CN107839920B - Combined tool for fire hose binding and use method of combined tool - Google Patents

Combined tool for fire hose binding and use method of combined tool Download PDF

Info

Publication number
CN107839920B
CN107839920B CN201711274214.8A CN201711274214A CN107839920B CN 107839920 B CN107839920 B CN 107839920B CN 201711274214 A CN201711274214 A CN 201711274214A CN 107839920 B CN107839920 B CN 107839920B
Authority
CN
China
Prior art keywords
binding
iron wire
winding
ring
fire hose
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711274214.8A
Other languages
Chinese (zh)
Other versions
CN107839920A (en
Inventor
江懿霏
郑凯修
杨光远
江志平
何海生
田海明
徐雅悯
沈涛
王朝瑞
周玲玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Wanna Nuclear Power Maintenance Co ltd
Original Assignee
Zhejiang Wanna Nuclear Power Maintenance Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Wanna Nuclear Power Maintenance Co ltd filed Critical Zhejiang Wanna Nuclear Power Maintenance Co ltd
Priority to CN201711274214.8A priority Critical patent/CN107839920B/en
Publication of CN107839920A publication Critical patent/CN107839920A/en
Application granted granted Critical
Publication of CN107839920B publication Critical patent/CN107839920B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65BMACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
    • B65B13/00Bundling articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)
  • Clamps And Clips (AREA)

Abstract

The invention discloses a combination tool for binding a fire hose and a use method of the combination tool, which designs a detachable fixing table, a detachable clamp for clamping a metal joint, a binding device for binding iron wires and the like, wherein the combination tool is convenient to detach and can be installed in a tool box for carrying, and can be quickly assembled and used in different occasions. By utilizing the combined tool and the use method thereof, the fire hose capable of bearing the water pressure of 1.4MP can be quickly bound, time and labor are saved, the working efficiency and the overhaul quality of fire-fighting maintainers are improved, and the combined tool can be suitable for fire-fighting overhaul in special complex fields such as nuclear power and the like.

Description

Combined tool for fire hose binding and use method of combined tool
Technical Field
The invention relates to the technical field of binding tools, in particular to a combination tool for binding a fire hose and a use method of the combination tool.
Background
The fire hose is an important component of a fire hydrant fire extinguishing system, and is a hose for conveying high-pressure water or fire-retardant liquid such as foam and the like when extinguishing fire. Because in the fire extinguishing process, the fire hose bears water pressure of 0.8MP, 1.0MP, 1.3MP, 1.6MP or higher, if the fire hose is not firmly bound, the water hose and the metal interface are tripped and water leakage occurs, the fire extinguishing purpose cannot be achieved, the fire extinguishing effect is affected or personnel are injured. At present, various convenient fire hose binding modes exist, such as metal binding band binding, bolt binding and the like, but the iron wire binding mode is still the most extensive, convenient and firm mode through comprehensive comparison.
The traditional iron wire ligature mode that uses needs 2-3 people to fix fire hose and metal interface earlier, uses tools such as pliers, spanner to twine the ligature, because be equipped with the ligature groove that twice was used for connecting the fire hose on the metal interface generally, its ligature process is very waste time and energy, has very big relation moreover with ligature staff's physical power, the infirm condition of ligature often can appear, the water leakage will appear, problem such as release.
Because the fire-fighting requirements are very strict in large industrial areas, especially in nuclear power stations, the daily fire-fighting water pressure is above 1.0MP, the water pressure which fire-fighting water belts generally need to bear is about 1.3MP, and a great deal of manpower and time cost are spent for the traditional binding mode to meet the requirements. In order to better meet the pressure-resistant requirement of a water hose and save labor time and cost, under the research background, the fire hose binding combination tool is designed, the binding efficiency is improved, the fire hose binding combination tool is convenient to carry, and the fire hose binding combination tool is used for maintenance and binding reinforcement of daily fire hoses of fire service maintainers.
Disclosure of Invention
Aiming at the problems in the prior art, the invention realizes rapid binding of the fire hose capable of bearing high-pressure water by arranging a set of portable combination tool, thereby being convenient for fire service personnel to use.
In order to achieve the above purpose, the invention adopts the following technical scheme:
the utility model provides a combination tool for ligature fire hose is used to ligature fire hose and metal joint, combination tool is including toolbox, fixed station, pliers, spanner, screwdriver, ligature ware, the fixed station is including the platform, be used for supporting platform and with the platform detachable support of connection, detachable anchor clamps of fixing on the platform, anchor clamps are including relative left arc splint and right arc splint that set up, left arc splint fixedly connected with left mounting panel, left mounting panel detachable fixes the one corner on the platform, right arc splint fixedly connected with regulating plate, and the regulating plate passes through adjusting bolt to be connected with left mounting panel, twists the distance between regulating plate and the left mounting panel, the support is including a plurality of landing legs and a plurality of connecting rods, and the landing leg passes through connecting bolt to be installed at the platform lower surface, through connecting rod detachable connection between the landing leg, the ligature ware is including two semicircular rings of relative setting, and the other end of two semicircular rings is equipped with the handle respectively, ligature ware, pliers, spanner, screwdriver, platform, anchor clamps, landing leg, connecting bolt homoenergetic dress into the toolbox.
Be equipped with first through-hole on the regulating plate, be equipped with on the left mounting panel with the corresponding second through-hole of first through-hole, the inner wall of second through-hole has with adjusting bolt matched with internal thread, adjusting bolt freely movable passes first through-hole, adjusting bolt's one end is equipped with the handle of being convenient for rotate adjusting bolt, the other end runs through in the second through-hole after the regulating plate through first through-hole, be fixed with the baffle on the adjusting bolt, the baffle can not pass first through-hole, the baffle is located between handle and the regulating plate.
The adjusting plate is provided with a third through hole, a jacking bolt is arranged in the third through hole, the inner surface of the third through hole is internally threaded with the jacking bolt in a matched mode, the jacking bolt can prop the left mounting plate after penetrating through the adjusting plate, and the adjusting bolt is located between the jacking bolt and the right arc clamping plate.
One ends of the two semicircular holding rings are hinged through a shaft pin, triangular notches are respectively arranged at the other ends of the two semicircular holding rings, and the triangular notches on the two semicircular holding rings are oppositely arranged.
The left mounting plate is fixed at one corner of the platform through screws.
The tool box is internally provided with a lower layer of foam-rubber cushion and an upper layer of foam-rubber cushion, the lower layer of foam-rubber cushion is provided with accommodating grooves for accommodating supporting legs, connecting bolts, connecting rods, binding devices, pliers, wrenches and screwdrivers respectively, and the upper layer of foam-rubber cushion is provided with accommodating platforms and clamps respectively.
The tool box comprises a box cover, wherein a lining is fixed on the inner side of the box cover, and uniformly distributed salient points are arranged on the lining.
One end of the tool box is provided with a handle, and the other end is provided with wheels.
The application method of the combination tool for binding the fire hose comprises the following steps:
step one, taking out a binding device, pliers, a spanner, a screwdriver, a platform, a clamp, supporting legs, connecting bolts and connecting rods from a tool box, assembling the supporting legs and the connecting rods by using the spanner to form a bracket with stable structure, mounting the platform on the bracket, and fixing the clamp at one corner of the platform to form a fixing table;
step two, a binding groove used for connecting the fire hose on the metal joint is outwards, the other end of the binding groove extends inwards between the left arc clamping plate and the right arc clamping plate, the metal joint is clamped by the left arc clamping plate and the right arc clamping plate by screwing the adjusting bolt, and the tightening bolt is screwed by using a spanner, so that the metal joint is clamped by the left arc clamping plate and the right arc clamping plate;
step three, sleeving one end of a fire hose on two binding grooves on a metal joint, winding and fixing the head end of an iron wire on an adjusting bolt, tensioning and pulling the iron wire to the binding groove on the outer side of the metal joint, tensioning and winding the iron wire from the outside to the inside to form a primary binding ring, winding part of the iron wire connected with the head end of the iron wire in the primary binding ring, then encircling the binding groove by two semicircular encircling rings of a binding device, clamping the primary binding ring in the two semicircular encircling rings, compressing two handles and rotating the binding device around the binding groove, enabling the iron wire to continue winding from the outside to the inside in the binding groove on the outer side of the metal joint, winding for a plurality of weeks to form a first binding ring, unwinding the head end of the iron wire on the adjusting bolt, twisting and knotting the exposed part of the iron wire from the first binding ring to form a first knot, tying the head end of the iron wire again on the adjusting bolt, pulling and tying the iron wire to the inner side of the metal joint to form a binding groove on the inner side of the semicircular encircling ring, winding the primary binding ring by two handles and winding the iron wire around the binding ring, continuously winding the iron wire around the binding ring from the inner side of the second binding ring to form a second knot, and winding part of the iron wire winding and winding head end of the iron wire winding around the iron wire winding ring from the second end of the iron wire winding ring to form a second knot winding ring, and winding part of the iron wire winding end of the iron wire winding ring continuously from the iron wire winding ring to the second knot winding end of the iron wire winding ring to form a second knot winding end of the iron binding ring;
and step four, loosening the jacking bolts and the adjusting bolts in sequence, and taking down the metal joint to complete the binding of the fire hose.
The winding number of turns of the iron wire in the first binding ring and the second binding ring is 5.
The beneficial effects of the invention are as follows: the combined tool for binding the fire hose has the advantages of portability, simplicity in operation, time and labor saving, is convenient to install, disassemble and use, can complete the binding work of the fire hose by a single person, can bind the fire hose bearing high-strength water pressure, and is suitable for service personnel with special requirements on fire-fighting equipment such as nuclear power plants.
Drawings
FIG. 1 is a schematic view of the structure of a stationary table, a clamp, and a metal fitting;
FIG. 2 is a schematic view of a fire hose being slipped over a metal fitting;
FIG. 3 is a schematic structural view of a clamp;
FIG. 4 is a schematic structural view of a ligator;
FIG. 5 is a schematic illustration of the banding of the first banding ring;
FIG. 6 is a schematic view of the fire hose after banding is completed;
fig. 7 is a schematic structural view of the tool box.
Detailed Description
The invention will now be further described with reference to the accompanying drawings.
As shown in fig. 1-7, a combination tool for binding fire hose 1 and metal joint 2 is used for binding fire hose, the combination tool is including toolbox 3, fixed station, pliers, spanner, screwdriver, ligature ware 4, the fixed station is including platform 5, be used for supporting platform 5 and with platform 5 detachable support 6, detachable anchor clamps 7 of fixing on platform 5, anchor clamps 7 are including relative left arc splint 71 and right arc splint 72 that set up, left arc splint 71 fixedly connected with left mounting plate 73, left mounting plate 73 detachable fixes the one corner on platform 5, right arc splint 72 fixedly connected with regulating plate 74, regulating plate 74 is connected with left mounting plate 73 through adjusting bolt 75, twists the distance between regulating plate 74 and the left mounting plate 73, support 6 is including a plurality of landing legs 61 and a plurality of connecting rods 62, and landing leg 61 is installed at platform 5 lower surface through connecting bolt, and detachable connection through connecting rod 62 between the landing leg 61, ligature ware 4 is including two relative setting up encircling clamp 41, two articulated clamp that encircle, two opposite ends, 4, spanner, tool 4 are equipped with in the other end, the spanner, the tool is equipped with, with 4.
As shown in fig. 3, a first through hole 76 is formed in the adjusting plate 74, a second through hole 77 corresponding to the first through hole 76 is formed in the left mounting plate 73, an inner wall of the second through hole 77 is provided with an inner thread matched with the adjusting bolt 75, the adjusting bolt 75 can freely move through the first through hole 76, one end of the adjusting bolt 75 is provided with a handle 78 which is convenient for rotating the adjusting bolt 75, the other end of the adjusting bolt 75 penetrates through the adjusting plate 74 through the first through hole 76 and then is screwed into the second through hole 77, a baffle 79 is fixed on the adjusting bolt 75, the baffle 79 cannot penetrate through the first through hole 76, and the baffle 79 is located between the handle 78 and the adjusting plate 74. The left mounting plate 73 is fixed to the platform 5, and the left mounting plate 73 can be clamped by the adjusting plate 74 under the action of the adjusting bolt 75, and by this adjustment, the left arc clamping plate 71 and the right arc clamping plate 72 can form a structure for holding the metal joint 2 tightly.
Further, in order to make the fixing effect of the metal joint 2 better, the fire hose 2 is more stable and labor-saving to bind, a third through hole 741 is formed in the adjusting plate 74, a jacking bolt 742 is installed in the third through hole 741, the inner surface of the third through hole 741 is provided with an inner thread matched with the jacking bolt 742, the jacking bolt 742 penetrates through the adjusting plate 74 and then can prop against the left mounting plate 73, and the adjusting bolt 75 is located between the jacking bolt 742 and the right arc clamping plate 72. By tightening the adjusting bolt 75 so that the adjusting plate 74 is continuously adjacent to the left mounting plate 73, the right arc clamping plate 72 is driven to continuously clamp the left arc clamping plate 71, and the metal joint 2 is clamped between the left arc clamping plate 71 and the right arc clamping plate 72. By screwing the jack bolt 742, the distance between the adjusting plate 74 and the left mounting plate 73 on one side of the jack bolt 742 is increased, and since the middle portions of the adjusting plate 74 and the left mounting plate 73 are fixed by the adjusting bolt 75, the adjusting bolt 75 is smaller than the first through hole 76, the adjusting plate 74 can rotate around the adjusting bolt 75 to a certain extent, so that the distance between the adjusting plate 74 and the other side of the left mounting plate 73 is reduced, and the metal joint 2 is clamped between the left arc clamping plate 71 and the right arc clamping plate 72.
As shown in fig. 4, one ends of the two semicircular holding rings 41 are hinged through a shaft pin 43, the other ends of the two semicircular holding rings 41 are respectively provided with a triangular notch 44, and the triangular notches 44 on the two semicircular holding rings 41 are oppositely arranged.
The left mounting plate 73 is fixed to a corner of the platform 5 by means of screws 731. The left mounting plate 73 is fixed on the corner of the platform 5 by a screwdriver, so that the operation of an maintainer can be facilitated. When binding the fire hose, the maintainer can assist to step on the connecting rod 62 with the foot for the fixed station is motionless, and the ligator 4 can be with the power when winding the iron wire, and makes things convenient for the rotation of ligator handle.
As shown in fig. 7, a lower layer foam-rubber cushion and an upper layer foam-rubber cushion 31 are arranged in the tool box 3, the lower layer foam-rubber cushion is provided with containing grooves 32 for placing supporting legs 61, connecting bolts, connecting rods 62, binding devices 4, pliers, wrenches and screwdrivers respectively, and the upper layer foam-rubber cushion 31 is provided with containing grooves 32 for placing a platform 5 and a clamp 7 respectively. The tool box 3 can orderly contain the components, various components cannot collide with each other in the tool box 3, are not easy to lose, and are convenient for overhauling and using the fire hose by overhauling personnel on fire-fighting facilities at different remote positions.
The tool box 3 comprises a box cover 33, a lining 34 is fixed on the inner side of the box cover 33, and uniformly distributed protruding points 35 are arranged on the lining 34. After all the parts are put into the tool box, the box cover 33 is tightly covered, the inner lining 34 and the convex points 35 form a compressing, buffering and protecting function on the parts in the box, and the tool box 3 can be lifted and carried at will.
The tool box 3 has a pull handle 36 at one end and a wheel 37 at the other end.
When the tool box is used, the binding device 4, the pliers, the wrench, the screwdriver, the platform 5, the clamp 7, the supporting legs 61, the connecting bolts and the connecting rods 62 are taken out from the tool box 3, the supporting legs 61 and the connecting rods 62 are assembled by using the wrench to form the support 6 with stable structure, the platform 5 is fixedly arranged on the support 6, and the clamp 7 is fixed at one corner of the platform 5 to form a fixed table.
Step two, a binding groove 21 used for connecting the fire hose 1 on the metal joint 2 is outwards extended, the other end of the binding groove inwards extends between the left arc clamping plate 71 and the right arc clamping plate 72, the adjusting bolt 75 is screwed to clamp the metal joint 2 by the left arc clamping plate 71 and the right arc clamping plate 72, and the wrench is used to screw the tightening bolt 742 to clamp the metal joint 2 by the left arc clamping plate 71 and the right arc clamping plate 72;
step three, one end of the fire hose 1 is sleeved on the two binding grooves 21 and 22 on the metal joint 2, the iron wire head end 81 is wound and fixed on the adjusting bolt 5, the iron wire 8 is tensioned and pulled into the binding groove 21 on the outer side of the metal joint 2, the iron wire 8 is tensioned and wound in the binding groove 21 from outside to inside to form an initial binding ring 82, part of the iron wire 83 connected with the iron wire head end 81 is wound in the initial binding ring, then the two semicircular holding rings 41 of the binding device 4 hold the binding groove 21, the initial binding ring 82 is clamped in the two semicircular holding rings 41, the iron wire 8 is clamped between the triangular notches 44 on the two semicircular holding rings 41, the two handles 42 are pressed and the binding device 4 is rotated around the binding groove 21, the triangular notches 44 form a wire guiding effect on the iron wire 8, the iron wire 8 continues to be wound in the binding groove 21 on the outer side of the metal joint 2 from outside to inside, forming a first binding ring 84 after winding for a plurality of weeks, unwinding an iron wire head end 81 on an adjusting bolt 5, twisting and knotting the part of the iron wire head end 8 exposed from the first binding ring 84 and the part of the iron wire 8 exposed from a semicircular holding ring 41 by using pliers to form a first knot 85, re-fixing the iron wire head end 81 on the adjusting bolt 5, pulling the twisted and knotted iron wire 8 into a binding groove 22 at the inner side of a metal joint 2 to wind for two weeks to form a second primary binding ring 86, winding part of the iron wire connected with the iron wire head end 81 into the second primary binding ring 86, repeating the operation formed by the first binding ring 84 to form a second binding ring 87, unwinding the iron wire head end 81, twisting and knotting the part of the iron wire head end 81 exposed from the second binding ring 87 and the part of the iron wire 8 exposed from the semicircular holding ring 41 by using pliers to form a second knot 88, the wire remaining on the knot is cut off using pliers and the ligator 4 is continued to be used to compress the second knot 88 into the ligature groove 22 inside the metal fitting 2. The iron wire head formed by the method is tightly attached to the metal joint, and the fracture position of the iron wire head is not higher than the heights of the second binding ring 84 and the second binding ring 87, so that hands cannot be cut when the iron wire head is used for fire protection.
And step four, loosening the jacking bolts 742 and the adjusting bolts 5 in sequence, and taking down the metal joint 2 to complete the binding of the fire hose 1.
The number of windings of the iron wire 8 in the first binding ring 84 and the second binding ring 87 is 5.
While the preferred embodiments of the present invention have been described in detail, it should be appreciated that numerous modifications and variations may be made in accordance with the principles of the present invention by those skilled in the art without undue burden, and thus, all technical solutions which may be obtained by logic analysis, reasoning or limited experimentation based on the principles of the present invention as defined by the claims are within the scope of protection as defined by the present invention.

Claims (7)

1. The use method of the combination tool for binding the fire hose is characterized in that the combination tool for binding the fire hose is used for binding the fire hose and the metal joint,
the combined tool comprises a tool box, a fixed table, pliers, a spanner, a screwdriver and a binding device, wherein the fixed table comprises a platform, a bracket used for supporting the platform and detachably connected with the platform, and a clamp detachably fixed on the platform, the clamp comprises a left arc clamping plate and a right arc clamping plate which are oppositely arranged, the left arc clamping plate is fixedly connected with a left mounting plate, the left mounting plate is detachably fixed at one corner on the platform, the right arc clamping plate is fixedly connected with an adjusting plate, the adjusting plate is connected with the left mounting plate through an adjusting bolt, the distance between the adjusting plate and the left mounting plate can be adjusted by screwing the adjusting bolt, the bracket comprises a plurality of supporting legs and a plurality of connecting rods, the supporting legs are mounted on the lower surface of the platform through the connecting bolts, the supporting legs are detachably connected through the connecting rods, the binding device comprises two semicircular holding rings which are oppositely arranged, one ends of the two semicircular holding rings are hinged, the other ends of the two semicircular holding rings are respectively provided with a handle, and the binding device, the pliers, the screwdriver, the platform, the clamp, the supporting leg, the connecting bolt and the connecting bolt can be assembled in the tool box;
the adjusting plate is provided with a first through hole, the left mounting plate is provided with a second through hole corresponding to the first through hole, the inner wall of the second through hole is provided with an internal thread matched with an adjusting bolt, the adjusting bolt can freely move to pass through the first through hole, one end of the adjusting bolt is provided with a handle which is convenient for rotating the adjusting bolt, the other end of the adjusting bolt passes through the first through hole and is screwed into the second through hole after passing through the adjusting plate, the adjusting bolt is fixedly provided with a baffle plate, the baffle plate cannot pass through the first through hole, and the baffle plate is positioned between the handle and the adjusting plate;
the adjusting plate is provided with a third through hole, a jacking bolt is arranged in the third through hole, the inner surface of the third through hole is provided with an inner thread matched with the jacking bolt, the jacking bolt can prop the left mounting plate after penetrating through the adjusting plate, and the adjusting bolt is positioned between the jacking bolt and the right arc clamping plate;
the using method of the combination tool for binding the fire hose comprises the following steps:
step one, taking out a binding device, pliers, a spanner, a screwdriver, a platform, a clamp, supporting legs, connecting bolts and connecting rods from a tool box, assembling the supporting legs and the connecting rods by using the spanner to form a bracket with stable structure, mounting the platform on the bracket, and fixing the clamp at one corner of the platform to form a fixing table;
step two, a binding groove used for connecting the fire hose on the metal joint is outwards, the other end of the binding groove extends inwards between the left arc clamping plate and the right arc clamping plate, the metal joint is clamped by the left arc clamping plate and the right arc clamping plate by screwing the adjusting bolt, and the tightening bolt is screwed by using a spanner, so that the metal joint is clamped by the left arc clamping plate and the right arc clamping plate;
step three, sleeving one end of a fire hose on two binding grooves on a metal joint, winding and fixing the head end of an iron wire on an adjusting bolt, tensioning and pulling the iron wire to the binding groove on the outer side of the metal joint, tensioning and winding the iron wire from the outside to the inside to form a primary binding ring, winding part of the iron wire connected with the head end of the iron wire in the primary binding ring, then encircling the binding groove by two semicircular encircling rings of a binding device, clamping the primary binding ring in the two semicircular encircling rings, compressing two handles and rotating the binding device around the binding groove, enabling the iron wire to continue winding from the outside to the inside in the binding groove on the outer side of the metal joint, winding for a plurality of weeks to form a first binding ring, unwinding the head end of the iron wire on the adjusting bolt, twisting and knotting the exposed part of the iron wire from the first binding ring to form a first knot, tying the head end of the iron wire again on the adjusting bolt, pulling and tying the iron wire to the inner side of the metal joint to form a binding groove on the inner side of the semicircular encircling ring, winding the primary binding ring by two handles and winding the iron wire around the binding ring, continuously winding the iron wire around the binding ring from the inner side of the second binding ring to form a second knot, and winding part of the iron wire winding and winding head end of the iron wire winding around the iron wire winding ring from the second end of the iron wire winding ring to form a second knot winding ring, and winding part of the iron wire winding end of the iron wire winding ring continuously from the iron wire winding ring to the second knot winding end of the iron wire winding ring to form a second knot winding end of the iron binding ring;
and step four, loosening the jacking bolts and the adjusting bolts in sequence, and taking down the metal joint to complete the binding of the fire hose.
2. The method of claim 1, wherein one ends of the two semicircular rings are hinged by a shaft pin, the other ends of the two semicircular rings are respectively provided with a triangular notch, and the triangular notches on the two semicircular rings are arranged oppositely.
3. The method of using a fire hose lashing combination tool of claim 1, wherein the left mounting plate is secured to a corner of the platform by screws.
4. The method of claim 1, wherein a lower layer of foam-rubber cushion and an upper layer of foam-rubber cushion are provided in the tool box, the lower layer of foam-rubber cushion is provided with accommodating grooves for accommodating supporting legs, connecting bolts, connecting rods, binding devices, pliers, wrenches and screwdrivers, and the upper layer of foam-rubber cushion is provided with accommodating grooves for accommodating platforms and clamps.
5. The method of claim 1, wherein the kit comprises a cover having an inner liner secured to an inner side thereof and having evenly distributed bumps thereon.
6. A method of using a fire hose lashing combination tool as claimed in claim 1, wherein the tool box has a handle at one end and a wheel at the other end.
7. The method of using a fire hose lashing combination tool of claim 1, wherein the number of windings of the wire in the first and second lashing rings is 5.
CN201711274214.8A 2017-12-06 2017-12-06 Combined tool for fire hose binding and use method of combined tool Active CN107839920B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711274214.8A CN107839920B (en) 2017-12-06 2017-12-06 Combined tool for fire hose binding and use method of combined tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711274214.8A CN107839920B (en) 2017-12-06 2017-12-06 Combined tool for fire hose binding and use method of combined tool

Publications (2)

Publication Number Publication Date
CN107839920A CN107839920A (en) 2018-03-27
CN107839920B true CN107839920B (en) 2024-03-19

Family

ID=61664461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711274214.8A Active CN107839920B (en) 2017-12-06 2017-12-06 Combined tool for fire hose binding and use method of combined tool

Country Status (1)

Country Link
CN (1) CN107839920B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108856597B (en) * 2018-05-31 2023-11-03 新疆国统管道股份有限公司 PCCP steel wire joint and binding method thereof
CN117357845B (en) * 2023-12-07 2024-02-23 江苏润泽安全科技有限公司 Strapping machine for fire hose

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104818854A (en) * 2015-05-08 2015-08-05 山东科技大学 Novel reinforcing steel bar binding device
CN204750646U (en) * 2015-05-18 2015-11-11 慈溪市南盾电器有限公司 A bind device for steel pipe
CN204850479U (en) * 2015-05-08 2015-12-09 山东科技大学 Novel reinforcement ware
CN105883108A (en) * 2016-04-28 2016-08-24 苏州达恩克精密机械有限公司 Wire bundling machine
CN106013929A (en) * 2016-06-07 2016-10-12 国网山东省电力公司临朐县供电公司 Multifunctional iron wire binding device
CN207670726U (en) * 2017-12-06 2018-07-31 浙江万纳核电检修有限公司 A kind of fire hose binding combination tool

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7458620B2 (en) * 2007-02-09 2008-12-02 Deere & Company Baler needle clamp arrangement for facilitating side-to-side adjustment of outer needle end

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104818854A (en) * 2015-05-08 2015-08-05 山东科技大学 Novel reinforcing steel bar binding device
CN204850479U (en) * 2015-05-08 2015-12-09 山东科技大学 Novel reinforcement ware
CN204750646U (en) * 2015-05-18 2015-11-11 慈溪市南盾电器有限公司 A bind device for steel pipe
CN105883108A (en) * 2016-04-28 2016-08-24 苏州达恩克精密机械有限公司 Wire bundling machine
CN106013929A (en) * 2016-06-07 2016-10-12 国网山东省电力公司临朐县供电公司 Multifunctional iron wire binding device
CN207670726U (en) * 2017-12-06 2018-07-31 浙江万纳核电检修有限公司 A kind of fire hose binding combination tool

Also Published As

Publication number Publication date
CN107839920A (en) 2018-03-27

Similar Documents

Publication Publication Date Title
CN107839920B (en) Combined tool for fire hose binding and use method of combined tool
CN103117522B (en) A kind of front cable plug separation device
CN207134729U (en) A kind of parallel groove clamp installation tool
CN205664033U (en) Clamp device
CN208028489U (en) A kind of high efficiency cord holder
CN202491196U (en) Electrification overhaul spanner
CN110011238A (en) A kind of cable bearer facilitating construction operation
CN206937191U (en) A kind of adjustable type hydraulic spanner special stand
CN206714376U (en) The Zipper-like tool bag that a kind of power industry uses
CN207670726U (en) A kind of fire hose binding combination tool
CN203251021U (en) Paying-off tackle clamping device
CN107333620B (en) Tree-stabilizing corrugated board bundle sleeve
CN203863297U (en) Pull rod tightener of iron core electric reactor
CN208943311U (en) A kind of protective device of inspection platform
CN208070097U (en) A kind of ship exhaust fume pipe insulation wrapping hooping device
CN208265678U (en) Portable overhead ground wire lifting device
CN106329394A (en) Line-tightening apparatus used in electric power installation
CN204538563U (en) A kind of conductor clamp boost motor
CN203205766U (en) Power transmission line coil-inserting insulated flat rope ladder
CN107047227B (en) Steady tree card tread assembly
CN216784271U (en) Packing box for large mechanical equipment
CN213989909U (en) A tensioner bullwheel for electric power installation
CN210838425U (en) Electromechanical installation electric wire head combining device
CN204361595U (en) Monofilament winding method repairs conductor combination instrument
CN208078532U (en) A kind of power ampere loads line apparatus

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant