CN108104278A - Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely - Google Patents

Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely Download PDF

Info

Publication number
CN108104278A
CN108104278A CN201711386646.8A CN201711386646A CN108104278A CN 108104278 A CN108104278 A CN 108104278A CN 201711386646 A CN201711386646 A CN 201711386646A CN 108104278 A CN108104278 A CN 108104278A
Authority
CN
China
Prior art keywords
construction
layers
installation
layer
residential building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711386646.8A
Other languages
Chinese (zh)
Inventor
于义翔
郭世江
胡利
樊开威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Ke Zhu Construction Management Co Ltd
Foshan Vanke Properties Development Co Ltd
Original Assignee
Guangdong Ke Zhu Construction Management Co Ltd
Foshan Vanke Properties Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Ke Zhu Construction Management Co Ltd, Foshan Vanke Properties Development Co Ltd filed Critical Guangdong Ke Zhu Construction Management Co Ltd
Priority to CN201711386646.8A priority Critical patent/CN108104278A/en
Publication of CN108104278A publication Critical patent/CN108104278A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/02Dwelling houses; Buildings for temporary habitation, e.g. summer houses
    • E04H1/04Apartment houses arranged in two or more levels

Abstract

Intert construction entirely after binding the invention discloses a kind of complete cast-in-place exterior wall high residential building main body and put forward efficacious prescriptions method, comprise the following steps:Agent structure binds;During Construction of Energy Room;Climbing frame and construction elevator are removed;Elevator is installed;Remove tower crane;Outdoor garden layout;Exterior wall nacelle construction;Lacquer painting is constructed;Storage installation;Table top lamp installation;Door and two times finishing coat constructions;Timber floor is installed;Hardware equipment is installed and house is kept a public place clean.The complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely, ensure that complete cast-in-place exterior wall high residential building main body bind after each construction operation work post can intert and work continuously, both total time of construction is shortened, improves work efficiency, and improves the level that becomes more meticulous of projects management.

Description

Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely
Technical field
Intert entirely after binding the present invention relates to the realm of building construction more particularly to a kind of complete cast-in-place exterior wall high residential building main body Construction puies forward efficacious prescriptions method.
Background technology
Traditional construction tissue promotes field operation generally to use, and first step main body construction is completed, second step alien invasion operation, 3rd step outrigger is removed, and the 4th step fitment operation is marched into the arena, and the backfill of the 5th step basement roof, the 6th step garden builds construction, exists so far It is still being continued to use in engineering.
Traditional construction organizational form essentially site tissue is carried out from single time shaft, i.e., the same time can not and meanwhile into The multinomial job placement of row is utilized so that time utility fails to maximize.
Traditional construction tissue is mostly the form under traditional construction technique (wooden model is built by laying bricks or stones, scaffold, wet construction etc.), can not Realize what the new construction system of existing use (aluminum dipping form, intelligent climbing frame, prefabricated panel, complete cast-in-place exterior wall, dry construction etc.) was brought Put forward the advantage of effect.
The content of the invention
Intert construction entirely after binding it is an object of the invention to provide a kind of complete cast-in-place exterior wall high residential building main body and carry efficacious prescriptions Method, the complete cast-in-place exterior wall high residential building main body intert construction after binding and put forward efficacious prescriptions method entirely, ensure that complete cast-in-place exterior wall high residential building Main body after binding each construction operation work post can intert and work continuously, both shorten total time of construction, improve work efficiency, and promoted The levels that becomes more meticulous of projects management.
Its technical solution is as follows:
Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely, comprises the following steps:
Agent structure binds;
During Construction of Energy Room:Agent structure proceeds by roof structure During Construction of Energy Room operation after binding;
Climbing frame and construction elevator are removed:After the completion of roof structure, During Construction of Energy Room operation, start climbing frame and construction elevator is torn open It removes;
Elevator is installed:After the completion of climbing frame is removed, construction elevator is removed, residential lift starts to install, and elevator installs laggard Row elevator debugging;
Remove tower crane:Climbing frame construction operation is removed to start to remove tower crane after finishing;
Outdoor garden layout:After the completion of removing tower crane construction operation, start outdoor garden layout operation and start;
Exterior wall nacelle construction:After the completion of removing tower crane construction operation, residence outer wall later work, exterior wall nacelle construction operation Start to construct;
Lacquer painting is constructed:After the completion of exterior wall nacelle construction, the lacquer painting construction operation of each layer of house is proceeded by;
Storage installation:After the completion of the lacquer painting construction operation of each layer of house, the collecting apparatus installation of each layer of house starts to construct Operation;
Table top lamp installation:After installation is complete, the table top lamps and lanterns of each layer of house start to install the collecting apparatus of each layer of house Construction operation;
Door and two times finishing coat constructions:After the completion of the table top lamps and lanterns of each layer of house start installation operation, each layer of house Door and two times finishing coats start construction operation;
Timber floor is installed:After the completion of the door of each layer of house and two times finishing coats start construction operation, the timber floor of each layer of house Installation operation starts;
Hardware equipment is installed and house is kept a public place clean:After the completion of the timber floor installation operation of each layer of house, each layer of house into Row hardware equipment is installed and house is kept a public place clean construction operation.
The outdoor garden layout comprises the following steps:
Gardens base layer construction;
Gardens arbor is planted;
Gardens capital construction is built by laying bricks or stones;
Garden shrub species are constructed;
Landscape ground is constructed;
Gardens turf construction;
Afforestation conserves.
The lacquer painting construction includes indoor lacquer painting construction, and the interior lacquer painting construction comprises the following steps:
Indoor ceiling mechanically spraying priming paint, repairing;
Indoor ceiling first pass finishing coat is constructed;
Second time finishing coat construction of indoor ceiling.
The lacquer painting construction further includes outdoor lacquer painting construction, and the outdoor lacquer painting construction comprises the following steps:
Balcony, air-conditioning plate, exterior window, wall face priming paint;
Balcony, air-conditioning plate, exterior window, wall face first pass finishing coat;
Second time balcony, air-conditioning plate, exterior window, wall face finishing coat;
Balcony, air-conditioning plate, exterior window, wall face clean for the first time;
Second of the cleaning of balcony, air-conditioning plate, exterior window, wall face.
The elevator debugging comprises the following steps:
Elevator intelligent equipment is installed;
Elevator installation and debugging;
Elevator intelligent equipment debugging.
The storage installation comprises the following steps:
Clean cabinet installation;
Mirror cabinet is installed;
Cabinet is installed;
Fire-fighting ventilation opening blinds is installed.
The table top lamp installation comprises the following steps:
The low window guardrail installation of toilet, room, escalator;
Parlor intelligent equipment starts to debug;
Toilet, washing room, kitchen countertop installation;
Toilet, kitchen, the indoor doorframe installation in room;
Kitchen, escalator, staircase, balcony lamp installation;
Room, the rectification of parlor thin portion;
Switch panel is installed.
The door and two times finishing coat constructions comprise the following steps:
Toilet, kitchen, the installation of room door leaf;
Toilet is installed;
Two times room, parlor, escalator metope finishing coat constructions;
Switch panel is installed;
Toilet, kitchen, the installation of room architrave;
Piping shaft, escalator, the installation of staircase fireproof door leaf.
The hardware equipment installation and house, which are kept a public place clean, to be comprised the following steps:
Kitchen appliance is installed;
Toilet, washing room, the installation of kitchen hardware;
It is indoor and outdoor just to keep a public place clean;
Indoor gluing;
Toilet, washing room, kitchen Wall or floor tile jointing.
The interior gluing comprises the following steps:
Toilet, washing room, kitchen countertop gluing;
Parlor is registered one's residence gluing outside door frame;
Escalator, staircase doorframe side gluing.
It should be noted that:
After the completion of " dismounting tower crane " construction operation, " outdoor garden layout " and " exterior wall nacelle construction " can be carried out at the same time, It can be with first progress " outdoor garden layout " carries out " exterior wall nacelle construction " again or first progress " exterior wall nacelle construction " carries out again " outdoor garden layout ".
Advantages of the present invention or principle are illustrated below:
1st, it is a kind of process organization and administration that this complete cast-in-place exterior wall high residential building main body interts construction to put forward efficacious prescriptions method entirely after binding Technology, each construction part is partitioning standards after being bound using high residential building main body;The scope of the complete interspersed construction covers high residential building Main body parts such as indoor and outdoor, gardens after binding are that comprehensive after high residential building main body truly binds interspersed is applied Work refine to the first job item that need to carry out interspersed construction, including indoor and outdoor, gardens;Its object is to clear and definite high levels to live The working procedure flowing water tissue of construction overall process and technology requirement, both shorten total time of construction, improve after residence main body binds Work efficiency, and improve the level that becomes more meticulous of projects management;
The complete cast-in-place exterior wall high residential building main body interts construction and proposes the duration contracting more whole than traditional construction of efficacious prescriptions method entirely after binding It is short, it realizes to deliver in advance and move in, create added value;Traditional construction organizational form is compared in the interspersed construction, operable strong, further Reduce subjective error;
It realizes each professional workers after high residential building main body binds and can intert and work continuously, it is ensured that high residential building main body is sealed Intert construction operation behind top entirely, shorten total time of construction, improve work efficiency.
To realize that high residential building main body interts construction after binding, interspersed construction node significant during having combed, Convenient for macroscopical control;
The interspersed construction, which realizes, effectively combines aluminum dipping form, intelligent climbing frame, prefabricated panel, complete cast-in-place exterior wall, dry construction etc. Advanced technologies, perspective height create surcharge for building trade, are the mainstreams of industry future development.
2nd, flowing water section is further segmented by each construction operation content, optimizes the arrangement of labour, reduced and work to single work post The surprise demand of power quantity accomplishes science, orderly, coherent, ensures that each professional workers can intert and work continuously.
Specific embodiment
The embodiment of the present invention is described in detail below.
Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely, comprises the following steps:
Agent structure binds;
During Construction of Energy Room:Agent structure proceeds by roof structure During Construction of Energy Room operation after binding;
Climbing frame and construction elevator are removed:After the completion of roof structure, During Construction of Energy Room operation, start climbing frame and construction elevator is torn open It removes;
Elevator is installed:After the completion of climbing frame is removed, construction elevator is removed, residential lift starts to install, and elevator installs laggard Row elevator debugging;
Remove tower crane:Climbing frame construction operation is removed to start to remove tower crane after finishing;
Outdoor garden layout:After the completion of removing tower crane construction operation, start outdoor garden layout operation and start;
Exterior wall nacelle construction:After the completion of removing tower crane construction operation, residence outer wall later work, exterior wall nacelle construction operation Start to construct;
Lacquer painting is constructed:After the completion of exterior wall nacelle construction, the lacquer painting construction operation of each layer of house is proceeded by;
Storage installation:After the completion of the lacquer painting construction operation of each layer of house, the collecting apparatus installation of each layer of house starts to construct Operation;
Table top lamp installation:After installation is complete, the table top lamps and lanterns of each layer of house start to install the collecting apparatus of each layer of house Construction operation;
Door and two times finishing coat constructions:After the completion of the table top lamps and lanterns of each layer of house start installation operation, each layer of house Door and two times finishing coats start construction operation;
Timber floor is installed:After the completion of the door of each layer of house and two times finishing coats start construction operation, the timber floor of each layer of house Installation operation starts;
Hardware equipment is installed and house is kept a public place clean:After the completion of the timber floor installation operation of each layer of house, each layer of house into Row hardware equipment is installed and house is kept a public place clean construction operation.
Wherein, complete cast-in-place exterior wall high residential building interts to construct entirely puies forward efficacious prescriptions method, comprises the following steps:
N layer main body structure construction layers:The agent structure of high residential building successively carries out main structure construction from the 1st layer to top layer Operation;
N-1 layers of form removal construction layer:When agent structure is when carrying out n-th layer construction operation, N-1 layers of main structure construction It completed already, N-1 layers carry out interspersed form removal construction operation;
N-2 layers of support top sealing construction layer:When carrying out form removal construction operation for N-1 layers, N-2 layers of form removal construction operation It has been completed that, N-2 layers carry out interspersed support top sealing construction operation;
N-3 layers of lining construction layer:When carrying out support top sealing construction operation for N-2 layers, N-3 layers of support top sealing is applied Work was completed already, and N-3 layers carry out interspersed lining construction operation;
N-4 layer water supplying and discharging installation layers:When carrying out lining construction operation for N-3 layers, N-4 layers of lining is applied Work was completed already, and N-4 layers carry out interspersed plumbing installation operation;
N-5 layers of pipeline installation layer:When carrying out plumbing installation operation for N-4 layers, N-5 layers of plumbing Installation was completed already, and N-5 layers carry out interspersed pipeline installation operation;
N-6 layers of smallpox putty construction layer:When carrying out pipeline installation operation for N-5 layers, N-6 layers of pipeline installation Construction operation has been completed, and N-6 layers carry out interspersed smallpox putty construction operation;
N-7 layers of kitchen and bath's wall brick paving construction layer:When carrying out smallpox putty construction operation for N-6 layers, N-7 layers of smallpox Putty construction operation has been completed, and N-7 layers carry out interspersed kitchen and bath's wall brick paving construction operation;
N-8 layers of tableland brick paving construction layer:When carrying out kitchen and bath's brick paving construction operation for N-7 layers, N-8 layers of kitchen and bath Brick paving construction was completed already, and N-8 layers carry out interspersed tableland brick paving construction operation;
N-9 layers of inner wall surface first pass putty construction layer:When carrying out tableland brick paving construction operation for N-8 layers, N-9 layers Tableland brick paving construction completed already, N-9 layers carry out interspersed inner wall surface first pass putty construction operation;
Second time putty construction layer of N-10 layers of inner wall surface:When carrying out inner wall surface first pass putty construction operation for N-9 layers, N-10 layers of inner wall surface first pass putty construction operation has been completed, and N-10 layers carry out interspersed second time putty construction of inner wall surface Operation;
N-11 layers of staircase construction layer:When carrying out interting second time putty construction operation for N-10 layers, N-11 layers Second time putty construction operation has been completed, and N-11 layers carry out interspersed staircase construction operation;
Complete cast-in-place exterior wall high residential building kitchen and bath interts construction and puies forward efficacious prescriptions method, comprises the following steps:
N layers of kitchen and bath's main structure construction layer:Kitchen and bath's agent structure of high residential building successively carries out kitchen and bath from the 1st layer to top layer Main structure construction operation;
N-1 layers of kitchen and bath's form removal construction layer:When kitchen and bath's agent structure is when carrying out n-th layer construction operation, N-1 layers of kitchen and bath Main structure construction was completed already, and N-1 layers carry out interspersed kitchen and bath's form removal construction operation;
N-2 layers of kitchen and bath's support top sealing construction layer:When carrying out kitchen and bath's form removal construction operation for N-1 layers, N-2 layers of kitchen and bath Form removal construction operation has been completed, and N-2 layers carry out interspersed kitchen and bath's support top sealing construction operation;
N-3 layers of kitchen and bath's lining construction layer:When carrying out kitchen and bath's support top sealing construction operation for N-2 layers, N-3 layers of kitchen It defends support top sealing construction to complete already, N-3 layers carry out interspersed kitchen and bath's lining construction operation;
N-4 layers of kitchen and bath's plumbing mounting layer:When carrying out kitchen and bath's lining construction operation for N-3 layers, N-4 layers of kitchen and bath Lining construction operation has been completed, and N-4 layers carry out interspersed kitchen and bath's plumbing installation operation;
N-5 layers of kitchen and bath's pipeline mounting layer:When carrying out kitchen and bath's plumbing installation operation for N-4 layers, N-5 layers of kitchen It defends plumbing installation to complete already, N-5 layers carry out interspersed kitchen and bath's pipeline installation operation;
N-6 layers of kitchen and bath's smallpox putty layer:When carrying out kitchen and bath's pipeline installation operation for N-5 layers, N-6 layers of kitchen and bath Pipeline installation was completed already, and N-6 layers carry out interspersed kitchen and bath's smallpox putty construction operation;
N-7 layers of kitchen and bath's wall brick paving layer:When carrying out kitchen and bath's smallpox putty construction operation for N-6 layers, N-7 layers of kitchen and bath Smallpox putty construction operation has been completed, and N-7 layers carry out interspersed kitchen and bath's wall brick paving construction operation;
N-8 layers of kitchen and bath tableland brick paving layer:When carrying out kitchen and bath's wall brick paving construction operation for N-7 layers, N-8 layers of kitchen It defends wall brick paving construction to complete already, N-8 layers carry out interspersed kitchen and bath tableland brick paving construction operation;
N-9 layers of kitchen and bath's doorframe base installation:When carrying out interspersed kitchen and bath tableland brick paving construction operation for N-8 layers, N-9 The kitchen and bath tableland brick paving construction of layer was completed already, and N-9 layers carry out the installation operation of interspersed kitchen and bath's doorframe base;
N-10 layers of kitchen and bath's shower set installation:When carrying out the base's installation operation of kitchen and bath's doorframe for N-9 layers, N-10 Kitchen and bath's doorframe base installation of layer was completed already, and N-10 layers carry out interspersed kitchen and bath's shower set installation operation;
The complete cast-in-place exterior wall high residential building hall interts construction and puies forward efficacious prescriptions method, comprises the following steps:
N layers of hall agent structure layer:The hall agent structure of high residential building successively carries out hall main body from the 1st layer to top layer Structure construction operation;
N-1 layers of hall form removal construction layer:When hall agent structure is when carrying out n-th layer construction operation, N-1 layers of the hall Main structure construction was completed already, and N-1 layers carry out interspersed hall form removal construction operation;
N-2 layers of hall support top sealing layer:When N-1 layers of carry out hall form removal construction operation, N-2 layers of hall form removal Construction operation has been completed, and N-2 layers carry out interspersed hall support top sealing construction operation;
N-3 layers of hall lining construction layer:When N-2 layers of carry out hall support top sealing construction operation, N-3 layers of the Room Room support top sealing construction was completed already, and N-3 layers carry out interspersed hall lining construction operation;
N-4 layers of hall plumbing installation:When N-3 layers of carry out hall lining construction operation, in N-4 layers of the hall Wallboard construction operation has been completed, and N-4 layers carry out interspersed hall plumbing installation operation;
N-5 layers of hall pipeline mounting layer:When N-4 layers of carry out hall plumbing installation operation, N-5 layers of the Room Room plumbing installation was completed already, and N-5 layers carry out interspersed hall pipeline installation operation;
N-6 layers of hall smallpox putty layer:When N-5 layers of carry out hall pipeline installation operation, N-6 layers of the hall Pipeline installation was completed already, and N-6 layers carry out interspersed hall smallpox putty construction operation;
N-8 layers of hall tableland brick paving layer:When N-6 layers of carry out hall smallpox putty construction operation, N-8 layers of the Room Room smallpox putty construction operation has been completed, and N-8 layers carry out interspersed hall tableland brick paving construction operation;
N-9 layers of hall inner wall surface first pass putty layer:When N-8 layers of carry out hall tableland brick paving construction operation, the N-9 layers of hall tableland brick paving construction was completed already, and N-9 layers carry out interspersed hall inner wall surface first pass putty construction and make Industry;
Second time putty layer of N-10 layers of hall inner wall surface:When N-9 layers of carry out hall inner wall surface first pass putty construction are made During industry, N-10 layers of hall inner wall surface first pass putty construction operation has been completed, and N-10 layers carry out interspersed hall inner wall surface Second time putty construction operation;
Intert construction outside complete cast-in-place exterior wall high residential building room and put forward efficacious prescriptions method, comprise the following steps:
N layers of outdoor main structure construction layer:The outdoor agent structure of high residential building successively carries out outdoor from the 1st layer to top layer Main structure construction operation;
N-1 layers of outdoor form removal construction layer:When outdoor agent structure is when carrying out n-th layer construction operation, N-1 layers of outdoor Main structure construction was completed already, and N-1 layers carry out interspersed outdoor form removal construction operation;
N-2 layers of outdoor support top sealing construction layer:When carrying out outdoor form removal construction operation for N-1 layers, N-2 layers of outdoor Form removal construction operation has been completed, and N-2 layers carry out interspersed outdoor support top sealing construction operation;
N-3 layers of balcony guardrail installation:When carrying out outdoor support top sealing construction operation for N-2 layers, N-3 layers of outdoor branch Top sealing construction was completed already, and N-3 layers carry out interspersed balcony guardrail installation exercise;
N-4 layers of balcony plumbing installation:When carrying out balcony guardrail installation exercise for N-3 layers, N-4 layers of balcony guardrail Installation exercise has been completed, and N-4 layers carry out interspersed balcony plumbing installation operation;
N-5 layers of balcony pipeline installation:When N-4 layers of carry out balcony plumbing installation operation, N-5 layers of balcony Plumbing installation was completed already, and N-5 layers carry out interspersed balcony pipeline installation operation;
N-8 layers of balcony floor tile paving:When N-5 layers of carry out balcony pipeline installation operation, N-8 layers of balcony pipe Line installation was completed already, and N-8 layers carry out interspersed balcony floor tile paving construction operation;
Complete cast-in-place exterior wall high residential building escalator, staircase intert construction and put forward efficacious prescriptions method, comprise the following steps:
N layers of escalator, staircase agent structure layer:The escalator of high residential building, staircase agent structure from the 1st layer successively Escalator, staircase main structure construction operation are carried out to top layer;
N-1 layers of escalator, staircase form removal construction layer:When escalator, staircase agent structure are carrying out n-th layer construction work During industry, N-1 layers of escalator, staircase main structure construction had been completed already, and N-1 layers carry out interspersed escalator, stair Between form removal construction operation;
N-2 layers of escalator, staircase support top sealing layer:Escalator, staircase form removal construction operation are carried out when N-1 layers When, N-2 layers of escalator, staircase form removal construction operation have been completed, and N-2 layers carry out interspersed escalator, staircase support top Sealing construction operation;
N-5 layers of escalator, staircase pipeline mounting layer:Escalator is carried out when N-2 layers, staircase support top sealing construction is made During industry, N-5 layers of escalator, staircase support top sealing construction had been completed already, and N-5 layers carry out interspersed escalator, stair Between pipeline installation operation;
N-6 layers of escalator, staircase smallpox putty layer:Escalator is carried out when N-5 layers, the installation of staircase pipeline is made During industry, N-6 layers of escalator, the installation of staircase pipeline had been completed already, and N-6 layers carry out interspersed escalator, stair Between smallpox putty construction operation;
N-8 layers of escalator floor tile paving layer:When carrying out escalator, staircase smallpox putty construction operation for N-6 layers, the N-8 layers of escalator, staircase smallpox putty construction operation have been completed, and N-8 layers carry out interspersed escalator floor tile paving construction Operation;
N-9 layers of escalator build layer by laying bricks or stones:When carrying out escalator floor tile paving construction operation for N-8 layers, N-9 layers of elevator Between floor tile paving construction completed already, N-9 layers carry out interspersed escalator building construction operation;
N-10 layers of escalator door construction layer:When carrying out escalator building construction operation for N-9 layers, N-10 layers of elevator Between building construction completed already, N-10 layers carry out interspersed escalator door construction operation;
N-11 layers of staircase construction layer:When carrying out escalator door construction operation for N-10 layers, N-11 layers of escalator Door construction operation has been completed, and N-11 layers carry out interspersed staircase construction operation;
N layer main body structure construction layers comprise the following steps:
N layer structure unwrapping wire;
N layers of wall column reinforcing bar binding;
N layer structures draw seam installation;
Hydropower installation in N layers of wall column;
N layers of aluminum alloy pattern plate installation;
N layers of beam reinforced steel bar binding;
N layers of concrete construction;
N layers of the foot of a wall portion are horizontal to draw seam installation;
N layer structure unwrapping wire comprises the following steps:
N layer structure line settings;
N layers of reinforcing bar positioning bar welding;
N layers of the foot of a wall portion template are levelling;
N layer structures draw seam installation to comprise the following steps:
N layers of vertical structure draw seam installation;
N layers of transversary draw seam installation;
The N layers of aluminum alloy pattern plate installation comprises the following steps:
N layers of wall column aluminum dipping form are assembled;
N layers of wall column formwork cleaning, reinforcing are adjusted in place;
N layers of beam slab aluminum dipping form are assembled;
N layers of beam-slab template cleaning;
N layers of beam reinforced steel bar binding comprise the following steps:
N layers of beam steel bar colligation;
N layers of waterstop joint, back box are pre-buried;
The muscle binding of N laminates bottom;
N layers of hydroelectric line are pre-buried;
N laminates gluten is installed;
N layers of lightning protection;
N layers of concrete construction comprise the following steps:
N layers of template surface pour preceding water drenching;
N floor plate levels degree controls;
N layers of toilet structure look for slope 1%;
N-1 layers of form removal construction layer comprise the following steps:
N-1 layers of outdoor security protection;
N-1 layers of wall column formwork are removed;
N-1 layers of beam, floor template are removed;
N-1 layers of rubbish cleaning;
Screw hole closure on the inside of N-1 layers of wall column;
N-1 layers of outdoor finishing;
The actual measurement of N-1 layer structure interior walls simultaneously marks polishing repairing point;
N-1 layers of outdoor security protection comprise the following steps:
The safe blanket net of N-1 layers of outdoor horizontal is set;
N-1 layers of outdoor mortar leakage prevention masking;
N-1 layers of outdoor finishing include N-1 layers of balcony and modify, and N-1 layers of balcony finishing comprise the following steps:
The anti-bank finishing of N-1 layers of balcony;
N-1 layers of balcony structure polishing finishing;
N-1 layers of balcony smallpox equating;
N-1 layers of outdoor finishing further include N-1 layers of air-conditioning plate finishing, and N-1 layers of air-conditioning plate finishing comprise the following steps:
N-1 layers of air-conditioning float plate portion position polishing;
N-1 layers of air-conditioning float plate portion position repairing;
N-1 layers of outdoor finishing further include N-1 layers of exterior window finishing, and N-1 layers of exterior window finishing comprise the following steps:
N-1 layers of window opening polishing;
N-1 layers of window opening repairing;
N-1 layers of outdoor finishing further include N-1 layers of wall face finishing, and N-1 layers of wall face finishing comprise the following steps:
N-1 layers of outer wall screw hole closure;
N-1 layers of outer surface of wall survey and mark polishing repairing point;
N-1 layers of outer surface of wall polishing repairing;
N-1 layers of outer surface of wall coating first pass putty;
Second time putty of N-1 layers of outer surface of wall coating;
N-2 layers of support top sealing construction layer include N-2 layers of indoor support top sealing layers, N-2 layers of balcony sealing construction, N-2 layers of sky Tuned plate sealing construction, N-2 layers of exterior window sealing construction, N-2 layers of indoor support top sealing layer comprise the following steps:
The polishing of N-2 layer structure interior walls;
The repairing of N-2 layer structure interior walls;
N-2 layers of wallboard unwrapping wire;
N-2 layer by layer between sealing;
N-2 layer structures close water, and floor, which reserves interim water supply and drainage, faces electric hole takes over;
The anti-bank conduit in N-2 layers of toilet is taken over;
The N-2 layers of anti-bank of toilet warterproof pour;
N-2 layers of toilet drainage pipe installation;
N-2 layers of toilet structure close water;
N-2 layers of toilet pipe well block of wood pour;
N-2 layers of upright bar are removed;
N-2 layers of balcony sealing construction comprise the following steps:
The N-2 layers of pre-buried installation of balcony feed pipe;
N-2 layers of balcony exterior coating first pass putty;
N-2 layers of balcony soil stack installation;
The interim floor drain installation of N-2 layers of balcony;
N-2 layers of air-conditioning plate sealing construction comprise the following steps:
N-2 layers of air-conditioning plate standpipe periphery putty construction;
N-2 layers of air-conditioning plate internal riser installation;
N-2 layers of air conditioner louver installation;
Installation on the outside of N-2 layers of fresh air system;
N-2 layers of exterior window sealing construction comprise the following steps:
N-2 layers of outer window frame installation;
N-2 layers of exterior window lightning protection iron plate welding;
N-2 layers of outer window frame stuff up a crack;
N-2 layers of outer window glass, outer leaf installation;
N-3 layers of lining construction layer include N-3 layers of wallboard and install, and N-3 layers of wallboard installation comprise the following steps:
N-3 layers of installation lining;
N-3 layer by layer between sealing;
N-3 layers of kitchen chimney flue installation, standpipe installation, temporary toilet installation;
The anti-bank closure of N-3 layers of flue waterproof.
N-3 layers of lining construction layer further include N-3 layers of balcony guardrail installation, and N-3 layers of balcony guardrail installation include following step Suddenly:
N-3 layers of installation railing;
N-3 layers of railing lightning protection;
N-4 layer water supplying and discharging installation layers comprise the following steps:
N-4 layers of toilet plumbing installation;
N-4 layers of washing room plumbing installation;
N-4 layers of kitchen plumbing installation;
N-4 layers of hall plumbing installation;
N-4 layers of balcony plumbing installation;
N-4 layers of toilet plumbing installation comprise the following steps:
The N-4 layers of anti-bank of toilet warterproof;
N-4 layers of toilet feed pipe installation;
The horizontal branch pipe installation of N-4 layers of toilet drainage;
N-4 layers of washing room plumbing installation comprise the following steps:
N-4 layers of washing room feed pipe installation;
N-4 layers of washing room transverse drainage branch pipe installation;
N-4 layers of kitchen plumbing installation comprise the following steps:
N-4 layers of kitchen feed pipe installation;
N-4 layers of kitchen gas piping installation;
N-4 layers of hall plumbing installation comprise the following steps:
N-4 layers of indoor ceiling cement plaster;
N-4 layers of parlor feed pipe installation;
N-4 layers of parlor smallpox unwrapping wire;
N-4 layers of balcony plumbing installation comprise the following steps:
N-4 layers of balcony smallpox cement plaster;
N-4 layers of balcony feed pipe installation;
N-4 layers of balcony gas piping installation;
N-5 layers of pipeline installation layer comprise the following steps:
N-5 layers of toilet pipeline installation;
N-5 layers of washing room pipeline installation;
N-5 layers of kitchen pipeline installation;
N-5 layers of room pipeline installation;
N-5 layers of parlor pipeline installation;
N-5 layers of escalator pipeline installation;
N-5 layers of staircase pipeline installation;
N-5 layers of pipeline well lines installation;
N-5 layers of balcony pipeline installation;
N-5 layers of toilet pipeline installation comprise the following steps:
N-5 layers of toilet wallboard filleting repairing;
N-5 layers of toilet wallboard wire box and spool installation;
The hidden examination water in N-5 layers of toilet;
N-5 layers of toilet illumination, socket connect line;
N-5 layers of toilet smallpox sunpender;
N-5 layers of washing room pipeline installation comprise the following steps:
N-5 layers of washing room wallboard filleting repairing;
N-5 layers of washing room wallboard wire box and spool installation;
N-5 layers of washing room illumination, socket connect line;
N-5 layers of washing room smallpox sunpender keel installation;
N-5 layers of kitchen pipeline installation comprise the following steps:
N-5 layers of kitchen wallboard filleting repairing;
N-5 layers of kitchen wall suture holding box and spool installation;
N-5 layers of kitchen check-valves installation;
N-5 layers of kitchen smallpox sunpender;
N-5 layers of room pipeline installation comprise the following steps:
N-5 layers of room wallboard filleting repairing;
N-5 layers of room wall suture holding box and spool installation;
N-5 layers of room illumination, socket connect line;
N-5 layers of parlor pipeline installation comprise the following steps:
N-5 layers of parlor wallboard filleting repairing;
N-5 layers of parlor wallboard wire box and spool installation;
N-5 layers of parlor illumination, socket connect line;
N-5 layers of parlor smallpox sunpender keel installation;
N-5 layers of escalator pipeline installation comprise the following steps:
N-5 layers of escalator wallboard filleting repairing;
N-5 layers of escalator wallboard wire box and spool installation;
N-5 layers of escalator fire-fighting equipment wiring;
N-5 layers of escalator fire-fighting ventilation opening blinds installation;
N-5 layers of escalator illumination, socket connect line;
N-5 layers of escalator smallpox sunpender keel installation.
N-5 layers of staircase pipeline installation comprise the following steps:
N-5 layers of staircase wallboard filleting repairing;
N-5 layers of staircase wallboard wire box and spool installation;
N-5 layers of staircase fire-fighting equipment wiring;
N-5 layers of staircase illumination, socket connect line;
N-5 layers of pipeline well lines installation kit include following steps:
N-5 layers of piping shaft wallboard filleting repairing;
N-5 layers of piping shaft wallboard wire box and spool installation;
N-5 layers of piping shaft power wiring duct installation;
N-5 layers of piping shaft supplying drainage installation;
N-5 layers of balcony pipeline installation comprise the following steps:
N-5 layers of balcony wallboard filleting repairing;
N-5 layers of balcony wallboard wire box and spool installation;
N-5 layers of balcony illumination, socket connect line;
N-6 layers of smallpox putty construction layer comprise the following steps:
N-6 layers of toilet smallpox putty;
N-6 layers of washing room smallpox putty;
N-6 layers of kitchen smallpox putty;
N-6 layers of room smallpox putty;
N-6 layers of parlor smallpox putty;
N-6 layers of pipe laying well doorframe;
N-6 layers of escalator smallpox putty;
N-6 layers of installation staircase doorframe;
N-6 layers of toilet smallpox putty comprise the following steps:
N-6 layers of toilet smallpox giant plucking;
N-6 layers of toilet illumination, socket threading and debugging;
N-6 layers of accomodation ground waterproof, wet area's metope waterproof;
N-6 layers of washing room smallpox putty comprise the following steps:
N-6 layers of washing room smallpox giant plucking;
N-6 layers of washing room illumination, socket threading and debugging;
N-6 layers of washing room smallpox fit up one, two time putty layer;
N-6 layers of washing room furred ceiling sealing plate;
N-6 layers of kitchen smallpox putty comprise the following steps:
N-6 layers of kitchen smallpox giant plucking;
N-6 layers of kitchen illumination, socket threading and debugging;
N-6 layers of room smallpox putty comprise the following steps:
N-6 layers of room smallpox thermal insulation board installation;
N-6 layers of room illumination, socket threading and debugging;
N-6 layers of room smallpox fit up one, two time putty layer;
N-6 layers of parlor smallpox putty comprise the following steps:
N-6 layers of parlor illumination, socket threading and debugging;
N-6 layers of parlor smallpox fit up one, two time putty layer;
N-6 layers of parlor register one's residence doorframe installation;
N-6 layers of parlor register one's residence doorframe stuff up a crack, close up;
N-6 layers of parlor furred ceiling sealing plate;
N-6 layers of pipe laying well doorframe comprise the following steps:
N-6 layers of piping shaft fireproof door frame installation;
N-6 layers of piping shaft fireproof door frame close up;
N-6 layers of escalator smallpox putty comprise the following steps:
N-6 layers of installation of escalator fireproof door frame, stuff up a crack;
N-6 layers of escalator illumination, socket threading and debugging;
N-6 layers of escalator fire hydrant installation;
N-6 layers of escalator furred ceiling sealing plate;
N-6 layers of escalator smallpox fit up one, two time putty layer;
N-6 layers of installation staircase doorframe comprise the following steps:
N-6 layers of installation of staircase fireproof door frame, stuff up a crack;
N-6 layers of staircase illumination, socket threading and debugging;
N-7 layers of kitchen and bath's wall brick paving construction layer comprise the following steps:
N-7 layers of toilet wall brick paving;
N-7 layers of washing room wall brick paving;
N-7 layers of kitchen wall brick paving;
N-8 layers of tableland brick paving construction layer comprise the following steps:
N-8 layers of toilet floor tile paving;
N-8 layers of washing room floor tile paving;
N-8 layers of kitchen block paving;
The brick paving of N-8 layers of room tableland;
N-8 layers of parlor floor tile paving;
N-8 layers of escalator floor tile paving;
N-8 layers of balcony floor tile paving;
N-8 layers of toilet floor tile paving following steps:
N-8 layers of toilet threshold, the construction of toilet water blocking stone;
N-8 layers of toilet floor tile construction;
N-8 layers of toilet floor tile finished product protection;
N-8 layers of toilet aluminum-pinch smallpox installation;
N-8 layers of washing room floor tile paving following steps:
N-8 layers of washing room floor tile construction;
N-8 layers of washing room floor tile finished product protection;
N-8 layers of kitchen block paving following steps:
N-8 layers of kitchen block construction;
N-8 layers of kitchen threshold stone;
N-8 layers of kitchen block finished product protection;
N-8 layers of kitchen chimney flue well install hose;
N-8 layers of kitchen aluminum-pinch smallpox installation;
N-8 layers of room tableland brick paving following steps:
N-8 layers of room windowsill brick paving;
N-8 layers of room threshold brick construction;
N-8 layers of parlor floor tile paving following steps:
N-8 layers of parlor floor tile construction;
N-8 layers of parlor register one's residence threshold stone construction;
N-8 layers of parlor floor tile finished product protection;
N-8 layers of escalator floor tile paving following steps:
N-8 layers of escalator floor tile construction;
N-8 layers of floor tile finished product protection;
N-8 layers of balcony floor tile paving following steps:
N-8 layers of balcony floor tile construction;
N-8 layers of balcony floor tile finished product protection;
Time putty layer of N-9 layers of inner wall surface comprises the following steps:
Time putty of N-9 layers of hall inner wall surface;
N-9 layers of kitchen and bath's doorframe base installation;
N-9 layers of escalator are built by laying bricks or stones;
N-9 layers of conduit shaft door construction;
Time putty following steps of N-9 layers of hall inner wall surface:
N-9 layers of room, parlor metope repair angle;
N-9 layers of room, parlor metope first pass putty;
N-9 layers of room doorframe base installation;
Following steps are installed by N-9 layers of kitchen and bath's doorframe base:
N-9 layers of toilet doorframe base installation;
N-9 layers of kitchen doorframe base installation;
N-9 layers of escalator build following steps by laying bricks or stones:
N-9 layers of elevator reinforcing bar cutting, put center line;
N-9 layers of elevator built track installation.
N-9 layers of conduit shaft doors construction following steps:
N-9 layers of piping shaft fireproof door frame installation;
N-9 layers of piping shaft fireproof door frame close up;
Two times putty layers of N-10 layers of inner wall surface comprise the following steps:
Two times putty of N-10 layers of hall inner wall surface;
N-10 layers of kitchen and bath's shower set installation;
N-10 layers of escalator door construction;
Two times putty of N-10 layers of hall inner wall surface comprise the following steps:
Second time N-10 layers of room, parlor metope putty;
N-10 layers of room, the polishing of parlor smallpox;
N-10 layers of room, the polishing of parlor metope;
N-10 layers of kitchen and bath's shower set installation comprise the following steps:
N-10 layers of toilet shower rods installation;
N-10 layers of toilet Shower screen installation;
N-10 layers of toilet Shower screen gluing;
N-10 layers of washing room smallpox polishing;
N-10 layers of escalator door construction comprise the following steps:
N-10 layers of escalator elevator door, doorframe installation;
N-10 layers of escalator wall brick and door side are closed up;
N-11 layers of staircase construction layer comprise the following steps:
N-11 layers of staircase are removed Lin Wei and are moved up toward agent structure floor;
N-11 layers of staircase anti-skid brick and mortar levelling;
N-11 layers of staircase smallpox, metope first pass putty;
Second time N-11 layers of staircase smallpox, metope putty;
N-11 layers of staircase putty polishing are checked and accepted;
This complete cast-in-place exterior wall high residential building interts construction and puies forward efficacious prescriptions method entirely further includes basement construction layer, basement construction layer Comprise the following steps:
Basement wall surface putty is constructed;
Power distribution room, Generators installation;
Living pump room, fire water pump house, fire protection control center, Ventilator Room installation;
Intelligentized control method center, intellectualizing system installation;
Water flowing, energization, fire water electric wind system installation and debugging;
Diamond dust terrace;
One, two time finishing coat of basement metope;
Cure terrace;
It rules parking stall;
Outdoor garden layout comprises the following steps:
Gardens base layer construction;
Gardens arbor is planted;
Gardens capital construction is built by laying bricks or stones;
Garden shrub species are constructed;
Landscape ground is constructed;
Gardens turf construction;
Afforestation conserves;
Lacquer painting construction includes indoor lacquer painting construction, and indoor lacquer painting construction comprises the following steps:
Indoor ceiling mechanically spraying priming paint, repairing;
Indoor ceiling first pass finishing coat is constructed;
Second time finishing coat construction of indoor ceiling;
Lacquer painting construction further includes outdoor lacquer painting construction, and outdoor lacquer painting construction comprises the following steps:
Balcony, air-conditioning plate, exterior window, wall face priming paint;
Balcony, air-conditioning plate, exterior window, wall face first pass finishing coat;
Second time balcony, air-conditioning plate, exterior window, wall face finishing coat;
Balcony, air-conditioning plate, exterior window, wall face clean for the first time;
Second of the cleaning of balcony, air-conditioning plate, exterior window, wall face;
Elevator debugging comprises the following steps:
Elevator intelligent equipment is installed;
Elevator installation and debugging;
Elevator intelligent equipment debugging;
Storage installation comprises the following steps:
Clean cabinet installation;
Mirror cabinet is installed;
Cabinet is installed;
Fire-fighting ventilation opening blinds is installed;
Table top lamp installation comprises the following steps:
The low window guardrail installation of toilet, room, escalator;
Parlor intelligent equipment starts to debug;
Toilet, washing room, kitchen countertop installation;
Toilet, kitchen, the indoor doorframe installation in room;
Kitchen, escalator, staircase, balcony lamp installation;
Room, the rectification of parlor thin portion;
Switch panel is installed;
Door and two times finishing coat constructions comprise the following steps:
Toilet, kitchen, the installation of room door leaf;
Toilet is installed;
Two times room, parlor, escalator metope finishing coat constructions;
Switch panel is installed;
Toilet, kitchen, the installation of room architrave;
Piping shaft, escalator, the installation of staircase fireproof door leaf;
Hardware equipment, which is installed, and house is kept a public place clean comprises the following steps:
Kitchen appliance is installed;
Toilet, washing room, the installation of kitchen hardware;
It is indoor and outdoor just to keep a public place clean;
Indoor gluing;
Toilet, washing room, kitchen Wall or floor tile jointing;
Indoor gluing comprises the following steps:
Toilet, washing room, kitchen countertop gluing;
Parlor is registered one's residence gluing outside door frame;
Escalator, staircase doorframe side gluing.
The present embodiment has the following advantages that:
1st, it is a kind of process organization and administration that this complete cast-in-place exterior wall high residential building main body interts construction to put forward efficacious prescriptions method entirely after binding Technology, each construction part is partitioning standards after being bound using high residential building main body;The scope of the complete interspersed construction covers high residential building Main body parts such as indoor and outdoor, gardens after binding are that comprehensive after high residential building main body truly binds interspersed is applied Work refine to the first job item that need to carry out interspersed construction, including indoor and outdoor, gardens;Its object is to clear and definite high levels to live The working procedure flowing water tissue of construction overall process and technology requirement, both shorten total time of construction, improve after residence main body binds Work efficiency, and improve the level that becomes more meticulous of projects management;
The complete cast-in-place exterior wall high residential building main body interts construction and proposes the duration contracting more whole than traditional construction of efficacious prescriptions method entirely after binding It is short, it realizes to deliver in advance and move in, create added value;Traditional construction organizational form is compared in the interspersed construction, operable strong, further Reduce subjective error;
It realizes each professional workers after high residential building main body binds and can intert and work continuously, it is ensured that high residential building main body is sealed Intert construction operation behind top entirely, shorten total time of construction, improve work efficiency.
To realize that high residential building main body interts construction after binding, interspersed construction node significant during having combed, Convenient for macroscopical control;
The interspersed construction, which realizes, effectively combines aluminum dipping form, intelligent climbing frame, prefabricated panel, complete cast-in-place exterior wall, dry construction etc. Advanced technologies, perspective height create surcharge for building trade, are the mainstreams of industry future development.
2nd, it is a kind of process organizing and management techniques that this complete cast-in-place exterior wall high residential building interts construction to put forward efficacious prescriptions method entirely, with structure The number of plies is partitioning standards, when the agent structure of high residential building is when carrying out n-th layer construction operation, at this point, N-1 layers of high residential building It can intert and carry out form removal construction operation, N-2 layers of high residential building, which can intert, carries out support top sealing construction operation, high residential building N-3 layers can intert progress lining construction operation, and N-4 layers of high residential building, which can intert, carries out plumbing installation work Industry, N-5 layers of high residential building, which can intert, carries out pipeline installation operation, and N-6 layers of high residential building can intert carry out day Flower putty construction operation, N-7 layers of high residential building, which can intert, carries out kitchen and bath's wall brick paving construction operation, high residential building N-8 Layer, which can intert, carries out tableland brick paving construction operation, and N-9 layers of high residential building, which can intert, carries out inner wall surface first pass putty Construction operation, N-10 layers of high residential building, which can intert, carries out second time putty construction operation of inner wall surface, high residential building N-11 Layer, which can intert, carries out staircase construction operation;The rest may be inferred causes time utility maximization to be utilized, and realizes high residential building Each each professional workers of floor, which can intert, works continuously, it is ensured that each floor of high residential building interts construction operation entirely, shortens construction Total lever factor improves work efficiency.
3rd, it is a kind of process organizing and management techniques that complete cast-in-place exterior wall high residential building kitchen and bath, which interts construction to put forward efficacious prescriptions method, with structure The number of plies is partitioning standards, when the agent structure of high residential building is when carrying out n-th layer construction operation, at this point, N-1 layers of high residential building It can intert and carry out form removal construction operation, N-2 layers of high residential building, which can intert, carries out support top sealing construction operation, high residential building N-3 layers can intert progress lining construction operation, and N-4 layers of high residential building, which can intert, carries out plumbing installation work Industry, N-5 layers of high residential building, which can intert, carries out pipeline installation operation, and N-6 layers of high residential building can intert carry out day Flower putty construction operation, N-7 layers of high residential building, which can intert, carries out kitchen and bath's wall brick paving construction operation, high residential building N-8 Layer, which can intert, carries out tableland brick paving construction operation, and N-9 layers of high residential building, which can intert, carries out inner wall surface first pass putty Construction operation, N-10 layers of high residential building, which can intert, carries out second time putty construction operation of inner wall surface, high residential building N-11 Layer, which can intert, carries out staircase construction operation;The rest may be inferred causes time utility maximization to be utilized, and realizes high residential building Each each professional workers of floor, which can intert, works continuously, it is ensured that each floor of high residential building interts construction operation entirely, shortens construction Total lever factor improves work efficiency.
4th, it is a kind of process organizing and management techniques that the complete cast-in-place exterior wall high residential building hall, which interts construction to put forward efficacious prescriptions method, with structure The number of plies is partitioning standards, when the hall agent structure of high residential building is when carrying out n-th layer construction operation, high residential building N- at this time 1 layer can intert progress hall form removal construction operation, and N-2 layers of high residential building, which can intert, carries out hall support top sealing construction work Industry, N-3 layers of high residential building, which can intert, carries out hall lining construction operation, and N-4 layers of high residential building can intert progress Hall plumbing installation operation, N-5 layers of high residential building, which can intert, carries out hall pipeline installation operation, and high level is lived N-6 layers of large house, which can intert, carries out hall smallpox putty construction operation, and N-8 layers of high residential building, which can intert, carries out hall tableland Brick paving construction operation, N-9 layers of high residential building, which can intert, carries out hall inner wall surface first pass putty construction operation, and high level is lived N-10 layers of large house, which can intert, carries out the hall second time putty construction operation of inner wall surface;The rest may be inferred so that time utility maximizes It is utilized, realizing each floor hall of high residential building each professional workers of constructing can intert and work continuously, it is ensured that high residential building is each The floor hall interts construction operation, shortens total time of construction, improves work efficiency.
5th, it is a kind of process organizing and management techniques to intert construction to put forward efficacious prescriptions method outside complete cast-in-place exterior wall high residential building room, with structure The number of plies is partitioning standards, when the outdoor agent structure of high residential building is when carrying out n-th layer construction operation, high residential building N- at this time 1 layer can intert the outdoor form removal construction operation of progress, and N-2 layers of high residential building can intert the outdoor support top sealing construction of progress and make Industry, N-3 layers of high residential building can intert carry out balcony guardrail installation operation, N-4 layers of high residential building can intert into Row balcony plumbing installation operation, N-5 layers of high residential building, which can intert, carries out balcony pipeline installation operation, high-rise N-8 layers of house, which can intert, carries out balcony floor tile paving construction operation;The rest may be inferred causes time utility maximization to be utilized, It realizes each each professional workers of floor outdoor construction of high residential building and can intert and work continuously, it is ensured that outside each floor room of high residential building Interspersed construction operation, shortens total time of construction, improves work efficiency.
6th, it is a kind of process organization and administration skill that complete cast-in-place exterior wall high residential building escalator, staircase, which intert construction to put forward efficacious prescriptions method, Art, using structure level number as partitioning standards, escalator, staircase agent structure when high residential building are carrying out n-th layer construction operation When, N-1 layers of high residential building, which can intert, at this time carries out escalator, staircase form removal construction operation, and N-2 layers of high residential building is It can intert and carry out escalator, staircase support top sealing construction operation, high residential building N-5 floor, which can intert, carries out escalator, building Pipeline installation operation between ladder, N-6 layers of high residential building, which can intert, carries out escalator, staircase smallpox putty construction work Industry, N-8 layers of high residential building, which can intert, carries out escalator floor tile paving construction operation, and N-9 layers of high residential building can intert Escalator building construction operation is carried out, N-10 layers of high residential building, which can intert, carries out escalator door construction operation, high residential building N-11 layers can intert progress staircase construction operation;The rest may be inferred causes time utility maximization to be utilized, and realizes height Layer each floor elevator of house between, staircase construction, each professional workers, which can intert, works continuously, it is ensured that each floor of high residential building is complete Interspersed construction operation, shortens total time of construction, improves work efficiency.
7th, flowing water section is further segmented by each construction operation content, optimizes the arrangement of labour, reduced and work to single work post The surprise demand of power quantity accomplishes science, orderly, coherent, ensures that each professional workers can intert and work continuously.
8th, this complete cast-in-place exterior wall high residential building interts to construct entirely puies forward efficacious prescriptions method, and the construction for further including basement construction layer is made Industry makes this intert boundary of works area entirely and covers indoor and outdoor, basement etc., realizes indoor and outdoor synchronous with basement Construction, further shortens total time of construction, improves work efficiency.
It these are only specific embodiments of the present invention, protection scope of the present invention do not limited with this;Do not violating this hair Any replacement made on the basis of bright design belongs to protection scope of the present invention with improving.

Claims (10)

1. complete cast-in-place exterior wall high residential building main body interts construction entirely after binding puies forward efficacious prescriptions method, which is characterized in that comprises the following steps:
Agent structure binds;
During Construction of Energy Room:Agent structure proceeds by roof structure During Construction of Energy Room operation after binding;
Climbing frame and construction elevator are removed:After the completion of roof structure, During Construction of Energy Room operation, start climbing frame and construction elevator is removed;
Elevator is installed:After the completion of climbing frame is removed, construction elevator is removed, residential lift starts to install, and elevator carries out electricity after installing Trapeziodal modulation tries;
Remove tower crane:Climbing frame construction operation is removed to start to remove tower crane after finishing;
Outdoor garden layout:After the completion of removing tower crane construction operation, start outdoor garden layout operation and start;
Exterior wall nacelle construction:After the completion of removing tower crane construction operation, residence outer wall later work, exterior wall nacelle construction operation start Construction;
Lacquer painting is constructed:After the completion of exterior wall nacelle construction, the lacquer painting construction operation of each layer of house is proceeded by;
Storage installation:After the completion of the lacquer painting construction operation of each layer of house, the collecting apparatus installation of each layer of house starts construction operation;
Table top lamp installation:For the collecting apparatus of each layer of house after installation is complete, the table top lamps and lanterns of each layer of house start installation Operation;
Door and two times finishing coat constructions:After the completion of the table top lamps and lanterns of each layer of house start installation operation, the door of each layer of house and Two times finishing coat starts construction operation;
Timber floor is installed:After the completion of the door of each layer of house and two times finishing coats start construction operation, the timber floor installation of each layer of house Construction operation starts;
Hardware equipment is installed and house is kept a public place clean:After the completion of the timber floor installation operation of each layer of house, each layer of house carries out five The installation of golden equipment and house are kept a public place clean construction operation.
2. complete cast-in-place exterior wall high residential building main body as described in claim 1 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the outdoor garden layout comprises the following steps:
Gardens base layer construction;
Gardens arbor is planted;
Gardens capital construction is built by laying bricks or stones;
Garden shrub species are constructed;
Landscape ground is constructed;
Gardens turf construction;
Afforestation conserves.
3. complete cast-in-place exterior wall high residential building main body as described in claim 1 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the lacquer painting construction includes indoor lacquer painting construction, and the interior lacquer painting construction comprises the following steps:
Indoor ceiling mechanically spraying priming paint, repairing;
Indoor ceiling first pass finishing coat is constructed;
Second time finishing coat construction of indoor ceiling.
4. complete cast-in-place exterior wall high residential building main body as described in claim 1 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the lacquer painting construction further includes outdoor lacquer painting construction, and the outdoor lacquer painting construction comprises the following steps:
Balcony, air-conditioning plate, exterior window, wall face priming paint;
Balcony, air-conditioning plate, exterior window, wall face first pass finishing coat;
Second time balcony, air-conditioning plate, exterior window, wall face finishing coat;
Balcony, air-conditioning plate, exterior window, wall face clean for the first time;
Second of the cleaning of balcony, air-conditioning plate, exterior window, wall face.
5. complete cast-in-place exterior wall high residential building main body as described in claim 1 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the elevator debugging comprises the following steps:
Elevator intelligent equipment is installed;
Elevator installation and debugging;
Elevator intelligent equipment debugging.
6. complete cast-in-place exterior wall high residential building main body as described in claim 1 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the storage installation comprises the following steps:
Clean cabinet installation;
Mirror cabinet is installed;
Cabinet is installed;
Fire-fighting ventilation opening blinds is installed.
7. interting construction after cast-in-place exterior wall high residential building main body binds entirely entirely such as claim 1 to 6 any one of them carries efficacious prescriptions Method, which is characterized in that the table top lamp installation comprises the following steps:
The low window guardrail installation of toilet, room, escalator;
Parlor intelligent equipment starts to debug;
Toilet, washing room, kitchen countertop installation;
Toilet, kitchen, the indoor doorframe installation in room;
Kitchen, escalator, staircase, balcony lamp installation;
Room, the rectification of parlor thin portion;
Switch panel is installed.
8. complete cast-in-place exterior wall high residential building main body as claimed in claim 7 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the door and two times finishing coat constructions comprise the following steps:
Toilet, kitchen, the installation of room door leaf;
Toilet is installed;
Two times room, parlor, escalator metope finishing coat constructions;
Switch panel is installed;
Toilet, kitchen, the installation of room architrave;
Piping shaft, escalator, the installation of staircase fireproof door leaf.
9. complete cast-in-place exterior wall high residential building main body as claimed in claim 7 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the hardware equipment, which is installed, and house is kept a public place clean comprises the following steps:
Kitchen appliance is installed;
Toilet, washing room, the installation of kitchen hardware;
It is indoor and outdoor just to keep a public place clean;
Indoor gluing;
Toilet, washing room, kitchen Wall or floor tile jointing.
10. complete cast-in-place exterior wall high residential building main body as claimed in claim 7 interts construction entirely after binding puies forward efficacious prescriptions method, feature It is, the interior gluing comprises the following steps:
Toilet, washing room, kitchen countertop gluing;
Parlor is registered one's residence gluing outside door frame;
Escalator, staircase doorframe side gluing.
CN201711386646.8A 2017-12-20 2017-12-20 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely Pending CN108104278A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711386646.8A CN108104278A (en) 2017-12-20 2017-12-20 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711386646.8A CN108104278A (en) 2017-12-20 2017-12-20 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely

Publications (1)

Publication Number Publication Date
CN108104278A true CN108104278A (en) 2018-06-01

Family

ID=62210609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711386646.8A Pending CN108104278A (en) 2017-12-20 2017-12-20 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely

Country Status (1)

Country Link
CN (1) CN108104278A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105275207A (en) * 2015-02-11 2016-01-27 中建四局第三建筑工程有限公司 Up-down cyclic alternating construction method for external vertical face of high-rise building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105275207A (en) * 2015-02-11 2016-01-27 中建四局第三建筑工程有限公司 Up-down cyclic alternating construction method for external vertical face of high-rise building

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
SS55863366: "《全穿插施工:N-10湿作业穿插+180后主体施工》", 4 December 2016 *
崔中全: "厨房和卫生间防水与安装工程穿插施工方案", 《山西建筑》 *
李世钟: "高层建筑精装修前置穿插施工的研究与应用", 《建筑施工》 *
白俊杰,黄原,刘秋红,周江,沈龙飞: "穿插流程优化在住宅及办公项目中的应用分析", 《管理模式创新》 *

Similar Documents

Publication Publication Date Title
Weeks et al. The Secretary of the Interior's Standards for the Treatment of Historic Properties: With Guidelines for Preserving, Rehabilitating, Restoring & Reconstructing Historic Buildings
Grimmer The Secretary of the Interior's standards for the treatment of historic properties: With guidelines for preserving, rehabilitating, restoring & reconstructing historic buildings
CN103510631B (en) A kind of indoor sound insulation constructing structure and construction method thereof
CN106121231A (en) A kind of skyscraper interts cross construction method
CN108049496A (en) Complete cast-in-place exterior wall high residential building interts construction and puies forward efficacious prescriptions method entirely
CN110158974A (en) A kind of complete interspersed construction method of high level assembled arthitecutral structure
CN103321393B (en) Plastering on inner walls construction method
CN104695706A (en) Construction method for AAC block free-loading wall
CN108104257A (en) The complete cast-in-place exterior wall high residential building hall interts construction and puies forward efficacious prescriptions method
CN108086714A (en) Complete cast-in-place exterior wall high residential building kitchen and bath interts construction and puies forward efficacious prescriptions method
CN108049495A (en) Complete cast-in-place exterior wall high residential building escalator, staircase intert construction and put forward efficacious prescriptions method
CN108104472A (en) Intert construction outside complete cast-in-place exterior wall high residential building room and put forward efficacious prescriptions method
CN104372877B (en) Tall and big vertical stone material Water curtain wall construction
CN108104278A (en) Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely
Davies et al. Architect's illustrated pocket dictionary
CN109989554A (en) A kind of skyscraper assembled piping shaft and preparation method thereof and installation method
CN114934588A (en) Efficient alternate flow construction method for building construction
CN108252518A (en) Construction method under the high residential building novel construction system master control duration
CN216665090U (en) Automatic spraying and health preserving system for basement shear wall
CN103422671A (en) Construction method of integrated process model house for building engineering construction
Goldoni et al. Palazzo Sartoretti in Reggiolo
CN209025491U (en) A kind of box-type room by waste and old Container Reconstruction
CN114809635A (en) Full-assembly integral concrete shear wall high-rise dwelling interpenetration construction method
Elkodousy Office center in Izyum city of Kharkiv region
CN112884426A (en) Full-penetration construction method based on northern constructional engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180601