- CN107853913A CN107853913A CN201710954305.XA CN201710954305A CN107853913A CN 107853913 A CN107853913 A CN 107853913A CN 201710954305 A CN201710954305 A CN 201710954305A CN 107853913 A CN107853913 A CN 107853913A
- Authority
- CN
- China
- Prior art keywords
- stone bench
- support
- reinforced concrete
- stool
- cut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000004575 stone Substances 0.000 title claims abstract description 67
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 44
- 238000000034 method Methods 0.000 title claims abstract description 25
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 13
- 238000005520 cutting process Methods 0.000 claims abstract description 41
- 238000005452 bending Methods 0.000 claims abstract description 7
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 5
- 230000002787 reinforcement Effects 0.000 claims description 15
- 239000004567 concrete Substances 0.000 claims description 7
- 230000011218 segmentation Effects 0.000 claims description 6
- 238000012545 processing Methods 0.000 claims description 5
- 238000005266 casting Methods 0.000 claims description 3
- 238000013461 design Methods 0.000 claims description 3
- 238000005498 polishing Methods 0.000 claims description 3
- 239000002699 waste material Substances 0.000 abstract description 7
- 239000004035 construction material Substances 0.000 abstract description 3
- 238000009435 building construction Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 210000003205 muscle Anatomy 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000001154 acute effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 239000004579 marble Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- A—HUMAN NECESSITIES
- A47—FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
- A47C—CHAIRS; SOFAS; BEDS
- A47C11/00—Benches not otherwise provided for
-
- A—HUMAN NECESSITIES
- A47—FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
- A47C—CHAIRS; SOFAS; BEDS
- A47C5/00—Chairs of special materials
Landscapes
- Tires In General (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The invention discloses a kind of method of reinforced concrete support manufacture municipal park stone bench, the reinforced concrete support for carrying out pattern foundation pit supporting structure is subjected to secondary use, staged and layered cutting is carried out to support using rope saw cut method, the stone bench for supplying people to rest in public places of entertainment such as parks is formed after bending grinding process is carried out to the support after cutting, there is reinforcing bar in the stool surface and stool leg in stone bench simultaneously and be not turned off, stress performance is preferable, it is not only able to reduce the discharge of building waste, construction material can also be saved, turn waste into wealth, meet the requirement of current Green environmental-protection building construction.
Description
Technical field
The present invention relates to municipal field is built, more particularly to a kind of reinforced concrete support manufactures municipal park stone bench
Method.
Background technology
In engineering typically higher to pattern foundation pit supporting structure requirement, it is a kind of normal to carry out pattern foundation pit supporting structure using reinforced concrete support
Way, but reinforced concrete support structure is abolished after basement construction terminates, and carried out as building waste
Corresponding abandonment processing, not only causes the waste of construction material, generates more building waste, and be also consumed by certain
Human and material resources and financial resources, it is unsatisfactory for the requirement currently to green building, green construction.
At present, with can not be kept away in the amusement and leisure recreating facility such as the continuous development of urbanization, city incity park
The meeting exempted from provides some for entertainment or rest crowd has a rest or the tool for taking rest of the stone bench rested or other tables and chairs etc, these works
Tool is typically all that factory is prefabricated using marble or other advanced stones, and cost is increased, and stress performance is bad.
The content of the invention
A kind of the defects of it is an object of the invention to overcome prior art, there is provided reinforced concrete for meeting environment protection requirement
The method of soil support manufacture municipal park stone bench, the technical scheme of the reinforced concrete support manufacture municipal park stone bench
It is realized in:
A kind of method of reinforced concrete support manufacture municipal park stone bench, is mainly included the following steps that:
(1) treat that reinforced concrete support rectangular structure floor pours completion and reaches more than the 80% of design strength, wait to tear open
The dismounting that the reinforced concrete support removed is supported using rope saw cut method;
(2) reinforced concrete support removed is rule according to the overall length dimension of stone bench, entered to the layout line
The overall cutting of row, obtains the larger support cut length of thickness after cutting;
(3) will branch according to the stool surface and stool pin thickness of stone bench the support cut length Slice by slice cutting cut down, during cutting
The Reinforcement supportted in cut length is centrally located, obtains the support layering identical with stone bench total length and thickness and cuts
Cut section;
(4) V-groove in 90 ° of angles is cut out below the Reinforcement of the intersection of the stool surface and stool leg of stone bench,
A cut-off rule is cut open above at the vertex correspondence of V-groove;
(5) reinforcing bar and support Slice by slice cutting section are carried out 90 ° simultaneously at the V-groove of the stool surface and stool leg intersection of stone bench
Bending, preliminarily forms stone bench basic structure, and groove is formed at stool pin and stool surface;
(6) in stool pin and the groove casting concrete of the intersection of stool surface, the stone bench of completion is formed;
(7) newly-laid concrete of stool pin and stool surface and groove is carried out polishing smooth processing and obtains complete stone bench knot
Structure.
Further, 90 ° of V-grooves are axisymmetricly set along apex, and the V-groove is completely heavy after folding
Close.
Further, the Reinforcement in the stool surface and stool leg of the stone bench is not turned off before and after bending
's.
Further, the total length of the stone bench includes the stool surface length of stone bench and the summation of both ends stool pin length.
Further, the stool surface thickness of the stone bench and stool pin thickness are identicals.
Further, the specific step cut in the step (1) to reinforced concrete support using rope saw cut method
It is rapid as follows:
(1) first determine reinforced concrete support cutting sequence, first cutting support both sides to support;
(2) segmentation division and then according to the size modulus of stone bench is carried out to main brace, entered according to the order of first intermediate and then both sides
Row rope saw cut, when specifically cutting, the cutting support lower section is used before being cut to interlude main brace and both ends main brace
Load-bearing bearing is supported.
Beneficial effects of the present invention are:The reinforced concrete support for carrying out pattern foundation pit supporting structure is subjected to secondary use, using rope
Saw cut method carries out staged and layered cutting to support, and the support after cutting is carried out to be formed after bending grinding process to give pleasure in park etc.
Happy place supplies the stone bench of people's rest, while has in the stool surface and stool leg in stone bench and reinforcing bar and be not turned off, stress performance compared with
It is good, it is not only able to reduce the discharge of building waste, additionally it is possible to save construction material, turn waste into wealth, meet currently green build
Build the requirement of construction.
Brief description of the drawings
Fig. 1 is that reinforced concrete support cutting planes of the present invention arrange schematic diagram;
Fig. 2 is reinforced concrete support cross-sectional configuration of the present invention and segmentation schematic diagram;
Fig. 3 is reinforced concrete support longitudinal plane structure of the present invention and segmentation schematic diagram;
Fig. 4 is the structural representation after reinforced concrete support layer and section of the present invention cutting;
Fig. 5 is formation stone bench structural representation after reinforced concrete support of the present invention bending;
Fig. 6 is the three dimensional structure diagram of stone bench of the present invention.
Reference:1- reinforced concrete supports, 2- is to support, 3- load-bearing bearings, 4- stone benches, the support of 11- interludes, 12-
Support Part II, 13- support Part III, 41- stool surfaces, 42- stool pin, 43-V type grooves, 44- cut-off rules, 45- grooves, 101-
Top Reinforcement, 102- centres waist muscle, 103- bottoms Reinforcement, 104- Slice by slice cutting lines.
Embodiment
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
As shown in figs. 1 to 6, a kind of method of reinforced concrete support manufacture municipal park stone bench, mainly including following
Step:
(1) treat that the rectangular structure floor of reinforced concrete support 1 pours completion and reaches more than the 80% of design strength, wait to tear open
The dismounting that the reinforced concrete support 1 removed is supported using rope saw cut method;
(2) reinforced concrete support 1 removed is rule according to the overall length dimension of stone bench 4, to the layout line
Overall cutting is carried out, the larger support cut length of thickness is obtained after cutting;
(3) according to the stool surface 41 and the thickness of stool pin 42 of stone bench 4 the support cut length cut down by Slice by slice cutting line 104
Slice by slice cutting is carried out, will support the Reinforcement in cut length during cutting, including it is top Reinforcement 101, middle
Waist muscle 102 and bottom Reinforcement 103, the centre position of support cut length is placed in, is obtained and the total length of stone bench 4 and thickness
Identical support Slice by slice cutting section;Certainly, when it is implemented, the Slice by slice cutting of reinforced concrete support 1 is according to the reality of support
Reinforcement in border size and support sets and specifically carries out layering setting, layering and longitudinal stress steel in the present embodiment
Muscle quantity is only to illustrate, the embodiment not limited to this that the present invention includes;
(4) stone bench 4 stool surface 41 and stool pin 42 intersection Reinforcement (101,102,103) below cut
Go out the V-groove 43 in 90 ° of angles, when it is implemented, the quantity of V-groove 43 is 2, the top at the vertex correspondence of V-groove 43
Cut a cut-off rule 44 open;
(5) at the stool surface 41 of stone bench 4 and the V-groove 43 of the intersection of stool pin 42 by Reinforcement (101,102,
103) and support Slice by slice cutting section carries out 90 ° of bendings simultaneously, preliminarily forms stone bench basic structure, the shape at stool pin 42 and stool surface 41
Into groove 45;
(6) casting concrete at the groove 45 of stool pin 42 and the intersection of stool surface 41, the stone bench of completion is formed;
(7) newly-laid concrete at stool pin 42 and stool surface 41 and groove 45 is carried out polishing smooth processing and obtains complete stone
Stool structure.
When it is implemented, described 90 ° of V-groove 43 is axisymmetricly set along apex, the V-groove 43 is folding
After be completely superposed;Certainly when it is implemented, being carried out when can be folded to V-groove 43 using concrete interface agent or other adhesives
Interface processing so that there is larger bond between stool surface 41 and stool pin 42.
When it is implemented, the Reinforcement (101,102,103) in the stool surface 41 and stool pin 4 of the stone bench 4 is curved
It is not turned off before and after folding, due to containing reinforcing bar in stone bench 4, therefore there is fabulous stress performance, can bear larger
Bearing capacity.
When it is implemented, the total length of the stone bench 4 includes the length of the stool surface 41 of stone bench 4 and the length of both ends stool pin 42
Summation.
When it is implemented, the thickness of the stool surface 41 of the stone bench 4 and the thickness of stool pin 42 are identicals.
When it is implemented, it is specific to use rope saw cut method to be cut in the step (1) to reinforced concrete support
Step is as follows:
(1) first determine reinforced concrete support 1 cutting sequence, first cutting support both sides to support 2;
(2) segmentation division and then according to the size modulus of stone bench 4 is carried out to reinforced concrete support 1, behind first centre
The order on both sides carries out rope saw cut, right before being cut to interlude support 11 and both ends support (12,13) when specifically cutting
Cutting support lower section is supported using load-bearing bearing 3.
When it is implemented, when being cut to reinforced concrete support 1, by reinforced concrete support 1 according to stone bench 4
Size modulus carries out segmentation cutting, and specifically segments during cutting is according to the length of reinforced concrete support 1 and the size of stone bench 4
Specific to determine, the cutting section number in the present embodiment is only to illustrate, and certain embodiments of the invention are not limited only to this.
As the other embodiment of the present invention, the stool surface 41 of stone bench 4 and the angle of stool pin 42 are not necessarily intersecting in 90 °, can
Set with an acute angle or oblique-angle intersection, when it is implemented, only needing to carry out the angle of the V-groove 43 in the above method accordingly
Change, you can realize;Certainly, the stool pin 42 at both ends can also differ with the intersecting angle of stool surface 41, can equally realize, herein
No longer repeat one by one;Due to containing steel bar stress in the stool surface 41 among stone bench 4 and stool pin 42, therefore even if present acute angle or
During obtuse angle, larger bearing capacity can be also born.
The technology contents and technical characteristic of the present invention have revealed that as above those skilled in the art are still potentially based on this
The teaching of invention and make the replacement and modification without departing substantially from essence of the invention, therefore, the scope of the present invention is not limited to embodiment
Disclosed content, also including various replacements and modification without departing substantially from essence of the invention.
Claims (6)
- A kind of 1. method of reinforced concrete support manufacture municipal park stone bench, it is characterised in that:Methods described mainly includes Following steps:(1) treat that reinforced concrete support rectangular structure floor pours completion and reaches more than the 80% of design strength, it is to be removed The dismounting that reinforced concrete support is supported using rope saw cut method;(2) reinforced concrete support removed is rule according to the overall length dimension of stone bench, carried out to the layout line total The cutting of body, the larger support cut length of thickness is obtained after cutting;(3) support is cut according to the stool surface and stool pin thickness of stone bench the support cut length Slice by slice cutting cut down, during cutting The Reinforcement cut in section is centrally located, obtains the support Slice by slice cutting identical with stone bench total length and thickness Section;(4) V-groove in 90 ° of angles is cut out below the Reinforcement of the intersection of the stool surface and stool leg of stone bench, in V-type Cut a cut-off rule above at the vertex correspondence of groove open;(5) by reinforcing bar and support Slice by slice cutting section, 90 ° of progress is curved simultaneously at the V-groove of the stool surface and stool leg intersection of stone bench Folding, preliminarily forms stone bench basic structure, and groove is formed at stool pin and stool surface;(6) in stool pin and the groove casting concrete of the intersection of stool surface, the stone bench of completion is formed;(7) newly-laid concrete of stool pin and stool surface and groove is carried out polishing smooth processing and obtains complete stone bench structure.
- 2. the method for reinforced concrete support manufacture municipal park stone bench according to claim 1, it is characterised in that:Institute State 90 ° of V-grooves axisymmetricly to set along apex, the V-groove is completely superposed after folding.
- 3. the method for reinforced concrete support manufacture municipal park stone bench according to claim 2, it is characterised in that:Institute The Reinforcement stated in the stool surface and stool leg of stone bench is not turned off before and after bending.
- 4. the method for reinforced concrete support manufacture municipal park stone bench according to claim 1, it is characterised in that:Institute Stating the total length of stone bench includes the stool surface length of stone bench and the summation of both ends stool pin length.
- 5. the method for reinforced concrete support manufacture municipal park stone bench according to claim 1, it is characterised in that:Institute The stool surface thickness and stool pin thickness for stating stone bench are identicals.
- 6. the method for reinforced concrete support manufacture municipal park stone bench according to claim 1, it is characterised in that:Institute State in step (1) and reinforced concrete support is comprised the following steps that using what rope saw cut method was cut:(1) first determine reinforced concrete support cutting sequence, first cutting support both sides to support;(2) segmentation division and then according to the size modulus of stone bench is carried out to main brace, restricted according to the order of first intermediate and then both sides Saw cut, when specifically cutting, load-bearing is used to the cutting support lower section before being cut to interlude main brace and both ends main brace Bearing is supported.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710954305.XA CN107853913B (en) | 2017-10-13 | 2017-10-13 | Method for manufacturing stone stool for municipal park through reinforced concrete support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710954305.XA CN107853913B (en) | 2017-10-13 | 2017-10-13 | Method for manufacturing stone stool for municipal park through reinforced concrete support |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107853913A true CN107853913A (en) | 2018-03-30 |
CN107853913B CN107853913B (en) | 2021-08-10 |
Family
ID=61698534
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710954305.XA Expired - Fee Related CN107853913B (en) | 2017-10-13 | 2017-10-13 | Method for manufacturing stone stool for municipal park through reinforced concrete support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107853913B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU199530U1 (en) * | 2020-03-11 | 2020-09-07 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Казанский государственный архитектурно-строительный университет" (КазГАСУ) | C-SHAPED BENCH MADE ON A 3D PRINTER |
RU211125U1 (en) * | 2021-09-01 | 2022-05-23 | Федеральное государственное бюджетное образовательное учреждение высшего образования «Казанский государственный архитектурно-строительный университет» (КазГАСУ) | LIGHTWEIGHT FIBER CONCRETE REINFORCED C-SHAPED BENCH MADE ON A 3D PRINTER |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000201774A (en) * | 1999-01-11 | 2000-07-25 | Ogasawara:Kk | Bench |
CN201171507Y (en) * | 2008-03-28 | 2008-12-31 | 成都市武侯专利咨询研发转化研究所 | Pure glass art bar stool |
CN201356294Y (en) * | 2009-01-13 | 2009-12-09 | 李平 | Park bench |
CN201550925U (en) * | 2009-12-10 | 2010-08-18 | 蒋清校 | Multifunctional bench |
CN201861184U (en) * | 2010-10-15 | 2011-06-15 | 陕西天和照明设备工程有限公司 | Outdoor landscape chair |
CN201968178U (en) * | 2011-04-24 | 2011-09-14 | 朱一军 | Stool |
CN202173024U (en) * | 2011-07-22 | 2012-03-28 | 彭建春 | Redwood furniture |
CN202312264U (en) * | 2011-11-04 | 2012-07-11 | 武倩男 | Integral type stone chair |
CN102781282A (en) * | 2009-11-10 | 2012-11-14 | 时代革命有限公司 | Reinforced cellular structure |
CN204862087U (en) * | 2015-07-30 | 2015-12-16 | 天津市鑫瑞阳景观材料科技有限公司 | Semicircle bench |
CN106880202A (en) * | 2017-03-29 | 2017-06-23 | 广西棕海园林工程有限公司 | Outdoor landscape stone bench |
CN107149321A (en) * | 2017-04-27 | 2017-09-12 | 广西棕海园林工程有限公司 | Garden seat |
-
2017
- 2017-10-13 CN CN201710954305.XA patent/CN107853913B/en not_active Expired - Fee Related
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000201774A (en) * | 1999-01-11 | 2000-07-25 | Ogasawara:Kk | Bench |
CN201171507Y (en) * | 2008-03-28 | 2008-12-31 | 成都市武侯专利咨询研发转化研究所 | Pure glass art bar stool |
CN201356294Y (en) * | 2009-01-13 | 2009-12-09 | 李平 | Park bench |
CN102781282A (en) * | 2009-11-10 | 2012-11-14 | 时代革命有限公司 | Reinforced cellular structure |
CN201550925U (en) * | 2009-12-10 | 2010-08-18 | 蒋清校 | Multifunctional bench |
CN201861184U (en) * | 2010-10-15 | 2011-06-15 | 陕西天和照明设备工程有限公司 | Outdoor landscape chair |
CN201968178U (en) * | 2011-04-24 | 2011-09-14 | 朱一军 | Stool |
CN202173024U (en) * | 2011-07-22 | 2012-03-28 | 彭建春 | Redwood furniture |
CN202312264U (en) * | 2011-11-04 | 2012-07-11 | 武倩男 | Integral type stone chair |
CN204862087U (en) * | 2015-07-30 | 2015-12-16 | 天津市鑫瑞阳景观材料科技有限公司 | Semicircle bench |
CN106880202A (en) * | 2017-03-29 | 2017-06-23 | 广西棕海园林工程有限公司 | Outdoor landscape stone bench |
CN107149321A (en) * | 2017-04-27 | 2017-09-12 | 广西棕海园林工程有限公司 | Garden seat |
Non-Patent Citations (1)
Title |
---|
中华人民共和国住房和城市建设部: "《混凝土结构设计规范GB50010-2010》", 31 December 2015 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU199530U1 (en) * | 2020-03-11 | 2020-09-07 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Казанский государственный архитектурно-строительный университет" (КазГАСУ) | C-SHAPED BENCH MADE ON A 3D PRINTER |
RU211125U1 (en) * | 2021-09-01 | 2022-05-23 | Федеральное государственное бюджетное образовательное учреждение высшего образования «Казанский государственный архитектурно-строительный университет» (КазГАСУ) | LIGHTWEIGHT FIBER CONCRETE REINFORCED C-SHAPED BENCH MADE ON A 3D PRINTER |
RU211298U1 (en) * | 2021-09-01 | 2022-05-30 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Казанский государственный архитектурно-строительный университет" (КазГАСУ) | 3D printed concrete bench |
Also Published As
Publication number | Publication date |
---|---|
CN107853913B (en) | 2021-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104446257B (en) | A kind of mixed sand self-compacting concrete and pouring construction method thereof | |
Binard | UHPC: A game-changing material for PCI bridge producers. | |
CN107853913A (en) | A kind of method of reinforced concrete support manufacture municipal park stone bench | |
Elbakry et al. | Factors affecting bond strength of RC column jackets | |
Nowak | Application of Voronoi diagrams in contemporary architecture and town planning | |
Gray | Cast steel yielding brace system for concentrically braced frames | |
CN202391036U (en) | House steel ladder with multistory and high-rise steel structure | |
Anwar | Practical techniques for restoration of architectural formation elements in historical buildings | |
Adriaenssens et al. | Structural analysis of reinforced concrete folded hyperbolic paraboloid: a case study of the modern miami marine stadium | |
CN102672828B (en) | Finish machining process of stone material dual/multi-splicing cylinder | |
CN107165317A (en) | It is a kind of to be used for the steel disc shape node component and application process of special-shaped Curtain wall frame | |
CN104213728B (en) | Oblique beam for grandstand of stadium and construction process for oblique beam | |
Eisenbach | Processing of Slender Concrete Shells-Fabrication and Installation | |
Boen | Observed reconstruction of houses in Aceh seven months after the great Sumatra earthquake and Indian Ocean tsunami of December 2004 | |
CN105985086A (en) | Cement imitation wood component and preparation method thereof | |
CN206034946U (en) | Structure is handled to large -scale pressure vertical shaft concrete defect based on slipform technology | |
CN205530681U (en) | Close rib composite wall panel structure system of bevel | |
CN203160237U (en) | Anti-floating anchor rod structure of raft | |
CN206567659U (en) | A kind of portable circle-cutting machine for being applied to circular thick plates cutting | |
Anderson | Fabrication and construction methods for low-cost, low-carbon structural components for housing in India | |
CN108298406A (en) | A kind of elevator frame component with glass shell | |
CN108331160A (en) | A kind of stair shaft frame unit | |
HABAS | The architectural heritage of the cities of the Decapolis in the Byzantine churches of Transjordan | |
Fonte | Building the Great Pyramid in about 385 days: A case study in energy management | |
CN106760189A (en) | Tall building structure transfer beam construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210810 |