CN107855690B - A kind of construction taper pile top welding preheating device - Google Patents

A kind of construction taper pile top welding preheating device Download PDF

Info

Publication number
CN107855690B
CN107855690B CN201711141065.8A CN201711141065A CN107855690B CN 107855690 B CN107855690 B CN 107855690B CN 201711141065 A CN201711141065 A CN 201711141065A CN 107855690 B CN107855690 B CN 107855690B
Authority
CN
China
Prior art keywords
pile top
connector sleeve
taper pile
water conservancy
conservancy diversion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711141065.8A
Other languages
Chinese (zh)
Other versions
CN107855690A (en
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU FENGSHITANG ENGINEERING TECHNOLOGY Co.,Ltd.
Original Assignee
Xuzhou Huaxian Kaixing Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Huaxian Kaixing Information Technology Co Ltd filed Critical Xuzhou Huaxian Kaixing Information Technology Co Ltd
Priority to CN201711141065.8A priority Critical patent/CN107855690B/en
Publication of CN107855690A publication Critical patent/CN107855690A/en
Application granted granted Critical
Publication of CN107855690B publication Critical patent/CN107855690B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups

Abstract

A kind of construction taper pile top welding preheating device of the present invention discloses a kind of inner lining apparatus preheated by internal circulating oil path to taper pile top welding position.It is characterized in that conical flow guiding set outside is equipped with lines, water conservancy diversion stator is placed in conical flow guiding set, the water conservancy diversion stator is pyramidal structure, it and is solid, connection is placed on conical flow guiding set big end, partition is placed in connector sleeve, and it is connected with water conservancy diversion stator, the partition will be divided into two cavitys inside connector sleeve, helicla flute there are two being opened on the outside of the water conservancy diversion stator, described two helicla flute rotation directions are identical, and it is connected in water conservancy diversion stator small end, the oral area of described two helicla flutes is corresponding with two cavitys in connector sleeve respectively, cover board is placed on connector sleeve, the cover board is made of two semi-circular plates, described two semicircular rings are corresponding with two cavitys in connector sleeve respectively.

Description

A kind of construction taper pile top welding preheating device
Technical field
A kind of construction taper pile top of the present invention welds preheating device, when being related to a kind of construction, to taper pile top The inner lining apparatus preheated before being welded to welding position, belongs to the realm of building construction.In particular to one kind passes through inside The inner lining apparatus that circulating oil path preheats taper pile top welding position.
Background technique
Currently, commonly rushing drilled pile in building construction process and all using taper pile top, taper pile top passes through fan-shaped steel Plate welds by bending roll bending and forms pyramidal structure, due to the working environment of taper pile top, in the construction process, pile top meeting With hole stake inner wall occur CONTACT WITH FRICTION, it is very high to the welding requirements of taper pile top, avoid in the construction process pile top opened along weld seam Split, therefore in order to ensure welding quality, non-weld seam two sides needed to be preheated so that welding when, solder flux preferably and substrate knot It closes, avoids cracking in the root of weld, existing pre-heating mean passes through man-hour manually hand-held flame gun mostly and preheated, preheating time It is longer, and welding preheating position preheating temperature is uneven, is easy to happen weld seam deformed in tension, also has and pass through plate using clamping device Part is rotated, and heat gun orients the heating of bright eruption fire, so that plate preheats, but the direct flame of spray gun sprays roasting meeting so that plate table Face is attached with carbide particle, influences the cleannes on surface when welding, influences weldquality, and can not be by the rotation of plate Preheating temperature is kept the temperature in welding process, and open fire preheats and brings security risk to construction site.
Publication number CN105397354A discloses a kind of welding pre-heating mean of arc steel member, first by arc-shaped steel structure Part is set up on positioning support, then moves the fired heater being slidably mounted on circuit orbit along circuit orbit, The height of fired heater is adjusted simultaneously, is guaranteed the welding position of fired heater alignment arc steel member, is finally started flame Heater, fired heater are moved along circuit orbit and are preheated to welding position.Invention adjusts fire first on circuit orbit Flame heater makes it be directed at the welding preheating position of arc steel member, guarantees preheating accurate positioning;The invention is heated using flame The movement of device guarantees that preheating temperature reaches set temperature value range, is directly added on component by way of open fire, in component Surface forms carbide, so that component, in welding, weld seam, which exists, is mingled with influence weldquality.
Summary of the invention
In order to improve above situation, a kind of construction taper pile top welding preheating device of the present invention provides one kind and passes through The inner lining apparatus that internal circulating oil path preheats taper pile top welding position.
A kind of construction taper pile top welding preheating device of the present invention is achieved in that a kind of construction of the present invention Taper pile top welding preheating device is made of agent set and drainage device, and agent set is led by flowline, water conservancy diversion stator, taper Set, helicla flute, partition, connector sleeve, cover board, oil inlet pipe and semicircle ring gear composition are flowed, conical flow guiding set outside is equipped with lines, Water conservancy diversion stator is placed in conical flow guiding set, and the water conservancy diversion stator is pyramidal structure, and to be solid, and connection is placed on conical flow guiding set Big end, partition are placed in connector sleeve, and are connected with water conservancy diversion stator, and the partition will be divided into two cavitys inside connector sleeve, Helicla flute there are two opening on the outside of the water conservancy diversion stator, described two helicla flute rotation directions are identical, and are connected in water conservancy diversion stator small end, The oral area of described two helicla flutes is corresponding with two cavitys in connector sleeve respectively, and cover board is placed on connector sleeve, the cover board It is made of two semi-circular plates, described two semi-circular plates are corresponding with two cavitys in connector sleeve respectively, two semicircle ring gears point It is not placed on two semi-circular plates, and matches, oil inlet pipe and flowline are respectively placed on two semi-circular plates, and respectively and connector sleeve Interior corresponding cavity is connected, and drainage device is by driving gear, transmission gear, transmission shaft, bearing, impeller, protective plate and driving Motor form, driving gear are placed on the motor shaft of driving motor, and are placed between two semicircle ring gears, the driving gear and Two semicircle ring gears fit, and protective plate is placed on the semi-circular plate with oil inlet pipe, and are located at driving gear side, the protection Plate is curved plate-like structure, and two transmission shaft one end pass through two skies that bearing is placed in connector sleeve across two semi-circular plates respectively Intracavitary, impeller is placed in transmission shaft one end, and transmission gear is placed in the transmission shaft other end, and is meshed with driving gear.
In use, conical flow guiding set is put into taper pile top first when the welded seam to taper pile top preheats It is interior, and fit with taper pile top welding position, then oil inlet pipe is connected with external pipe respectively with flowline, is driven Motor work, motor shaft drives driving gear rotation, since driving gear and two semicircle ring gears fit, and then driving gear Cover board rotation is driven by two semicircle ring gears, and then cover board drives water conservancy diversion stator and conical flow guiding set entirety to exist by connector sleeve Rotation in taper pile top, and driving gear drives two driven gears rotation of engagement, and then two transmission shaft rotations, and Connected wheel rotation is driven respectively, meanwhile, hot oil is entered in connector sleeve in corresponding cavity by oil inlet pipe, and warp pair The impeller answered drives flowing, is then entered in corresponding helicla flute by corresponding helicla flute oral area, with water conservancy diversion stator Rotation is flowed along corresponding helicla flute, when flowing to water conservancy diversion stator small end, is flowed into another helicla flute of connection, then edge Helicla flute flowing, flowed into connector sleeve in the cavity for corresponding to flowline finally by helicla flute oral area, under the drive of impeller, It is flowed into external pipe by flowline, forms circulation, hot oil in along helicla flute flow process, lead by heat transfer to taper In stream set, it is transferred to taper pile top commissure through conical flow guiding set, and then preheat to taper pile top commissure;
The design of the protective plate can protect driving gear, prevent external environment from causing shadow to driving gear It rings, influences overall operation of the invention;
Textured design is set in conical flow guiding set outside, can be improved the heat dissipation effect of conical flow guiding set, Jin Erti Pre-heat effect of the height to taper pile top weld seam;
The impeller and two helical flute cooperations, and the transmitting of the rotation progress heat of conical flow guiding set is combined, to cone The structure design that shape pile top welding position is preheated, can be such that the welding position of taper pile top is heated evenly, and then make to weld Position preheating temperature is uniform, and then improves welding effect;
The structure preheated is designed by the circulation of hot oil in taper pile top welding position, does not use open fire, into Without causing safety accident, safety coefficient is high, and will not damage to welding position, and welding position will not generate carbon Compound particle, and then will not influence postorder welding, improve welding effect;
When reaching construction, welding position is preheated before being welded to taper pile top purpose.
Beneficial effect.
One, taper pile top weld seam welding effect is improved.
Two, can ensure to weld being heated evenly property.
Three, it can be improved the pre- thermal efficiency of plate.
Detailed description of the invention
Fig. 1 is the stereo-resolution figure that a kind of construction taper pile top of the present invention welds preheating device.
In attached drawing
Wherein part are as follows: driving gear (1), transmission gear (2), transmission shaft (3), bearing (4), flowline (5), impeller (6), water conservancy diversion stator (7), conical flow guiding set (8), helicla flute (9), partition (10), connector sleeve (11), cover board (12), protective plate (13), oil inlet pipe (14), semicircle ring gear (15), driving motor (16).
Specific embodiment:
A kind of construction taper pile top welding preheating device of the present invention is achieved in that in use, when to tapered pile Conical flow guiding set (8) is put into taper pile top when being preheated by the welded seam of point first, and with taper pile top welding position It sets and fits, then oil inlet pipe (14) is connected with external pipe respectively with flowline (5), driving motor (16) work, electricity Arbor drives driving gear (1) rotation, since driving gear (1) and two semicircle ring gears (15) fit, and then driving gear (1) cover board (12) rotation is driven by two semicircle ring gears (15), and then cover board (12) drives water conservancy diversion fixed by connector sleeve (11) Sub (7) and conical flow guiding set (8) integrally rotate in taper pile top, and driving gear (1) drives two driven tooths of engagement Wheel rotation, and then two transmission shaft (3) rotations, and connected impeller (6) is driven to rotate respectively, meanwhile, hot oil passes through oil inlet Pipe (14) enters in connector sleeve (11) in corresponding cavity, and drives and flow through corresponding impeller (6), then passes through correspondence Helicla flute (9) oral area enter in corresponding helicla flute (9), with the rotation of water conservancy diversion stator (7), along corresponding helicla flute (9) it flows, when flowing to water conservancy diversion stator (7) small end, flows into another helicla flute (9) of connection, flowed then along helicla flute (9) It is dynamic, it is flowed into connector sleeve (11) in the cavity for corresponding to flowline (5) finally by helicla flute (9) oral area, the drive in impeller (6) Under, it is flowed into external pipe by flowline (5), forms circulation, in along helicla flute (9) flow process, heat passes hot oil It is handed in conical flow guiding set (8), is transferred to taper pile top commissure through conical flow guiding set (8), and then to taper pile top commissure It is preheated;
The design of the protective plate (13) can protect driving gear (1), prevent external environment to driving gear (1) it impacts, influences overall operation of the invention;
Textured design is set on the outside of the conical flow guiding set (8), can be improved the heat dissipation effect of conical flow guiding set (8), And then raising is to the pre-heat effect of taper pile top weld seam;
The impeller (6) and two helical flute cooperations, and combine the biography of the rotation progress heat of conical flow guiding set (8) It passs, the structure preheated to taper pile top welding position designs, and the welding position of taper pile top can be made to be heated evenly, in turn Keep welding position preheating temperature uniform, and then improves welding effect;
The structure preheated is designed by the circulation of hot oil in taper pile top welding position, does not use open fire, into Without causing safety accident, safety coefficient is high, and will not damage to welding position, and welding position will not generate carbon Compound particle, and then will not influence postorder welding, improve welding effect;
When reaching construction, welding position is preheated before being welded to taper pile top purpose.

Claims (6)

1. a kind of construction taper pile top welds preheating device, it is characterized in that: being made of agent set and drainage device, main body Device is by flowline, water conservancy diversion stator, conical flow guiding set, helicla flute, partition, connector sleeve, cover board, oil inlet pipe and semicircle ring gear group At water conservancy diversion stator is placed in conical flow guiding set, and connection is placed on conical flow guiding set big end, and partition is placed in connector sleeve, and and is led Stream stator is connected, and the partition will be divided into two cavitys inside connector sleeve, opens that there are two spirals on the outside of the water conservancy diversion stator Slot, described two helicla flute rotation directions are identical, and are connected in water conservancy diversion stator small end, the oral area of described two helicla flutes respectively and even Two cavitys in female connector are corresponding, and cover board is placed on connector sleeve, and the cover board is made of two semi-circular plates, described two semicircles Plate is corresponding with two cavitys in connector sleeve respectively, and two semicircle ring gears are respectively placed on two semi-circular plates, and are matched, into Oil pipe and flowline are respectively placed on two semi-circular plates, and are connected respectively with cavity corresponding in connector sleeve, drainage device by Driving gear, transmission gear, transmission shaft, bearing, impeller, protective plate and driving motor composition, driving gear are placed in driving motor Motor shaft on, and be placed between two semicircle ring gears, the driving gear and two semicircle ring gears fit, and protective plate is placed in On semi-circular plate with oil inlet pipe, and it is located at driving gear side, two transmission shaft one end pass through bearing across two and half respectively Plectane is placed in two in connector sleeve cavitys, and impeller is placed in transmission shaft one end, and transmission gear is placed in the transmission shaft other end, and and Driving gear is meshed.
2. a kind of construction taper pile top according to claim 1 welds preheating device, it is characterised in that the taper Lines is equipped on the outside of flow guide sleeve.
3. a kind of construction taper pile top according to claim 1 welds preheating device, it is characterised in that the water conservancy diversion Stator is pyramidal structure, and is solid.
4. a kind of construction taper pile top according to claim 1 welds preheating device, it is characterised in that the protection Plate is curved plate-like structure.
5. a kind of construction taper pile top according to claim 1 welds preheating device, it is characterised in that the impeller Cooperate with two helical flutes, and the rotation of conical flow guiding set combined to carry out the transmitting of heat, to taper pile top welding position into Row preheating.
6. a kind of construction taper pile top welds preheating device according to claim 1 or 5, it is characterised in that the cone Shape pile top welding position is by the circulation of hot oil to preheating.
CN201711141065.8A 2017-11-17 2017-11-17 A kind of construction taper pile top welding preheating device Active CN107855690B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711141065.8A CN107855690B (en) 2017-11-17 2017-11-17 A kind of construction taper pile top welding preheating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711141065.8A CN107855690B (en) 2017-11-17 2017-11-17 A kind of construction taper pile top welding preheating device

Publications (2)

Publication Number Publication Date
CN107855690A CN107855690A (en) 2018-03-30
CN107855690B true CN107855690B (en) 2019-10-01

Family

ID=61702020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711141065.8A Active CN107855690B (en) 2017-11-17 2017-11-17 A kind of construction taper pile top welding preheating device

Country Status (1)

Country Link
CN (1) CN107855690B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4386813B2 (en) * 2004-08-27 2009-12-16 株式会社コベルコ マテリアル銅管 Heat transfer tube with inner groove for evaporator
CN102444977B (en) * 2010-10-12 2014-05-07 朱忠日 Device for heating oil-water mixture
CN201969728U (en) * 2010-12-16 2011-09-14 邢台纳科诺尔极片轧制设备有限公司 Conduction oil heating roller
CN202442625U (en) * 2012-02-18 2012-09-19 董斌 Energy-saving self-cleaning pipe
CN103061333B (en) * 2013-01-07 2014-12-31 广东保威新能源有限公司 Split screw pile and welding method thereof

Also Published As

Publication number Publication date
CN107855690A (en) 2018-03-30

Similar Documents

Publication Publication Date Title
CN107470080B (en) A kind of application method of metal tube hot spraying device
CN107855690B (en) A kind of construction taper pile top welding preheating device
CN104722912B (en) Track-following-type friction-stir-welding device for pipeline and welding method
CN107524620A (en) A kind of centrifugal hot air circulation blower
CN109570696A (en) A kind of water cooling tube rotation surfacing equipment
CN105817731A (en) Circumferential automatic brazing welding equipment for pipes
CN210587575U (en) Rotary welding head for welding device
WO2022016614A1 (en) High-efficiency heat absorption device for hot galvanizing pot
CN103205553B (en) Quenching inductor for concave spherical surface of scraper knife connecting seat and determination method of matched size
CN209532370U (en) A kind of water cooling tube rotation surfacing equipment
CN206469667U (en) A kind of energy-conserving and environment-protective mineral hot furnace for being easy to feed
CN207104129U (en) Online for hydraulic support welding automates preheating device by formula
CN110258211A (en) A kind of lithium electricity drilling of the rail device
CN203703982U (en) Combustor and combustion furnace
CN110319582A (en) A kind of hot-blast stove of automatic control
CN206122855U (en) Soldering rotary device
CN108165723A (en) A kind of solution device for bearing
CN202329133U (en) Melting furnace group
CN211680455U (en) Heating device for build-up welding of inner wall of seal head
CN107606952B (en) Metallurgical furnace feeding device
CN209326386U (en) A kind of fume afterheat high efficiente callback device
CN105014231B (en) A kind of aluminium alloy pipe end composite seal device and encapsulating method
CN216264547U (en) Aluminum pipe coalignment convenient to remove fixedly
CN215062051U (en) Heat preservation stove with variable angle combustor
CN216656211U (en) Natural gas stove controlling means is used in forging production and processing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200402

Address after: 215000 6th Floor, Building C, Suzhou Design Town, No. 9 Jinpu Road, Suzhou Industrial Park, Jiangsu Province

Patentee after: SUZHOU FENGSHITANG ENGINEERING TECHNOLOGY Co.,Ltd.

Address before: Quanshan District mausoleum building 221008 Jiangsu city of Xuzhou province people rational number 58

Patentee before: XUZHOU HUAXIAN KAIXING INFORMATION TECHNOLOGY Co.,Ltd.