CN107968398B - Node merging simplified modeling method - Google Patents

Node merging simplified modeling method Download PDF

Info

Publication number
CN107968398B
CN107968398B CN201711237543.5A CN201711237543A CN107968398B CN 107968398 B CN107968398 B CN 107968398B CN 201711237543 A CN201711237543 A CN 201711237543A CN 107968398 B CN107968398 B CN 107968398B
Authority
CN
China
Prior art keywords
node
voltage
branch
load
nodes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711237543.5A
Other languages
Chinese (zh)
Other versions
CN107968398A (en
Inventor
王文彬
伍小生
范瑞祥
蒙天骐
李琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201711237543.5A priority Critical patent/CN107968398B/en
Publication of CN107968398A publication Critical patent/CN107968398A/en
Application granted granted Critical
Publication of CN107968398B publication Critical patent/CN107968398B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/30Circuit design
    • G06F30/36Circuit design at the analogue level
    • G06F30/367Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A node merging simplified modeling method comprises a branch sorting method and a low-voltage tail end node sorting method for judging node low voltage, dividing a main line and a branch line and enabling tail end nodes not to have low voltage, and merging node loads by adopting a load node merging equivalent algorithm. According to the node merging simplified modeling method, node loads are merged, the number of load nodes is reduced, the fact that the load flow calculation result of a simplified power grid model is strong in equivalence with that before simplification is guaranteed, errors can be controlled within a specified range, equivalent modeling of a power distribution network is combined with a physical simulation platform, low-voltage simplified modeling of a power distribution network with the voltage of below 400V is combined with the physical simulation model, and the low-voltage governing process can be verified by the simplified physical simulation platform.

Description

Node merging simplified modeling method
Technical Field
The invention relates to a node merging simplified modeling method, in particular to a node merging simplified modeling method for a low-voltage physical simulation platform of a power distribution network below 400V, and belongs to the technical field of power grid operation.
Background
Along with the development of Chinese economy and electric power, the scales of urban and rural power grids in China are continuously enlarged, and the power distribution grids of 400V and below have the problems of more branch lines, numerous load nodes, larger load grade difference, complex load distribution and the like, so that the power distribution grid area has the characteristic of complex power grid structure. Due to the characteristic of complex structure of the power grid, the situation of numerous branch lines and nodes can occur when a topological graph of the power grid of the transformer area is drawn, so that the situation of numerous nodes and branch lines when a physical simulation platform of low voltage of a power distribution network below 400V is built is caused, and the physical simulation platform is difficult to accurately verify the low voltage treatment process.
Therefore, the invention provides a node merging simplified modeling method, which merges node loads, reduces the number of load nodes, ensures that the load flow calculation result of a simplified power grid model has stronger equivalence with that before simplification, can control errors within a specified range, combines the equivalent modeling of a power distribution network with a physical simulation platform, combines the 'low voltage' simplified modeling of a distribution network with the voltage of below 400V with the physical simulation model, and ensures that the 'low voltage' governing process can be verified by the simplified physical simulation platform.
Disclosure of Invention
The invention aims to merge node loads and provide a node merging simplified modeling method aiming at the defects of the prior art.
The technical scheme for realizing the invention is as follows: the method comprises the steps of judging node low voltage, dividing a main line and a branch line, and sequencing branches without low voltage at a tail end node and sequencing low voltage tail end nodes before simplifying modeling; when the branch nodes and the end nodes are reserved after sorting, merging the node loads by adopting a load node merging equivalent algorithm, and equating the loads between the branch nodes and the end nodes into a load. The load node number is reduced, the power flow calculation result of the simplified power grid model is ensured to have stronger equivalence with the power flow calculation result before simplification, and the error can be controlled within a specified range.
The invention discloses a node merging and simplifying modeling method, which comprises the following steps:
(1) and carrying out load flow calculation on the distribution network platform area. And (4) carrying out load flow calculation by adopting a three-phase four-wire system implicit Gaussian method (the load flow calculation is carried out by adopting the method later), and judging whether the node voltage has a low voltage condition. The judging method comprises the following steps: if the node is a three-phase node, a low voltage is generated when the voltage of the node is lower than 353.4V; if the node is a single phase node, a low voltage is present when its voltage is below 198V.
(2) And judging a main line of the distribution transformer area.
The method for judging the main line of the distribution transformer area comprises the following steps: if only one line is connected with an initial node (a node connected with a distribution transformer), the main line distinguishing method comprises the following steps: setting the line between the initial node and the end node with the lowest voltage as a main line, and setting the other lines as branch lines; if a plurality of lines are connected with the initial node, the main line consists of two parts, and the main line distinguishing method comprises the following steps: firstly, searching a first part of the main line (namely, a line between the initial node and the end node with the lowest voltage is the first part of the main line) by using the method, and recording the first part of the main line; then, the lines from other lines connected with the initial node to the tail end node with the lowest voltage are used as a second part of the main line; the main line is composed of a first part and a second part of the main line, and the rest lines are branch lines.
(3) A branch sequence judging method. And judging the branch sequence according to the branch condition of the power grid topological structure line and the voltage of the terminal node of the load flow calculation result. The branch line from the main line branch point to the end node of the line is a 1-stage branch line, and the specific judgment method is to set the line from the main line node to the end node with the lowest voltage as the 1-stage branch line and set the other branch lines as lower-stage branch lines. The branch point of the 1-level branch to the end node of the line is a 2-level branch, and the specific judgment method is that the line between the 1-level branch and the end node with the lowest voltage is the 2-level branch, and the other branches are lower branch lines … …; and repeating the method to divide the branches.
(4) The branch ordering method with low voltage at the end node does not occur. Calculating branches without low voltage according to the following formula, and sorting calculation results according to the requirements of reserved nodes and the number of the branches:
Figure BDA0001489278440000031
wherein Y is a branch calculation value, YjCalculating the load from the jth end node to the main branch node on the branch, nThe number of end nodes included in a branch,
Figure BDA0001489278440000032
for the L-th line from the j-th end node to the main line branch nodejThe apparent power on the individual nodes is,
Figure BDA0001489278440000033
for the L-th line from the j-th end node to the main line branch nodejLine impedance of the individual nodes to the branch node.
(5) Low voltage end node sequencing method
The total voltage of the low voltage end node is counted by the following formula:
Figure BDA0001489278440000034
wherein, VlowIs the total voltage value of the low voltage end node, ViThe voltage value of the ith tail end node is obtained, and n is the voltage number of the tail end node;
calculating the branches with low voltage according to the following formula, and sorting the calculation results according to the requirements of reserved nodes and the number of the branches:
Figure BDA0001489278440000035
wherein X is a calculated value of the end node,
Figure BDA0001489278440000036
for the ith end low voltage node to the L-th line of the main line branch nodeiThe apparent power on the individual nodes is,
Figure BDA0001489278440000037
for the ith end node to the line of the main line branch nodeiLine impedance of the individual nodes to the branch node.
(6) And (5) according to the sequencing results in the step (4) and the step (5), if the branch node and the end node are not reserved, adopting a direct equivalent method to equivalent the load on the branch line to the branch node. If the branch node and the end node are reserved, a load node merging equivalent algorithm is adopted to enable the load between the branch node and the end node to be equivalent to a load.
The specific equivalent method is as follows:
fig. 2 shows a typical distribution network line, and a and B are two nodes on the line.
From the load flow calculation, UA,UAp,UB,UBpThe voltage amplitude (kV) and the phase angle of the voltage on the two nodes A and B respectively; sA,SAp,SB,SBpAt the two nodes a and B, respectively, is the power load (kVA) and its phase angle; z is the impedance per unit length of the line between a and B (Ω/km), r + jx; the total length of the line between a and B is l (km).
FIG. 3 is a simplified model of an equivalent algorithm employing load node merge, where SkAnd SkpThe amplitude (kVA) and the phase angle of the equivalent load node expressed by apparent power are respectively adopted; l is1And L2The length (km) of the line from the two nodes A and B, respectively, to the equivalent load node (node K), obviously L1+L2=L;IA,IAp,IB,IBp,IK,IKpThe amplitude (a) and the phase angle of each branch current shown in fig. 2 are shown.
Referring to fig. 3, the voltage magnitude at the equivalent load node can be calculated from node a as:
Figure BDA0001489278440000041
wherein, PAAnd QARespectively, active power (kW) and reactive power (kVar) flowing through node a.
Calculating the voltage amplitude at the equivalent load node according to the node B as follows:
Figure BDA0001489278440000042
wherein, PBAnd QBRespectively active power (kW) and reactive power (kVar) flowing through the node B.
Design equivalent error UerrComprises the following steps: u shapeerr=UK-U′K
Determination of L by iterative method1And L2The value of (c). When U is turnederrWhen the absolute value of (a) is less than the specified error limit, the iteration is considered to have converged, i.e. the equivalence has been completed; otherwise, when UerrWhen the value is more than zero, L is properly increased in the next iteration1Taking the value of (A); when U is turnederrLess than zero, then L is reduced appropriately at the next iteration1The value of (a).
Solving the value of the equivalent load node according to the following expression:
Figure BDA0001489278440000051
UK=UA-IAzL1
Figure BDA0001489278440000052
wherein the content of the first and second substances,
Figure BDA0001489278440000053
i.e. the initial apparent power value S at point BB
Figure BDA0001489278440000054
Is the initial voltage value U of the point BB
Figure BDA0001489278440000055
I.e. the initial apparent power value S at point AA
Figure BDA0001489278440000056
Is the initial voltage value U of the point AA
Figure BDA0001489278440000057
Namely the current value I from the point K to the equivalent terminal node calculated according to the formulaK,UKNamely the equivalent K point voltage value, SKNamely the equivalent K point apparent power value.
All parameters of the simplified model based on the load equivalence method can be obtained by the formula.
(7) And carrying out load flow calculation on the distribution network area subjected to the equivalent modeling to obtain the voltage value of each node, and calculating the low-voltage error of the node subjected to the equivalent.
The node merging simplified modeling method has the advantages that the number of load nodes is reduced by merging node loads, the fact that the load flow calculation result of the simplified power grid model has strong equivalence with that before simplification is guaranteed, errors can be controlled within a specified range, equivalent modeling of a power distribution network is combined with a physical simulation platform, low-voltage simplified modeling of a distribution network with the voltage of below 400V is combined with the physical simulation model, and the low-voltage governing process can be verified by the simplified physical simulation platform.
Drawings
FIG. 1 is a flow chart of a simplified modeling method for node merging according to the present invention;
FIG. 2 is a section of a typical distribution grid line;
FIG. 3 is an equivalent circuit using equivalent load nodes instead of all the loads on the line of FIG. 1;
FIG. 4 is a structural diagram of a left lining camp plot of Huanglong institute 945 in Jiangxi province;
FIG. 5 is a diagram of a result of a power flow calculation in a district in a farm;
FIG. 6 is an equivalent diagram of a region in a field camp without a "low voltage" node;
fig. 7 is an equivalent diagram of a platform region node in a field camp.
Detailed Description
A specific embodiment of the present invention is shown in fig. 1.
As shown in fig. 1, the node merging simplified modeling method of the embodiment includes the following steps:
(1) and carrying out load flow calculation on the distribution network platform area. And carrying out load flow calculation by adopting a three-phase four-wire system implicit Gaussian method, and judging whether the node voltage has a low-voltage condition or not.
(2) And judging a main line of the distribution transformer area.
(3) And branch sequence judgment, namely branch sequence judgment is carried out according to the branch condition of the power grid topological structure line and the voltage of the terminal node of the load flow calculation result.
(4) The branches with no low voltage appearing at the end node are sorted.
(5) The low voltage end nodes are sorted.
(6) According to the sequencing result, if the branch node and the end node are reserved, a load node merging equivalent algorithm is adopted to equate the load between the branch node and the end node into a load; and solving the value of the equivalent load node.
(7) And carrying out load flow calculation on the distribution network area subjected to the equivalent modeling to obtain the voltage value of each node, and calculating the low-voltage error of the node subjected to the equivalent.
This embodiment is implemented by taking a left-line-drawing field camp area of huanglonginstitute 945 in Jiangxi province as an example.
It is known that the capacity of a distribution transformer in a district in rural areas is 50KVA, and the main line is mainly LGJ-25. The structure of the camp site is shown in fig. 4.
Step 1, obtaining a load distribution condition of a platform area according to detection historical data of the platform area in the field camp, drawing a distribution transformer, a tower, a load and a line of a topological graph of the platform area in the field camp according to a graph 4, and performing load flow calculation, wherein the load flow calculation result is shown in a graph 5, the voltage of all the tail ends of black lines is lower than a low-voltage threshold value of 0.354KV, the black area is a low-voltage area, and the lowest voltage reaches 0.336 KV.
Step 2, judging the main line, and as can be seen from fig. 5, the main line from the distribution and transformation outlet to the node 39 is the first part of the main line, and the main line from the distribution and transformation outlet to the node 9 is the second part of the main line; thus, the main line is from node 9 to node 39.
Step 3, branch line sequence judgment, as can be seen from fig. 5, the nodes from the branch point on the main line to 1Y25, 9a1, and 9B1 are all 1-level branches.
Step 4, sequencing branches without low voltage at the end node, combining the load flow calculation result from the graph 5, wherein the length from the distribution transformer outlet to the node 1Y25 is 0.5km, and the load connected with the node 1Y25 is 3kW + j1.45kVar; the length of the line from the distribution transformer outlet to the 9 nodes is 0.45km, and the load connected to the 9 nodes is 4.8KW + j2.32kVar. The node 1A25 is reserved, the load connected to the node 9 is directly equivalent to the node 9, and the load equivalent between the distribution transformer outlet and the node 9 is equivalent by adopting a load node merging equivalent algorithm.
Step 5, merging the equivalent load of the district in rural areas according to the step 4 and the load node, and calculating the equivalent load of the district in rural areas as shown in fig. 6, wherein the load on the node 9 is 9kW + j4.35kVar, the load on the node 6 is 9kW + j4.35kVar, the voltage of the node 9 is 0.371kV, and compared with the 0.372kV before the equivalent, the voltage error is 2.688 × 10-3
Step 6, a low-voltage terminal node sorting method, according to the equivalent result of fig. 6, the load from the distribution transformer outlet to the 39 node can be directly equivalent by adopting a load node merging equivalent algorithm, the equivalent power flow calculation is shown in fig. 7, at this time, the load on the node 34 is 8.4kW + j4.06kvar, the load on the node 39 is 3.6kW + j1.74kvar, the voltage of the node 39 is 0.339kV, and compared with the 0.338kV before the equivalence, the equivalent error is 2.959 × 10-3

Claims (2)

1. A node merging simplified modeling method comprises node low voltage judgment, main line and branch line division, and is characterized in that the method also comprises the steps of sorting branches without low voltage at end nodes and sorting low-voltage end nodes before simplified modeling; when the branch nodes and the tail end nodes are reserved after sorting, merging the node loads by adopting a load node merging equivalent algorithm, and equating the loads between the branch nodes and the tail end nodes into a load;
the branch sorting method without low voltage at the tail end node comprises the steps of counting the sum of products of apparent power on a node in a line from the tail end node to a main line branch node and line impedance from the node in the line from the tail end node to the main line branch node to the branch node, and sorting according to a calculation result;
Figure FDA0002547724500000011
wherein Y is a branch calculation value; y isjCalculating the load calculation value from the jth tail end node to the main line branch node on the branch; n is the number of end nodes contained in the branch;
Figure FDA0002547724500000012
for the L-th line from the j-th end node to the main line branch nodejApparent power on the individual nodes;
Figure FDA0002547724500000013
for the L-th line from the j-th end node to the main line branch nodejLine impedance from individual node to branch node;
the low-voltage tail end node sequencing method comprises the steps of counting the total voltage of the low-voltage tail end nodes, counting the sum of the product of the apparent power of the tail end low-voltage nodes to the line middle nodes of the main line branch node and the product of the line impedance of the nodes to the branch nodes, and sequencing according to the product of the ratio of the voltage of the tail end nodes in the total voltage and the sum of the products;
the total voltage expression of the low-voltage end node is counted as:
Figure FDA0002547724500000014
wherein, VlowIs the total voltage value of the low voltage end node, ViThe voltage value of the ith tail end node is obtained, and n is the voltage number of the tail end node;
the expression for the calculation of the branch in which the low voltage occurs is:
Figure FDA0002547724500000021
wherein X is a calculated value of the end node,
Figure FDA0002547724500000022
for the ith end low voltage node to the L-th line of the main line branch nodeiThe apparent power on the individual nodes is,
Figure FDA0002547724500000023
for the ith end node to the line of the main line branch nodeiLine impedance from individual node to branch node;
the method adopting the load node merging equivalent algorithm comprises the following steps:
A. b are two nodes of a typical distribution network area line respectively, and U is obtained by load flow calculationA,UAp,UB,UBpThe voltage amplitude and the phase angle of the voltage on the two nodes A and B are respectively; sA,SAp,SB,SBpAt the two nodes a and B, respectively, is the power load and its phase angle; z is the impedance per unit length of the line between A and B; the total length of the line between A and B is L; simplified model using load node merging equivalent algorithm, where SkAnd SkpRespectively representing the amplitude and the phase angle of the equivalent load node by adopting the apparent power; l is1And L2The lengths of the lines from the two nodes A and B to the equivalent load node K, respectively, are obviously L1+L2=L;IA,IAp,IB,IBp,IK,IKpRespectively representing the amplitude and phase angle of each branch current;
from node a, the voltage magnitude at the equivalent load node is calculated by:
Figure FDA0002547724500000024
wherein, PAAnd QARespectively the active power and the reactive power flowing through the node A;
from node B, the voltage magnitude at the equivalent load node is calculated by:
Figure FDA0002547724500000025
wherein, PBAnd QBActive power and reactive power flowing through the node B, respectively;
equivalent error UerrComprises the following steps: u shapeerr=UK-U'K
Determination of L by iterative method1And L2A value of (d); when U is turnederrWhen the absolute value of (a) is less than the specified error limit, the iteration is considered to have converged, i.e. the equivalence has been completed; otherwise, when UerrWhen the value is more than zero, L is properly increased in the next iteration1Taking the value of (A); when U is turnederrLess than zero, then L is reduced appropriately at the next iteration1Taking the value of (A);
solving equivalent load nodes:
Figure FDA0002547724500000031
UK=UA-IAzL1
Figure FDA0002547724500000032
wherein the content of the first and second substances,
Figure FDA0002547724500000033
i.e. the initial apparent power value S at point BB
Figure FDA0002547724500000034
Is the initial voltage value U of the point BB
Figure FDA0002547724500000035
I.e. the initial apparent power value S at point AA
Figure FDA0002547724500000036
Namely point AInitial voltage value UA
Figure FDA0002547724500000037
Namely the current value I from the point K to the equivalent terminal node calculated according to the formulaK,UKNamely the equivalent K point voltage value, SKThe equivalent K point apparent power value is obtained;
from the above expressions, all parameters of the simplified model based on the load equivalence method can be derived.
2. The node merging simplified modeling method according to claim 1, characterized in that the method steps are as follows:
(1) carrying out load flow calculation on a distribution network region, carrying out load flow calculation by adopting a three-phase four-wire system implicit Gaussian method, and judging whether the node voltage has a low-voltage condition or not;
(2) judging a main line of a distribution transformer area;
(3) judging the branch sequence of the distribution transformer area, and judging the branch sequence according to the branch condition of the power grid topological structure line and the voltage of the terminal node of the load flow calculation result;
(4) sorting branches of which the end nodes do not have low voltage;
(5) sequencing the low-voltage end nodes;
(6) according to the sequencing result, if the branch node and the end node are reserved, a load node merging equivalent algorithm is adopted to equate the load between the branch node and the end node into a load; solving the value of the equivalent load node;
(7) and carrying out load flow calculation on the distribution network area subjected to the equivalent modeling to obtain the voltage value of each node, and calculating the low-voltage error of the node subjected to the equivalent.
CN201711237543.5A 2017-11-30 2017-11-30 Node merging simplified modeling method Active CN107968398B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711237543.5A CN107968398B (en) 2017-11-30 2017-11-30 Node merging simplified modeling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711237543.5A CN107968398B (en) 2017-11-30 2017-11-30 Node merging simplified modeling method

Publications (2)

Publication Number Publication Date
CN107968398A CN107968398A (en) 2018-04-27
CN107968398B true CN107968398B (en) 2020-09-11

Family

ID=61999192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711237543.5A Active CN107968398B (en) 2017-11-30 2017-11-30 Node merging simplified modeling method

Country Status (1)

Country Link
CN (1) CN107968398B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108933439B (en) * 2018-07-12 2021-11-09 竺炜 10kV line voltage rapid estimation method based on line voltage drop moment model

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103248044A (en) * 2013-05-07 2013-08-14 广东电网公司电力科学研究院 Load flow calculation method and system for power distribution network
CN106532727A (en) * 2016-12-13 2017-03-22 国网北京市电力公司 Configuration method and device of installation points of dynamic reactive power compensator
CN106549376A (en) * 2016-12-08 2017-03-29 东北大学 The branch road comprehensive stability appraisal procedure of power distribution network containing DG based on equivalent node method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103248044A (en) * 2013-05-07 2013-08-14 广东电网公司电力科学研究院 Load flow calculation method and system for power distribution network
CN106549376A (en) * 2016-12-08 2017-03-29 东北大学 The branch road comprehensive stability appraisal procedure of power distribution network containing DG based on equivalent node method
CN106532727A (en) * 2016-12-13 2017-03-22 国网北京市电力公司 Configuration method and device of installation points of dynamic reactive power compensator

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Voltage stability assessment using equivalent Thevenin;L.Paniagua等;《2015 IEEE Thirty Fifth Central American and Panama Convention(CONCAPAN XXXV)》;20151113;1-6页 *
微电网潮流计算及可靠性评估研究;彭寒梅;《中国博士学位论文全文数据库 工程科技Ⅱ辑》;20170615;C042-47 *

Also Published As

Publication number Publication date
CN107968398A (en) 2018-04-27

Similar Documents

Publication Publication Date Title
CN106972504B (en) Interval reactive power optimization method based on genetic algorithm
CN105321003B (en) A kind of ac and dc systems multiple target tide optimization method containing VSC-HVDC
CN105449675B (en) The electric power networks reconstructing method of Optimum distribution formula energy access point and access ratio
CN104578159B (en) A kind of power distribution network Three-phase Power Flow modification method containing distributed power source
CN104537580B (en) The construction method of distribution network structure based on K means clusters
CN107392418B (en) Urban power distribution network reconstruction method and system
CN106374513B (en) A kind of more microgrid dominant eigenvalues optimization methods based on leader-followers games
CN105656031B (en) The methods of risk assessment of power system security containing wind-powered electricity generation based on Gaussian Mixture distribution characteristics
CN104539221B (en) Photovoltaic generating system controls parameter global optimization method
CN104899396B (en) A kind of algorithm quicksort tidal current computing method of correction factor matrix
CN104113061A (en) Three-phase load flow calculation method of power distribution network with distributed power supply
CN107994582A (en) Reconstruction method of power distribution network and system containing distributed generation resource
CN110896231A (en) Distributed photovoltaic capacity receiving calculation method and system for power distribution network in poverty alleviation area
CN104201671A (en) Static voltage stability assessment method of three-phase unbalanced power distribution network including wind power
CN107565556B (en) Power distribution network maximum power supply capacity calculation method considering three-phase imbalance factor
CN103279661B (en) Substation capacity Optimal Configuration Method based on Hybrid quantum inspired evolution algorithm
CN102891485B (en) Three-phase decoupling load flow calculation method for weakly meshed distribution network based on sequence component method
CN103956735A (en) Harmonic power flow analysis method of distributed power generation system
CN107968398B (en) Node merging simplified modeling method
CN106443276A (en) Radio interference computing method and radio interference computing system for alternating-current high-voltage multi-loop electric transmission line
CN104135038B (en) A kind of alternating current-direct current combined hybrid system unbalanced fault analytical method
CN112531765A (en) Method and device for determining short circuit ratio of new energy station
CN103887823A (en) Micro-grid connection position selection method based on fuzzy hierarchical analysis
CN104484832B (en) The method of assessment 220KV handle net net capability
CN112531731A (en) Reactive compensation method for alternating current-direct current hybrid power distribution network based on sensitivity analysis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant