CN108131257A - 一种海上风机的一体化安装方法 - Google Patents

一种海上风机的一体化安装方法 Download PDF

Info

Publication number
CN108131257A
CN108131257A CN201810039340.3A CN201810039340A CN108131257A CN 108131257 A CN108131257 A CN 108131257A CN 201810039340 A CN201810039340 A CN 201810039340A CN 108131257 A CN108131257 A CN 108131257A
Authority
CN
China
Prior art keywords
installation
blade
wheel hub
wind turbine
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810039340.3A
Other languages
English (en)
Inventor
任政儒
蒋致禹
施伟
宁德志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CN201810039340.3A priority Critical patent/CN108131257A/zh
Priority to PCT/CN2018/077529 priority patent/WO2019134242A1/zh
Publication of CN108131257A publication Critical patent/CN108131257A/zh
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Wind Motors (AREA)

Abstract

本发明属于海上风电技术领域,涉及一种海上风机一体化安装方法。步骤如下:(1)在岸上,组装各部件形成预安装机组;固定装置将叶片固定于塔筒周围,缆绳将叶片的根部与轮毂相连接;(2)将预安装机组垂直放置至安装船的甲板上,保持安全距离;安装船运送到安装地点,将预安装机组装配到风机基座上;(3)打开固定装置的一部分,释放其中一枚叶片,旋转机舱到安装位置;旋转轮毂,使轮毂的装配法兰朝下;收紧缆绳,叶片的根部插入法兰中,使叶片安装在轮毂上;重复以上步骤直到所有叶片都安装完毕。本发明由岸上预安装从而降低离岸操作时间,提高甲板利用率,增加风机机组运输效率,从而提高安装效率,降低安装成本,增强安装安全性。

Description

一种海上风机的一体化安装方法
技术领域
本发明属于海上风电技术领域,涉及一种海上风机整体安装方法,特别涉及一种提高甲板利用率的海上风机一体化安装方法。
背景技术
海上风机的安装方法可以分类为整体安装和分部安装。其中,后者根据各部件的岸上安装完成度又有多种选择,例如单叶片安装、转子及叶片整体吊装,兔耳朵型转子及叶片吊装。通常安装方式由安装船起重能力、海洋天气条件、离岸距离等因素综合决定。整体安装的突出优点是依靠风机岸上的预组装降低离岸操作时间,从而降低海上安装成本。然而由于叶片需要占据极大的甲板面积,整机安装有较低的甲板利用率。当安装风场离岸距离比较远的时候,大量时间将被浪费在风机机组的运输阶段。
发明内容
为解决上述问题,本发明提出海上风机的整体安装方法。该方法可以极大提高甲板利用率,降低安装船的操作时间,从而降低海上风电价格,加快清洁能源的普及。
为了达到上述目的,本发明提供如下方案:
一种海上风机一体化安装方法,具体步骤如下:
1)在岸上,自下而上依次组装过渡段1、塔筒2、叶片3、机舱4和轮毂5,固定装置7将叶片3固定于塔筒2周围,叶片3的根部通过缆绳6与轮毂5相连接,形成预安装机组8;
2)预安装机组8组装完成后,多个预安装机组8垂直安放于安装船9的甲板上,保持各预安装机组8的间距处于安全距离;安装船9运送预安装机组8到安装地点,预安装机组8通过过渡段1装配到风机基座11上;
3)打开固定装置7的一部分,释放其中一枚叶片3,旋转机舱4到安装位置;旋转轮毂5,使轮毂5的装配法兰朝下;收紧缆绳6,叶片3的根部插入法兰中,使叶片3安装在轮毂5上;重复以上步骤直到所有叶片都安装完毕。
本发明的有益效果:由岸上预安装从而降低离岸操作时间,提高甲板利用率,增加风机机组运输效率,从而提高安装效率,降低安装成本,增强安装安全性。进而降低海上风电价格,推广清洁能源。
附图说明
图1是待安装风机岸上组装形式示意图。
图2是风机机组的甲板布置图。
图3是海上安装示意图。
其中:1过渡段;2塔筒;3叶片;4机舱;5轮毂;6缆绳;7固定装置;8预安装机组;9安装船;10水面;11风机桩底;12海床。
具体实施方式
以下结合附图和技术方案,进一步说明本发明的具体实施方式。
如图1-3所示,一种海上风机一体化安装方法,具体步骤如下:
1)在岸上,自下而上依次组装过渡段1、塔筒2、叶片3、机舱4和轮毂5,固定装置7将叶片3固定于塔筒2周围,叶片3的根部通过缆绳6与轮毂5相连接,形成预安装机组8;
2)预安装机组8组装完成后,多个预安装机组8垂直安放于安装船9的甲板上,保持各预安装机组8的间距处于安全距离;安装船9运送预安装机组8到安装地点,预安装机组8通过过渡段1装配到风机基座11上;
3)打开固定装置7的一部分,释放其中一枚叶片3,旋转机舱4到安装位置;旋转轮毂5,使轮毂5的装配法兰朝下;收紧缆绳6,叶片3的根部插入法兰中,使叶片3安装在轮毂5上;重复以上步骤直到所有叶片都安装完毕。

Claims (1)

1.一种海上风机一体化安装方法,其特征在于,具体步骤如下:
1)在岸上,自下而上依次组装过渡段(1)、塔筒(2)、叶片(3)、机舱(4)和轮毂(5),固定装置(7)将叶片(3)固定于塔筒(2)周围,叶片(3)的根部通过缆绳(6)与轮毂(5)相连接,形成预安装机组(8);
2)预安装机组(8)组装完成后,多个预安装机组(8)垂直安放于安装船(9)的甲板上,保持各预安装机组(8)的间距处于安全距离;安装船(9)运送预安装机组(8)到安装地点,预安装机组(8)通过过渡段(1)装配到风机基座(11)上;
3)打开固定装置(7)的一部分,释放其中一枚叶片(3),旋转机舱(4)到安装位置;旋转轮毂(5),使轮毂(5)的装配法兰朝下;收紧缆绳(6),叶片(3)的根部插入法兰中,使叶片(3)安装在轮毂(5)上;重复以上步骤直到所有叶片都安装完毕。
CN201810039340.3A 2018-01-08 2018-01-08 一种海上风机的一体化安装方法 Pending CN108131257A (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810039340.3A CN108131257A (zh) 2018-01-08 2018-01-08 一种海上风机的一体化安装方法
PCT/CN2018/077529 WO2019134242A1 (zh) 2018-01-08 2018-02-28 一种海上风机的一体化安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810039340.3A CN108131257A (zh) 2018-01-08 2018-01-08 一种海上风机的一体化安装方法

Publications (1)

Publication Number Publication Date
CN108131257A true CN108131257A (zh) 2018-06-08

Family

ID=62400329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810039340.3A Pending CN108131257A (zh) 2018-01-08 2018-01-08 一种海上风机的一体化安装方法

Country Status (2)

Country Link
CN (1) CN108131257A (zh)
WO (1) WO2019134242A1 (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112283024A (zh) * 2020-11-18 2021-01-29 西安热工研究院有限公司 一种叶片位置可调的风轮及其工作方法
CN113107780A (zh) * 2020-01-10 2021-07-13 新疆金风科技股份有限公司 风力发电机组的叶片组装方法及单向转动装置

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO345276B1 (en) * 2019-03-05 2020-11-23 Blue Wind As Solution for floating windmill
JP7551638B2 (ja) 2019-03-05 2024-09-17 ブルー-ウインド アクティーゼルスカブ 浮体式風車設備

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101318542A (zh) * 2008-05-16 2008-12-10 中国海洋石油总公司 一种风电机组海上整体安全运输的方法
CN101825071A (zh) * 2009-03-03 2010-09-08 西门子公司 安装风力涡轮机的方法和装置
CN101903235A (zh) * 2007-12-21 2010-12-01 维斯塔斯风力系统集团公司 安装离岸风轮机的方法与驳船系统
CN102011714A (zh) * 2010-10-08 2011-04-13 中交第一航务工程局有限公司 海上风力发电机组整体安装施工方法及其设备
CN102616339A (zh) * 2011-01-30 2012-08-01 华锐风电科技(江苏)有限公司 一种风电机组的运输安装船及风电机组的船运和安装方法
CN103670946A (zh) * 2012-08-30 2014-03-26 远景能源(江苏)有限公司 安装离岸风力涡轮机的方法及其运输船
CN104192272A (zh) * 2014-08-11 2014-12-10 中国石油大学(华东) 自航自升式风电运输安装船及风电机组的安装方法
CN106014874A (zh) * 2016-06-30 2016-10-12 海阳中集来福士海洋工程有限公司 海上风力发电机组的安装方法

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102616338A (zh) * 2011-01-30 2012-08-01 华锐风电科技(集团)股份有限公司 一种运输风电机组的船、一种风电机组的运输方法
CN103133267B (zh) * 2011-12-02 2015-11-25 新疆金风科技股份有限公司 风力发电机组的叶片更换方法及叶片更换辅助系统
US8985948B2 (en) * 2012-02-21 2015-03-24 Clean Green Energy LLC Fluid driven vertical axis turbine
CN103015445B (zh) * 2012-12-19 2015-10-21 江苏龙源振华海洋工程有限公司 浅海域风电场无过渡段单桩基础施工和风机设备安装工艺
CN104314761B (zh) * 2014-08-25 2017-02-22 丁健威 一种叶片收叠式风能机
CN205117606U (zh) * 2015-11-13 2016-03-30 北京唐浩电力工程技术研究有限公司 一种提升发电能力的风电机组
CN105971828B (zh) * 2016-06-30 2018-08-21 洛阳双瑞风电叶片有限公司 一种大型风力发电叶片翻转、运输一体装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101903235A (zh) * 2007-12-21 2010-12-01 维斯塔斯风力系统集团公司 安装离岸风轮机的方法与驳船系统
CN101318542A (zh) * 2008-05-16 2008-12-10 中国海洋石油总公司 一种风电机组海上整体安全运输的方法
CN101825071A (zh) * 2009-03-03 2010-09-08 西门子公司 安装风力涡轮机的方法和装置
CN102011714A (zh) * 2010-10-08 2011-04-13 中交第一航务工程局有限公司 海上风力发电机组整体安装施工方法及其设备
CN102616339A (zh) * 2011-01-30 2012-08-01 华锐风电科技(江苏)有限公司 一种风电机组的运输安装船及风电机组的船运和安装方法
CN103670946A (zh) * 2012-08-30 2014-03-26 远景能源(江苏)有限公司 安装离岸风力涡轮机的方法及其运输船
CN104192272A (zh) * 2014-08-11 2014-12-10 中国石油大学(华东) 自航自升式风电运输安装船及风电机组的安装方法
CN106014874A (zh) * 2016-06-30 2016-10-12 海阳中集来福士海洋工程有限公司 海上风力发电机组的安装方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113107780A (zh) * 2020-01-10 2021-07-13 新疆金风科技股份有限公司 风力发电机组的叶片组装方法及单向转动装置
CN113107780B (zh) * 2020-01-10 2023-03-03 新疆金风科技股份有限公司 风力发电机组的叶片组装方法及单向转动装置
CN112283024A (zh) * 2020-11-18 2021-01-29 西安热工研究院有限公司 一种叶片位置可调的风轮及其工作方法

Also Published As

Publication number Publication date
WO2019134242A1 (zh) 2019-07-11

Similar Documents

Publication Publication Date Title
CN108131257A (zh) 一种海上风机的一体化安装方法
CN100406721C (zh) 风力涡轮机及其安装方法
US9890763B2 (en) Counterweighting a wind turbine hub
CN104121154A (zh) 用于装配和运输海上风力涡轮机的方法
US20100135768A1 (en) Column structure with protected turbine
CN103015445B (zh) 浅海域风电场无过渡段单桩基础施工和风机设备安装工艺
CN202295334U (zh) 集成型直升机起落平台
CN105649884A (zh) 海上风能与海洋潮流能联合发电平台
WO2013137744A1 (en) Floating wind turbine with wave energy converter
CN201763532U (zh) 一种海上可再生能源转换装置
CN108443079A (zh) 一种海上风力发电机组叶片的运输及安装方法
CN110043429A (zh) 一种大型风力发电机单叶片安装工艺施工方法
CN202987471U (zh) 适用于浅海海域风电场基础和设备批量运输的专用驳船
CN201474858U (zh) 海上垂直轴可升降复合式发电平台
CN102400862A (zh) 风力发电机组的叶轮装配方法
CN202278363U (zh) 风力发电机组的叶轮装配辅助设备
US20240209825A1 (en) Cycloturbine modular river current energy converter and method and apparatus for deploying marine hydrokinetic turbine assembly to harvest riverine and ocean tidal current energy
CN101988468B (zh) 海上垂直轴可升降复合式发电平台
CN108757332B (zh) 一种光伏与风机联合发电的海上半潜式平台发电系统
CN102092645B (zh) 潮间带浅水区风力发电设备安装方法
CN103726992B (zh) 塔吊式稳固叶片拉件大型高效风力发电机及安装方法
CN203184903U (zh) 用于海上风力发电机组叶轮拼装的设备
WO2010120186A1 (en) Floating windmill and method of installation, intervention or decommissioning
CN201560898U (zh) 基于三角帆动力的竖直轴海上风力发电机
CN201972846U (zh) 螺旋式涡轮风叶及垂直轴螺旋式涡轮风叶风力发电机

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180608