CN108062633A - A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone - Google Patents

A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone Download PDF

Info

Publication number
CN108062633A
CN108062633A CN201810010716.8A CN201810010716A CN108062633A CN 108062633 A CN108062633 A CN 108062633A CN 201810010716 A CN201810010716 A CN 201810010716A CN 108062633 A CN108062633 A CN 108062633A
Authority
CN
China
Prior art keywords
distribution network
risk assessment
power distribution
generation resource
distributed generation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810010716.8A
Other languages
Chinese (zh)
Inventor
苏亮
王秀茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suqian Power Supply Branch Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Suqian Power Supply Branch Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suqian Power Supply Branch Jiangsu Electric Power Co Ltd, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd filed Critical Suqian Power Supply Branch Jiangsu Electric Power Co Ltd
Priority to CN201810010716.8A priority Critical patent/CN108062633A/en
Publication of CN108062633A publication Critical patent/CN108062633A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种分布式电源高渗透下的配电网风险评估方法,考虑大规模分布式电源的接入的特点,对配电网进行风险评估,步骤:1)考虑分布式电源出力的波动性和间歇性,建立分布式电源出力模型;2)根据线路历史故障信息建立线路停运模型;3)考虑分布式电源高渗透下配电网运行风险的概率和后果,建立考虑配电网运行可靠性和充裕性的风险评估指标体系;4)利用蒙特卡罗模拟‑粒子群‑广度搜索综合算法对分布式电源高渗透下的配电网风险评估模型进行求解,确定风险评估指标值,完成分布式电源高渗透下的配电网风险评估。

The invention discloses a distribution network risk assessment method under the high penetration of distributed power sources, which considers the characteristics of the access of large-scale distributed power sources, and performs risk assessment on the distribution network. The steps are: 1) Consider the output of distributed power sources 2) Establish a line outage model based on historical line fault information; 3) Consider the probability and consequences of distribution network operation risks under the high penetration of distributed Risk assessment index system for operational reliability and adequacy; 4) Using Monte Carlo simulation-particle swarm-breadth search comprehensive algorithm to solve the distribution network risk assessment model under the high penetration of distributed power generation, and determine the risk assessment index value, Complete the distribution network risk assessment under the high penetration of distributed power.

Description

一种分布式电源高渗透下的配电网风险评估方法A distribution network risk assessment method under the high penetration of distributed generation

技术领域technical field

本发明属于配电网风险评估领域,具体涉及一种分布式电源高渗透下的配电网风险评估方法。The invention belongs to the field of distribution network risk assessment, and in particular relates to a distribution network risk assessment method under the high penetration of distributed power sources.

背景技术Background technique

近年来,随着一次能源形势的日益严峻,电力需求的持续增长,世界各国正在积极开发利用可代替的新能源。以风能发电和光伏发电为主的分布式能源接入配电网的问题也越来越受到重视,已成为国内外的研究热点。大规模分布式电源的接入具有节能减排、减轻环境污染、降低线路损耗、改善电能质量和提高供电可靠性等优点,但同时其功率输出受气候环境影响很大,具有明显的间歇性、随机性以及波动性,会影响电力系统的正常运行。In recent years, with the increasingly severe primary energy situation and the continuous growth of electricity demand, countries around the world are actively developing and utilizing alternative new energy sources. More and more attention has been paid to the access of distributed energy sources, mainly wind power and photovoltaic power generation, to the distribution network, and it has become a research hotspot at home and abroad. The access of large-scale distributed power supply has the advantages of energy saving and emission reduction, environmental pollution reduction, line loss reduction, power quality improvement and power supply reliability improvement, etc., but at the same time, its power output is greatly affected by the climate environment, which has obvious intermittent, Randomness and volatility will affect the normal operation of the power system.

对含分布式电源的配电网进行风险评估,可以有效提高含分布式电源的配电网运行的安全性和供电可靠性,避免发生重大安全问题。而目前国内外对于含分布式能源的配电网的风险评估研究较少,而且存在一定的困难。首先,由于含分布式能源的配电网元件众多,风险评估涉及大量的元件参数及运行数据,所以电网等值处理及计算分析工作量较大。另外,风险指标体系的计算与配电网潮流状态息息相关,因而电网状态是否能反应运行特征对风险评估结果具有较大的影响。目前对含分布式能源的配电网风险评估研究缺乏考虑分布式能源发电的不确定性和高渗透率对配电网安全运行的影响问题。针对以上问题,本文提出了一种分布式电源高渗透下的配电网风险评估方法。Risk assessment of distribution network with distributed generation can effectively improve the safety and power supply reliability of distribution network with distributed generation, and avoid major safety problems. At present, there are few researches on the risk assessment of distribution network with distributed energy at home and abroad, and there are certain difficulties. First of all, due to the large number of components in the distribution network containing distributed energy, risk assessment involves a large number of component parameters and operating data, so the workload of grid equivalent processing and calculation and analysis is relatively large. In addition, the calculation of the risk index system is closely related to the power flow state of the distribution network, so whether the state of the power grid can reflect the operating characteristics has a greater impact on the risk assessment results. At present, the research on the risk assessment of distribution network with distributed energy resources lacks consideration of the influence of the uncertainty of distributed energy generation and the high penetration rate on the safe operation of distribution network. Aiming at the above problems, this paper proposes a distribution network risk assessment method under the high penetration of distributed generation.

发明内容Contents of the invention

本发明的目的在于考虑分布式能源发电的不确定性和高渗透率对配电网安全运行的影响,对配电网进行风险评估。The purpose of the present invention is to consider the influence of the uncertainty of distributed energy generation and the high penetration rate on the safe operation of the distribution network, and carry out risk assessment on the distribution network.

为了解决上述技术问题,本发明提供一种分布式电源高渗透下的配电网风险评估方法,包括以下步骤:In order to solve the above technical problems, the present invention provides a distribution network risk assessment method under the high penetration of distributed power sources, including the following steps:

步骤一、考虑分布式电源出力的波动性和间歇性,建立分布式电源出力模型;Step 1. Consider the fluctuation and intermittency of distributed power output, and establish a distributed power output model;

步骤二、根据线路历史故障信息建立线路停运模型;Step 2, establishing a line outage model according to line history fault information;

步骤三、考虑分布式电源高渗透下配电网运行风险的概率和后果,建立考虑配电网运行可靠性和充裕性的风险评估指标体系;Step 3. Consider the probability and consequences of distribution network operation risk under the high penetration of distributed power generation, and establish a risk assessment index system that considers the reliability and adequacy of distribution network operation;

步骤四、利用蒙特卡罗模拟-粒子群-广度搜索综合算法对分布式电源高渗透下的配电网风险评估模型进行求解,确定风险评估指标值,完成分布式电源高渗透下的配电网风险评估。Step 4. Use Monte Carlo simulation-particle swarm-breadth search comprehensive algorithm to solve the distribution network risk assessment model under the high penetration of distributed generation, determine the risk assessment index value, and complete the distribution network under the high penetration of distributed generation risk assessment.

进一步,步骤一中,分布式电源出力模型包括风力发电出力模型和光伏发电出力模型。Further, in step 1, the distributed power generation output model includes a wind power generation output model and a photovoltaic power generation output model.

进一步,步骤一中,首先建立风速模型和日照模型,再根据风速与风机出力、日照与光伏发电出力的关系,建立风力发电出力模型和光伏发电出力模型。Further, in step 1, first establish a wind speed model and a sunshine model, and then establish a wind power generation output model and a photovoltaic power generation output model according to the relationship between wind speed and fan output, sunshine and photovoltaic power generation output.

进一步,步骤一中,风速模型采用Weibull分布模型,日照模型采用Beta分布模型,模型的参数通过历史风速信息和历史日照信息计算求得。Further, in step 1, the wind speed model adopts the Weibull distribution model, the sunshine model adopts the Beta distribution model, and the parameters of the models are obtained by calculating historical wind speed information and historical sunshine information.

进一步,步骤二中,线路停运模型采用元件的两状态模型,所述元件具有运行状态和故障状态。Further, in step 2, the line outage model adopts a two-state model of an element, and the element has a running state and a fault state.

进一步,步骤三中,可靠性指标包括负荷点可靠性指标和系统可靠性指标,负荷点可靠性指标包括平均故障率、平均停电持续时间和年平均停电持续时间,系统可靠性指标包括系统平均停电频率、系统平均停电持续时间和平均供电可用率,所述充裕性指标包括失负荷概率严重度、电量不足严重度和重要负荷损失程度。Further, in step 3, the reliability index includes the load point reliability index and the system reliability index, the load point reliability index includes the average failure rate, the average power outage duration and the annual average power outage duration, and the system reliability index includes the system average power outage Frequency, system average power outage duration and average power supply availability rate, the adequacy index includes the severity of load loss probability, the severity of power shortage, and the degree of loss of important loads.

进一步,步骤四中,分布式电源高渗透下的配电网风险评估模型求解包含以下步骤:Further, in Step 4, the solution of the distribution network risk assessment model under the high penetration of distributed generation includes the following steps:

(1)基本数据输入,所述基础数据包括线路参数、电源参数、负荷参数和分布式电源参数等;(1) Basic data input, the basic data includes line parameters, power supply parameters, load parameters and distributed power supply parameters, etc.;

(2)设置仿真总时间,初始化风险评估指标和仿真参数为0;(2) Set the total simulation time, and initialize the risk assessment indicators and simulation parameters to 0;

(3)对每个元件产生(0,1)之间的随机数,并计算各个元件的运行时间和修复时间;(3) Generate a random number between (0,1) for each component, and calculate the running time and repair time of each component;

(4)产生与分布式电源对应的(0,1)之间的随机数,并计算风速和日照强度,进而计算风力发电出力和光伏发电出力;(4) Generate a random number between (0,1) corresponding to the distributed power supply, and calculate the wind speed and sunshine intensity, and then calculate the output of wind power generation and photovoltaic power generation;

(5)选取运行时间最小的元件i作为每次抽样的故障元件,并将其运行时间TTF(i)和修复时间TTR(i)累积至仿真时间t,即t= TTF(i)+ TTR(i);此处i的取值为不为0的自然数;(5) Select the component i with the smallest running time as the faulty component for each sampling, and accumulate its running time TTF(i) and repair time TTR(i) to the simulation time t, that is, t= TTF(i)+ TTR( i); Here, the value of i is a natural number other than 0;

(6)运用广度搜索算法对配电网进行连通性分析,得到故障后初始连通性矩阵A;(6) Use the breadth search algorithm to analyze the connectivity of the distribution network, and obtain the initial connectivity matrix A after the fault;

(7)断开故障支路,运用粒子群算法对配网进行孤岛划分;(7) Disconnect the faulty branch and use the particle swarm algorithm to divide the distribution network into islands;

(8)再次运用广度搜索算法对配电网进行连通性分析,得到孤岛划分后连通性矩阵B;(8) Use the breadth search algorithm to analyze the connectivity of the distribution network again, and obtain the connectivity matrix B after islanding;

(9)比较步骤(6)中的A和步骤(8)中的B,将负荷点进行分类,A、B中均与电源连通的,不停电;A中连通,B中不连通的,停电,停电时间为元件i修复时间TTR(i),根据分类情况计算仿真参数;所述A为故障后初始连通性矩阵A,B为孤岛划分后连通性矩阵;(9) Compare A in step (6) and B in step (8), and classify the load points. If both A and B are connected to the power supply, there will be no power failure; if A is connected and B is not connected, the power will be cut off. , the outage time is the repair time TTR(i) of component i, and the simulation parameters are calculated according to the classification; the A is the initial connectivity matrix A after the fault, and B is the connectivity matrix after the islanding;

(10)判断仿真时间t是否大于仿真总时间,若仿真时间t大于等于仿真总时间,则转入步骤(11);若仿真时间t小于仿真总时间,则转入步骤(3);(10) Determine whether the simulation time t is greater than the total simulation time, if the simulation time t is greater than or equal to the total simulation time, then go to step (11); if the simulation time t is less than the total simulation time, go to step (3);

(11)根据仿真参数计算风险评估指标值。(11) Calculate the risk assessment index value according to the simulation parameters.

进一步,步骤四中,广度搜索算法进行连通性分析步骤如下:Further, in Step 4, the connectivity analysis steps of the breadth search algorithm are as follows:

(L1)输入起点和终点,并将起点加入集合Q中;(L1) Input the start point and end point, and add the start point to the set Q;

(L2)从步骤(L1)所述集合Q中依次拿出节点Vn,判断集合Q此时是否为空,若集合Q为空,则输出起点和终点不连通;若集合Q不为空,则转入下一步骤(L3);(L2) Take the node Vn from the set Q described in step (L1) in turn, and judge whether the set Q is empty at this time. If the set Q is empty, then output the starting point and the end point are not connected; if the set Q is not empty, then Go to the next step (L3);

(L3)找出步骤(L2)中拿出的节点Vn中所有的未包含在集合Q中的相邻节点Vw,判断相邻节点Vw是否有终点,若相邻节点Vw有终点,则输出起点和终点连通;若相邻节点Vw没有终点,将该相邻节点Vw加入集合Q,并转入步骤(L2)。(L3) Find out all the adjacent nodes Vw in the node Vn taken out in step (L2) that are not included in the set Q, judge whether the adjacent node Vw has an end point, if the adjacent node Vw has an end point, output the starting point It is connected with the end point; if the adjacent node Vw has no end point, add the adjacent node Vw to the set Q, and turn to step (L2).

进一步,步骤四中,粒子群算法对配网进行孤岛划分的步骤如下:Further, in Step 4, the steps for the particle swarm optimization algorithm to divide the distribution network into islands are as follows:

(G1)随机初始生成粒子,初始化种群数,同时初始化迭代次数;(G1) Initially generate particles randomly, initialize the number of populations, and initialize the number of iterations at the same time;

(G2)使用广度搜索算法进行连通性分析;(G2) Connectivity analysis using breadth search algorithm;

(G3)根据步骤(G2)的连通性分析结果,计算配电网的适应度值,若存在孤岛若不满足功率约束,适应度值置为负无穷;(G3) According to the connectivity analysis results of step (G2), calculate the fitness value of the distribution network. If there is an island or the power constraint is not satisfied, the fitness value is set to negative infinity;

(G4)更新群体最优和个体最优后,更新粒子的速度和位置;(G4) After updating the group optimal and individual optimal, update the velocity and position of the particle;

(G5)判断是否达到步骤(G1)中设定的迭代次数,若是,输出最优解,若否,转入步骤(G2)。(G5) Judging whether the number of iterations set in step (G1) has been reached, if yes, output the optimal solution, if not, go to step (G2).

本发明与现有技术相比,其显著优点在于:(1)本发明考虑分布式能源发电的不确定性和高渗透率对配电网安全运行的影响,评估结果更为准确有效;(2)本发明运用广度搜索算法进行故障后、孤岛划分后的配网的连通性分析,能快速的判断配电网的连通性,进而进行风险指标的计算;(3)本发明采用粒子群算法进行孤岛划分,收敛速度快,可以实现孤岛的快速划分。Compared with the prior art, the present invention has the following significant advantages: (1) The present invention considers the impact of the uncertainty of distributed energy generation and the high penetration rate on the safe operation of the distribution network, and the evaluation results are more accurate and effective; (2) ) The present invention uses the breadth search algorithm to analyze the connectivity of the distribution network after the fault and island division, and can quickly judge the connectivity of the distribution network, and then calculate the risk index; (3) The present invention uses the particle swarm algorithm to carry out Island division, the convergence speed is fast, and the rapid division of islands can be realized.

附图说明Description of drawings

以下将结合附图对本发明作进一步详细描述:The present invention will be described in further detail below in conjunction with accompanying drawing:

图1是本发明分布式电源高渗透下的配电网风险评估方法流程图;Fig. 1 is the flow chart of the distribution network risk assessment method under the distributed power generation high penetration of the present invention;

图2是本发明分布式电源高渗透下的配电网风险评估模型求解算法流程图;Fig. 2 is a flow chart of the algorithm for solving the distribution network risk assessment model under the high penetration of distributed power sources in the present invention;

图3是本发明中的广度搜索算法连通性分析算法流程图;Fig. 3 is the flow chart of connectivity analysis algorithm of breadth search algorithm among the present invention;

图4是本发明中的粒子群算法对配网进行孤岛划分流程图。Fig. 4 is a flow chart of dividing the distribution network into islands by the particle swarm optimization algorithm in the present invention.

具体实施方式Detailed ways

本发明提供一种分布式电源高渗透下的配电网风险评估方法,方法流程图如附图1所示,包括以下步骤:The present invention provides a distribution network risk assessment method under the high penetration of distributed power sources. The flow chart of the method is shown in Figure 1, which includes the following steps:

步骤一、考虑分布式电源出力的波动性和间歇性,建立分布式电源出力模型;Step 1. Consider the fluctuation and intermittency of distributed power output, and establish a distributed power output model;

步骤二、根据线路历史故障信息建立线路停运模型;Step 2, establishing a line outage model according to line history fault information;

步骤三、考虑分布式电源高渗透下配电网运行风险的概率和后果,建立考虑配电网运行可靠性和充裕性的风险评估指标体系;Step 3. Consider the probability and consequences of distribution network operation risk under the high penetration of distributed power generation, and establish a risk assessment index system that considers the reliability and adequacy of distribution network operation;

步骤四、利用蒙特卡罗模拟-粒子群-广度搜索综合算法对分布式电源高渗透下包含分布式电源出力模型和线路停运模型的配电网风险评估模型进行求解,确定风险评估指标值,完成分布式电源高渗透下的配电网风险评估。Step 4. Use Monte Carlo simulation-particle swarm-breadth search comprehensive algorithm to solve the distribution network risk assessment model including distributed power output model and line outage model under the high penetration of distributed power, and determine the risk assessment index value. Complete the distribution network risk assessment under the high penetration of distributed power.

进一步,步骤一中,分布式电源出力模型包括风力发电出力模型、光伏发电出力模型。Further, in step 1, the distributed power generation output model includes a wind power generation output model and a photovoltaic power generation output model.

进一步,步骤一中,首先建立风速模型和日照模型,再根据风速与风力发电出力、日照与光伏发电出力的关系,建立风力发电出力模型、光伏发电出力模型。Further, in step 1, first establish a wind speed model and a sunshine model, and then establish a wind power generation output model and a photovoltaic power generation output model according to the relationship between wind speed and wind power generation output, sunshine and photovoltaic power generation output.

进一步,步骤一中,风速模型采用Weibull分布模型,日照模型采用Beta分布模型,模型的参数通过历史风速信息、历史日照信息计算求得。Further, in step 1, the wind speed model adopts the Weibull distribution model, the sunshine model adopts the Beta distribution model, and the parameters of the models are obtained by calculating historical wind speed information and historical sunshine information.

Weibull风速分布模型如下:The Weibull wind speed distribution model is as follows:

(1) (1)

式中, 分别表示Weibull分布中的形状参数与规模参数,是风速。In the formula, and represent the shape parameter and scale parameter in the Weibull distribution, respectively, is the wind speed.

可由历史风速统计信息平均风速和风速样本标准差得到,计算公式如下: and The average wind speed can be obtained from historical wind speed statistics and wind speed sample standard deviation Obtained, the calculation formula is as follows:

(2) (2)

(3) (3)

(4) (4)

(5) (5)

上式中: 为历史风速统计信息的第个样本值;为样本数量。In the above formula: is the first of the historical wind speed statistics sample value; is the sample size.

进而,可据下式风速与风电出力关系,建立下式所示的风力发电出力模型:Furthermore, according to the following relationship between wind speed and wind power output, the wind power output model shown in the following formula can be established:

(6) (6)

式中, 表示风速,表示风力发电出力,,分别表示切入风速、切出风速和额定风速,表示风力发电的额定出力。In the formula, represents the wind speed, Indicates the output of wind power generation, , and Respectively represent cut-in wind speed, cut-out wind speed and rated wind speed, Indicates the rated output of wind power generation.

Beta日照分布模型如下:The Beta sunshine distribution model is as follows:

(7) (7)

式中:为日照强度,为统计时间段内的最大日照强度值,单位为 W/m2;a 和 b为 Beta 分布的形状参数,可由一定时段内的日照强度平均值和方差计算得到,计算公式如下:In the formula: is the sunlight intensity, is the maximum sunshine intensity value in the statistical time period, and the unit is W/m 2 ; a and b are the shape parameters of the Beta distribution, which can be determined by the average value of sunshine intensity in a certain period of time and variance Calculated, the calculation formula is as follows:

(8) (8)

(9) (9)

进而,可据下式日照与光伏发电出力关系,建立下式所示的光伏发电出力模型:Furthermore, according to the following relationship between sunshine and photovoltaic power generation output, the photovoltaic power generation output model shown in the following formula can be established:

(10) (10)

式中:r 表示光照强度,表示光伏发电出力, 分别表示受光面积和光电转换效率。In the formula: r represents the light intensity, Indicates the output of photovoltaic power generation, , Respectively represent the light-receiving area and photoelectric conversion efficiency.

进一步,步骤二中,线路停运模型采用元件的两状态模型,即元件只有运行状态和故障状态。Further, in step 2, the line outage model adopts the two-state model of the element, that is, the element only has the running state and the fault state.

元件处于运行状态的时间为平均持续工作时间TTF,元件处于故障状态的时间为平均修复时间TTR。平均持续工作时间TTF和平均修复时间TTR的累积分布函数分别为:The time when the component is in the running state is the average continuous working time TTF, and the time when the component is in the fault state is the average repair time TTR. The cumulative distribution functions of the average continuous working time TTF and the average repair time TTR are respectively:

(11) (11)

(12) (12)

式中,为(0,1)之间的随机数,为元件的故障率,为元件的修复率。In the formula, is a random number between (0,1), is the component failure rate, is the repair rate of the component.

由上述可知,元件的平均持续工作时间TTF和平均修复时间TTR可分别由下式计算所得,这样就可得到元件在模拟过程中的运行状态序列,即为线路停运模型。From the above, it can be seen that the average continuous working time TTF and average repair time TTR of the components can be calculated by the following formulas respectively, so that the operating state sequence of the components during the simulation process can be obtained, which is the line outage model.

(13) (13)

(14) (14)

进一步,步骤三中,可靠性指标包括负荷点可靠性指标和系统可靠性指标,负荷点可靠性评估指标包含:Further, in step 3, the reliability index includes the load point reliability index and the system reliability index, and the load point reliability evaluation index includes:

平均故障率 average failure rate

它代表某负荷点在一年期间因配电网元件故障而造成停电的次数。it represents a load point Number of outages during a year due to failure of distribution network components.

年平均停电持续时间 Average annual power outage duration

它代表负荷点i一年内停电的时间总数。计算如下:It represents the total number of times that load point i is out of power within a year. Calculated as follows:

(15) (15)

式中,表示负荷点i第j次停电的持续时间,为负荷点i的平均故障率。In the formula, Indicates the duration of the jth power outage at load point i, is the average failure rate of load point i.

平均停电持续时间 Average outage duration

它代表负荷点i每次停电从开始到恢复供电所需时间的平均值。计算如下:It represents the average time required for each power outage at load point i from the beginning to the restoration of power supply. Calculated as follows:

(16) (16)

式中,为负荷点i年平均停电持续时间, 为负荷点i的平均故障率。In the formula, is the annual average power outage duration of load point i, is the average failure rate of load point i.

系统可靠性指标包括:System reliability indicators include:

①系统平均停电频率指标 ① System average power outage frequency index

它代表在规定时间内系统中平均每个用户停电的次数。It represents the average number of power outages per user in the system within a specified time.

(17) (17)

式中:为负荷点j的用户数,为负荷点j的平均故障率。In the formula: is the number of users at load point j, is the average failure rate of load point j.

系统平均停电持续时间指标 System average outage duration indicator

它代表系统中运行的用户在一年时间中的平均停电持续时间。It represents the average outage duration for users operating on the system over a period of one year.

(18) (18)

式中,表示负荷点j的年平均停电持续时间,为负荷点j的用户数。In the formula, Indicates the annual average power outage duration of load point j, is the number of users at load point j.

平均供电可用率指标 Average Power Supply Availability Index

它代表一年中用户被供电的小时数与用户要求的总供电小时数之比。It represents the ratio of the number of hours a user is supplied with electricity to the total hours of electricity required by the user in a year.

(19) (19)

式中,表示负荷点j的年平均停电持续时间,为负荷点j的用户数。In the formula, Indicates the annual average power outage duration of load point j, is the number of users at load point j.

充裕性指标包括:Adequacy indicators include:

失负荷概率严重度 Loss of Load Probability Severity

(20) (20)

式中:M为系统状态总抽样次数;为系统的失负荷次数;为可容许的失负荷概率界限。In the formula: M is the total sampling times of the system state; is the load loss times of the system; is the allowable load loss probability limit.

电量不足严重度 Low battery severity

(21) (twenty one)

式中:为造成负荷损失电量和,为可容许的电量不足界限;M为系统状态总抽样次数。In the formula: In order to cause the load to lose power and, is the allowable power shortage limit; M is the total number of sampling times of the system state.

重要负荷损失程度 Important load loss degree

(22) (twenty two)

式中: 为重要负荷损失和,n为重要负荷总数, 为重要负荷的负荷权重和负荷容量。In the formula: is the sum of important load losses, n is the total number of important loads, , is the load weight and load capacity of important loads.

进一步,步骤四中,分布式电源高渗透下的配电网风险评估模型求解的蒙特卡罗模拟-粒子群-广度搜索综合算法流程图如附图2,包含以下步骤:Further, in Step 4, the Monte Carlo simulation-particle swarm-breadth search comprehensive algorithm flow chart for solving the distribution network risk assessment model under the high penetration of distributed power sources is shown in Figure 2, which includes the following steps:

(1) 基本数据输入(1) Basic data input

线路参数:元件数,每个元件的修复率、故障率 Line parameters: number of components , the repair rate of each element ,failure rate ;

负荷参数:负荷数,每个负荷的平均负荷、用户数,重要负荷总数n,重要负荷的负荷权重和负荷容量 Load parameter: load number , the average load of each load, the number of users , the total number of important loads n, the load weight of important loads and load capacity ;

电源参数:电源数,每个电源额定容量; Power parameters: number of power supplies , the rated capacity of each power supply;

分布式电源参数:风力发电数,光伏发电数,每个风力发电的参数包括由风速历史信息据式(2)-(5)处理求得的c、k以及额定容量、切入风速、切出风速、额定风速,每个光伏发电的参数即由光照历史信息据式(8)、(9)处理求得的a、b以及rmax、光伏发电的受光面积和光电转换效率 Distributed Power Parameters: Number of Wind Power Generation , the number of photovoltaic power generation , the parameters of each wind power generation include c, k and rated capacity obtained from the historical wind speed information according to formula (2)-(5) , cut-in wind speed , cut out wind speed , rated wind speed , the parameters of each photovoltaic power generation are a, b and r max , the light-receiving area of photovoltaic power generation and the photoelectric conversion efficiency obtained by processing the historical illumination information according to formulas (8) and (9). , ;

其他数据:可容许的失负荷概率界限,可容许的电量不足界限; Other data: Permissible bounds for loss of load probability , the allowable power shortage limit ;

(2)设置仿真总时间Tmax,初始化指标体系包括平均故障率、年平均停电持续时间、平均停电持续时间、系统平均停电频率指标、系统平均停电持续时间指标、平均供电可用率指标、失负荷概率严重度、电量不足严重度、重要负荷损失程度为0,设置仿真参数,包括仿真时间T、系统的总抽样次数M、负荷点的故障次数m、故障时间t、系统的重要负荷损失、负荷损失、失负荷次数J为0;(2) Set the total simulation time T max , initialize the index system including the average failure rate , Average annual power outage duration , average outage duration , System average power outage frequency index , System average outage duration index , Average power supply availability index , Loss of load probability severity , Insufficient battery severity , the degree of important load loss is 0, set the simulation parameters, including simulation time T, total sampling times M of the system, failure times m of load points, failure time t, important load loss of the system , load loss , The number of times of load loss J is 0;

(3)产生个(0,1)之间的随机数,并一一对应于个元件,通过步骤(1)中线路参数以及式(13)、(14)所示的线路停运模型,计算各个元件的平均运行时间TTF和平均修复时间TTR;(3) produce Random numbers between (0,1), and one-to-one correspondence Calculate the average running time TTF and average repair time TTR of each element through the line parameters in step (1) and the line outage model shown in formulas (13) and (14);

(4)产生+个(0,1)之间的随机数,并一一对应于个风力发电、个光伏发电,根据步骤(1)输入的分布式电源参数,以及式(1)、(7)求取每个风力发电的风速值和每个光伏发电的日照强度值,进而据式(6)、(10)求得每个风力发电的出力和每个光伏发电的出力;(4) produce + Random numbers between (0,1), and one-to-one correspondence wind power, According to the distributed power generation parameters input in step (1) and formulas (1) and (7), the wind speed value of each wind power generation and the sunshine intensity value of each photovoltaic power generation are obtained, and then according to formula (6) , (10) Obtain the output of each wind power generation and the output of each photovoltaic power generation ;

(5)选取平均运行时间TTF最小的元件i作为每次抽样的故障元件,并将其运行时间TTF(i)和修复时间TTR(i)累积至仿真时间T,即T= TTF(i)+ TTR(i),同时更新仿真次数M=M+1;(5) Select the component i with the smallest average running time TTF as the faulty component for each sampling, and accumulate its running time TTF(i) and repair time TTR(i) to the simulation time T, that is, T= TTF(i)+ TTR(i), while updating the number of simulations M=M+1;

(6)运用广度搜索算法对配电网进行连通性分析,得到故障后初始连通性矩阵A;(6) Use the breadth search algorithm to analyze the connectivity of the distribution network, and obtain the initial connectivity matrix A after the fault;

(7)断开故障支路,根据步骤(1)中输入的负荷参数和电源参数以及步骤(4)求得的每个风力发电的出力和每个光伏发电的出力,运用粒子群算法对配网进行孤岛划分;(7) Disconnect the fault branch, according to the load parameters and power parameters input in step (1) and the output of each wind power generation obtained in step (4) and the output of each photovoltaic power generation , using the particle swarm algorithm to divide the distribution network into islands;

(8)再次运用广度搜索算法对配电网进行连通性分析,得到孤岛划分后连通性矩阵B;(8) Use the breadth search algorithm to analyze the connectivity of the distribution network again, and obtain the connectivity matrix B after islanding;

(9)比较矩阵A和B,判断负荷点情况,对于负荷点,若A、B中该负荷点均与电源连通的,不停电;A中连通,B中不连通的,停电,累加负荷点的故障次数m=m+1,故障时间t=t+TTR。负荷点判断完毕后,对于系统,计算并累加负荷损失、重要负荷损失、失负荷次数J;(9) Compare the matrix A and B to judge the condition of the load point. For the load point, if the load point in A and B is connected to the power supply, there will be no power failure; if the load point in A and B is not connected, the power will be cut off and the load point will be accumulated The number of failures m=m+1, the failure time t=t+TTR. After the load point is judged, for the system, calculate and accumulate the load loss , important load loss , The number of times of load loss J;

(10)判断仿真时间T是否大于仿真总时间Tmax,若是转(11),若否,转(3);(10) Determine whether the simulation time T is greater than the total simulation time T max , if so, go to (11), if not, go to (3);

(11)根据式(15)-(22)和步骤(9)的数据计算初始化指标体系平均故障率、年平均停电持续时间、平均停电持续时间、系统平均停电频率指标、系统平均停电持续时间指标、平均供电可用率指标、失负荷概率严重度、电量不足严重度、重要负荷损失程度(11) Calculate the average failure rate of the initialization index system according to the data in formulas (15)-(22) and step (9) , Average annual power outage duration , average outage duration , System average power outage frequency index , System average outage duration index , Average power supply availability index , Loss of load probability severity , Insufficient battery severity , the degree of important load loss .

进一步,步骤四中,广度搜索算法进行连通性分析流程图如附图3,步骤如下:Further, in step 4, the flow chart of the breadth search algorithm for connectivity analysis is shown in Figure 3, and the steps are as follows:

(1)输入起点和终点,并将起点加入集合Q中;(1) Input the start point and end point, and add the start point to the set Q;

(2)从集合Q中依次拿出节点Vn,判断Q此时是否为空,若是,则输出起终点不连通,若否,转(3);(2) Take out the nodes Vn from the set Q one by one, judge whether Q is empty at this time, if so, output the start and end points are not connected, if not, go to (3);

(3)找出Vn所有的未包含在Q中的相邻节点Vw,判断Vw是否有终点,若有,输出起终点连通,若否,将Vw加入Q,转(2)。(3) Find out all the adjacent nodes Vw of Vn that are not included in Q, judge whether Vw has an end point, if so, output the start and end points connected, if not, add Vw to Q, and go to (2).

进一步,步骤四中,粒子群算法对配网进行孤岛划分流程图如附图4,步骤如下:Further, in Step 4, the flow chart of the particle swarm optimization algorithm for islanding the distribution network is shown in Figure 4, and the steps are as follows:

(1)随机生成初始粒子,初始化种群数为50,同时初始化迭代次数;(1) Randomly generate initial particles, initialize the population number to 50, and initialize the number of iterations at the same time;

(2)使用广度搜索算法进行连通性分析;(2) Connectivity analysis using breadth search algorithm;

(3)根据连通性分析结果,计算配电网的适应度值,若存在孤岛若不满足功率约束,适应度值置为负无穷;(3) According to the connectivity analysis results, calculate the fitness value of the distribution network. If there is an island or if the power constraint is not satisfied, the fitness value is set to negative infinity;

(4)更新群体最优和个体最优,更新粒子的速度和位置;(4) Update the group optimal and individual optimal, and update the speed and position of the particles;

(5)判断是否达到步骤(1)中设定的迭代次数,若是,输出最优解,若否,转(2)。(5) Judging whether the number of iterations set in step (1) has been reached, if so, output the optimal solution, if not, go to (2).

Claims (9)

1. the power distribution network methods of risk assessment under a kind of distributed generation resource Thief zone, considers the access of large-scale distributed power supply Feature carries out risk assessment, which is characterized in that specific steps to power distribution network:
Step 1: considering fluctuation and intermittence that distributed generation resource is contributed, distributed generation resource output model is established;
Step 2: line outage model is established according to circuit historical failure information;
Step 3: considering the probability and consequence of power distribution network operation risk under distributed generation resource Thief zone, establish and consider power distribution network fortune Row reliability and abundance Risk Assessment Index System;
Step 4: using Monte Carlo simulation-population-breadth first search's integration algorithm to the distribution under distributed generation resource Thief zone Net risk evaluation model is solved, and determines risk assessment desired value, completes the power distribution network risk under distributed generation resource Thief zone Assessment.
2. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 1, which is characterized in that step In rapid one, the distributed generation resource output model includes wind power generation output model and photovoltaic generation output model.
3. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 1 or 2, feature exist In, Wind speed model and sunlight model are initially set up, is contributed further according to wind speed and wind turbine, the relation that sunshine and photovoltaic generation are contributed, Establish wind power generation output model and photovoltaic generation output model.
4. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 3, which is characterized in that wind Fast model uses Weibull distributed models, and sunlight model uses Beta distributed models, and the parameter of model passes through historical wind speed information It is acquired with the calculating of history sunshine information.
5. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 1, which is characterized in that step In rapid two, the line outage model uses two state models of element, and the element has running status and fault status.
6. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 1, which is characterized in that step In rapid three, the reliability index includes load point reliability index and Reliability Index, load point reliability index bag Failure rate, System average interruption duration and annual interruption duration, Reliability Index is included to be averaged including system Power failure frequency, system System average interruption duration and availability of averagely powering, it is tight that the abundance index includes load-loss probability Severe, not enough power supply severity and the important load extent of damage.
7. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 1, which is characterized in that step In rapid four, the power distribution network risk evaluation model solution under the distributed generation resource Thief zone comprises the steps of:
(1)Master data inputs, and the basic data includes line parameter circuit value, power parameter, load parameter and distributed generation resource ginseng Number etc.;
(2)Emulation total time is set, and it is 0 to initialize risk assessment index and simulation parameter;
(3)Each element is generated(0,1)Between random number, and calculate run time and the repair time of each element;
(4)It generates corresponding with distributed generation resource(0,1)Between random number, and calculation of wind speed and intensity of sunshine, and then calculate Wind power generation output and photovoltaic generation are contributed;
(5)The element i of run time minimum is chosen as the fault element sampled every time, and by its running time T TF (i) and is repaiied Multiple time TTR (i) is accumulate to simulation time t, i.e. t=TTF (i)+TTR (i);The value of i is 0 natural number herein;
(6)Connectivity analysis is carried out to power distribution network with breadth first search method, obtains initial connective matrix A after failure;
(7)Fault branch is disconnected, isolated island division is carried out to distribution with particle cluster algorithm;
(8)Connectivity analysis is carried out to power distribution network with breadth first search method again, obtains connective matrix B after isolated island division;
(9)Comparison step(6)In A and step(8)In B, load point is classified, is connected in A, B with power supply, no Have a power failure;It is connected in A, it is disconnected in B, have a power failure, power off time is element i repair time TTR(i), calculated according to classification situation Simulation parameter;The A is initial connective matrix A after failure, and B is connective matrix after isolated island division;
(10)Judge whether simulation time t is more than emulation total time, if simulation time t is more than or equal to emulation total time, be transferred to Step(11);If simulation time t is less than emulation total time, step is transferred to(3);
(11)According to simulation parameter calculation risk evaluation index value.
8. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 7, which is characterized in that adopt The step of carrying out connectivity analysis with the breadth first search method is as follows:
(L1)Beginning and end is inputted, and starting point is added in set Q;
(L2)From step(L1)Node Vn is taken out successively in the set Q, judges whether set Q is at this time empty, if set Q is Sky then exports beginning and end and does not connect;If set Q is not sky, next step is transferred to(L3);
(L3)Find out step(L2)In adjacent node Vw being not included in set Q all in the node Vn that takes out, judge phase Whether neighbors Vw has terminal, if adjacent node Vw has terminal, exports beginning and end connection;If adjacent node Vw is without eventually Adjacent node Vw is added in set Q, and is transferred to step by point(L2).
9. the power distribution network methods of risk assessment under distributed generation resource Thief zone according to claim 7, which is characterized in that adopt The step of carrying out isolated island division to distribution with the particle cluster algorithm is as follows:
(G1)It is random to be initially generated particle, population number is initialized, while initializes iterations;
(G2)Connectivity analysis is carried out using breadth first search method;
(G3)According to step(G2)Connectivity analysis as a result, calculate power distribution network fitness value, if to be unsatisfactory for if there are isolated islands Power constraint, fitness value are set to negative infinite;
(G4)Update group it is optimal and individual it is optimal after, the speed of more new particle and position;
(G5)Judge whether to reach step(G1)The iterations of middle setting, if so, output optimal solution, if it is not, being transferred to step (G2).
CN201810010716.8A 2018-01-05 2018-01-05 A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone Pending CN108062633A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810010716.8A CN108062633A (en) 2018-01-05 2018-01-05 A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810010716.8A CN108062633A (en) 2018-01-05 2018-01-05 A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone

Publications (1)

Publication Number Publication Date
CN108062633A true CN108062633A (en) 2018-05-22

Family

ID=62141252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810010716.8A Pending CN108062633A (en) 2018-01-05 2018-01-05 A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone

Country Status (1)

Country Link
CN (1) CN108062633A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108830485A (en) * 2018-06-19 2018-11-16 广州供电局有限公司 A kind of electric-thermal integrated energy system method for evaluating reliability
CN109034653A (en) * 2018-08-16 2018-12-18 广东电网有限责任公司 A kind of power source planning schemes synthesis evaluation method
CN109657913A (en) * 2018-11-16 2019-04-19 国网江苏省电力有限公司南京供电分公司 A kind of transmission and distribution network joint methods of risk assessment considering distributed generation resource
CN110009207A (en) * 2019-03-25 2019-07-12 深圳供电局有限公司 Urban power grid risk assessment method and device with high power receiving ratio
CN111553075A (en) * 2020-04-27 2020-08-18 广东电网有限责任公司 Power distribution network reliability assessment method and device considering distributed power source network access
CN111682550A (en) * 2020-06-18 2020-09-18 国网山东省电力公司德州供电公司 Reliability assessment method of distribution network with access to high-penetration power and electric vehicles
CN111767633A (en) * 2020-05-19 2020-10-13 国网山东省电力公司烟台供电公司 A high-efficiency simulation method and related equipment for a micro-turbine in an integrated energy system
CN111882228A (en) * 2020-07-31 2020-11-03 国网重庆市电力公司电力科学研究院 Reliability evaluation method for power distribution network containing distributed power supply
CN112508313A (en) * 2019-08-28 2021-03-16 北京科东电力控制系统有限责任公司 Method, device and system for evaluating operation sequence of recoverable equipment after fault
CN112671045A (en) * 2019-12-24 2021-04-16 国网新疆电力有限公司伊犁供电公司 Distributed power supply optimal configuration method based on improved genetic algorithm
CN113449968A (en) * 2021-06-09 2021-09-28 重庆锦禹云能源科技有限公司 New energy power grid frequency risk assessment method and device based on deep learning

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
廖婧舒: "计及分布式电源的配电网风险评估研究", 《中国优秀硕士学位论文全文数据库(电子期刊) 工程科技Ⅱ辑》 *
李缙: ""含光伏发电系统的配电网可靠性评估研究"", 《电器与能效管理技术》 *
陆亚南等: ""基于改进粒子群算法的含分布式发电配网孤岛划分"", 《电工电能新技术》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108830485A (en) * 2018-06-19 2018-11-16 广州供电局有限公司 A kind of electric-thermal integrated energy system method for evaluating reliability
CN109034653A (en) * 2018-08-16 2018-12-18 广东电网有限责任公司 A kind of power source planning schemes synthesis evaluation method
CN109034653B (en) * 2018-08-16 2022-02-15 广东电网有限责任公司 Comprehensive evaluation method for power supply planning scheme
CN109657913A (en) * 2018-11-16 2019-04-19 国网江苏省电力有限公司南京供电分公司 A kind of transmission and distribution network joint methods of risk assessment considering distributed generation resource
CN110009207A (en) * 2019-03-25 2019-07-12 深圳供电局有限公司 Urban power grid risk assessment method and device with high power receiving ratio
CN112508313B (en) * 2019-08-28 2022-09-09 北京科东电力控制系统有限责任公司 Method, device and system for evaluating operation sequence of recoverable equipment after failure
CN112508313A (en) * 2019-08-28 2021-03-16 北京科东电力控制系统有限责任公司 Method, device and system for evaluating operation sequence of recoverable equipment after fault
CN112671045A (en) * 2019-12-24 2021-04-16 国网新疆电力有限公司伊犁供电公司 Distributed power supply optimal configuration method based on improved genetic algorithm
CN112671045B (en) * 2019-12-24 2023-09-22 国网新疆电力有限公司伊犁供电公司 An optimized configuration method for distributed power sources based on improved genetic algorithm
CN111553075A (en) * 2020-04-27 2020-08-18 广东电网有限责任公司 Power distribution network reliability assessment method and device considering distributed power source network access
CN111767633A (en) * 2020-05-19 2020-10-13 国网山东省电力公司烟台供电公司 A high-efficiency simulation method and related equipment for a micro-turbine in an integrated energy system
CN111682550B (en) * 2020-06-18 2022-04-01 国网山东省电力公司德州供电公司 Reliability evaluation method for power distribution network connected with high-permeability power supply and electric automobile
CN111682550A (en) * 2020-06-18 2020-09-18 国网山东省电力公司德州供电公司 Reliability assessment method of distribution network with access to high-penetration power and electric vehicles
CN111882228A (en) * 2020-07-31 2020-11-03 国网重庆市电力公司电力科学研究院 Reliability evaluation method for power distribution network containing distributed power supply
CN113449968A (en) * 2021-06-09 2021-09-28 重庆锦禹云能源科技有限公司 New energy power grid frequency risk assessment method and device based on deep learning
CN113449968B (en) * 2021-06-09 2023-08-29 重庆锦禹云能源科技有限公司 New energy power grid frequency risk assessment method and device based on deep learning

Similar Documents

Publication Publication Date Title
CN108062633A (en) A kind of power distribution network methods of risk assessment under distributed generation resource Thief zone
CN110071505A (en) The power transmission network enlarging of the access containing large-scale wind power configures joint planing method with energy storage
CN111861029A (en) A Power Supply Reliability Evaluation Method Considering Island Division and Network Reconfiguration
CN103986194B (en) A kind of self microgrid Optimal Configuration Method and device
CN104037793A (en) Energy storing unit capacity configuration method applied to initiative power distribution network
CN114725926B (en) Distributed resource-assisted black start strategy for key nodes of the main network to improve resilience
CN109149555B (en) A credible capacity evaluation method of generalized power substation in distribution network considering power supply mode
CN107959307A (en) A kind of DG Optimal Configuration Methods of meter and power distribution network operation risk cost
CN114285034B (en) Day-ahead regulation and optimization method and system considering power supply and new energy fluctuation
CN111882228A (en) Reliability evaluation method for power distribution network containing distributed power supply
CN116505579A (en) A method for dividing microgrid islands and actively supporting distribution network power supply recovery under fault conditions
CN109934437A (en) A method and system for risk assessment of power outage in distribution network
CN118656668A (en) A new power system power and electricity balance analysis method based on multi-cascade multi-process panoramic timing operation simulation
CN114268124B (en) Distributed power supply credible capacity assessment method based on equal power supply reliability
CN110571791B (en) An optimal configuration method for transmission network planning under the access of new energy
CN114142461B (en) Differentiated allocation method of new energy taking into account the evolution and structural development of power grid
CN107359611A (en) Power distribution network equivalence method considering various random factors
CN118353010B (en) Source network charge storage simulation method and device based on multi-node link relation
CN112713621B (en) Multi-objective optimal configuration method and system for AC/DC hybrid system
CN114329857A (en) Distributed power supply planning method based on improved whale algorithm
CN117810990B (en) Method for improving new energy bearing capacity based on distribution network two-line three-station structure
CN112671045B (en) An optimized configuration method for distributed power sources based on improved genetic algorithm
CN104504606A (en) Credible capacity calculating method for distributed grid connection of multiple types of power supplies
CN109713720B (en) A power balance method for new energy grid-connected operation
CN115374999B (en) Water-electricity hydrogen production optimal configuration method suitable for start-stop characteristics of hydrogen production equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination