave ribbon skylight node upper end connecting structure and its installation method Download PDFInfo
- Publication number
- CN108149852A CN108149852A CN201810083874.6A CN201810083874A CN108149852A CN 108149852 A CN108149852 A CN 108149852A CN 201810083874 A CN201810083874 A CN 201810083874A CN 108149852 A CN108149852 A CN 108149852A
- Authority
- CN
- China
- Prior art keywords
- ribbon skylight
- ribbon
- skylight
- metal roofing
- roofing board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D3/00—Roof covering by making use of flat or curved slabs or stiff sheets
- E04D3/36—Connecting; Fastening
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D3/00—Roof covering by making use of flat or curved slabs or stiff sheets
- E04D3/38—Devices for sealing spaces or joints between roof-covering elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Abstract
The present invention provides a kind of double wave ribbon skylight node upper end connecting structure and its installation methods, realize the secure seal connection of double wave ribbon skylight node upper end junction, have good waterproof effect for the rainwater flow down from top of the slope.Installation method, including:Hole upper end-face edge at the ribbon skylight hole of roofing fixes the heat-preservation cotton veneer turned with pressure cotton part;The super bearing of ribbon skylight is installed on the purlin of the hole upper end-face edge;Ribbon skylight bearing, upper end installation roof boarding sliding support are installed in the lower end of the super bearing of the ribbon skylight;Ribbon skylight is installed on the ribbon skylight bearing;Saddle cushion is installed at the center wave crest of the ribbon skylight;The liner plate of overlap joint is installed, is laid with butyl clay;Metal roofing board on the left of upper end, metal roofing board on the right side of upper end are installed;Stainless steel press strip is installed;It lockstitches a border to metal roofing board.
Description
Technical field
The present invention relates to construction steel structure field, more particularly to a kind of double wave ribbon skylight node upper end connecting structure and its
Installation method.
Background technology
Many workshops use the form of steel construction at present, and steel-structure factory building feature has:1st, steel building light weight, intensity
Height, span are big;2nd, the steel building construction period is short, accordingly reduces cost of investment;3rd, steel building fire line is high, anticorrosion
Property is strong;4th, steel building is moved conveniently, and recycling is pollution-free.
Fig. 1 is the schematic diagram of steel-structure factory building, as shown in Figure 1, being the both sides to the left and right with certain slope at the top of workshop
The metal Roof 101 of extension is tilted, the left and right sides is gable 103, and front is cornice 102, has main body steelframe etc. inside workshop
Support construction.Wherein, metal Roof 101 and on-plane surface, as shown in figure 2, metal Roof have periodic 211 trough of wave crest
Structure 212.
Metal Roof is assembled by multiple roof boardings, and roofing has certain gradient, for daylighting, in acclive room
The ribbon skylight of energy transmitted light is provided on face, ribbon skylight is also equipped with Wave crest and wave trough structure.Therefore, on inclined roofing,
Ribbon skylight and being connected for roof boarding, are extremely difficult, often result in seepy question, the prior art in order to prevent breathe freely by leak, can use
A large amount of fluid sealants and water-repellent paint are sealed, and cause shape lofty, waste of material and waterproof effect is undesirable, therefore,
Ribbon skylight is connected sealing problem with roof boarding, is to have the problem of to be solved.
Invention content
The invention aims to provide a kind of double wave ribbon skylight node upper end connecting structure and its installation method, realize
The robust seal connection of double wave ribbon skylight node upper end junction there is protection well to imitate the rainwater flow down from top of the slope
Fruit.
To achieve these goals, the present invention provides a kind of installation sides of double wave ribbon skylight node upper end connecting structure
Method, including:
Step 1: the hole upper end-face edge at the ribbon skylight hole on roof, the guarantor turned is fixed with pressure cotton part
Warm cotton patch face;
Step 2: the super bearing of ribbon skylight is installed in the hole upper end-face edge;
Step 3: ribbon skylight bearing is installed in the lower end of the super bearing of the ribbon skylight;
Step 4: roof boarding sliding support is installed in the upper end of the super bearing of the ribbon skylight;
Step 5: installing ribbon skylight on the ribbon skylight bearing, the ribbon skylight hole is covered;
Step 6: Saddle cushion is installed at the center wave crest of the ribbon skylight;
Step 7: the liner plate of the outside installation overlap joint in the ribbon skylight upper end-face edge of the ribbon skylight;
Step 8: the ribbon skylight upper end-face edge in the ribbon skylight is laid with butyl clay;
Step 9: the metal roofing board on the left of ribbon skylight upper end-face edge installation upper end;
Step 10: the metal roofing board on the right side of ribbon skylight upper end-face edge installation upper end;
Step 11: it is installed respectively not on metal roofing board on the right side of metal roofing board and the upper end on the left of the upper end
Become rusty steel press strip;
Step 12: it lockstitches a border to metal roofing board on the right side of metal roofing board on the left of the upper end and the upper end.
Preferably, it in above-mentioned installation method, in the step 6, is set between the Saddle cushion and the ribbon skylight
There is butyl clay.
Preferably, in above-mentioned installation method, in the step 8, including:In the ribbon skylight of the ribbon skylight
One layer of butyl clay is laid at the trough of upper end-face edge, two layers of butyl rubber is laid at the wave crest of the ribbon skylight upper end-face edge
Mud.
Preferably, it in above-mentioned installation method, is further included before the step 10:In the left side metal roofing board
Butyl clay is laid at lock seaming.
In order to preferably realize goal of the invention, the present invention also provides a kind of double wave ribbon skylight node upper end connecting structure, packets
It includes:
Cotton part is pressed, is arranged on the hole upper end-face edge at the ribbon skylight hole on roof, and the fixed heat preservation turned
Cotton patch face;
The super bearing of ribbon skylight, mounted on the hole upper end-face edge;
Ribbon skylight bearing, mounted on the lower end of the super bearing of the ribbon skylight;
Roof boarding sliding support, mounted on the upper end of the super bearing of the ribbon skylight;
Ribbon skylight on the ribbon skylight bearing, and covers the ribbon skylight hole;
Saddle cushion, at the center wave crest of the ribbon skylight;
The liner plate of overlap joint, mounted on the outside of the ribbon skylight upper end-face edge of the ribbon skylight;
Metal roofing board on the left of upper end, mounted on the left side of the ribbon skylight upper end-face edge;
Metal roofing board on the right side of upper end, mounted on the right side of the ribbon skylight upper end-face edge;
Metal roofing board is connected with metal roofing board on the right side of the upper end by lock seaming on the left of the upper end.
Preferably, it in above-mentioned double wave ribbon skylight node upper end connecting structure, further includes:
Two stainless steel press strips are separately mounted on the left of the upper end on metal roofing board and metal house on the right side of the upper end
On panel.
Preferably, in above-mentioned double wave ribbon skylight node upper end connecting structure, the end edge on the ribbon skylight of the ribbon skylight
Edge is equipped with butyl clay.
Preferably, in above-mentioned double wave ribbon skylight node upper end connecting structure, between the Saddle cushion and the ribbon skylight
It is provided with butyl clay.
Preferably, in above-mentioned double wave ribbon skylight node upper end connecting structure, in the lock seaming of the left side metal roofing board
Place is equipped with butyl clay.
The embodiment of the present invention has following technique effect:
1) in the embodiment of the present invention, ribbon skylight bearing 701 and sliding support by the super bearing 601 of ribbon skylight and thereon
801 realize that ribbon skylight is connected with the overlap joint of roof boarding, by the pressure cotton part 502 that is stacked, liner plate 1101, butyl clay and
Stainless steel press strip 1501, which is realized, to be compressed and seals, so as to be realized on double wave ribbon skylight node by this structure being stacked
The robust seal connection of junction is held, there is good protection effect for the rainwater flow down from top of the slope.
2) there is the Saddle cushion in the present invention upper end to meet water the full-closed structure in direction, upper end can be further prevented to flow down
Rainwater penetrate into, and the structure after the lock seaming of the bulge-structure of the shape of a saddle and metal roofing board matches so that entire be laminated is tied
Structure is closely knit tight.
According to the accompanying drawings to the detailed description of the specific embodiment of the invention, those skilled in the art will be brighter
The above and other objects, advantages and features of the present invention.
Description of the drawings
Some specific embodiments of detailed description of the present invention by way of example rather than limitation with reference to the accompanying drawings hereinafter.
Identical reference numeral denotes same or similar component or part in attached drawing.It should be appreciated by those skilled in the art that these
What attached drawing was not necessarily drawn to scale.In attached drawing:
Fig. 1 is the schematic diagram of steel-structure factory building
Fig. 2 is roof boarding Wave crest and wave trough schematic diagram;
Fig. 3 is the flow chart of the installation method of inventive embodiments;
Fig. 4 is the sectional view of the double wave ribbon skylight node upper end connecting structure of inventive embodiments;
Fig. 5 is the scheme of installation of the pressure cotton part of inventive embodiments;
Fig. 6 is the scheme of installation of the super bearing of ribbon skylight of inventive embodiments;
Fig. 7 is the scheme of installation of the ribbon skylight bearing of inventive embodiments;
Fig. 8 is the scheme of installation of the sliding support of inventive embodiments;
Fig. 9 is the scheme of installation of the ribbon skylight of inventive embodiments;
Figure 10 is the scheme of installation of the Saddle cushion of inventive embodiments;
Figure 11 is the scheme of installation of the metal roofing board overlap joint liner plate of inventive embodiments;
Figure 12 is the schematic diagram of the laying butyl clay of inventive embodiments;
Figure 13 is the scheme of installation of metal roofing board on the left of the upper end of inventive embodiments;
Figure 14 is the scheme of installation of metal roofing board on the right side of the upper end of inventive embodiments;
Figure 15 is the scheme of installation of the stainless steel press strip of inventive embodiments;
Figure 16 is the schematic diagram that the metal roofing board of inventive embodiments is lockstitched a border.
Specific embodiment
Fig. 3 is the flow chart of the installation method of inventive embodiments, and Fig. 4 is the double wave ribbon skylight node upper end of inventive embodiments
The sectional view of connection structure.
As shown in Figure 3, Figure 4, the embodiment of the present invention provides a kind of installation side of double wave ribbon skylight node upper end connecting structure
Method, including:
Step 301, the hole upper end-face edge at the ribbon skylight hole on roof fix the guarantor turned with pressure cotton part
Warm cotton patch face;
Step 302 installs the super bearing of ribbon skylight in the hole upper end-face edge;
Step 303 installs ribbon skylight bearing in the lower end of the super bearing of the ribbon skylight;
Step 304 installs roof boarding sliding support in the upper end of the super bearing of the ribbon skylight;
Step 305 installs ribbon skylight on the ribbon skylight bearing, covers the ribbon skylight hole;
Step 306 installs Saddle cushion at the center wave crest of the ribbon skylight;
Step 307 installs the liner plate of overlap joint in the outside of the ribbon skylight upper end-face edge of the ribbon skylight;
Step 308, the ribbon skylight upper end-face edge laying butyl clay in the ribbon skylight;
Step 309, the metal roofing board on the left of ribbon skylight upper end-face edge installation upper end;
Step 310, the metal roofing board on the right side of ribbon skylight upper end-face edge installation upper end;
Step 311 is installed not on the right side of metal roofing board and the upper end on metal roofing board respectively on the left of the upper end
Become rusty steel press strip;
Step 312 lockstitches a border to metal roofing board on the right side of metal roofing board on the left of the upper end and the upper end.
As it can be seen that in the embodiment of the present invention, ribbon skylight bearing and sliding support by the super bearing of ribbon skylight and thereon come
Realize that ribbon skylight is connected with the overlap joint of roof boarding, it is real by the pressure cotton part, liner plate, butyl clay and the stainless steel press strip that are stacked
It now compresses and seals, so as to realize the secured close of double wave ribbon skylight node upper end junction by this structure being stacked
Envelope connection has good protection effect for the rainwater flow down from top of the slope.
Below in conjunction with specific installation diagram, each installation steps are described in further detail.
Fig. 5 is the scheme of installation of the pressure cotton part of inventive embodiments;As shown in figure 5, the daylighting in step 301, on roof
Hole upper end-face edge with hole 501 fixes the heat-preservation cotton veneer 503 turned with pressure cotton part 502;
Fig. 6 is the scheme of installation of the super bearing of ribbon skylight of inventive embodiments;As shown in fig. 6, in step 302,
Ribbon skylight super bearing 601 is installed on the roof purline of the hole upper end-face edge;
Fig. 7 is the scheme of installation of the ribbon skylight bearing of inventive embodiments;As shown in fig. 7, it is adopted in step 303, described
The lower end installation ribbon skylight bearing 701 of the super bearing of light belt;
Fig. 8 is the scheme of installation of the sliding support of inventive embodiments;As shown in figure 8, step 304, in the ribbon skylight
The upper end installation roof boarding sliding support 801 of super bearing;
Fig. 9 is the scheme of installation of the ribbon skylight of inventive embodiments;As shown in figure 9, step 305, in the ribbon skylight branch
Ribbon skylight 901 on seat is installed, covers the ribbon skylight hole;
Figure 10 is the scheme of installation of the Saddle cushion of inventive embodiments;As shown in Figure 10, step 306, in the ribbon skylight
Center wave crest at install Saddle cushion 1001;Note that butyl clay, after fastening, micro- extrusion are set in Saddle cushion and daylighting interband.
There is upper end to meet water the full-closed structure in direction for Saddle cushion in the present invention, can further prevent what upper end flow down
Rainwater penetrates into, and the bulge-structure of the shape of a saddle matches with the structure after metal roofing board lock seaming so that entire stepped construction
It is closely knit tight.
Figure 11 is the scheme of installation of the metal roofing board overlap joint liner plate of inventive embodiments;As shown in figure 11, step
307th, in the liner plate 1101 of the outside of the ribbon skylight upper end-face edge of ribbon skylight installation overlap joint.
Figure 12 is the scheme of installation of the laying butyl clay of inventive embodiments;As shown in figure 12, step 308, described
The ribbon skylight upper end-face edge of ribbon skylight is laid with butyl clay 1201.First a butyl clay is laid with along ribbon skylight is laterally elongated;
Again a clay is re-layed in intermediate peak and both sides wave crest.
Figure 13 is the scheme of installation of metal roofing board on the left of the upper end of inventive embodiments;As shown in the figure, step, described
Metal roofing board 1301 on the left of ribbon skylight upper end-face edge installation upper end;
Figure 14 is the scheme of installation of metal roofing board on the right side of the upper end of inventive embodiments;As shown in the figure, step 310,
Metal roofing board 1401 on the right side of the ribbon skylight upper end-face edge installation upper end;Note that before step 310, it first will be in ribbon skylight
Butyl clay is laid at the lock seaming of upper end one time.
Figure 15 is the scheme of installation of the stainless steel press strip of inventive embodiments;As shown in the figure, step 311, in the upper end
Stainless steel press strip 1501 is installed respectively on metal roofing board on the right side of left side metal roofing board and the upper end;
Figure 16 is the schematic diagram that the metal roofing board of inventive embodiments is lockstitched a border;As shown in the figure, step 312, to institute
It states metal roofing board and upper end right side metal roofing board on the left of upper end to lockstitch a border, forms lock seaming structure 1601.
In another embodiment of invention, in the step 306, set between the Saddle cushion and the ribbon skylight
There is butyl clay.In the step 308, including:It is laid at the trough of the ribbon skylight upper end-face edge of the ribbon skylight
One layer of butyl clay is laid with two layers of butyl clay at the wave crest of the ribbon skylight upper end-face edge.Before the step 310 also
Including:Butyl clay is laid at the lock seaming of the left side metal roofing board.
Fig. 4 is the sectional view of the double wave ribbon skylight node upper end connecting structure of the embodiment of the present invention.With reference to figure 4 and Fig. 5-figure
16, the embodiment of the present invention provides a kind of double wave ribbon skylight node upper end connecting structure, including:
Cotton part 502 is pressed, is arranged on the hole upper end-face edge at the ribbon skylight hole 501 on roof, and fixation has turned
Heat-preservation cotton veneer 503;
The super bearing 601 of ribbon skylight, mounted on the hole upper end-face edge;
Ribbon skylight bearing 701, mounted on the lower end of the super bearing 601 of the ribbon skylight;
Roof boarding sliding support 801, mounted on the upper end of the super bearing 601 of the ribbon skylight;
Ribbon skylight 901 on the ribbon skylight bearing 701, and covers the ribbon skylight hole;
Saddle cushion 1001, at the center wave crest of the ribbon skylight;
The liner plate 1101 of overlap joint, mounted on the outside of the ribbon skylight upper end-face edge of the ribbon skylight;
Metal roofing board 1301 on the left of upper end, mounted on the left side of the ribbon skylight upper end-face edge;
Metal roofing board 1401 on the right side of upper end, mounted on the right side of the ribbon skylight upper end-face edge;
Metal roofing board is connected with metal roofing board on the right side of the upper end by lock seaming on the left of the upper end, forms lock seaming
Structure 1601.
As it can be seen that in the embodiment of the present invention, ribbon skylight bearing 701 by the super bearing 601 of ribbon skylight and thereon and slip
Bearing 801 realizes that ribbon skylight is connected with the overlap joint of roof boarding, passes through pressure cotton part 502, liner plate 1101, the butyl rubber being stacked
Mud and stainless steel press strip 1501, which are realized, to be compressed and seals, so as to realize double wave daylighting belt segment by this structure being stacked
The robust seal connection of point upper end junction has good protection effect for the rainwater flow down from top of the slope.
As shown in figure 15, in one embodiment of the invention, it further includes:Two stainless steel press strips 1501, are installed respectively
On the left of the upper end on metal roofing board and on the right side of the upper end on metal roofing board.
As shown in figure 12, in one embodiment of the invention, it is equipped in the ribbon skylight upper end-face edge of the ribbon skylight
Butyl clay 1201.
In one embodiment of the invention, butyl clay is provided between the Saddle cushion and the ribbon skylight.
In one embodiment of the invention, it is equipped with butyl clay at the lock seaming of the left side metal roofing board.
Fig. 4 is the sectional view of the double wave ribbon skylight node upper end connecting structure of the embodiment of the present invention, refering to what is shown in Fig. 4, adopting
Ribbon skylight bearing 701 and sliding support 801 are set on the super bearing 601 of light belt.
Ribbon skylight 901 is supported on ribbon skylight bearing 701.Metal roofing board 1401 is supported on sliding support on the right side of upper end
On 801.
In the ribbon skylight side of lap-joint, what is be stacked from the bottom to top is ribbon skylight bearing 701, ribbon skylight 901, glue
Mud, fastener and suturing nail.In the roof boarding side of lap-joint, what is be stacked from the bottom to top is ribbon skylight 901, clay, upper end
Right side metal roofing board 1401.
From the foregoing, it will be observed that the present invention has the advantage that:
1) in the embodiment of the present invention, ribbon skylight bearing 701 and sliding support by the super bearing 601 of ribbon skylight and thereon
801 realize that ribbon skylight is connected with the overlap joint of roof boarding, by the pressure cotton part 502 that is stacked, liner plate 1101, butyl clay and
Stainless steel press strip 1501, which is realized, to be compressed and seals, so as to be realized on double wave ribbon skylight node by this structure being stacked
The robust seal connection of junction is held, there is good protection effect for the rainwater flow down from top of the slope.
2) there is the Saddle cushion in the present invention upper end to meet water the full-closed structure in direction, upper end can be further prevented to flow down
Rainwater penetrate into, and the structure after the lock seaming of the bulge-structure of the shape of a saddle and metal roofing board matches so that entire be laminated is tied
Structure is closely knit tight.
So far, although those skilled in the art will appreciate that detailed herein have shown and described multiple showing for the present invention
Example property embodiment, still, without departing from the spirit and scope of the present invention, still can according to the present disclosure directly
Determine or derive many other variations or modifications consistent with the principles of the invention.Therefore, the scope of the present invention is understood that and recognizes
It is set to and covers other all these variations or modifications.
Claims (9)
1. a kind of installation method of double wave ribbon skylight node upper end connecting structure, which is characterized in that including:
Step 1: the hole upper end-face edge at the ribbon skylight hole on roof, the heat-preservation cotton turned is fixed with pressure cotton part
Veneer;
Step 2: the super bearing of ribbon skylight is installed in the hole upper end-face edge;
Step 3: ribbon skylight bearing is installed in the lower end of the super bearing of the ribbon skylight;
Step 4: roof boarding sliding support is installed in the upper end of the super bearing of the ribbon skylight;
Step 5: installing ribbon skylight on the ribbon skylight bearing, the ribbon skylight hole is covered;
Step 6: Saddle cushion is installed at the center wave crest of the ribbon skylight;
Step 7: the liner plate of the outside installation overlap joint in the ribbon skylight upper end-face edge of the ribbon skylight;
Step 8: the ribbon skylight upper end-face edge in the ribbon skylight is laid with butyl clay;
Step 9: the metal roofing board on the left of ribbon skylight upper end-face edge installation upper end;
Step 10: the metal roofing board on the right side of ribbon skylight upper end-face edge installation upper end;
Step 11: stainless steel is installed respectively on metal roofing board on the right side of metal roofing board and the upper end on the left of the upper end
Press strip;
Step 12: it lockstitches a border to metal roofing board on the right side of metal roofing board on the left of the upper end and the upper end.
2. installation method according to claim 1, which is characterized in that in the step 6, the Saddle cushion with it is described
Butyl clay is provided between ribbon skylight.
3. installation method according to claim 1, which is characterized in that in the step 8, including:In the ribbon skylight
The ribbon skylight upper end-face edge trough at be laid with one layer of butyl clay, at the wave crest of the ribbon skylight upper end-face edge be laid with
Two layers of butyl clay.
4. installation method according to claim 1, which is characterized in that further included before the step 10:On the left side
Butyl clay is laid at the lock seaming of side metal roofing board.
5. a kind of double wave ribbon skylight node upper end connecting structure, which is characterized in that including:
Cotton part is pressed, is arranged on the hole upper end-face edge at the ribbon skylight hole on roof, and the fixed heat preservation cotton patch turned
Face;
The super bearing of ribbon skylight, mounted on the hole upper end-face edge;
Ribbon skylight bearing, mounted on the lower end of the super bearing of the ribbon skylight;
Roof boarding sliding support, mounted on the upper end of the super bearing of the ribbon skylight;
Ribbon skylight on the ribbon skylight bearing, and covers the ribbon skylight hole;
Saddle cushion, at the center wave crest of the ribbon skylight;
The liner plate of overlap joint, mounted on the outside of the ribbon skylight upper end-face edge of the ribbon skylight;
Metal roofing board on the left of upper end, mounted on the left side of the ribbon skylight upper end-face edge;
Metal roofing board on the right side of upper end, mounted on the right side of the ribbon skylight upper end-face edge;
Metal roofing board is connected with metal roofing board on the right side of the upper end by lock seaming on the left of the upper end.
6. double wave ribbon skylight node upper end connecting structure according to claim 5, which is characterized in that further include:
Two stainless steel press strips are separately mounted on the left of the upper end on metal roofing board and metal roofing board on the right side of the upper end
On.
7. double wave ribbon skylight node upper end connecting structure according to claim 5, which is characterized in that in the ribbon skylight
Ribbon skylight upper end-face edge is equipped with butyl clay.
8. double wave ribbon skylight node upper end connecting structure according to claim 5, which is characterized in that the Saddle cushion and institute
It states and is provided with butyl clay between ribbon skylight.
9. double wave ribbon skylight node upper end connecting structure according to claim 5, which is characterized in that in the left side metal
Butyl clay is equipped at the lock seaming of roof boarding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810083874.6A CN108149852A (en) | 2018-01-29 | 2018-01-29 | A kind of double wave ribbon skylight node upper end connecting structure and its installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810083874.6A CN108149852A (en) | 2018-01-29 | 2018-01-29 | A kind of double wave ribbon skylight node upper end connecting structure and its installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108149852A true CN108149852A (en) | 2018-06-12 |
Family
ID=62459112
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810083874.6A Pending CN108149852A (en) | 2018-01-29 | 2018-01-29 | A kind of double wave ribbon skylight node upper end connecting structure and its installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108149852A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108999345A (en) * | 2018-09-10 | 2018-12-14 | 安徽建筑大学 | A kind of ribbon skylight lap-joint water proof structure and its construction method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201011061Y (en) * | 2007-03-27 | 2008-01-23 | 广州市广易实业有限公司 | Roof pantile leak-proof fastening member |
CN201268922Y (en) * | 2008-08-13 | 2009-07-08 | 罗菁 | Uncovered nail type roofing wall panel |
CN202866134U (en) * | 2012-09-29 | 2013-04-10 | 安徽杭萧钢结构有限公司 | Pressing bar of steel structure roof sheathing |
CN204098363U (en) * | 2014-09-03 | 2015-01-14 | 北京北方空间建筑科技股份有限公司 | Single-layer roof ribbon skylight structural system |
CN204386040U (en) * | 2014-12-22 | 2015-06-10 | 安徽伟宏钢结构集团股份有限公司 | A kind of face, house slidingtype ribbon skylight syndeton |
CN205206153U (en) * | 2015-12-28 | 2016-05-04 | 吴征 | Various steel tile roof waterproof structure |
CN208009768U (en) * | 2018-01-29 | 2018-10-26 | 北京东方诚国际钢结构工程有限公司 | A kind of double wave ribbon skylight node upper end connecting structure |
-
2018
- 2018-01-29 CN CN201810083874.6A patent/CN108149852A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201011061Y (en) * | 2007-03-27 | 2008-01-23 | 广州市广易实业有限公司 | Roof pantile leak-proof fastening member |
CN201268922Y (en) * | 2008-08-13 | 2009-07-08 | 罗菁 | Uncovered nail type roofing wall panel |
CN202866134U (en) * | 2012-09-29 | 2013-04-10 | 安徽杭萧钢结构有限公司 | Pressing bar of steel structure roof sheathing |
CN204098363U (en) * | 2014-09-03 | 2015-01-14 | 北京北方空间建筑科技股份有限公司 | Single-layer roof ribbon skylight structural system |
CN204386040U (en) * | 2014-12-22 | 2015-06-10 | 安徽伟宏钢结构集团股份有限公司 | A kind of face, house slidingtype ribbon skylight syndeton |
CN205206153U (en) * | 2015-12-28 | 2016-05-04 | 吴征 | Various steel tile roof waterproof structure |
CN208009768U (en) * | 2018-01-29 | 2018-10-26 | 北京东方诚国际钢结构工程有限公司 | A kind of double wave ribbon skylight node upper end connecting structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108999345A (en) * | 2018-09-10 | 2018-12-14 | 安徽建筑大学 | A kind of ribbon skylight lap-joint water proof structure and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5394672A (en) | Interlocking insulated roof panel system | |
US8887464B1 (en) | Metal panel roof recover | |
CN106193444A (en) | A kind of embedding stacked waterproof sealing wallboard | |
US3909998A (en) | Roof construction system | |
CN202187487U (en) | Metal roof ridge | |
CN211472893U (en) | Parapet department movement joint structure | |
US8938924B1 (en) | Standing seam metal panel roof recover | |
CN212534838U (en) | Waterproof structure of peripheral low wall of building roof | |
CN113107142B (en) | Construction method of wind-resistant metal roof structure | |
CN107762073B (en) | Double-deck roofing system of waterproof performance improves | |
CN110195489A (en) | A kind of double slope metal Sloping roof ridge nodes and its installation method | |
CN208009768U (en) | A kind of double wave ribbon skylight node upper end connecting structure | |
CN108149852A (en) | A kind of double wave ribbon skylight node upper end connecting structure and its installation method | |
EP1099032A1 (en) | Insulating material element made of mineral wool as well as a process for its production and use of the same | |
CN108149853A (en) | A kind of double wave ribbon skylight node lower end connection structure and its installation method | |
CN208009769U (en) | A kind of double wave ribbon skylight node lower end connection structure | |
CN209494067U (en) | Steel structural plant roof deformation joint structure | |
CN105464299B (en) | A kind of gable waterproof construction | |
CN107419857A (en) | Built-up roofing Durchgangshohle node and its construction method | |
CN211080818U (en) | Passive ultralow-energy-consumption dry-operation flat roof slope-finding heat-insulation waterproof integrated eaves gutter | |
CN210395788U (en) | Double-slope metal inclined roof ridge node | |
CN207727781U (en) | A kind of deformation joint of roof connecting structure | |
CN203174913U (en) | Rigid waterproof structure at fan opening of steel roof | |
CN207597727U (en) | The plane skylight waterproof connecting device of colored steel roof | |
CN206554289U (en) | A kind of building iron roofing, metope and tile roofing flashing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |