CN108035534A CN201810017863.8A CN201810017863A CN108035534A CN 108035534 A CN108035534 A CN 108035534A CN 201810017863 A CN201810017863 A CN 201810017863A CN 108035534 A CN108035534 A CN 108035534A
Authority
CN
China
Prior art keywords
latch
template
fixed seat
slot
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810017863.8A
Other languages
Chinese (zh)
Inventor
赵楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jining Xinyu Trademark Agency Ltd
Original Assignee
Jining Xinyu Trademark Agency Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jining Xinyu Trademark Agency Ltd filed Critical Jining Xinyu Trademark Agency Ltd
Priority to CN201810017863.8A priority Critical patent/CN108035534A/en
Publication of CN108035534A publication Critical patent/CN108035534A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/002Workplatforms, railings; Arrangements for pouring concrete, attached to the form
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses quick-clamping building template and its concrete casting device of assembling, including master module, first plate, first slot, first fixed seat, sliding slot, first spring, first latch, auxiliary template, second plate, second slot, limiting plate, limiting slot, second fixed seat, second latch, slide bar, second spring, the quick-clamping building template and its concrete casting device of assembling, clever structure, it is powerful, effect first by plugging together mechanism, the rapid shaping of template can be facilitated, improve the convenient of operation, secondly by the mating reaction of multiple fixed mechanism, connected fastness can not only be improved, it also can ensure that planarization between master module and auxiliary template, the final plane effect that ensure that concreting, beneficial to the popularization and application of building trade.

Description

Quick-clamping building template and its concrete casting device of assembling
Technical field
The present invention relates to technical field of building construction, more particularly to quick-clamping building template and its concrete of assembling to pour Build device.
Background technology
In building trade, commonly used concrete carries out cast-in-place operation to form the building structure such as wall or column, this Wherein need to apply and pour device.
Currently, pour that device carries out wall and column is isostructural pours in effect for application, for pouring acquisition Pour building body planarization and simple operation etc. requirement it is higher and higher, therefore, improve application and pour the operation of device just Victory and pour planarization and become design object.
According to above-mentioned, the structure of existing concrete building template junction, universal simple at present, because bonding strength is low, leads Cause the planarization for pouring building body poor, in addition, when existing concrete building template is constructed, connection and dismounting are relatively time consuming, also to work Personnel operate installation and bring great inconvenience, add expense and the cycle of construction, are unfavorable for the popularization and application of industry, in view of with Upper defect, it is really necessary to design the concrete casting device of quick-clamping building template and its assembling.
The content of the invention
The technical problems to be solved by the invention are:The concreting of quick-clamping building template and its assembling is provided Device, to solve the problems, such as that background technology proposes.
In order to solve the above technical problems, the technical scheme is that:Quick-clamping building template and its coagulation of assembling Soil pours device, including master module, the first plate, the first slot, the first fixed seat, sliding slot, the first spring, the first latch, auxiliary Template, the second plate, the second slot, limiting plate, limiting slot, the second fixed seat, the second latch, slide bar, second spring are helped, it is described Master module quantity be some, the master module is rectangular slab, and first plate is located at master module side, described First plate is integrally connected with master module, and first slot is located at master module opposite side, and first slot is rectangle Groove, first fixed seating are weldingly connected in master module outer wall upper and lower ends, first fixed seat with master module, The sliding slot is located at the first fixed seat interior side, and the sliding slot is rectangular recess, and first spring is located at sliding slot Inside, first spring are weldingly connected with the first fixed seat, and first latch is located inside sliding slot, and described first Latch is slided with the first fixed seat to be connected, and first latch is weldingly connected with the first spring, the auxiliary template number To measure and be located at master module both sides for two pieces, the auxiliary template, the auxiliary template is movably connected with master module, and described Two plates are located at auxiliary template inner wall one end, and the plate is integrally connected with auxiliary template, and second slot is positioned at auxiliary The template inner wall other end is helped, second slot is rectangular recess, and the limiting plate is located at auxiliary template outer wall one end, institute The limiting plate stated is weldingly connected with auxiliary template, and the limiting slot is located at limiting plate inner wall middle-end, and the limiting slot is square Connected in star, second fixed seating are welded in the auxiliary template outer wall other end, second fixed seat with auxiliary template It is connected, second latch runs through the second fixed seat, and second latch is slided with the second fixed seat to be connected, the cunning Bar is located at the second latch side wall, and the slide bar is integrally connected with the second latch, and the second spring is described through slide bar Second spring be weldingly connected with the second latch.
Further, opposite side is additionally provided with mating groove inside first fixed seat, and the mating groove is rectangular recess.
Further, the sliding slot outer wall is additionally provided with avoid holes, and the avoid holes are rectangular through-hole.
Further, outside is additionally provided with baffle ring inside second fixed seat, and the baffle ring and the second fixed seat are welded It is connected, and the baffle ring is connected with sliding bar.
Further, draw ring is additionally provided with the outside of the slide bar, the draw ring is integrally connected with slide bar.
Further, the first bolt is also equipped with inside first fixed seat, the first latch and the second latch, it is described First bolt is connected with the first fixed seat, the first latch and the second latch screw thread respectively.
Further, the second bolt, second bolt difference are also equipped with inside the limiting plate and the first latch It is connected with limiting plate and the first latch screw thread.
Compared with prior art, the quick-clamping building template and its concrete casting device of assembling, during assembling, by One piece of the first plate of master module side is mutually plugged together with second piece of the first slot of master module to be connected, meanwhile, unclamp first and insert Pin, i.e., by the screen resilience of the first spring, making the first latch, the personnel that proceed with one's work, which screw in, to twist inside sliding slot insertion mating groove Tight first bolt, i.e. the first bolt are reached the purpose that is fixedly connected to master module two-by-two, are connect by the first fixed seat and the first latch According to the length needs for actually pouring building body, a number of master module combination can be carried out successively, after master module combines, The second plate on auxiliary template is plugged together with the first slot on master module again and is connected, synchronous, the first plate on master module Plug together and be connected with the second slot on auxiliary template, meanwhile, staff unclamps draw ring, that is, passes through the rebound masterpiece of second spring With making inside the mating groove that the second latch is inserted into moving slide-bar inside the first fixed seat, then screw in and tighten the first bolt, i.e., First bolt similarly, then unclamps the first latch, passes through the rebound masterpiece of the first spring by the first fixed seat and the second latch With, the first latch is inserted into inside limiting slot, and screw in the second bolt, i.e. the second bolt by limiting plate and the first latch, Eventually through aforesaid operations, so as to fulfill the assembled formation of rectangle formwork for placing, matching somebody with somebody by multiple fixed strengthening mechanism in addition Close effect, it is possible to increase the connected fastness of template entirety, when casting concrete, need to be poured from template upper end and under, i.e., Concrete enters template cavity, i.e., by the moulding effect of rectangle template, the shaping of building body, the fast quick-mounting are poured so as to fulfill rectangle Building template and its concrete casting device of assembling are pressed from both sides, clever structure is powerful, first by plugging together the effect of mechanism, The rapid shaping of template can be facilitated, improve the convenient of operation, can not only secondly by the mating reaction of multiple fixed mechanism It is enough to improve the fastness that is connected, additionally it is possible to ensure planarization between master module and auxiliary template, finally ensure that concreting Plane effect, beneficial to the popularization and application of building trade.
Brief description of the drawings
Fig. 1 is the front view of quick-clamping building template and its concrete casting device of assembling;
Fig. 2 is the top view of quick-clamping building template and its concrete casting device of assembling;
Fig. 3 is the sectional view of quick-clamping building template and its concrete casting device of assembling;
Fig. 4 is the second fixed seat position cutaway view Amplified image;
Fig. 5 is limiting plate position cutaway view Amplified image.
It is master module 1, the first plate 2, the first slot 3, the first fixed seat 4, sliding slot 5, the first spring 6, the first latch 7, auxiliary Help template 8, the second plate 9, the second slot 10, limiting plate 11, limiting slot 12, the second fixed seat 13, the second latch 14, slide bar 15th, second spring 16, mating groove 401, avoid holes 402, the first bolt 403, the second bolt 1101, baffle ring 1301, draw ring 1501.
Following embodiment will combine above-mentioned attached drawing and further illustrate.
Embodiment
Hereinafter, a variety of specific details are elaborated, in order to provide the saturating of the concept to forming described embodiment basis Thorough understanding, however, it will be apparent to those skilled in the art that described embodiment can be in these no specific details In it is some or all in the case of put into practice, in other cases, do not specifically describe well-known processing step.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, the concrete casting device of quick-clamping building template and its assembling, bag Include master module 1, the first plate 2, the first slot 3, the first fixed seat 4, sliding slot 5, the first spring 6, the first latch 7, auxiliary template 8th, the second plate 9, the second slot 10, limiting plate 11, limiting slot 12, the second fixed seat 13, the second latch 14, slide bar 15, second Spring 16,1 quantity of master module are some, and the master module 1 is rectangular slab, and first plate 2 is positioned at master 1 side of template, first plate 2 are connected with the one of master module 1, and first slot 3 is located at 1 opposite side of master module, First slot 3 is rectangular recess, and first fixed seat 4 is located at 1 outer wall upper and lower ends of master module, described first Fixed seat 4 is weldingly connected with master module 1, and the sliding slot 5 is located at 4 interior side of the first fixed seat, and the sliding slot 5 is rectangle Groove, first spring 6 are located inside sliding slot 5, and first spring 6 is weldingly connected with the first fixed seat 4, described First latch 7 is located inside sliding slot 5, and first latch 7 is slided with the first fixed seat 4 to be connected, and first latch 7 It is weldingly connected with the first spring 6,8 quantity of auxiliary template is two pieces, and the auxiliary template 8 is located at 1 both sides of master module, The auxiliary template 8 is movably connected with master module 1, and second plate 9 is located at 8 inner wall one end of auxiliary template, described Plate 9 is connected with the one of auxiliary template 8, and second slot 10 is located at the 8 inner wall other end of auxiliary template, and described second inserts Groove 10 is rectangular recess, and the limiting plate 11 is located at 8 outer wall one end of auxiliary template, the limiting plate 11 and auxiliary template 8 It is weldingly connected, the limiting slot 12 is located at 11 inner wall middle-end of limiting plate, and the limiting slot 12 is rectangular recess, and described Two fixed seats 13 are located at the 8 outer wall other end of auxiliary template, and second fixed seat 13 is weldingly connected with auxiliary template 8, described The second latch 14 run through the second fixed seat 13, second latch 14 is slided with the second fixed seat 13 to be connected, the cunning Bar 15 is located at 14 side wall of the second latch, and the slide bar 15 is connected with the one of the second latch 14, and the second spring 16 runs through In slide bar 15, the second spring 16 is weldingly connected with the second latch 14, and the 4 inside opposite side of the first fixed seat is also set There is mating groove 401, the mating groove 401 is rectangular recess, and 5 outer wall of sliding slot is additionally provided with avoid holes 402, and described keeps away Hole 402 is allowed to be rectangular through-hole, the inside of second fixed seat 13 outside is additionally provided with baffle ring 1301, the baffle ring 1301 and the Two fixed seats 13 are weldingly connected, and the baffle ring 1301 is slided with slide bar 15 and is connected, and the outside of slide bar 15 is additionally provided with drawing Ring 1501, the draw ring 1501 are connected with the one of slide bar 15, first fixed seat 4, the first latch 7 and the second latch 14 Inside is also equipped with the first bolt 403, and first bolt 403 is inserted with the first fixed seat 4, the first latch 7 and second respectively 14 screw thread of pin is connected, and the second bolt 1101, second bolt are also equipped with inside 11 and first latch 7 of limiting plate 1101 are connected with 11 and first latch of limiting plate, 7 screw thread respectively.
The quick-clamping building template and its concrete casting device of assembling, during assembling, by first piece of master module 1 one The first plate of side 2 is mutually plugged together with second piece of 1 first slot 3 of master module to be connected, meanwhile, the first latch 7 is unclamped, i.e., by the The screen resilience of one spring 6, makes the first latch 7 be inserted into along sliding slot 5 inside mating groove 401, and the personnel that proceed with one's work, which screw in, tightens the One bolt 403, i.e. the first bolt 403 reach the mesh that is fixedly connected to master module 1 two-by-two by the first fixed seat 4 and the first latch 7 , then according to the length needs for actually pouring building body, a number of master module 1 can be carried out successively and is combined, when master module 1 combines After, then the second plate 9 on auxiliary template 8 is plugged together with the first slot 3 on master module 1 and is connected, synchronous, master module 1 On the first plate 2 plug together and be connected with the second slot 10 on auxiliary template 8, meanwhile, staff unclamps draw ring 1501, i.e., logical The rebound effect of second spring 16 is crossed, the mating groove for making the second latch 14 be inserted into moving slide-bar 15 inside first fixed seat 13 Inside 401, then screw in and tighten the first bolt 403, is i.e. the first bolt 403 is by the first fixed seat 4 and the second latch 14, together Reason, then the first latch 14 is unclamped, by the rebound effect of the first spring 6, the first latch 7 is inserted into inside limiting slot 12, And screw in the second bolt 1101, i.e. the second bolt 1101 is by 11 and first latch 7 of limiting plate, eventually through aforesaid operations, from And realize the assembled formation of rectangle formwork for placing, in addition by the fiting effect of multiple fixed strengthening mechanism, it is possible to increase template Overall connected fastness, when casting concrete, need to only be poured from template upper end and under, i.e. concrete enters template cavity, I.e. by the moulding effect of rectangle template, the shaping of building body is poured so as to fulfill rectangle.
The present invention is not limited to above-mentioned specific embodiment, those of ordinary skill in the art from above-mentioned design, Without performing creative labour, a variety of conversion made, are within the scope of the present invention.

Claims (7)

1. quick-clamping building template and its concrete casting device of assembling, it is characterised in that including master module, the first plate, First slot, the first fixed seat, sliding slot, the first spring, the first latch, auxiliary template, the second plate, the second slot, limiting plate, Limiting slot, the second fixed seat, the second latch, slide bar, second spring, the master module quantity are some, the main mould Plate is rectangular slab, and first plate is located at master module side, and first plate is integrally connected with master module, described First slot is located at master module opposite side, and first slot is rectangular recess, and first fixed seating is in master module Outer wall upper and lower ends, first fixed seat are weldingly connected with master module, and the sliding slot is located at one inside the first fixed seat Side, the sliding slot are rectangular recess, and first spring is located inside sliding slot, first spring and the first fixed seat It is weldingly connected, first latch is located inside sliding slot, and first latch is slided with the first fixed seat to be connected, and described The first latch be weldingly connected with the first spring, the auxiliary template quantity is two pieces, and the auxiliary template is located at main mould Plate both sides, the auxiliary template are movably connected with master module, and second plate is located at auxiliary template inner wall one end, described Plate and auxiliary template be integrally connected, second slot is located at the auxiliary template inner wall other end, second slot For rectangular recess, the limiting plate is located at auxiliary template outer wall one end, and the limiting plate is weldingly connected with auxiliary template, institute The limiting slot stated is located at limiting plate inner wall middle-end, and the limiting slot is rectangular recess, and second fixed seating is in auxiliary The template outer wall other end, second fixed seat are weldingly connected with auxiliary template, and second latch is fixed through second Seat, second latch and the second fixed seat, which are slided, to be connected, and the slide bar is located at the second latch side wall, the slide bar and Second latch is integrally connected, and the second spring is weldingly connected through slide bar, the second spring with the second latch.
2. quick-clamping building template as claimed in claim 1 and its concrete casting device of assembling, it is characterised in that institute Opposite side is additionally provided with mating groove inside the first fixed seat stated, and the mating groove is rectangular recess.
3. quick-clamping building template as claimed in claim 2 and its concrete casting device of assembling, it is characterised in that institute The sliding slot outer wall stated is additionally provided with avoid holes, and the avoid holes are rectangular through-hole.
4. quick-clamping building template as claimed in claim 3 and its concrete casting device of assembling, it is characterised in that institute Outside is additionally provided with baffle ring inside the second fixed seat stated, and the baffle ring is weldingly connected with the second fixed seat, and the baffle ring It is connected with sliding bar.
5. quick-clamping building template as claimed in claim 4 and its concrete casting device of assembling, it is characterised in that institute Draw ring is additionally provided with the outside of the slide bar stated, the draw ring is integrally connected with slide bar.
6. quick-clamping building template as claimed in claim 5 and its concrete casting device of assembling, it is characterised in that institute Also it is equipped with the first bolt inside the first fixed seat, the first latch and the second latch stated, first bolt is respectively with One fixed seat, the first latch and the second latch screw thread are connected.
7. quick-clamping building template as claimed in claim 6 and its concrete casting device of assembling, it is characterised in that institute Also be equipped with the second bolt inside the limiting plate and the first latch stated, second bolt respectively with limiting plate and the first latch Screw thread is connected.
CN201810017863.8A 2018-01-09 2018-01-09 Quick-clamping building template and its concrete casting device of assembling Withdrawn CN108035534A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810017863.8A CN108035534A (en) 2018-01-09 2018-01-09 Quick-clamping building template and its concrete casting device of assembling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810017863.8A CN108035534A (en) 2018-01-09 2018-01-09 Quick-clamping building template and its concrete casting device of assembling

Publications (1)

Publication Number Publication Date
CN108035534A true CN108035534A (en) 2018-05-15

Family

ID=62099450

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810017863.8A Withdrawn CN108035534A (en) 2018-01-09 2018-01-09 Quick-clamping building template and its concrete casting device of assembling

Country Status (1)

Country Link
CN (1) CN108035534A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627520A (en) * 2020-12-01 2021-04-09 机械工业第九设计研究院有限公司 Fixed template structure of pouring frame for civil construction engineering
CN114718304A (en) * 2022-04-11 2022-07-08 洛阳理工学院 Safety locking device for building template connection

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627520A (en) * 2020-12-01 2021-04-09 机械工业第九设计研究院有限公司 Fixed template structure of pouring frame for civil construction engineering
CN114718304A (en) * 2022-04-11 2022-07-08 洛阳理工学院 Safety locking device for building template connection

Similar Documents

Publication Publication Date Title
CN108035534A (en) Quick-clamping building template and its concrete casting device of assembling
CN105064619A (en) Rebar sleeve grouting connection member for prefabricated assembled type concrete component and connection method
CN105649326A (en) Template structure for plugging reserved hole in exterior wall and plugging method
CN103590541A (en) Grout sleeve for connecting prefabricated member steel bars and construction method of grout sleeve
CN208473281U (en) Quick-clamping building template and its concrete casting device of assembling
CN207256481U (en) A kind of fast disassembly type PC wallboard moulds for possessing framework of steel reinforcement and integrally entering mould function
CN205804771U (en) A kind of reinforcing bar grout sleeve
CN210421512U (en) Positioning, mounting and connecting structure of PC prefabricated wall board
CN107696248A (en) For pouring sectional die, casting method and the prefabricated overlapping wall body structure of prefabricated overlapping wall
CN204510810U (en) A kind of formwork structure for shutoff exterior wall reserved opening
CN207256483U (en) A kind of PC wallboard moulds with window opening module
CN205171839U (en) Reinforcing bar grout connecting sleeve
CN213476636U (en) Preformed hole forming device and pouring mold
CN209082770U (en) A kind of connection structure of prefabricated sleeper and prefabricated panel
CN209308404U (en) Concrete duct cast-in-place concrete covers the mold of ring interface construction
CN207647515U (en) A kind of automatic material distributing device for tunnel-liner
CN206144143U (en) Round hole type concrete structure design steel mould
CN204590620U (en) A kind of construction formwork support member
CN205712492U (en) A kind of connector
CN215889339U (en) Assembled integral reinforced concrete shear wall structure
CN209959262U (en) Two lining concrete placement switching device
CN109372259A (en) A kind of window mold that floats of waterproof effect maintenance easy to disassemble by force
CN219581654U (en) Multilayer composite flow steel brick
CN201521110U (en) Reusable building templates connecting and positioning device
CN205437063U (en) Double -purpose molding machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180515