CN107953064B CN201711093015.7A CN201711093015A CN107953064B CN 107953064 B CN107953064 B CN 107953064B CN 201711093015 A CN201711093015 A CN 201711093015A CN 107953064 B CN107953064 B CN 107953064B
Authority
CN
China
Prior art keywords
blade
impeller
arc
length
chord length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711093015.7A
Other languages
Chinese (zh)
Other versions
CN107953064A (en
Inventor
杨鹏
韩俊
李宏武
张雷
何芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHIZONG COKE CHEMICAL INDUSTRY Co Ltd
Original Assignee
SHIZONG COKE CHEMICAL INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHIZONG COKE CHEMICAL INDUSTRY Co Ltd filed Critical SHIZONG COKE CHEMICAL INDUSTRY Co Ltd
Priority to CN201711093015.7A priority Critical patent/CN107953064B/en
Publication of CN107953064A publication Critical patent/CN107953064A/en
Application granted granted Critical
Publication of CN107953064B publication Critical patent/CN107953064B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P6/00Restoring or reconditioning objects
    • B23P6/002Repairing turbine components, e.g. moving or stationary blades, rotors

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The invention discloses a kind of restorative procedures of half-opened impeller, it is desirable to provide a kind of to overhaul quickly and easily restorative procedure.The following steps are included: it is step 1: impeller is removed from pump, and blade is considered as arc plate shape, measures blade dimensions respectively: chord length S, arc length L, high H1, H2 of both ends of the blade;Step 2: arc length L dimension is mapped on AutoCAD according to the chord length S that measurement blade obtains, pass through three strokes and dots arcs;It draws by chord length S two-end-point and by certain point on chord length S perpendicular bisector, and arc length is equal to the circular arc of L;Step 3: measurement arc diameter φ;According to surveyed diameter phi, selecting diameter is the seamless steel pipe of φ ± 5mm as blade base material;Step 4: cutting line is drawn according to chord length S, arc length L, high H1, H2 of both ends of the blade in the steel tube surface selected, the part cut from steel pipe blade as new after polishing smooth;Step 5: new blade is welded on impeller after the blade of damage is removed from impeller, that is, complete the reparation of impeller.

Description

A kind of restorative procedure of half-opened impeller
Technical field
The present invention relates to water pump service technique fields, more particularly, to a kind of restorative procedure of half-opened impeller.
Background technique
There are a large amount of waste water and waste liquid pond in industrial enterprise, mating self priming pump carries out the conveying and processing of waste liquid, due to useless Liquid impurity content is high, and corrosivity is stronger, generates serious abrasion and corrosion to the impeller of water pump, shortens the water pump service life sharply, It is frequent to replace impeller, increases production cost and labor intensity.
The damage of water pump vane is mainly the abrasion and corrosion of blade, and blade is thinned, perforates, deformation leads to not reach water Suction, lift and the flow of pump.Under normal circumstances, be all to replace the method for completely new impeller and carry out repair and maintenance, but need to be from water Pump genuine man purchase impeller is just able to satisfy matching requirements or sends old impeller outside tailor-made.Such maintenance mode cause it is at high cost with And the time between overhauls(TBO) is long, is unfavorable for the stabilization of production.
Summary of the invention
The purpose of the present invention is intended to overcome the shortcomings of the prior art, provides that a kind of time between overhauls(TBO) is short, the cost of overhaul Low, the convenient half-opened impeller of maintenance restorative procedure.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions:
A kind of restorative procedure of half-opened impeller comprising following steps:
Step 1: impeller is removed from pump, blade is considered as arc plate shape, measures blade dimensions respectively: chord length S, arc Long L, high H1, H2 of both ends of the blade;
Step 2: arc length L dimension is mapped on AutoCAD according to the chord length S that measurement blade obtains, pass through three strokes and dots Arc;It draws by chord length S two-end-point and by certain point on chord length S perpendicular bisector, and arc length is equal to the circular arc of L;
Step 3: measurement arc diameter φ;According to surveyed diameter phi, select diameter for the seamless steel pipe conduct of φ ± 5mm Blade base material;
Step 4: cutting line is drawn according to chord length S, arc length L, high H1, H2 of both ends of the blade in the steel tube surface selected, from The part that steel pipe is cut is new blade after polishing smooth;
Step 5: new blade is welded on impeller after the blade of damage is removed from impeller, that is, complete impeller It repairs.
Preferably, arc length error≤0.1mm in the mapping.
Compared with prior art, the present invention has the advantage that
The present invention the new blade of several piece of quality such as is cut to size using common pipe materials as base material, replaces all on impeller Blade.Have the advantages that at low cost, the period is short, maintenance is convenient, without doing impeller static balance, dynamic balance running, have immediately extensive The effect of rehydration pumping function.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the structural schematic diagram of impeller.
Fig. 2 is the schematic diagram for making leaf chord length S and arc length L on AutoCAD.
Fig. 3 is the schematic diagram that blade arc diameter phi is measured on AutoCAD.
Fig. 4 is to draw the schematic diagram of cutting line in steel tube surface.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under that premise of not paying creative labor Embodiment shall fall within the protection scope of the present invention.
A kind of restorative procedure of half-opened impeller comprising following steps:
Step 1: impeller is removed from pump, blade is considered as arc plate shape, measures blade dimensions respectively: chord length S, arc Long L, high H1, H2 of both ends of the blade;
Step 2: arc length L dimension is mapped on AutoCAD according to the chord length S that measurement blade obtains, pass through three strokes and dots Arc;It draws through chord length S two-end-point and passes through certain point on chord length S perpendicular bisector, and circular arc of the arc length equal to L, arc length L error≤ 0.1mm;As shown in Figure 2;
Step 3: measurement arc diameter φ;As shown in Figure 3;According to surveyed diameter phi, select diameter for the nothing of φ ± 5mm Steel pipe is stitched as blade base material;
Step 4: cutting line is drawn according to chord length S, arc length L, high H1, H2 of both ends of the blade in the steel tube surface selected, from The part that steel pipe is cut is new blade after polishing smooth;As shown in Figure 4;
Step 5: new blade is welded on impeller after the blade of damage is removed from impeller, that is, complete impeller It repairs.
The present invention have the advantages that at low cost, the period is short, maintenance is convenient, without doing impeller static balance, dynamic balance running, Impaired impeller can quickly be repaired, it is ensured that the stability of production.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (2)

1. a kind of restorative procedure of half-opened impeller, it is characterised in that the following steps are included:
Step 1: impeller is removed from pump, blade is considered as arc plate shape, measures blade dimensions respectively: chord length S, arc length L, High H1, H2 of both ends of the blade;
Step 2: arc length L dimension is mapped on AutoCAD according to the chord length S that measurement blade obtains, pass through three strokes and dots arcs;It draws Out by chord length S two-end-point and by certain point on chord length S perpendicular bisector, and arc length is equal to the circular arc of L;
Step 3: measurement arc diameter φ;According to surveyed diameter phi, selecting diameter is the seamless steel pipe of φ ± 5mm as blade Base material;
Step 4: arc length L, high H1, H2 of both ends of the blade draw cutting line, from steel pipe in the steel tube surface selected according to chord length S The part cut is new blade after polishing smooth;
Step 5: new blade is welded on impeller after the blade of damage is removed from impeller, that is, complete repairing for impeller It is multiple.
2. the restorative procedure of half-opened impeller according to claim 1, it is characterised in that: arc length error in the mapping≤ 0.1mm。
CN201711093015.7A 2017-11-08 2017-11-08 A kind of restorative procedure of half-opened impeller Active CN107953064B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711093015.7A CN107953064B (en) 2017-11-08 2017-11-08 A kind of restorative procedure of half-opened impeller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711093015.7A CN107953064B (en) 2017-11-08 2017-11-08 A kind of restorative procedure of half-opened impeller

Publications (2)

Publication Number Publication Date
CN107953064A CN107953064A (en) 2018-04-24
CN107953064B true CN107953064B (en) 2019-07-05

Family

ID=61963417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711093015.7A Active CN107953064B (en) 2017-11-08 2017-11-08 A kind of restorative procedure of half-opened impeller

Country Status (1)

Country Link
CN (1) CN107953064B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112846248B (en) * 2021-01-07 2021-11-09 安徽莱恩电泵有限公司 Semi-open impeller cutting method of self-priming pump
CN114851047B (en) * 2022-05-10 2024-03-26 岳阳大陆激光技术有限公司 Fan impeller repairing method and duplicating type detection tool

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6416278B1 (en) * 2000-11-16 2002-07-09 General Electric Company Turbine nozzle segment and method of repairing same
FR2983757B1 (en) * 2011-12-07 2014-09-12 Snecma PROCESS FOR REFORMING A TURBOMACHINE BLADE COMPRISING AT LEAST ONE ZONE DEFORMEE BY GRASPING
CN102773655B (en) * 2012-07-20 2014-09-03 哈尔滨汽轮机厂有限责任公司 Repairing method of steam turbine rotor fir type wheel groove
EP2949418B1 (en) * 2014-05-30 2017-02-01 General Electric Technology GmbH Method for repairing a turbine blade tip
CN105057969B (en) * 2015-05-29 2017-12-08 西安交通大学 Repairing method of solid impeller disc based on MICROBEAM PLASMA WELDING and electric spark finishing
CN105414877A (en) * 2015-11-04 2016-03-23 鲁一军 Die core repairing process
CN106925943A (en) * 2017-04-06 2017-07-07 中交天津航道局有限公司 A kind of restorative procedure of rich chromium cast iron material dredging pump impeller

Also Published As

Publication number Publication date
CN107953064A (en) 2018-04-24

Similar Documents

Publication Publication Date Title
CN107953064B (en) A kind of restorative procedure of half-opened impeller
CN201327460Y (en) Filling-up plate device for pipeline hydrotest
CN204283897U (en) A kind of Pontoon pump station
CN207858608U (en) A kind of bend pipe is interior to throw special fixture
CN205852742U (en) The high-pressure pump machining tool car of filling ceramic plunger
CN204878073U (en) Large -scale pump diffuser structure
CN207997150U (en) A kind of stainless steel square tube production cutting fixed seat
CN207326721U (en) A kind of titanium tube end grinding head
CN207687546U (en) A kind of glass reinforced plastic push pipe Simple connecting structure
CN206769830U (en) One kind repairs sucker rod
CN207064956U (en) A kind of special end socket of power plant's heavy caliber circulating water pipeline water pressure test
CN109332927A (en) A kind of Francis Turbine Blade outlet edge crackle processing method
CN101602394A (en) Copper-nickel-iron communication cabin component
CN206190593U (en) High -power dredge pump impeller structure
CN206054987U (en) A kind of novel pipe fitting
CN214248616U (en) Joint structure for end part of non-metal pipeline
CN205877421U (en) Detachable conduit coupling
CN205779865U (en) A kind of sea water pump coupling structure
CN208638130U (en) A kind of chemical industry pumping electricity consumption machine fixing seat
CN208024620U (en) A kind of bearing gland for immersible pump
CN213392837U (en) Wear-resistant special water pump impeller for sewage
CN205350715U (en) Novel seawater lift pump carbon fiber lifting pipe
CN208854539U (en) A kind of impeller lock ring dismantling device
CN203808367U (en) Composite carbon fiber threaded bar
CN107120069A (en) One kind repairs sucker rod

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant