CN107990076A CN201711326157.3A CN201711326157A CN107990076A CN 107990076 A CN107990076 A CN 107990076A CN 201711326157 A CN201711326157 A CN 201711326157A CN 107990076 A CN107990076 A CN 107990076A
Authority
CN
China
Prior art keywords
pipeline
pipe clamp
equipment
pipe
cushion collar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201711326157.3A
Other languages
Chinese (zh)
Inventor
杨云忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinchang Bojie Machinery Co Ltd
Original Assignee
Xinchang Bojie Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinchang Bojie Machinery Co Ltd filed Critical Xinchang Bojie Machinery Co Ltd
Priority to CN201711326157.3A priority Critical patent/CN107990076A/en
Publication of CN107990076A publication Critical patent/CN107990076A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L43/00Bends; Siphons
    • F16L43/02Bends; Siphons adapted to make use of special securing means
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/02Energy absorbers; Noise absorbers

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Vibration Prevention Devices (AREA)

Abstract

The present invention provides a kind of equipment of firm pipeline, including buffer gear, the buffer gear includes buffer head and cushion collar;The outer wall of the cushion collar is threaded, and is fixed respectively by nut and pipe clamp through the front and back end of pipe clamp perforation;The buffer head is actively plugged in cushion collar, and one end in the buffer head insertion cushion collar is connected with spring, and the other end of the spring is fixed in the fixed seat inside cushion collar.The equipment that pipe of the present invention consolidates pipeline, it is reasonable in design, it is possible to achieve to the cushioning effect of pipeline, to eliminate vibrations, avoid being damaged using body caused by welding support.

Description

A kind of equipment of firm pipeline
Technical field
The invention belongs to heat exchanger tube pipeline support field, more particularly, to a kind of bend pipe support device.
Background technology
In existing cooling water transportation system, liquid transporting, but the water inside pipe-line are generally carried out by pipeline Stream is in pipeline and elbow is varied widely because of duty parameters such as flow velocity, flow directions, causes larger to having at pipeline inside Impact and make pipe-line produce vibration.At present, channel bend is mainly typically employed in Construction Process of Engineering Project Stability of the mode of place's one support of welding to reduce vibration, improve channel bend, but existing this mode is easily made It is damaged into pipeline body, while using existing this mode elbow detection or monitoring can be caused to be difficult to realize.
The content of the invention
In view of this, the present invention is directed to propose a kind of bend pipe support device, it is possible to achieve to the cushioning effect of pipeline, eliminate Vibrations.
To reach above-mentioned purpose, the technical proposal of the invention is realized in this way:
A kind of equipment of firm pipeline, including stent and pipe clamp, the pipe clamp are in semicircular arc, and the both ends of the pipe clamp are divided Hole is not threaded, and the both ends of the pipe clamp are fixed by shank of bolt and stent;
Perforation is set on the arcwall of the pipe clamp, and buffer gear is fixed through perforation with pipe clamp;The buffer gear bag Include buffer head and cushion collar;The outer wall of the cushion collar is threaded, through pipe clamp perforation front and back end respectively by nut with Pipe clamp is fixed;The buffer head is actively plugged in cushion collar, and one end in the buffer head insertion cushion collar is connected with spring, The other end of the spring is fixed in the fixed seat inside cushion collar.
Further, the second perforation is set on the stent, and buffer gear is fixed through the second perforation with stent.
Further, the stent is arranged to be bent into 90 degree.
Further, the top that the buffer head is placed in outside cushion collar is provided in round.
Further, the curvature of the inner wall of the pipe clamp is more than the curvature of pipeline.
Further, the quantity of the buffer gear for 4 and more than.
Further, the quantity of the pipe clamp for 2 and more than.
Relative to the prior art, equipment that pipe of the present invention consolidates pipeline has the advantage that:
1) buffer gear is equipped with the bend pipe support device, pipeline can be held, it is right after liquid in pipe pressure becomes larger Pipeline plays certain cushioning effect.
2) the pipe clamp parcel pipeline, can eliminate the excessive caused vibrations of pressure, the impaired of body be avoided, on pipe clamp Buffer gear is again provided with, easy to the real-time monitoring to pipeline.
Brief description of the drawings
The attached drawing for forming the part of the present invention is used for providing a further understanding of the present invention, schematic reality of the invention Apply example and its explanation is used to explain the present invention, do not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the schematic elevation view for the equipment that pipe of the present invention consolidates pipeline;
Fig. 2 is the diagrammatic cross-section that pipe of the present invention consolidates buffer gear in the equipment of pipeline;
Fig. 3 is the structure diagram that pipe of the present invention consolidates pipe clamp in the equipment of pipeline;
Fig. 4 is the left view schematic diagram for the equipment supporter that pipe of the present invention consolidates pipeline.
Description of reference numerals:
1- supporting racks;2- buffer gears;3- pipe clamps;4- bend pipes;21- buffer heads;22- cushion collars;23- springs;24- is fixed Seat;25- nuts;31- shanks of bolt.
Embodiment
It should be noted that in the case where there is no conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
In the description of the present invention, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " on ", " under ", The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer " are Based on orientation shown in the drawings or position relationship, it is for only for ease of the description present invention and simplifies description, rather than instruction or dark Show that the device of meaning or element there must be specific orientation, with specific azimuth configuration and operation, thus it is it is not intended that right The limitation of the present invention.In addition, term " first ", " second " etc. are only used for description purpose, and it is not intended that instruction or hint phase To importance or the implicit quantity for indicating indicated technical characteristic.Thus, the feature for defining " first ", " second " etc. can To express or implicitly include one or more this feature.In the description of the present invention, unless otherwise indicated, " multiple " It is meant that two or more.
In the description of the present invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or be electrically connected;It can be directly connected, can also be indirectly connected by intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood by concrete condition Concrete meaning in the present invention.
Below with reference to the accompanying drawings and the present invention will be described in detail in conjunction with the embodiments.
A kind of equipment of firm pipeline, including stent 1 and pipe clamp 3, the pipe clamp 3 are in semicircular arc, and the two of the pipe clamp 3 End is threaded hole respectively, and the both ends of the pipe clamp 3 are fixed by shank of bolt 31 and stent 1;
Perforation is set on the arcwall of the pipe clamp 3, and buffer gear 2 is fixed through perforation with pipe clamp 3;The buffer gear 2 include buffer head 21 and cushion collar 22;The outer wall of the cushion collar 22 is threaded, through the front and back end that pipe clamp 3 is perforated difference Fixed by nut 25 and pipe clamp 3;The buffer head 21 is actively plugged in cushion collar 22, and the buffer head 21 is inserted into cushion collar One end in 22 is connected with spring 23, and the other end of the spring 23 is fixed in the fixed seat 24 inside cushion collar 22.
Described 21 one end of buffer head is circle.
The pipe clamp 3 is in semicircular arc, and the pipe clamp 3 is equipped with buffer gear 3.
The curvature of the inner wall of the pipe clamp 3 is more than the curvature of pipeline 4.
The quantity of the buffer gear 2 for 4 and more than.
The quantity of the pipe clamp for 2 and more than.
The pipeline 4 can be bend pipe or straight tube.
Buffer gear 2 is equipped with the bend pipe support device, pipeline 4 can be held, it is right after liquid in pipe pressure becomes larger Pipeline 4 plays certain cushioning effect.
The pipe clamp 3 wraps up pipeline 4, can eliminate the excessive caused vibrations of pressure, avoid the impaired of body, pipe clamp 3 Buffer gear 2 is again provided with upper and stent 1, easy to the duplicate protection to pipeline 4.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on, should all be included in the protection scope of the present invention god.

Claims (7)

  1. A kind of 1. equipment of firm pipeline, it is characterised in that:Including stent (1) and pipe clamp (3), the pipe clamp (3) is in semi arch Shape, the both ends of the pipe clamp (3) are threaded hole respectively, and the both ends of the pipe clamp (3) are solid by shank of bolt (31) and stent (1) It is fixed;
    Perforation is set on the arcwall of the pipe clamp (3), and buffer gear (2) is fixed with pipe clamp (3) through perforation;The buffer Structure (2) includes buffer head (21) and cushion collar (22);The outer wall of the cushion collar (22) is threaded, and is perforated through pipe clamp (3) To pass through nut (25) and pipe clamp (3) respectively fixed for front and back end;The buffer head (21) is actively plugged in cushion collar (22), institute The one end stated in buffer head (21) insertion cushion collar (22) is connected with spring (23), and the other end of the spring (23) is fixed on slow In the internal fixed seat (24) of punching set (22).
  2. 2. the equipment that pipe according to claim 1 consolidates pipeline, it is characterised in that:Second is set to wear on the stent (1) Hole (11), buffer gear (2) are fixed through the second perforation (11) and stent (1).
  3. 3. the equipment that pipe according to claim 1 consolidates pipeline, it is characterised in that:The stent (1) is arranged to be bent into 90 degree.
  4. 4. the equipment that pipe according to claim 2 consolidates pipeline, it is characterised in that:Described buffer head (21) one end is circle Shape.
  5. 5. the equipment that pipe according to claim 1 consolidates pipeline, it is characterised in that:The curvature of the inner wall of the pipe clamp (3) More than the curvature of pipeline (4).
  6. 6. the equipment that pipe according to claim 1 consolidates pipeline, it is characterised in that:The quantity of the buffer gear (2) is 4 It is a and more than.
  7. 7. the equipment that pipe according to claim 1 consolidates pipeline, it is characterised in that:The quantity of the pipe clamp (3) for 2 and More than.
CN201711326157.3A 2017-12-13 2017-12-13 A kind of equipment of firm pipeline Withdrawn CN107990076A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711326157.3A CN107990076A (en) 2017-12-13 2017-12-13 A kind of equipment of firm pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711326157.3A CN107990076A (en) 2017-12-13 2017-12-13 A kind of equipment of firm pipeline

Publications (1)

Publication Number Publication Date
CN107990076A true CN107990076A (en) 2018-05-04

Family

ID=62037668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711326157.3A Withdrawn CN107990076A (en) 2017-12-13 2017-12-13 A kind of equipment of firm pipeline

Country Status (1)

Country Link
CN (1) CN107990076A (en)

Similar Documents

Publication Publication Date Title
ZA200806306B (en) Tube bundle heat exchanger
CN113236879B (en) Air conditioner pipe fitting, air conditioner pipeline and air conditioner
EP1471323A3 (en) Header tank for heat exchanger
US8479709B2 (en) Automotive line bundling system
CN107990076A (en) A kind of equipment of firm pipeline
CN205300050U (en) Higher scale control condenser of factor of safety
CN207634809U (en) A kind of tube support arrangement
CN205806742U (en) Corrugated tube power transmission positioning joint
JP2014238093A (en) Compact coulomb damper
CN210830868U (en) Metal corrugated pipe assembly
CN204924011U (en) Seal structure of heat exchange tube and tube sheet
CN208203401U (en) Gas exhaust piping assembly
CN103162055A (en) Novel multifunctional ripple compensator
CN104420938A (en) Transverse silencer
CN203927217U (en) A kind of bidirectional compensator
JP6002426B2 (en) Evaporator
CN209495032U (en) High temperature conduit crossing cabin part and Ship Power Equipment
JPH11182979A (en) Flexible tube for refrigerant piping in car air conditioner
CN106287029A (en) A kind of anti-high-pressure plastic conveying corrugated tube
CN102537585A (en) Silencing rectification hood behind pressure adjusting valve of gas transmission pipeline
KR102581885B1 (en) Heat Exchanger
ATE416338T1 (en) FLEXIBLE HOSE LINE FOR THE AIR CONDITIONING SYSTEM CIRCUIT WITH A FLUID TIGHT CONNECTION SYSTEM BETWEEN A RIGID PIPE ELEMENT AND A HOSE
CN104390396A (en) Compact evaporator liquid reservoir
JP2566279B2 (en) Resin filler tube for vehicles
CN213421505U (en) A damping structure and heat pump for jet-propelled enthalpy that increases

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180504