CN107993780A - Cover voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer - Google Patents

Cover voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer Download PDF

Info

Publication number
CN107993780A
CN107993780A CN201711181243.XA CN201711181243A CN107993780A CN 107993780 A CN107993780 A CN 107993780A CN 201711181243 A CN201711181243 A CN 201711181243A CN 107993780 A CN107993780 A CN 107993780A
Authority
CN
China
Prior art keywords
wet paperboard
nylon bandage
paperboard
wet
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711181243.XA
Other languages
Chinese (zh)
Other versions
CN107993780B (en
Inventor
吴东阳
张博
王强
王涛
李丹丹
贾洪顺
尚吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning XINGQI Electric Material Co.,Ltd.
Original Assignee
Liaoning Xing Kai Electrical Materials LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Xing Kai Electrical Materials LLC filed Critical Liaoning Xing Kai Electrical Materials LLC
Priority to CN201711181243.XA priority Critical patent/CN107993780B/en
Publication of CN107993780A publication Critical patent/CN107993780A/en
Application granted granted Critical
Publication of CN107993780B publication Critical patent/CN107993780B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01BCABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
    • H01B19/00Apparatus or processes specially adapted for manufacturing insulators or insulating bodies
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01BCABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
    • H01B19/00Apparatus or processes specially adapted for manufacturing insulators or insulating bodies
    • H01B19/02Drying; Impregnating

Landscapes

  • Laminated Bodies (AREA)
  • Paper (AREA)

Abstract

Covering voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer are related to voltage equalizing ball, the technique of balance pipe covering insulating layer.Mainly solve existing voltage equalizing ball, balance pipe insulating layer covering process change a time it is long the problems such as and invent.Mold clean;Wet paperboard is detected and cut;Soaked wet paperboard is taken out tiling on the table, with hand roller wet paperboard rolling, bubble is discharged, scratches out overlap joint groove, l Water Paper plate surface is patted and is fluffed;Wet paperboard is surrounded into balance pipe one week, then to being handled at the overlap joint groove of wet paperboard, is bound with nylon bandage;Wet paperboard is surrounded one week on voltage equalizing ball;Overlapping part at the overlapping part at wet paperboard both ends and R angles is pounded paste, then appropriateness is patted with hand and pressed repeatedly, is bound with nylon bandage, vacuumizes dehydration after covering first layer, nylon bandage is pulled down;The two or six layer is covered successively, and dryness finalization, cooling, nylon bandage is extracted out.Advantage is can to reduce drying time.

Description

Cover voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer
Technical field:
The present invention relates to the technique of voltage equalizing ball, balance pipe covering insulating layer, is specifically related to a kind of covering voltage equalizing ball, balance pipe one The technique of body formula structure ultrathick insulating layer.
Background technology:
Voltage equalizing ball, the thickness of insulating layer of balance pipe are ultrathick insulating layer at 20 millimeters.Existing voltage equalizing ball, balance pipe insulating layer There are the following problems for covering process:The moisture of insulating layer cannot leak out completely, can cause to produce between each layer of insulating layer Gap forms air cavity, and product can not use, and cause the qualification rate of product low, wastes more.In addition drying time is grown, and work efficiency is low.
The content of the invention:
The technical problems to be solved by the invention, which are to provide a kind of moisture of insulating layer, to be leaked out completely, each layer of insulating layer Between will not form air cavity, drying time is short, the high covering voltage equalizing ball of product qualification rate, balance pipe integral structure ultrathick insulating The technique of layer.
The object of the present invention is achieved like this:
One, mold clean:
The inside and outside portion of mould need to be carried out to clean to remove repeatedly to depollute using giant or dedicated cleaning equipment between mould Thing, the mould after cleaning must ensure surfaces externally and internally cleanliness without any pollution thing;
Two, the detection of wet paperboard, prepare:
Wet paperboard is detected using X-ray machine, it is ensured that in the wet paperboard used during shaped piece production without metallic foreign body and Pollutant;
Three, wet paperboard is cut:
The wet paperboard of correspondingly-sized is cut according to the specification of product, tears 1~2 layer of wet paperboard outer surface off, and ensures l Water Paper thickness Degree meets that wet paperboard is required with finished product thickness than defined.
Four, wet paperboard immersion:
By the wet paperboard stripped tiling in the sink, soaking time 5-8min;
Soaked wet paperboard is taken out tiling on the table, with hand roller wet paperboard rolling, bubble is discharged, l Water Paper is scratched with hand One end of plate, scratches out the overlap joint groove that width is 60-80 ㎜, and the outer peripheral thickness of overlap joint groove is the half of l Water Paper plate thickness, L Water Paper plate surface is patted with deionized water and is fluffed;
Five, make at balance pipe and improving bud grafting:
Wet paperboard is surrounded into balance pipe one week, then to being handled at the overlap joint groove of wet paperboard, i.e., scratches wet paperboard with hand The other end, equally scratches out the overlap joint groove that width is 60-80 ㎜, the overlap joint groove at wet paperboard both ends overlap after thickness Degree is identical with the thickness of wet paperboard, then the wet paperboard lap of splice carries out half lap binding between 60-80mm with nylon bandage; Three layers of binding;
Process of binding pays attention to lap-joint's groove direction, ensures that nylon bandage binding direction is consistent with groove lapping direction, clockwise Direction is spirally bound from top to bottom.
Six, make at voltage equalizing ball and improving bud grafting:
Feeding, from light to heavy, moderately will firmly be patted according to the humidity of wet paperboard, wet paperboard is being pressed when patting wet paperboard Surrounded one week on ball;Overlapping part at the overlapping part at wet paperboard both ends and R angles is pounded paste, then appropriateness is patted with hand And press repeatedly, until the fiber of wet paperboard fully merges(Close slurry), then with nylon bandage half lap binding is carried out, make nylon bandage Wet paperboard is completely covered;Three layers of binding;
When nylon bandage winds the lower edge of voltage equalizing ball, opposite side is wound to from voltage equalizing ball side, coordinates personnel to pin at this time Nylon bandage, then loops back to origination side lower edge by nylon bandage, and whole process will ensure that nylon bandage continues stress;
After covering first layer, the voltage equalizing ball of disjunctor, balance pipe are put into vacuum (-tight) housing and carry out vacuumizing dehydration, dewatering time is 10min, pulls down nylon bandage after dehydration, and second of covering is carried out in the way of the 5th step and the 6th step;Cover the second layer When, the binding number of plies of nylon bandage is three layers, and the dewatering time in vacuum (-tight) housing is 15min;During overlays third layer, nylon bandage The binding number of plies be four layers, the dewatering time in vacuum (-tight) housing is 20min;When covering the 4th layer, the binding number of plies of nylon bandage For five layers, the dewatering time in vacuum (-tight) housing is 30min;When covering layer 5, the binding number of plies of nylon bandage is seven layers, true Dewatering time in sky cover is 40min;When covering layer 6, the binding number of plies of nylon bandage is nine layers, de- in vacuum (-tight) housing The water time is 50min;
A small amount of water is sprayed to nylon bandage after dehydration, nylon bandage is lashed with cardboard, can so improve the smooth of insulating layer outer surface Degree, and the outer surface of insulating layer is formed reticulate pattern;
Then product is sent in baking room and sizing is dried, drying time is 7 days or so, and drying temperature is 120 DEG C;So After take out product, after it is completely cooled down to room temperature, nylon bandage is extracted out, covering complete.
It is an advantage of the invention that:Bind and all carry out vacuum dehydration due to each layer, so moisture can leak out completely Come, drying time can be reduced, air cavity will not be formed between each layer of insulating layer.In addition its technique is simple, and work efficiency is high, and product is qualified Rate is high.
Embodiment:
One, mold clean:
The inside and outside portion of mould need to be carried out to clean to remove repeatedly to depollute using giant or dedicated cleaning equipment between mould Thing, the mould after cleaning must ensure surfaces externally and internally cleanliness without any pollution thing;
Two, the detection of wet paperboard, prepare:
Wet paperboard is detected using X-ray machine, it is ensured that in the wet paperboard used during shaped piece production without metallic foreign body and Pollutant;
Three, wet paperboard is cut:
The wet paperboard of correspondingly-sized is cut according to the specification of product, tears 1~2 layer of wet paperboard outer surface off, and ensures l Water Paper thickness Degree meets that wet paperboard is required with finished product thickness than defined.
Four, wet paperboard immersion:
By the wet paperboard stripped tiling in the sink, soaking time 5-8min;
Soaked wet paperboard is taken out tiling on the table, with hand roller wet paperboard rolling, bubble is discharged, l Water Paper is scratched with hand One end of plate, scratches out the overlap joint groove that width is 60 ㎜ or 70 ㎜ or 80 ㎜, the overlap joint outer peripheral thickness of groove is l Water Paper thickness of slab The half of degree, l Water Paper plate surface is patted fluff with deionized water;
Five, make at balance pipe and improving bud grafting:
Wet paperboard is surrounded into balance pipe one week, then to being handled at the overlap joint groove of wet paperboard, i.e., scratches wet paperboard with hand The other end, equally scratches out the overlap joint groove that width is 60 ㎜ or 70 ㎜ or 80 ㎜, and the overlap joint groove at wet paperboard both ends is overlapped on one Thickness after rising is identical with the thickness of wet paperboard, then the wet paperboard lap of splice uses nylon between 60 ㎜ or 70 ㎜ or 80 ㎜ Bandage carries out half lap binding;Three layers of binding;
Process of binding pays attention to lap-joint's groove direction, ensures that nylon bandage binding direction is consistent with groove lapping direction, clockwise Direction is spirally bound from top to bottom.
Six, make at voltage equalizing ball and improving bud grafting:
Feeding, from light to heavy, moderately will firmly be patted according to the humidity of wet paperboard, wet paperboard is being pressed when patting wet paperboard Surrounded one week on ball;Overlapping part at the overlapping part at wet paperboard both ends and R angles is pounded paste, then appropriateness is patted with hand And press repeatedly, until the fiber of wet paperboard fully merges(Close slurry), then with nylon bandage half lap binding is carried out, make nylon bandage Wet paperboard is completely covered;Three layers of binding;
When nylon bandage winds the lower edge of voltage equalizing ball, opposite side is wound to from voltage equalizing ball side, coordinates personnel to pin at this time Nylon bandage, then loops back to origination side lower edge by nylon bandage, and whole process will ensure that nylon bandage continues stress;
After covering first layer, the voltage equalizing ball of disjunctor, balance pipe are put into vacuum (-tight) housing and carry out vacuumizing dehydration, dewatering time is 10min, pulls down nylon bandage after dehydration, and second of covering is carried out in the way of the 5th step and the 6th step;Cover the second layer When, the binding number of plies of nylon bandage is three layers, and the dewatering time in vacuum (-tight) housing is 15min;During overlays third layer, nylon bandage The binding number of plies be four layers, the dewatering time in vacuum (-tight) housing is 20min;When covering the 4th layer, the binding number of plies of nylon bandage For five layers, the dewatering time in vacuum (-tight) housing is 30min;When covering layer 5, the binding number of plies of nylon bandage is seven layers, true Dewatering time in sky cover is 40min;When covering layer 6, the binding number of plies of nylon bandage is nine layers, de- in vacuum (-tight) housing The water time is 50min;
A small amount of water is sprayed to nylon bandage after dehydration, nylon bandage is lashed with cardboard, can so improve the smooth of insulating layer outer surface Degree, and the outer surface of insulating layer is formed reticulate pattern;
Then product is sent in baking room and sizing is dried, drying time is 7 days or so, and drying temperature is 120 DEG C;So After take out product, after it is completely cooled down to room temperature, nylon bandage is extracted out, covering complete.

Claims (1)

1. voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer are covered, it is characterized in that:
One, mold clean:
The inside and outside portion of mould need to be carried out to clean to remove repeatedly to depollute using giant or dedicated cleaning equipment between mould Thing, the mould after cleaning must ensure surfaces externally and internally cleanliness without any pollution thing;
Two, the detection of wet paperboard, prepare:
Wet paperboard is detected using X-ray machine, it is ensured that in the wet paperboard used during shaped piece production without metallic foreign body and Pollutant;
Three, wet paperboard is cut:
The wet paperboard of correspondingly-sized is cut according to the specification of product, tears 1~2 layer of wet paperboard outer surface off;
Four, wet paperboard immersion:
By the wet paperboard stripped tiling in the sink, soaking time 5-8min;
Soaked wet paperboard is taken out tiling on the table, with hand roller wet paperboard rolling, bubble is discharged, l Water Paper is scratched with hand One end of plate, scratches out the overlap joint groove that width is 60-80 ㎜, and the outer peripheral thickness of overlap joint groove is the half of l Water Paper plate thickness, L Water Paper plate surface is patted with deionized water and is fluffed;
Five, make at balance pipe and improving bud grafting:
Wet paperboard is surrounded into balance pipe one week, then to being handled at the overlap joint groove of wet paperboard, i.e., scratches wet paperboard with hand The other end, equally scratches out the overlap joint groove that width is 60-80 ㎜, the overlap joint groove at wet paperboard both ends overlap after thickness Degree is identical with the thickness of wet paperboard, then the wet paperboard lap of splice carries out half lap binding between 60-80mm with nylon bandage; Three layers of binding;
Six, make at voltage equalizing ball and improving bud grafting:
Feeding, from light to heavy, moderately will firmly be patted according to the humidity of wet paperboard, wet paperboard is being pressed when patting wet paperboard Surrounded one week on ball;Overlapping part at the overlapping part at wet paperboard both ends and R angles is pounded paste, then appropriateness is patted with hand And press repeatedly, until the fiber of wet paperboard fully merges(Close slurry), then with nylon bandage half lap binding is carried out, make nylon bandage Wet paperboard is completely covered;Three layers of binding;
When nylon bandage winds the lower edge of voltage equalizing ball, opposite side is wound to from voltage equalizing ball side, coordinates personnel to pin at this time Nylon bandage, then loops back to origination side lower edge by nylon bandage, and whole process will ensure that nylon bandage continues stress;
After covering first layer, the voltage equalizing ball of disjunctor, balance pipe are put into vacuum (-tight) housing and carry out vacuumizing dehydration, dewatering time is 10min, pulls down nylon bandage after dehydration, and second of covering is carried out in the way of the 5th step and the 6th step;Cover the second layer When, the binding number of plies of nylon bandage is three layers, and the dewatering time in vacuum (-tight) housing is 15min;During overlays third layer, nylon bandage The binding number of plies be four layers, the dewatering time in vacuum (-tight) housing is 20min;When covering the 4th layer, the binding number of plies of nylon bandage For five layers, the dewatering time in vacuum (-tight) housing is 30min;When covering layer 5, the binding number of plies of nylon bandage is seven layers, true Dewatering time in sky cover is 40min;When covering layer 6, the binding number of plies of nylon bandage is nine layers, de- in vacuum (-tight) housing The water time is 50min;
A small amount of water is sprayed to nylon bandage after dehydration, nylon bandage is lashed with cardboard, can so improve the smooth of insulating layer outer surface Degree, and the outer surface of insulating layer is formed reticulate pattern;
Then product is sent in baking room and sizing is dried, drying time is 7 days or so, and drying temperature is 120 DEG C;So After take out product, after it is completely cooled down to room temperature, nylon bandage is extracted out, covering complete.
CN201711181243.XA 2017-11-23 2017-11-23 Process for covering super-thick insulating layer of pressure equalizing ball and pressure equalizing pipe integrated structure Active CN107993780B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711181243.XA CN107993780B (en) 2017-11-23 2017-11-23 Process for covering super-thick insulating layer of pressure equalizing ball and pressure equalizing pipe integrated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711181243.XA CN107993780B (en) 2017-11-23 2017-11-23 Process for covering super-thick insulating layer of pressure equalizing ball and pressure equalizing pipe integrated structure

Publications (2)

Publication Number Publication Date
CN107993780A true CN107993780A (en) 2018-05-04
CN107993780B CN107993780B (en) 2020-04-07

Family

ID=62032777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711181243.XA Active CN107993780B (en) 2017-11-23 2017-11-23 Process for covering super-thick insulating layer of pressure equalizing ball and pressure equalizing pipe integrated structure

Country Status (1)

Country Link
CN (1) CN107993780B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111341555A (en) * 2020-03-28 2020-06-26 潍坊汇胜绝缘技术有限公司 Method for manufacturing conical coil of transformer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101425369A (en) * 2008-05-07 2009-05-06 常州市英中电气有限公司 Insulation voltage equalizing ball used for super-high or extra-high voltage transformer and production process thereof
CN102930978A (en) * 2012-11-15 2013-02-13 常州市英中电气有限公司 Wet forming process of super-high voltage transformer insulator
CN203013437U (en) * 2012-12-13 2013-06-19 天威保变(合肥)变压器有限公司 220kV guide rod type casing pipe voltage-sharing ball insulation protective structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101425369A (en) * 2008-05-07 2009-05-06 常州市英中电气有限公司 Insulation voltage equalizing ball used for super-high or extra-high voltage transformer and production process thereof
CN102930978A (en) * 2012-11-15 2013-02-13 常州市英中电气有限公司 Wet forming process of super-high voltage transformer insulator
CN203013437U (en) * 2012-12-13 2013-06-19 天威保变(合肥)变压器有限公司 220kV guide rod type casing pipe voltage-sharing ball insulation protective structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111341555A (en) * 2020-03-28 2020-06-26 潍坊汇胜绝缘技术有限公司 Method for manufacturing conical coil of transformer
CN111341555B (en) * 2020-03-28 2021-09-24 潍坊汇胜绝缘技术有限公司 Method for manufacturing conical coil of transformer

Also Published As

Publication number Publication date
CN107993780B (en) 2020-04-07

Similar Documents

Publication Publication Date Title
EP3666510A3 (en) Method for forming a sealant layer in a tire and tire having a sealant layer
CN107993780A (en) Cover voltage equalizing ball, the technique of balance pipe integral structure ultrathick insulating layer
CN102930978B (en) Wet forming process of super-high voltage transformer insulator
CN103117159B (en) Large Oil immersion insulating end ring of transformer and manufacture craft thereof
WO2007033158A3 (en) Method and device for making towel, tissue, and wipers on an air carding or air lay line utilizing hydrogen bonds
CN101447246A (en) Wire rod structure of non-woven fabrics-clad and polyester film-clad aluminum wire and manufacturing method thereof
CN109610109B (en) Degumming method and degumming device for PVA non-woven fabric embroidery
CN104934214B (en) Low pressure is segmented paper tinsel around structures and methods
CN204738130U (en) Be used for canvas gumming and air dried device
CN205529637U (en) Artificial imitation leather leather coating drying device
CN101618626B (en) Technology for processing plant leaves
KR20150141981A (en) A hatschek process for the production of fiber cement plates
CN103898803A (en) Method for manufacturing glass fiber air filter paper and special coating and sizing device
CN207736851U (en) The covering fabric for being convenient to clean and constructing
CN207119604U (en) A kind of instrument and meter dust exhaust apparatus
KR101224609B1 (en) The method of manufacturing of The color Han-ji which has different colors in front and back part sheets
CN204891423U (en) Electrolytic copper foil aftertreatment filter equipment that bloies
TWI384508B (en) The process of paper insulation
CN213140766U (en) Compression-resistant blanket production winding device for papermaking
CN205631645U (en) Store up cloth and drying device
CN103280310A (en) Method for binding iron cores of transformer with wound stereoscopic triangular iron core before annealing
CN203198374U (en) All-in-one laminating machine integrating film sticking, liquid applying and squeezing
CN209951576U (en) Water-absorbing core material joint connecting structure free of elimination
CN202573224U (en) Carpet supporting layer airing screen
CN202461031U (en) Safe and efficient auxiliary cleaning device for parts of turbine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 111000 No. 124, Rongxing Road, Taizihe District, Liaoyang City, Liaoning Province

Patentee after: Liaoning XINGQI Electric Material Co.,Ltd.

Address before: 111000 daoxizhuang village, wangshuitai street, Taizihe District, Liaoyang City, Liaoning Province

Patentee before: LIAONING XINGQI ELECTRIC MATERIAL LLC

CP03 Change of name, title or address