CN107916955A - High inclination-angle continuous flush practice device for constructing metro tunnel - Google Patents

High inclination-angle continuous flush practice device for constructing metro tunnel Download PDF

Info

Publication number
CN107916955A
CN107916955A CN201711364033.4A CN201711364033A CN107916955A CN 107916955 A CN107916955 A CN 107916955A CN 201711364033 A CN201711364033 A CN 201711364033A CN 107916955 A CN107916955 A CN 107916955A
Authority
CN
China
Prior art keywords
belt
pressure
roller
frame
pressing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711364033.4A
Other languages
Chinese (zh)
Inventor
秦庆华
宋朋洋
徐会敢
车新宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Original Assignee
China Railway Engineering Equipment Group Co Ltd CREG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Equipment Group Co Ltd CREG filed Critical China Railway Engineering Equipment Group Co Ltd CREG
Priority to CN201711364033.4A priority Critical patent/CN107916955A/en
Publication of CN107916955A publication Critical patent/CN107916955A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/04Transport of mined material in gravity inclines; in staple or inclined shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structure Of Belt Conveyors (AREA)

Abstract

本发明提出一种用于地铁隧道施工的大倾角连续出渣装置,包括设在竖井段的压带部分,压带部分包括驱动滚筒、压带、机架和转向滚筒,驱动滚筒和转向滚筒设在两端并与压带配合,机架设在驱动滚筒与转向滚筒之间,机架上设有若干承载托辊和活动的压辊架,压辊架与机架之间设有弹簧,压辊架上设有压辊,压辊与压带配合,承载托辊与承载皮带配合,压辊和承载托辊将压带、承载皮带压在一起。本发明的优点:压带式连续皮带机可直接进行大倾角输送,无需转渣,简化了设备整体结构,提高了效率;采用两条胶带夹住物料的方式,保证大倾角输送过程不漏料;相比于波纹挡边垂直提升皮带机,其成本低、可靠性高、胶带清渣效果好。

The present invention proposes a continuous slag discharge device with a large dip angle for subway tunnel construction, which includes a belt pressing part arranged in a vertical shaft section. The belt pressing part includes a driving drum, a pressing belt, a frame and a steering drum. At both ends and in cooperation with the pressure belt, the frame is set between the driving drum and the steering drum. There are several bearing rollers and movable pressure roller frames on the frame. Springs are arranged between the pressure roller frames and the frame. Pressing rollers are arranged on the frame, and the pressing rollers cooperate with the pressing belt, and the carrying rollers cooperate with the carrying belt, and the pressing rollers and carrying supporting rollers press the pressing belt and the carrying belt together. The advantages of the present invention: the pressure belt type continuous belt conveyor can be directly conveyed at a large inclination without turning the slag, which simplifies the overall structure of the equipment and improves the efficiency; the method of clamping the material with two tapes ensures that there is no material leakage during the conveying process at a large inclination ;Compared with the corrugated sidewall vertically lifting belt conveyor, it has low cost, high reliability, and good tape slag cleaning effect.

Description

用于地铁隧道施工的大倾角连续出渣装置Large-inclination continuous slag discharge device for subway tunnel construction

技术领域technical field

本发明涉及连续皮带输送机,特别是指一种用于地铁隧道施工的大倾角连续出渣装置。The invention relates to a continuous belt conveyor, in particular to a large-inclination continuous slag discharging device used in subway tunnel construction.

背景技术Background technique

在地铁隧道施工领域,连续皮带机可以使得掘进机不停机连续向前推进,但是在竖井出渣时,由于其倾角过大时,会导致物料下滑,无法使用传统连续皮带机输送,需进行转渣,目前一般采用连续皮带机+垂直提升皮带机或者连续皮带机+提升机的组合方式。垂直提升皮带机采用波纹挡边胶带,结构复杂、价格昂贵且清渣困难,提升机效率低且不能连续出渣,因此,地铁隧道竖井大倾角提升这一问题有待解决。In the field of subway tunnel construction, the continuous belt conveyor can make the roadheader move forward continuously without stopping the machine. However, when the slag is discharged from the shaft, because the inclination angle is too large, the material will slide down, and the traditional continuous belt conveyor cannot be used for transportation. For slag, the combination of continuous belt conveyor + vertical lifting belt conveyor or continuous belt conveyor + hoist is generally used at present. The vertical lifting belt conveyor uses corrugated sidewall tape, which has a complex structure, is expensive, and is difficult to remove slag. The hoist has low efficiency and cannot continuously discharge slag. Therefore, the problem of large-inclination elevators in subway tunnel shafts needs to be solved.

发明内容Contents of the invention

本发明提出一种用于地铁隧道施工的大倾角连续出渣装置,解决了现有地铁隧道竖井出渣困难的问题。本发明的压带式结构可以不受提升倾角的限制,将渣土直接通过连续皮带机由竖井口提升至地面。The invention proposes a large-inclination continuous slag discharging device used in subway tunnel construction, which solves the problem of difficult slag discharging in existing subway tunnel shafts. The belt-pressing structure of the present invention can directly lift the muck from the shaft mouth to the ground through the continuous belt conveyor without being limited by the lifting inclination angle.

本发明的技术方案是这样实现的:一种用于地铁隧道施工的大倾角连续出渣装置,包括设在竖井段的压带部分,压带部分包括驱动滚筒、压带、机架和转向滚筒,驱动滚筒和转向滚筒设在两端并与压带配合,机架设在驱动滚筒与转向滚筒之间,机架上设有若干承载托辊和活动的压辊架,压辊架与机架之间设有弹簧,压辊架上设有压辊,压辊与压带配合,承载托辊与承载皮带配合,压辊和承载托辊将压带、承载皮带压在一起。The technical solution of the present invention is realized in the following way: a large-inclination continuous slag discharge device for subway tunnel construction includes a belt pressing part arranged in the shaft section, and the belt pressing part includes a driving roller, a pressing belt, a frame and a steering roller , the driving roller and the steering roller are arranged at both ends and cooperate with the pressure belt. Springs are arranged between them, and pressure rollers are arranged on the pressure roller frame, and the pressure rollers cooperate with the pressure belt, and the carrying idler cooperates with the carrying belt, and the pressure roller and the carrying idler press the pressure belt and the carrying belt together.

所述的机架上设有连接板,连接板与连接杆活动连接,连接杆与压辊架活动连接。The frame is provided with a connecting plate, the connecting plate is movably connected with the connecting rod, and the connecting rod is movably connected with the pressure roller frame.

所述的承载托辊为槽形,槽形包括两端的倾斜段和中间的水平段,压辊架的两侧设有连杆,压辊架与连杆的中部活动连接,连杆的两端均与压辊活动连接,连杆一端的压辊与水平段的压带配合,连杆另一端的压辊与倾斜段的压带配合。The carrying roller is groove-shaped, and the groove shape includes inclined sections at both ends and a horizontal section in the middle. There are connecting rods on both sides of the pressure roller frame, and the middle part of the pressure roller frame is movably connected with the connecting rod. The two ends of the connecting rod All are movably connected with the pressure roller, the pressure roller at one end of the connecting rod cooperates with the pressure belt of the horizontal section, and the pressure roller at the other end of the connecting rod cooperates with the pressure belt of the inclined section.

所述的压带上设有张紧装置,张紧装置为重锤或电动绞车。A tensioning device is provided on the pressure belt, and the tensioning device is a weight or an electric winch.

所述的驱动滚筒位于竖井段底部,转向滚筒位于竖井段顶部。The driving drum is located at the bottom of the shaft section, and the steering drum is located at the top of the shaft section.

还包括机尾部分、中间标准段、储带仓部分、驱动部分和机头部分,承载皮带的两端通过机尾部分和机头部分支撑,机尾部分与机头部分之间设有与承载皮带配合的中间标准段、储带仓部分和驱动部分。It also includes the tail part, the middle standard section, the storage bin part, the driving part and the head part. The two ends of the carrying belt are supported by the tail part and the head part. Intermediate standard section, stocker section and drive section for belt fit.

所述的机尾部分设在盾构机上,中间标准段位于盾构机与竖井段底部之间,储带仓部分设在中间标准段的下侧,驱动部分设在竖井段底部,机头部分设在地表面。The tail part of the machine is set on the shield machine, the middle standard section is located between the shield machine and the bottom of the shaft section, the belt storage part is set on the lower side of the middle standard section, the driving part is set at the bottom of the shaft section, and the head part located on the ground surface.

本发明的优点:压带式连续皮带机可直接进行大倾角输送,无需转渣,简化了设备整体结构,提高了效率;采用两条胶带夹住物料的方式,保证大倾角输送过程不漏料;相比于波纹挡边垂直提升皮带机,其成本低、可靠性高、胶带清渣效果好。The advantages of the present invention: the pressure belt type continuous belt conveyor can be directly conveyed at a large inclination without turning the slag, which simplifies the overall structure of the equipment and improves the efficiency; the method of clamping the material with two tapes ensures that there is no material leakage during the conveying process at a large inclination ;Compared with the corrugated sidewall vertically lifting belt conveyor, it has low cost, high reliability, and good tape slag cleaning effect.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1为本发明侧视图。Fig. 1 is a side view of the present invention.

图2为本发明压带部分侧视图。Fig. 2 is a partial side view of the pressure belt of the present invention.

图3为本发明压带部分截面图。Fig. 3 is a partial sectional view of the pressure belt of the present invention.

图4为本发明压辊架侧视图。Fig. 4 is a side view of the pressing roller frame of the present invention.

图中:1-机尾部分,2-中间标准段,3-储带仓部分,4-驱动部分,5-压带部分,6-机头部分,7-驱动滚筒,8-压带,9-机架,10-连接杆,11-弹簧,12-压辊架,13-压辊,14-承载托辊,15-张紧装置,16-转向滚筒,17-承载皮带,18-连接板,19-连杆。In the figure: 1-tail part, 2-middle standard section, 3-storage bin, 4-driving part, 5-pressing belt part, 6-head part, 7-driving roller, 8-pressing belt, 9 -frame, 10-connecting rod, 11-spring, 12-pressure roller frame, 13-pressure roller, 14-loading roller, 15-tensioning device, 16-turning drum, 17-carrying belt, 18-connecting plate , 19-connecting rod.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

如图1-4所示,一种用于地铁隧道施工的大倾角连续出渣装置,包括设在竖井段的压带部分5,压带部分5包括驱动滚筒7、压带8、机架9和转向滚筒16,驱动滚筒7和转向滚筒16设在两端并与压带8配合,机架9设在驱动滚筒7与转向滚筒16之间,机架9上设有若干承载托辊14和活动的压辊架12,压辊架12与机架9之间设有弹簧11,压辊架12上设有压辊13,压辊13与压带8配合,承载托辊14与承载皮带17配合,压辊13和承载托辊14将压带8、承载皮带17压在一起。As shown in Figure 1-4, a large-inclination continuous slag discharge device for subway tunnel construction includes a belt pressing part 5 arranged in the shaft section, and the belt pressing part 5 includes a driving drum 7, a pressing belt 8, and a frame 9 And the turning drum 16, the driving drum 7 and the steering drum 16 are located at both ends and cooperate with the pressure belt 8, the frame 9 is arranged between the driving drum 7 and the steering drum 16, and the frame 9 is provided with a number of bearing rollers 14 and The movable pressure roller frame 12, the spring 11 is arranged between the pressure roller frame 12 and the frame 9, the pressure roller frame 12 is provided with a pressure roller 13, the pressure roller 13 cooperates with the pressure belt 8, the carrying idler roller 14 and the carrying belt 17 Cooperate, the pressure roller 13 and the carrying roller 14 press the pressure belt 8 and the carrying belt 17 together.

所述的机架9上设有连接板18,连接板18与连接杆10活动连接,连接杆10与压辊架12活动连接。The frame 9 is provided with a connecting plate 18, the connecting plate 18 is movably connected with the connecting rod 10, and the connecting rod 10 is movably connected with the pressure roller frame 12.

所述的承载托辊14为槽形,槽形包括两端的倾斜段和中间的水平段,压辊架12的两侧设有连杆,压辊架12与连杆19的中部活动连接,连杆19的两端均与压辊13活动连接,连杆19一端的压辊13与水平段的压带8配合,连杆19另一端的压辊13与倾斜段的压带8配合。The carrying idler 14 is groove-shaped, and the groove shape includes inclined sections at both ends and a horizontal section in the middle, and connecting rods are arranged on both sides of the pressure roller frame 12, and the middle part of the pressure roller frame 12 is movably connected with the connecting rod 19. The two ends of bar 19 are all movably connected with pressure roller 13, and the pressure roller 13 of connecting rod 19 one end cooperates with the pressure belt 8 of horizontal section, and the pressure roller 13 of connecting rod 19 other ends cooperates with the pressure belt 8 of inclined section.

所述的压带8上设有张紧装置15,张紧装置15为重锤或电动绞车。The tensioning device 15 is provided on the pressure belt 8, and the tensioning device 15 is a weight or an electric winch.

所述的驱动滚筒7位于竖井段底部,转向滚筒16位于竖井段顶部。The driving drum 7 is located at the bottom of the shaft section, and the steering drum 16 is located at the top of the shaft section.

还包括机尾部分1、中间标准段2、储带仓部分3、驱动部分4和机头部分6,承载皮带17的两端通过机尾部分1和机头部分6支撑,机尾部分1与机头部分6之间设有与承载皮带17配合的中间标准段2、储带仓部分3和驱动部分4。Also comprise tail part 1, middle standard section 2, storage tape warehouse part 3, drive part 4 and head part 6, the two ends of bearing belt 17 are supported by tail part 1 and head part 6, tail part 1 and head part 6 An intermediate standard section 2 , a storage bin 3 and a driving part 4 which cooperate with the carrying belt 17 are arranged between the head parts 6 .

所述的机尾部分1设在盾构机上,中间标准段2位于盾构机与竖井段底部之间,储带仓部分3设在中间标准段2的下侧,驱动部分4设在竖井段底部,机头部分6设在地表面。机尾部分、机头部分和中间标准段上设置转向托辊或滚筒对承载皮带进行支撑导向。The tail part 1 is set on the shield machine, the middle standard section 2 is located between the shield machine and the bottom of the shaft section, the belt storage bin part 3 is set on the lower side of the middle standard section 2, and the driving part 4 is set at the shaft section Bottom, the nose part 6 is located on the ground surface. Turning rollers or rollers are arranged on the tail part, the nose part and the middle standard section to support and guide the carrying belt.

机尾部分设在盾构机上,在盾构机的拉动下机尾部分带动承载皮带向前运动,中间标准段设在机尾与竖井段底部之间,随着盾构机向前移动,中间标准段逐段跟进安装,储带仓对承载皮带进行储存,驱动部分对承载皮带提供动力,机头设在地表面并对渣土进行卸料,在竖井段,压带部分压紧渣土带着渣土上升。The tail part is set on the shield machine. Under the pull of the shield machine, the tail part drives the carrying belt to move forward. The middle standard section is set between the tail and the bottom of the shaft section. As the shield machine moves forward, the middle section The standard section is followed up and installed section by section. The storage bin stores the load-bearing belt, and the drive part provides power to the load-bearing belt. The machine head is set on the ground surface to unload the muck. In the shaft section, the press belt part compresses the muck. Rising with muck.

压带部分由承载段皮带和压带配合,物料被夹在两条皮带之间,以保证大倾角输送时不落料,机架以物料提升倾角角度固定安装,连续皮带机的承载托辊组设置在机架底部,将连续皮带机的承载皮带直接延伸至机架内,压带靠压辊紧压在承载皮带上物料的表面,压辊铰接在连杆上,连杆中间部位铰接在压辊架上,使得压辊可以适应物料断面形状,始终保持对物料表面的压紧力,连杆一端的压辊将压带和承载皮带压在一起,保证不漏料,连杆另一端的压辊将渣土夹在压带和承载皮带之间,保证渣土不下落,压辊架由连接杆铰接在机架上,使得压辊架位置上下可以活动,压紧力由安装在压辊架上部的弹簧提供,弹簧另一端安装在机架顶部,高低位置可调,以提供不同的压紧力,压带由单独的驱动滚筒提供驱动力,同时要求压带与承载皮带具有相同的运行速度。The pressure belt part is matched by the load-bearing belt and the pressure belt. The material is clamped between the two belts to ensure that the material does not drop when conveying at a large inclination angle. The frame is fixed and installed at the angle of material lifting inclination. It is installed at the bottom of the frame, and the carrying belt of the continuous belt conveyor is directly extended into the frame. The pressure belt is pressed against the surface of the material on the carrying belt by the pressure roller. The pressure roller is hinged on the connecting rod, and the middle part of the connecting rod is hinged on the pressure roller. On the roller frame, the pressure roller can adapt to the cross-sectional shape of the material, and always maintain the pressing force on the surface of the material. The pressure roller at one end of the connecting rod presses the pressure belt and the carrying belt together to ensure no material leakage. The pressure roller at the other end of the connecting rod The roller clamps the dregs between the pressing belt and the carrying belt to ensure that the muck does not fall. The pressing roller frame is hinged on the frame by a connecting rod, so that the position of the pressing roller frame can move up and down. The pressing force is installed on the pressing roller frame. The upper spring is provided, and the other end of the spring is installed on the top of the frame. The height can be adjusted to provide different pressing forces. The pressing belt is driven by a separate driving roller, and the pressing belt and the carrying belt are required to have the same operating speed. .

物料横截面大小变化时,压带长度有较大的变化,且变化较为频繁,在压带上设置张紧装置,可以为重锤或电动绞车张紧,在压带长度变化时张紧或者放松压带,保证压带稳定运行。When the size of the cross-section of the material changes, the length of the pressing belt changes greatly, and the change is relatively frequent. A tensioning device is installed on the pressing belt, which can be used for tensioning by a heavy hammer or an electric winch, and can be tensioned or relaxed when the length of the pressing belt changes. Press the belt to ensure the stable operation of the press belt.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (7)

  1. A kind of 1. high inclination-angle continuous flush practice device for constructing metro tunnel, it is characterised in that:Pressure including being located at vertical shaft section Band part(5), pressure zone part(5)Including driving drum(7), pressure zone(8), rack(9)And bending roller(16), driving drum (7)And bending roller(16)It is located at both ends and and pressure zone(8)Coordinate, rack(9)It is located at driving drum(7)With bending roller(16) Between, rack(9)It is equipped with some carrying idlers(14)With the roller frame of activity(12), roller frame(12)With rack(9)Between Equipped with spring(11), roller frame(12)It is equipped with pressure roller(13), pressure roller(13)With pressure zone(8)Coordinate, carrying idler(14)With holding Carry belt(17)Coordinate, pressure roller(13)And carrying idler(14)By pressure zone(8), carrying belt(17)Force together.
  2. 2. the high inclination-angle continuous flush practice device according to claim 1 for constructing metro tunnel, it is characterised in that:It is described Rack(9)It is equipped with connecting plate(18), connecting plate(18)With connecting rod(10)It is flexibly connected, connecting rod(10)With roller frame (12)It is flexibly connected.
  3. 3. the high inclination-angle continuous flush practice device according to claim 1 for constructing metro tunnel, it is characterised in that:It is described Carrying idler(14)For flute profile, flute profile includes the tilting section at both ends and middle horizontal segment, roller frame(12)Both sides be equipped with Connecting rod, roller frame(12)With connecting rod(19)Middle part be flexibly connected, connecting rod(19)Both ends and pressure roller(13)It is flexibly connected, even Bar(19)The pressure roller of one end(13)With the pressure zone of horizontal segment(8)Coordinate, connecting rod(19)The pressure roller of the other end(13)With tilting section Pressure zone(8)Coordinate.
  4. 4. the high inclination-angle continuous flush practice device according to claim 1 for constructing metro tunnel, it is characterised in that:It is described Pressure zone(8)It is equipped with tensioning apparatus(15), tensioning apparatus(15)For weight or electric winch.
  5. 5. the high inclination-angle continuous flush practice device according to claim 1 for constructing metro tunnel, it is characterised in that:It is described Driving drum(7)Positioned at vertical shaft section bottom, bending roller(16)At the top of vertical shaft section.
  6. 6. the high inclination-angle continuous flush practice device according to claim 1 for constructing metro tunnel, it is characterised in that:Also wrap Include tail part(1), intermediate standard section(2), storage cassette holder part(3), drive part(4)And head section(6), carry belt (17)Both ends pass through tail part(1)And head section(6)Support, tail part(1)With head section(6)Between be equipped with Carry belt(17)The intermediate standard section of cooperation(2), storage cassette holder part(3)And drive part(4).
  7. 7. the high inclination-angle continuous flush practice device according to claim 6 for constructing metro tunnel, it is characterised in that:It is described Tail part(1)It is located on shield machine, intermediate standard section(2)Between shield machine and vertical shaft section bottom, cassette holder part is stored up (3)It is located at intermediate standard section(2)Downside, drive part(4)It is located at vertical shaft section bottom, head section(6)It is located at ground surface.
CN201711364033.4A 2017-12-18 2017-12-18 High inclination-angle continuous flush practice device for constructing metro tunnel Pending CN107916955A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711364033.4A CN107916955A (en) 2017-12-18 2017-12-18 High inclination-angle continuous flush practice device for constructing metro tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711364033.4A CN107916955A (en) 2017-12-18 2017-12-18 High inclination-angle continuous flush practice device for constructing metro tunnel

Publications (1)

Publication Number Publication Date
CN107916955A true CN107916955A (en) 2018-04-17

Family

ID=61893410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711364033.4A Pending CN107916955A (en) 2017-12-18 2017-12-18 High inclination-angle continuous flush practice device for constructing metro tunnel

Country Status (1)

Country Link
CN (1) CN107916955A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110356770A (en) * 2019-08-22 2019-10-22 中煤科工集团上海有限公司 A kind of vertical storage band device
CN110395552A (en) * 2018-10-24 2019-11-01 中煤张家口煤矿机械有限责任公司 A kind of airbag type bulk material continuous lifting equipment
CN119460532A (en) * 2024-12-27 2025-02-18 辽宁工程技术大学 A new type of belt-pressed large-angle belt conveyor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106089231A (en) * 2016-07-23 2016-11-09 车新宁 The device slagged tap continuously for subway work and the slag tapping method using this device
CN106144397A (en) * 2016-08-02 2016-11-23 华电郑州机械设计研究院有限公司 A kind of Novel clamp belt high inclination angle conveyer
CN206280078U (en) * 2016-12-18 2017-06-27 中铁二十局集团第五工程有限公司 Earth pressure balanced shield, EPBS construction belt-conveying muck removal device
CN207609444U (en) * 2017-12-18 2018-07-13 中铁工程装备集团有限公司 A kind of high inclination-angle continuous flush practice device for constructing metro tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106089231A (en) * 2016-07-23 2016-11-09 车新宁 The device slagged tap continuously for subway work and the slag tapping method using this device
CN106144397A (en) * 2016-08-02 2016-11-23 华电郑州机械设计研究院有限公司 A kind of Novel clamp belt high inclination angle conveyer
CN206280078U (en) * 2016-12-18 2017-06-27 中铁二十局集团第五工程有限公司 Earth pressure balanced shield, EPBS construction belt-conveying muck removal device
CN207609444U (en) * 2017-12-18 2018-07-13 中铁工程装备集团有限公司 A kind of high inclination-angle continuous flush practice device for constructing metro tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110395552A (en) * 2018-10-24 2019-11-01 中煤张家口煤矿机械有限责任公司 A kind of airbag type bulk material continuous lifting equipment
CN110356770A (en) * 2019-08-22 2019-10-22 中煤科工集团上海有限公司 A kind of vertical storage band device
CN119460532A (en) * 2024-12-27 2025-02-18 辽宁工程技术大学 A new type of belt-pressed large-angle belt conveyor

Similar Documents

Publication Publication Date Title
CN107187885A (en) A kind of pallet bin device
CN105035688B (en) Automatic conveying device for material disc
CN105692068A (en) Rail belt-type conveyor with rotary wheel structures
CN107916955A (en) High inclination-angle continuous flush practice device for constructing metro tunnel
CN101943024B (en) Whole pulling and moving type whole-process unloading belt conveyor for coal mine underground filling
CN108979710A (en) A kind of continuous slag tapping method of high inclination-angle for constructing metro tunnel
CN110816941A (en) Tray circulating line for destacking production line
CN212474888U (en) Plate arranging device
CN206384459U (en) A kind of scratch board conveyor
CN112027496A (en) Novel pinch roller device of belt conveyor
CN107824988A (en) A kind of electronic waste automatic cutting retracting device of energy-conserving and environment-protective
CN201763386U (en) Integral pulling and moving type whole-course unloading belt conveyor for coal mine downhole filling
CN207609444U (en) A kind of high inclination-angle continuous flush practice device for constructing metro tunnel
KR101421828B1 (en) Appratus for exchanging pulley in conveyor belt and method thereof
CN103625834B (en) The synchronous clamping convey device of a kind of biobelt
CN214217096U (en) Coal mine operation protection device
CN108861336B (en) Material lifting assembly
CN111285024A (en) Heading machine and slag discharging device thereof
CN103466274A (en) Discharging car with discharging direction capable of being adjusted
CN213536085U (en) Automatic lifting temporary storage rack
CN210064552U (en) Remove dummy car device of horizontal belt feeder is equipped with
CN205802313U (en) Transfer machine
CN114803376A (en) Bidirectional lifting conveyor
CN217674856U (en) Multi-specification pipe elevator
JP5317150B2 (en) Roller conveyor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180417