CN108149797A CN201810122471.8A CN201810122471A CN108149797A CN 108149797 A CN108149797 A CN 108149797A CN 201810122471 A CN201810122471 A CN 201810122471A CN 108149797 A CN108149797 A CN 108149797A
Authority
CN
China
Prior art keywords
tie
type steel
assembling type
steel structure
culture facility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810122471.8A
Other languages
Chinese (zh)
Inventor
张朝辉
徐佳红
潘智伟
陈敬烨
李欣
胡诗文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810122471.8A priority Critical patent/CN108149797A/en
Publication of CN108149797A publication Critical patent/CN108149797A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/3483Elements not integrated in a skeleton the supporting structure consisting of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34869Elements for special technical purposes, e.g. with a sanitary equipment

Abstract

The present invention relates to modular architectural technical fields, disclosing one kind can the multi-functional sports culture facility of load moduleization, including one or more assembling type steel structures, the assembling type steel structure is made of the connection of multiple prefabricated components, the assembling type steel structure is connected with floor and side plate, the floor and side plate are the prefabricated component, the space of sports equipment can be accommodated by being formed between the assembling type steel structure, floor and side plate, identical or different sports equipment can be placed in the space, is detachably connected between the adjacent assembling type steel structure.It can the multi-functional sports culture facility of load moduleization the object of the present invention is to provide one kind, gymnasium is built to solve building in the prior art, occupied space area is big, implementation cost is relatively high, the time is longer and it is less efficient the problem of, filled up the blank that mounting technology uses in sports culture facility.

Description

One kind can the multi-functional sports culture facility of load moduleization
Technical field
The present invention relates to modular architectural technical fields, can the multi-functional sport text of load moduleization more particularly to one kind Change facility.
Background technology
Various policy documents all in the development for emphasizing nationwide fitness programs, improve people's fitness, promote social sports The development of cause, " athletics sports " have started to turn to " Mass sports ", and unquestionable " nationwide fitness programs " will become next sport The new direction of industry development.
Stadiums do not carry out numerous sports projects still as the important carrier for carrying out nationwide fitness programs sports Essential important place;The concrete conditions such as facility, function and the service of venue simultaneously in itself also become to a certain extent The reason of whether people select to perform physical exercise becomes the basis of effectively carrying physical training.
The characteristics of inadequate natural endowment is built below Chinese Sport venue generally existing at present:(1) function is single, at present state's inner body Most of design function for educating venue is laid particular emphasis on based on the single athletics sports of function, the Mass sports function with " nationwide fitness programs " There are deviations;(2) cost is high, builds class height, cost height, ignores the practicability of stadiums;(3) it takes up a large area, from residence People area is farther out;(4) utilization rate is low, and the big venue for the athletics sports of Held by Government large-scale game is more, and is good for suitable for the whole people The venue of body is less;(5) environment is polluted, the construction period is long.Stadiums are mainly reinforced concrete structure at present, are non-disconnectable Structure is unloaded, it is larger to the pollution of environment.Embody the unmanageable big venue of athletics sports for Held by Government large-scale game It is more, and it is suitble to the multi-functional manageable small venue of nationwide fitness programs few.
Invention content
For the technical problems in the prior art, the purpose of the present invention is:There is provided one kind can the more work(of load moduleization Can sports culture facility, with solve gymnasium function is single in the prior art, cost is high, occupied space area is big, implement into The problem of this is relatively high and less efficient.
To achieve these goals, the present invention provide one kind can the multi-functional sports culture facility of load moduleization, it is special Sign is, including one or more assembling type steel structures, the assembling type steel structure is made of the connection of multiple prefabricated components, the dress Have a floor and side plate with formula steel structure connection, the floor and side plate are the prefabricated component, the assembling type steel structure, floor and The space of sports equipment can be accommodated by being formed between side plate, and identical or different sports equipment can be placed in the space;
Be detachably connected between the adjacent assembling type steel structure, it is described turn accessories steel construction and the floor and It is detachably connected between side plate.
Preferably, the assembling type steel structure include two the first tie-beams being arranged in parallel and two with it is described First tie-beam the second tie-beam connected vertically, adjacent first tie-beam and the second tie-beam are detachably connected, institute The bottom end for stating the first tie-beam and the second tie-beam is connected with more root posts;
The more girders are connected between two first tie-beams, the top of the girder is connected with more times Beam, the both ends of the secondary beam are detachably connected respectively with two second tie-beams, can between the girder and the secondary beam Dismantling connection, first tie-beam, the second tie-beam, column, girder and secondary beam are the different prefabricated components.
Preferably, the bottom end of the column connects the floor, and the both sides of the column connect the side plate.
Preferably, the girder is made of multistage beam body, and the beam body of the adjacent composition girder passes through fastening Part is detachably connected, and the beam body of the composition girder on the outermost side is connect with the side of first tie-beam.
Preferably, the secondary beam is made of multistage beam body, second tie-beam and with second tie-beam The beam body for forming the secondary beam is connected between the adjacent girder, is connected between the beam body of the adjacent composition girder Form the beam body of the secondary beam.
Preferably, the height of the column is between 5m~10m.
Preferably, the height of the column can be 6m, 7m or 9.5m.
Preferably, the side plate is made of Side fascia and the lining being connect with the Side fascia.
Preferably, the sports equipment include ball facility and/or art installations and/or health-care facilities and/or Swimming pool.
Preferably, it is connected with top plate at the top of the assembling type steel structure of top.
One kind that the embodiment of the present invention is provided can the multi-functional sports culture facility of load moduleization, have following technology Effect:
The present embodiment can the multi-functional sports culture facility of load moduleization, including one or more assembled steel knots Structure, assembling type steel structure are formed by connecting by multiple prefabricated components, and assembling type steel structure is connected with floor and side plate, and floor and side plate are equal For prefabricated component, prefabricated component can pre-production it is good, pass through the good prefabricated component of pre-production, it is ensured that the quality of prefabricated component and size essence Then degree transports prefabricated component to construction site, at the construction field (site) by being detachably connected between upper different prefabricated component, so as to The progress of installation and dismounting, and gymnasium is built relative to using armored concrete, this programme passes through component body between base body Shop is educated, the building time and operation cost of construction can be reduced, in the form of community-type, school's type, park type and sport small town type etc. All parts of the country are presented in, the development for sports for the entire people (culture) industry provides configuration equilibrium, suitable scale, convenient and practical, safe Rational carrier is carrier has greatly pushed national nationwide fitness programs implementation;
The space of sports equipment can be accommodated by being formed between assembling type steel structure, floor and side plate, in space placement it is identical or Different sports equipments, it is real so as to realize that the masses carry out different sports culture projects in same sports culture facility The multifunctionality of same sports culture facility is showed, an existing sports culture venue is avoided to only exist a small amount of sports culture Project;The present invention is not only technological innovation creation, more carries the social effect benefited the nation and the people of epoch imparting.Therefore, this reality Apply in example can the multi-functional sports culture facility of load module have the following advantages that:
(1) capital quantity needed for present invention construction is small, and construction material of the invention is mainly steel construction, and steel construction is in factory In it is prefabricated, then steel construction is sent to construction site, construction personnel only need at the construction field (site) be pacified steel construction by fastener It installing and completes process of construction, installation process is fast, and in the prior art, by armored concrete constructing sports grounds shop, taken Between it is longer, cost of labor is higher, therefore in the case where realizing equal function, build the sports culture facility of the present invention only need it is several Ten million, and several hundred million to tens are then needed using armored concrete constructing sports grounds shop, therefore, the required construction cost of the present invention It substantially reduces;
(2) assembling type steel structure of the invention is assembled by multiple prefabricated components, assembling type steel structure be connected with floor and Side plate is detachably connected between adjacent assembling type steel structure, is detachably connected between assembling type steel structure and floor It connects, is detachably connected between assembling type steel structure and side plate, only need that will first the dress built will be needed respectively at the construction field (site) It assembles and completes with formula steel construction, then different assembling type steel structures is detachably connected, finally floor and side plate are installed The installation of entire sports culture facility can be completed into assembling type steel structure, the present invention required construction period is shorter, generally It is 1-2 months, and the construction in constructing sports grounds shop needs to carry out casting reinforced concrete in the prior art, the construction period is longer, Generally 2-3;
(3) present invention includes one or more assembling type steel structures being superimposed up and down successively, assembling type steel structure, floor and Side plate connects the space to be formed and can accommodate sports equipment, and space is equipped with identical or different sports equipment, therefore, body of the invention Educating cultural facility functionally has the characteristics of intensive, diversification, content are complete, one-stop service and operational management cost are few, real Now by the nationwide fitness programs such as swimming, football, tennis, basketball, land ice hockey, wushu, sports dancing, boxing, Yoga, strength body-building with And the sports culture of 20 multiple combinations that cultural more than the 30 kinds of project of the common people such as nautch, the fine arts, hand-made, small theatre integrates Facility meets Mass sports cultural demand to greatest extent;
(4) assembling type steel structure of the invention is formed by connecting by multiple prefabricated components, and floor and side plate are prefabricated component, adjacent It is detachably connected between base body, steel construction has the spy of environmental protection relative to reinforced concrete structure of the prior art Point, and can Reusability assembling type steel structure, floor and side plate by being detachably connected;
(5) in the case where being becoming tight the land resource day in city, the present invention by by different assembling type steel structures into Row is superimposed up and down, and the soil space of occupancy is small, generally only takes up the soil of 1200 ㎡, and the story height of existing stadiums It is not high, generally there was only a sheaf space or two sheaf spaces, it is relatively large per the occupied area of sheaf space, therefore occupy a large amount of Soil space construction, so as to which present invention saves soil spaces, realize efficiently using for land resource;
(6) assembling type steel structure of the invention includes multiple prefabricated components, is detachably connected between prefabricated component by fastener, It by setting multiple prefabricated components, after completing in factory, is sent to construction site and is assembled, realize in process of construction The assembly rate of assembling assembly is up to more than 95% (other than ground) and realizes the Standardization Construction of sports culture facility.
Description of the drawings
Fig. 1 is the structure diagram of the assembling type steel structure of the present invention;
Fig. 2 is the structure diagram of the assembling type steel structure after the superposition of the present invention;
Fig. 3 is the distribution schematic diagram 1 of the sports equipment of the present invention;
Fig. 4 is the distribution schematic diagram 2 of the sports equipment of the present invention;
Fig. 5 is the distribution schematic diagram 3 of the sports equipment of the present invention;
Fig. 6 is the structure diagram of the girder of the present invention;
Fig. 7 is structural representation Fig. 1 of the sports culture facility of the present invention;
Fig. 8 is structural representation Fig. 2 of the sports culture facility of the present invention;
Fig. 9 is the structure diagram of the sports culture facility superposition of the present invention;
Figure 10 is composition structural representation Fig. 1 of the side plate of the present invention;
Figure 11 is composition structural representation Fig. 2 of the side plate of the present invention;
Figure 12 is the assembling structure schematic diagram of column of the invention, the first tie-beam and floor.
Wherein, 1, assembling type steel structure;11st, the first tie-beam;12nd, the second tie-beam;13rd, column;14th, girder;141、 First beam body;142nd, the second beam body;15th, secondary beam;2nd, connecting plate;3rd, fastener;4th, sports equipment;5th, elevator;6th, stair;7、 Side plate;71st, Side fascia;72nd, lining;73rd, puigging;74th, insulating layer;8th, top plate;9th, floor.
Specific embodiment
With reference to the accompanying drawings and examples, the specific embodiment of the present invention is described in further detail.Implement below Example is used to illustrate the present invention, but be not limited to the scope of the present invention.
As shown in Fig. 1,2,3,4,5,7,8 and 9, one kind provided in an embodiment of the present invention can the multi-functional body of load moduleization Cultural facility is educated, including one or more assembling type steel structures 1, assembling type steel structure 1 is made of the connection of multiple prefabricated components, is assembled Formula steel construction 1 is connected with floor 9 and side plate 7, and floor 9 and side plate 7 are prefabricated component, assembling type steel structure 1, floor 9 and side plate 7 it Between formed and can accommodate the space of sports equipment 4, can place identical or different sports equipment 4 in space;
It is detachably connected between adjacent assembling type steel structure 1.
Based on above-mentioned setting, the present embodiment can the multi-functional sports culture facility of load moduleization, including one or more A assembling type steel structure 1, assembling type steel structure 1 are formed by connecting by multiple prefabricated components, and assembling type steel structure 1 is connected with 9 He of floor Side plate 7, floor 9 and side plate 7 are prefabricated component, prefabricated component can pre-production it is good, pass through the good prefabricated component of pre-production, Ke Yibao The quality and dimensional accuracy of prefabricated component are demonstrate,proved, then prefabricated component is transported to construction site, goes up different prefabricated components at the construction field (site) Between by being detachably connected, so as to the progress installed and dismantled, and relative to using armored concrete build gymnasium, we Case can reduce the building time and operation cost of construction, with community-type, school's type, public affairs by component gymnasium between base body The forms such as garden type and sport small town type are presented in all parts of the country, the development for sports for the entire people (culture) industry provide configuration it is balanced, Suitable scale, convenient and practical, safe and reasonable carrier is carrier, have greatly pushed national nationwide fitness programs implementation;
The space of sports equipment 4 can be accommodated by being formed between assembling type steel structure 1, floor 9 and side plate 7, and phase is placed in space Same or different sports equipment 4, so as to realize that the masses carry out different sports culture items in same sports culture facility Mesh realizes the multifunctionality of same sports culture facility, and an existing sports culture venue is avoided to only exist a small amount of body Educate cultural project;The present invention is not only technological innovation creation, more carries the social effect benefited the nation and the people of epoch imparting.Cause This, in the present embodiment can the multi-functional sports culture facility of load module have the following advantages that:
(1) capital quantity needed for present invention construction is small, and construction material of the invention is mainly steel construction, and steel construction is in factory In it is prefabricated, then steel construction is sent to construction site, construction personnel only need at the construction field (site) be pacified steel construction by fastener 3 It installing and completes process of construction, installation process is fast, and in the prior art, by armored concrete constructing sports grounds shop, taken Between it is longer, cost of labor is higher, therefore in the case where realizing equal function, build the sports culture facility of the present invention only need it is several Ten million, and several hundred million to tens are then needed using armored concrete constructing sports grounds shop, therefore, the required construction cost of the present invention It substantially reduces;
(2) assembling type steel structure 1 of the invention is assembled by multiple prefabricated components, and assembling type steel structure 1 is connected with floor 9 It with side plate 7, is detachably connected between adjacent assembling type steel structure 1, being carried out between assembling type steel structure 1 and floor 9 can Dismantling connection is detachably connected between assembling type steel structure 1 and side plate 7, and only needing at the construction field (site) respectively will be first by needs The assembling of assembling type steel structure 1 built is completed, then different assembling type steel structures 1 is detachably connected, finally by floor 9 and side plate 7 installation that entire sports culture facility can be completed is installed into assembling type steel structure 1, the required construction of the present invention Period is shorter, generally 1-2 months, and the construction in constructing sports grounds shop needs to carry out casting reinforced concrete in the prior art, Construction period is longer, generally 2-3;
(3) present invention includes one or more assembling type steel structures 1 being superimposed up and down successively, assembling type steel structure 1, building Plate 9 and the connection of side plate 7 form the space that can accommodate sports equipment 4, and space is equipped with identical or different sports equipment 4, therefore, this The sports culture facility of invention functionally has intensive, diversification, content complete, one-stop service and the operational management cost few Feature is realized complete by swimming, football, tennis, basketball, land ice hockey, wushu, sports dancing, boxing, Yoga, strength body-building etc. 20 multiple combinations that people's body-building and cultural more than the 30 kinds of project of the common people such as nautch, the fine arts, hand-made, small theatre integrate Sports culture facility meets Mass sports cultural demand to greatest extent;
(4) assembling type steel structure 1 of the invention is formed by connecting by multiple prefabricated components, and floor 9 and side plate 7 are prefabricated component, phase It is detachably connected between adjacent base body, steel construction has environmental protection relative to reinforced concrete structure of the prior art Feature, and can Reusability assembling type steel structure 1, floor 9 and side plate 7 by being detachably connected;
(5) in the case where being becoming tight the land resource day in city, the present invention by by different assembling type steel structures 1 into Row is superimposed up and down, and the soil space of occupancy is small, generally only takes up the soil of 1200 ㎡, and the story height of existing stadiums It is not high, generally there was only a sheaf space or two sheaf spaces, it is relatively large per the occupied area of sheaf space, therefore occupy a large amount of Soil space construction, so as to which present invention saves soil spaces, realize efficiently using for land resource;
(6) assembling type steel structure 1 of the invention includes multiple prefabricated components, is detachably connected by fastener 3 between prefabricated component It connects, by setting multiple prefabricated components, after completing in factory, is sent to construction site and is assembled, realization was built The assembly rate of assembling assembly is up to more than 95% (other than ground) and realizes the Standardization Construction of sports culture facility in journey.
In the present embodiment, as shown in Figure 1, assembling type steel structure 1 includes two the first tie-beams 11 and two being arranged in parallel 11 second tie-beam 12 connected vertically of root and the first tie-beam, by setting the first tie-beam 11 and the second tie-beam 12, energy Increase the overall stability and intensity of assembling type steel structure 1, the first adjacent tie-beam 11 and the second tie-beam 12 detachably connect It connects, facilitates the installation and dismounting of the first tie-beam 11 and the second tie-beam 12, the first tie-beam 11 and the second tie-beam 12 Bottom end is connected with more root posts 13, and column 13 can enhance entire assembled as the core for supporting entire assembling type steel structure 1 The strength and stability of steel construction 1;
More girders 14 are connected between two first tie-beams 11, the top of girder 14 is connected with more secondary beams 15, when When secondary beam 15 is by load, since secondary beam 15 is located at the top of girder 14, secondary beam 15 is by load transmission to girder 14, girder 14 pairs of load load-bearing from secondary beam 15 and be transferred in column 13, the both ends of secondary beam 15 respectively with two second tie-beams 12 It is detachably connected, the junction of 15 and second tie-beam 12 of secondary beam is equipped with connecting plate 2, and connecting plate 2 is equipped with threaded hole, by bolt Secondary beam 15 and the second tie-beam 12 can be fastenedly connected across threaded hole, detachably connected between girder 14 and secondary beam 15 It connects, the junction of girder 14 and secondary beam 15 is equipped with connecting plate 2, and connecting plate 2 is equipped with threaded hole, is across threaded hole by bolt Girder 14 and secondary beam 15 can be fastenedly connected, the first tie-beam 11, the second tie-beam 12, column 13, girder 14 and secondary beam 15 be different prefabricated components;Thus, when being installed, the installation site of column 13 is set on construction location, Column 13 to be fixed in installation site, the bottom end of column 13 can be connect by fastener 3 with ground, and fastener 3 can be bolt, The connection mode of column 13 is equipped with threaded hole to be connected with connecting plate 2, connecting plate 2 in the bottom end of column 13, and bolt passes through spiral shell Column 1323 is fastenedly connected by pit with ground;
In the installed position of column 13, opposite both sides are equipped with 6 root posts 13, and opposite other both sides are equipped with two and stand Column 13, the quantity of this programme column 13 can be designed as needed not to be limited, by setting the first tie-beam 11, the Two tie-beams 12, girder 14 and secondary beam 15 can improve overall stability, the strength and stiffness of assembling type steel structure 1, and each The junction of beam is attached by fastener 3, and more firm relative to welding, disassembly and installation is more convenient.
In the present embodiment, as shown in figure 12, the bottom end connection floor 9 of column 13, in adjacent assembling type steel structure 1, Floor 9, floor 9 and the assembled steel knot positioned at lower floor are connected with positioned at the bottom end of the column 13 of the assembling type steel structure 1 on upper strata The top connection of structure 1, thus floor 9 can bear the vertical load of horizontal direction, and can be in adjacent assembling type steel structure 1 In play the role of separation, the both sides connecting lateral plate 7 of column 13, by the both sides connecting lateral plate 7 in column 13, so as to right Assembling type steel structure 1 plays the role of going along with sb. to guard him.
In the present embodiment, as shown in fig. 6, girder 14 is made of multistage beam body, the length of girder 14 is 27m, for the ease of The transport and installation of girder 14 divide girder 14 for 3 sections of beam bodies, respectively the first beam body 141, the second beam body 142 and third beam Body, the length of every section of beam body is 9m, and the type of girder 14 is I-beam, and the beam body of adjacent composition girder 14 passes through fastener 3 It is detachably connected, the left and right sides at the middle part of adjacent two beam bodies is equipped with connecting plate 2, and connecting plate 2 is equipped with threaded hole, spiral shell Bolt passes through threaded hole that will be fastenedly connected in the middle part of two beam bodies;The both sides up and down of the bottom end of two adjacent beam bodies, which are equipped with, to be connected Fishplate bar 2, connecting plate 2 are equipped with threaded hole, and the bottom end of two beam bodies is fastenedly connected by bolt across threaded hole, wherein setting The quantity of threaded hole in two beam bodies on the connecting plate 2 on top, middle part and bottom end respectively have it is multiple, this programme not to be limited, It can be designed as needed;
The beam body of composition girder 14 on the outermost side is connect with the side of the first tie-beam 11, the first tie-beam 11 and position Connecting plate 2 is equipped in the side of the beam body of outermost composition girder 14, connecting plate 2 is equipped with threaded hole, positioned at outermost Top, middle part and the bottom end of beam body of composition girder 14 be equipped with connecting plate 2, above-mentioned composition girder 14 on the outermost side Beam body and the first tie-beam 11 on connecting plate 2 be equipped with threaded hole, bolt pass through above-mentioned connecting plate 2 threaded hole, so as to The beam body of composition girder 14 on the outermost side is connect with the side of the first tie-beam 11.
In the present embodiment, secondary beam 15 is made of multistage beam body, can be by secondary beam 15 for the ease of the transport and installation of secondary beam 15 It is divided into multistage beam body, the length for forming the beam body of secondary beam 15 is determined according to the length of the first tie-beam 11 and the radical of girder 14, This programme to be limited, can not be designed as needed, the second tie-beam 12 and the girder 14 adjacent with the second tie-beam 12 Between be connected with composition secondary beam 15 beam body, be connected with connecting plate 2 in the second tie-beam 12, girder 14 is connected with connecting plate 2, position The both sides of the beam body of composition secondary beam 15 between the second tie-beam 12 and the girder 14 adjacent with the second tie-beam 12 are connected with Connecting plate 2, the above-mentioned connecting plate 2 being connect with the second tie-beam 12 and the girder 14 adjacent with the second tie-beam 12 are equipped with screw thread Hole, bolt pass through the threaded hole of connecting plate 2 that the second tie-beam 12 and the girder 14 adjacent with the second tie-beam 12 are connect, from And the beam body that composition secondary beam 15 is connected between the second tie-beam 12 and the girder 14 adjacent with the second tie-beam 12 is carried out tight It is solidly connected, the beam body of composition secondary beam 15, similarly, adjacent composition girder is connected between the beam body of adjacent composition girder 14 14 beam body and the secondary beam 15 between the beam body of two composition girders 14 are attached by fastener 3, pass through fastener 3 are attached, and are attached compared to by welding, are attached by fastener 3, can guarantee the good result and section of connection It saves time, and the environment on periphery can be protected.
In the present embodiment, as shown in Figs. 1-5, the height of column 13 is between 5m~10m, assembling type steel structure 1, floor 9 Space is formed between side plate 7 can place identical or different sports equipment 4, when the placement sports equipment higher to space requirement When 45, when placing the sports equipment 45 relatively low to space requirement, it need to be can be selected with being highly column 13 between 7m~10m Column 13 highly between 5m~7m selects the column 13 of different height, and the placement for being suitable for different sports equipments 45 will It asks, application range is big.
In the present embodiment, as shown in Figs. 1-5, the height of column 13 can be 6m, 7m or 9.5m, when the height of column 13 During for 6m, 4 type of sports equipment placed in the space that is formed between assembling type steel structure 1, floor 9 and side plate 7 can be ball Class facility, art installations and swimming pool, wherein, ball facility can be table tennis facility and billiards facility etc., and art installations can Think chess facility, tae kwon do place, Fitness Dance place, land ice hockey place, martial arts ground, sports dancing place, boxing ring Ground, Yoga place, fine arts place, hand-made place, musical instrument performance venue, theatrical performances place and nautch place etc., When 13 height of column is 6m, the inside in space formed between assembling type steel structure 1, floor 9 and side plate 7 can place above-mentioned one kind Sports equipment 4 or a variety of sports equipments 4 improve the utilization rate of base body, the need of exercise made things convenient for the people;
When the height of column 13 is 7m, placement in the space that is formed between assembling type steel structure 1, floor 9 and side plate 7 4 type of sports equipment can be ball facility, and ball facility can be pitch, tennis court and court etc.;
When the height of column 13 is 9.5m, put in the space that is formed between assembling type steel structure 1, floor 9 and side plate 7 4 type of sports equipment put can be ball facility and art installations, ball facility can be court, shuttlecock place, Pitch and tennis court etc., art installations can be small-sized arenas, conference hall and show room etc.;
It, can assembled steel knot of 13 height of column for 6m when needing to be overlapped different assembling type steel structures 1 The assembling type steel structure 1 that the assembling type steel structure 1 and 13 height of column that structure 1,13 height of column are 7m are 9.5m carries out different Permutation and combination.
In the present embodiment, as shown in Fig. 3,4 and 5, sports equipment 4 includes ball facility and/or art installations and/or is good for Body facility and/or swimming pool, therefore, sports culture facility of the invention functionally have the characteristics of diversification and full content, real Now by swimming, football, tennis, basketball, land ice hockey, wushu, sports dancing, boxing, Yoga, nautch, the by hand fine arts, system The sports culture facility of 20 multiple combinations that more than 30 kinds of project of work, nationwide fitness programs etc. integrates, meets Mass sports to greatest extent Cultural demand.
In the present embodiment, as shown in figure 9, being connected with top plate 8, top plate 8 positioned at the top of the assembling type steel structure 1 of top Play the role of one to the assembling type steel structure 1 for being located at top to go along with sb. to guard him.
In the present embodiment, in order to strengthen the connection tightness between adjacent assembling type steel structure 1, the assembling set on lower part The top of formula steel construction 1 be equipped with floor 9, can by set on the column 13 of the assembling type steel structure 1 on top and with the dress set on lower part The floor 9 connected with formula steel construction 1 is fastenedly connected, and is equipped with connecting plate 2 in the junction of column 13 and floor 9, on connecting plate 2 Equipped with threaded hole, adjacent assembling type steel structure 1 is fastenedly connected by fastener 3 across threaded hole, fastener 3 can be bolt or Rivet, this programme can be designed as needed not to be limited.
In the present embodiment, as in Figure 3-5, the installation position equipped with elevator 5 and stair 6 in each assembling type steel structure 1 It puts, elevator 5 and stair 6 are transported on construction site by manufacturing works and are assembled after manufacturing works are prefabricated, wherein, stair 6 Installation site be located at the opposite both sides of assembling type steel structure 1, elevator 5 is located at the side of base body, makes things convenient for the people in different bases Activity in plinth body.
In the present embodiment, as shown in FIG. 10 and 11, side plate 7 is by 72 groups of Side fascia 71 and the lining being connect with Side fascia 71 Into, the boundary mechanism of Side fascia 71 and the formation indoor and outdoors of lining 72, and Side fascia 71 and lining 72 can undertake one Fixed load improves the monolithic stability degree of assembling type steel structure 1.
In the present embodiment, Side fascia 71 is decoration of exterior wall layer, and decoration of exterior wall layer is manufactured from manufacturing works, then is transported to Construction site is assembled, and decoration of exterior wall layer is metal finish layer, and the type of decoration of exterior wall layer is aluminum plate facing layer, aluminum plate facing Layer has the characteristics that sturdy and durable, decoration is graceful and stability and durability, lining 72 are inner wall decoration layer, and 72 decorative layer of lining is Metal finish layer, the type of 72 decorative layer of lining is aluminum plate facing layer;
Side fascia 71 and lining 72 be it is prefabricated and then be transported in construction site and assembled in manufacturing works, can be real Existing site operation is efficient, and labor intensity reduces, and dead weight is lighter, and structural strength is preferable with deformability.
Embodiment two:
One kind of the present embodiment can the multi-functional sports culture facility of load moduleization, the difference with embodiment one only exists In:In order to improve the sports culture facility of the present invention in the use of severe cold area, cold district and hot-summer and cold-winter area, Side fascia Insulating layer and puigging are equipped between 71 and lining 72, insulating layer is made with styrofoam, and puigging is then using keel, suction Sound cotton and plasterboard are made by mixing, and the side of insulating layer and the side of puigging are connected by adhesive linkage, insulating layer it is another Side is connected with the side of Side fascia 71, and the opposite side of puigging is connected with the side of lining 72.
Embodiment three:
One kind of the present embodiment can the multi-functional sports culture facility of load moduleization, the difference with embodiment one only exists In:Side fascia 71 and lining 72 can be made of glass curtain wall or wire glass, and glass curtain wall has light and handy beauty, is not easy Pollution and it is energy saving the features such as, wire glass is superior with fire line, can block flame, and when high temperature does not burst.
To sum up, it is of the invention can the multi-functional sports culture facility of load moduleization installation process, with three assembleds For the installation process of steel construction:
1) the construction place of sport cultural facility is selected;
2) to the construction place of selected sports culture facility carry out based process, based process include build place into Row line setting, foundation trench excavate, put ground line, formwork and foundation structure examination etc.;
3) construction of the assembling type steel structure 1 of lowermost end is carried out on place is built, is the installation for carrying out column 13 first;
4) two first tie-beams 11 and two second tie-beams 12 are installed on the top of column 13;
5) more girders 14 are installed between two first tie-beams 11, after installation is complete to girder 14, at two More secondary beams 15 are installed between two tie-beams 12;
6) distribution situation according to sports equipment in assembling type steel structure 1, between adjacent sports equipment 4 in setting Partition wall installs sports equipment 4 in the space then surrounded in internal partition wall, and installs elevator 5 and stair 6;
7) floor 9 on the top of the assembling type steel structure of lowermost end 1 is installed, and pavement material face is carried out to floor 9 Layer, the column 13 of the assembling type steel structure 1 on floor 9 in the middle part of installation;
8) two first tie-beams 11 and two second companies are installed on the top of the column 13 of the assembling type steel structure at middle part 1 Connect beam 12;
9) in the assembling type steel structure at middle part 1, more girders 14 are installed between two first tie-beams 11, to master Beam 14 installs more secondary beams 15 after installation is complete between two second tie-beams 12;
10) distribution situation according to sports equipment in assembling type steel structure 1 is set between adjacent sports equipment 4 Internal partition wall installs sports equipment 1 in the space then surrounded in internal partition wall, and installs elevator 5 and stair 6;
11) floor 9 on the top of the assembling type steel structure at middle part 1 is installed, and pavement material face layer is carried out to floor 9, The column 13 of the assembling type steel structure 1 on top is installed on floor 9;
12) two first tie-beams 11 and two second are installed on the top of the column 13 of the assembling type steel structure on top 1 Tie-beam 12;
13) in the assembling type steel structure on top 1, more girders 14 are installed between two first tie-beams 11, right Girder 14 installs more secondary beams 15 after installation is complete between two second tie-beams 12;
14) distribution situation according to sports equipment 4 in assembling type steel structure 1 is set between adjacent sports equipment 4 Internal partition wall installs sports equipment 4 in the space then surrounded in internal partition wall, and installs elevator 5 and stair 6;
15) top plate 8 on the top of the assembling type steel structure on top 1 is installed, and water-proofing treatment is carried out to top plate 8;
16) the assembling type steel structure of lowermost end 1, middle part assembling type steel structure 1 and top assembling type steel structure 1 Side installation side plate 7.
In the present embodiment can the multi-functional sports culture facility of load module have the following advantages that:
(1) capital quantity needed for present invention construction is small, and construction material of the invention is mainly steel construction, and steel construction is in factory In it is prefabricated, then steel construction is sent to construction site, construction personnel only need at the construction field (site) be pacified steel construction by fastener 3 It installing and completes process of construction, installation process is fast, and in the prior art, by armored concrete constructing sports grounds shop, taken Between it is longer, cost of labor is higher, therefore in the case where realizing equal function, build the sports culture facility of the present invention only need it is several Ten million, and several hundred million to tens are then needed using armored concrete constructing sports grounds shop, therefore, the required construction cost of the present invention It substantially reduces;
(2) assembling type steel structure 1 of the invention is assembled by multiple prefabricated components, and assembling type steel structure 1 is connected with floor 9 It with side plate 7, is detachably connected between adjacent assembling type steel structure 1, being carried out between assembling type steel structure 1 and floor 9 can Dismantling connection is detachably connected between assembling type steel structure 1 and side plate 7, and only needing at the construction field (site) respectively will be first by needs The assembling of assembling type steel structure 1 built is completed, then different assembling type steel structures 1 is detachably connected, finally by floor 9 and side plate 7 installation that entire sports culture facility can be completed is installed into assembling type steel structure 1, the required construction of the present invention Period is shorter, generally 1-2 months, and the construction in constructing sports grounds shop needs to carry out casting reinforced concrete in the prior art, Construction period is longer, generally 2-3;
(3) present invention includes one or more assembling type steel structures 1 being superimposed up and down successively, assembling type steel structure 1, building Plate 9 and the connection of side plate 7 form the space that can accommodate sports equipment 4, and space is equipped with identical or different sports equipment 4, therefore, this The sports culture facility of invention functionally has intensive, diversification, content complete, one-stop service and the operational management cost few Feature is realized complete by swimming, football, tennis, basketball, land ice hockey, wushu, sports dancing, boxing, Yoga, strength body-building etc. 20 multiple combinations that people's body-building and cultural more than the 30 kinds of project of the common people such as nautch, the fine arts, hand-made, small theatre integrate Sports culture facility meets Mass sports cultural demand to greatest extent;
(4) assembling type steel structure 1 of the invention is formed by connecting by multiple prefabricated components, and floor 9 and side plate 7 are prefabricated component, phase It is detachably connected between adjacent base body, steel construction has environmental protection relative to reinforced concrete structure of the prior art Feature, and can Reusability assembling type steel structure 1, floor 9 and side plate 7 by being detachably connected;
(5) in the case where being becoming tight the land resource day in city, the present invention by by different assembling type steel structures 1 into Row is superimposed up and down, and the soil space of occupancy is small, generally only takes up the soil of 1200 ㎡, and the story height of existing stadiums It is not high, generally there was only a sheaf space or two sheaf spaces, it is relatively large per the occupied area of sheaf space, therefore occupy a large amount of Soil space construction, so as to which present invention saves soil spaces, realize efficiently using for land resource;
(6) assembling type steel structure 1 of the invention includes multiple prefabricated components, is detachably connected by fastener 3 between prefabricated component It connects, by setting multiple prefabricated components, after completing in factory, is sent to construction site and is assembled, realization was built The assembly rate of assembling assembly is up to more than 95% (other than ground) and realizes the Standardization Construction of sports culture facility in journey.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvement and replacement can also be made, these improve and replace Also it should be regarded as protection scope of the present invention.

Claims (10)

1. one kind can the multi-functional sports culture facility of load moduleization, which is characterized in that including one or more assembled steels Structure, the assembling type steel structure are made of the connection of multiple prefabricated components, and the assembling type steel structure is connected with floor and side plate, institute It is the prefabricated component to state floor and side plate, and sports equipment can be accommodated by being formed between the assembling type steel structure, floor and side plate Space can place identical or different sports equipment in the space;
It is detachably connected between the adjacent assembling type steel structure.
It 2. as described in claim 1 can the multi-functional sports culture facility of load moduleization, which is characterized in that the assembled Steel construction includes two the first tie-beams being arranged in parallel and two and first tie-beam the second tie-beam connected vertically, Adjacent first tie-beam and the second tie-beam are detachably connected, and the bottom end of first tie-beam and the second tie-beam connects It is connected to more root posts;
The more girders are connected between two first tie-beams, the top of the girder is connected with more secondary beams, institute The both ends for stating secondary beam are detachably connected respectively with two second tie-beams, are detachably connected between the girder and the secondary beam It connects, first tie-beam, the second tie-beam, column, girder and secondary beam are the different prefabricated components.
It 3. as claimed in claim 2 can the multi-functional sports culture facility of load moduleization, which is characterized in that the column Bottom end connects the floor, and the both sides of the column connect the side plate.
4. as described in claim 1 can the multi-functional sports culture facility of load moduleization, which is characterized in that the girder by Multistage beam body forms, and the beam body of the adjacent composition girder is detachably connected by fastener, composition institute on the outermost side The beam body for stating girder is connect with the side of first tie-beam.
5. as claimed in claim 4 can the multi-functional sports culture facility of load moduleization, which is characterized in that the secondary beam by Multistage beam body forms, and is connected with described in composition between second tie-beam and the girder adjacent with second tie-beam The beam body of secondary beam is connected with the beam body for forming the secondary beam between the beam body of the adjacent composition girder.
It 6. as claimed in claim 2 can the multi-functional sports culture facility of load moduleization, which is characterized in that the column Height is between 5m~10m.
It 7. as claimed in claim 6 can the multi-functional sports culture facility of load moduleization, which is characterized in that the column Height can be 6m, 7m or 9.5m.
8. as described in claim 1 can the multi-functional sports culture facility of load moduleization, which is characterized in that the side plate by Side fascia and the lining composition being connect with the Side fascia.
It 9. as described in claim 1 can the multi-functional sports culture facility of load moduleization, which is characterized in that the sport is set It applies including ball facility and/or art installations and/or health-care facilities and/or swimming pool.
It 10. as described in claim 1 can the multi-functional sports culture facility of load moduleization, which is characterized in that positioned at most pushing up Top plate is connected at the top of the assembling type steel structure at end.
CN201810122471.8A 2018-02-07 2018-02-07 One kind can the multi-functional sports culture facility of load moduleization Withdrawn CN108149797A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810122471.8A CN108149797A (en) 2018-02-07 2018-02-07 One kind can the multi-functional sports culture facility of load moduleization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810122471.8A CN108149797A (en) 2018-02-07 2018-02-07 One kind can the multi-functional sports culture facility of load moduleization

Publications (1)

Publication Number Publication Date
CN108149797A true CN108149797A (en) 2018-06-12

Family

ID=62457035

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810122471.8A Withdrawn CN108149797A (en) 2018-02-07 2018-02-07 One kind can the multi-functional sports culture facility of load moduleization

Country Status (1)

Country Link
CN (1) CN108149797A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252781A (en) * 2020-08-18 2021-01-22 杭州焱非智能科技有限公司 Assembled basketball court

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005105537A (en) * 2003-09-26 2005-04-21 Bdm:Kk House construction method using module for house construction and house construction method using the module and the house
CN102995744A (en) * 2012-11-26 2013-03-27 北京工业大学 Industrialized multi-high-rise assembly type steel structure frame-pre-stressed center support system
CN205296906U (en) * 2016-01-04 2016-06-08 山东盛发科工贸有限公司 Filling station's lightweight steel construction awning support
CN106193311A (en) * 2016-08-22 2016-12-07 Modular assembled building structure
CN208088519U (en) * 2018-02-07 2018-11-13 张朝辉 One kind can the multi-functional sports culture facility of load moduleization

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005105537A (en) * 2003-09-26 2005-04-21 Bdm:Kk House construction method using module for house construction and house construction method using the module and the house
CN102995744A (en) * 2012-11-26 2013-03-27 北京工业大学 Industrialized multi-high-rise assembly type steel structure frame-pre-stressed center support system
CN205296906U (en) * 2016-01-04 2016-06-08 山东盛发科工贸有限公司 Filling station's lightweight steel construction awning support
CN106193311A (en) * 2016-08-22 2016-12-07 Modular assembled building structure
CN208088519U (en) * 2018-02-07 2018-11-13 张朝辉 One kind can the multi-functional sports culture facility of load moduleization

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252781A (en) * 2020-08-18 2021-01-22 杭州焱非智能科技有限公司 Assembled basketball court

Similar Documents

Publication Publication Date Title
Charleson Structure as architecture: a source book for architects and structural engineers
Lennartz et al. New Architecture in wood: forms and structures
CN208088519U (en) One kind can the multi-functional sports culture facility of load moduleization
CN108149797A (en) One kind can the multi-functional sports culture facility of load moduleization
CN107578691A (en) Frame structure construction training model is used in a kind of assembled architecture teaching
Luong et al. Finding structural solutions by connecting towers
CN207765047U (en) A kind of assembled architecture teaching frame structure construction training model
Zhdanova et al. Basics of architectural typology of modern fitness centers
Billington et al. Thin shell concrete structures: the master builders
CN206071120U (en) A kind of integrated form timber structure solid track and field venue
Baričević et al. Idejni projekt stadiona Arena Nikola Gazdić Split
CN103122699A (en) Multifunctional composite space gymnasium
CN202391170U (en) Multifunctional composite space gym
RU2649705C1 (en) School building
Oleinik et al. Organizational and Process Design Solutions for Sports Facilities
Soyluk et al. THE USE OF TRUSS SYSTEMS IN UNIVERSITY BUILDINGS: CASE OF ABANT İZZET BAYSAL UNIVERSITY
RU136839U1 (en) GAME ATTRACTION FOR SPORTS OR GAME EVENTS
Pawlikowska-Piechotka Sports and recreation facilities in schools-history and present state
Meriggi Mosca-le aree di progetto: la “Direttrice della cultura” e l’” Ansambl’architettonico socialista”/Moscow-Project areas: the “Cultural Directrix” and the “Socialist Architectural Ensamble”
Bell et al. Multi-Use Academic, Athletic, and Parking Structure, Considering Vibration Performance
Apine Activities of Āgenskalns Gymnastics and Sports Society and Its Headquarters at 7 Baldones Street
McGilvray The architectural design of tubular steel structures
Borrego et al. Detect, React: Vertical types and transformation studies
Richardson Hannes Meyer and the general plan for the reconstruction of Moscow, 1931–5
Ibragimov et al. Free space-planning solutions in the architecture of multi-storey buildings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180612