CN1078265A - Steel ball heat treatment process - Google Patents

Steel ball heat treatment process Download PDF

Info

Publication number
CN1078265A
CN1078265A CN 92108118 CN92108118A CN1078265A CN 1078265 A CN1078265 A CN 1078265A CN 92108118 CN92108118 CN 92108118 CN 92108118 A CN92108118 A CN 92108118A CN 1078265 A CN1078265 A CN 1078265A
Authority
CN
China
Prior art keywords
steel ball
tempering
temperature
quenching
treatment process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 92108118
Other languages
Chinese (zh)
Inventor
刘吉实
敬守政
刘基
朱有贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xichang Iron Works
PANZHIHUA MINING Co MINISTRY OF METALLURGICAL INDUSTRY
Original Assignee
Xichang Iron Works
PANZHIHUA MINING Co MINISTRY OF METALLURGICAL INDUSTRY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xichang Iron Works, PANZHIHUA MINING Co MINISTRY OF METALLURGICAL INDUSTRY filed Critical Xichang Iron Works
Priority to CN 92108118 priority Critical patent/CN1078265A/en
Publication of CN1078265A publication Critical patent/CN1078265A/en
Pending legal-status Critical Current

Links

Images

Abstract

A kind of steel ball heat treatment process, be specially adapted to produce the ore grinding steel ball, it is characterized in that quenching temperature is 800~850 ℃, the steel ball surface temperature is 40~60 ℃ after the quench cooled, steel ball after the quenching in time carries out low-temperaturetempering, and tempering temperature is 150~210 ℃, and the time is 3 hours, tempering medium is 50~No. 100 machinery oil, and air cooling is to normal temperature after the tempering.This technology is easy to grasp and control, and steel ball average-volume hardness reaches 45~50HRC, and impelling strength reaches 12~15J/cm 2, improvement expenses is low, and the ratio of input and output is 1: 30~40, remarkable in economical benefits.

Description

Steel ball heat treatment process
Utilize common middle and high carbon steel base.Be heated to 1050~1150 ℃ of insulations and carry out die forging after 30 minutes.It is characterized in that: quenching temperature is 800~850 ℃, and the back steel ball surface temperature of quenching is 40~60 ℃, and the steel ball after the quenching in time carries out low-temperaturetempering.Tempering temperature is 150~210 ℃, and the time is 3 hours.Tempering medium is 50~No. 100 machinery oil, and air cooling is to normal temperature after the tempering.
The advantage of this thermal treatment process is:
1) steel billet C content allowed band is bigger, and it is lower to contain Mn, and material source extensively is easy to promote.
2) cool time long, cooling temperature is low, portion still can obtain a considerable amount of martensites at the steel ball heart.
3) the steel ball leaving water temperature(LWT) is easy to control and grasp after the quench cooled.
4) tempering temperature is stable, and steel ball performance inconsistency scope is little.
5) steel ball average-volume hardness (AVH) value is 45-50HRC, and notched bar impact strength is 12~15J/cm 2
6) improvement expenses is low, the duration is short, and the workman is easy to grasp, the economic benefit height, and the ratio of transforming the back input and output is 1: 30~40.
The present invention is achieved by the following measures:
The steel ball technological process of production is: steel billet selection → blanking → heating → die forging → precooling → quenching → tempering → air cooling.
Each operation specific requirement is as follows:
1) steel billet is selected: it is 0.5~0.8% that steel billet contains C; Siliceous 0.11~0.40%; Manganese 0.5~1.3%; Sulphur≤0.05%; Phosphorus≤0.06%.Use the mixing base to select through strictness.
2) blanking: adopt earnestly or cold saw.
3) heating: it is too short both to have prevented to heat the too fast time, prevents to heat slow overlong time again.Insulation is 30 minutes after reaching 1050~1150 ℃.
4) die forging: have certain density and garden degree for making steel ball, general requirement forges more than 50 times, and removes the iron scale in the mould at any time.
5) precooling: forge the back waste heat and be generally about 900 ℃, begin when making it be pre-chilled to 800~850 ℃ to quench, quenching temperature is crossed and lowly too highly all can be influenced ball hardness.
6) quench: quenching bath should have enough volumes, and water will long stream, is strictly on guard against that water temperature surpasses 60 ℃, in order to avoid influence quenching effect.Quenchant is a clear water, and forbidden that suds are arranged, foreign material such as grease sneak into.Should in time remove the iron scale of piling up in the pond.
7) tempering: in time removing quenching stress, prevent to burst, should in time carry out tempering.Tempering temperature is 150-210 ℃, and the time is 3 hours.Tempering medium is the 50-100 machinery oil, and air cooling is to normal temperature after the tempering.

Claims (1)

  1. A kind of steel ball heat treatment process, be specially adapted to produce the ore grinding steel ball, it is characterized in that, quenching temperature is 800~850 ℃, and the steel ball surface temperature is 40~60 ℃ after the quench cooled, and the steel ball after the quenching in time carries out low-temperaturetempering, tempering temperature is 150-210 ℃, time is 3 hours, and tempering medium is 50~No. 100 machinery oil, and air cooling is to normal temperature after the tempering.
CN 92108118 1992-04-27 1992-04-27 Steel ball heat treatment process Pending CN1078265A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 92108118 CN1078265A (en) 1992-04-27 1992-04-27 Steel ball heat treatment process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 92108118 CN1078265A (en) 1992-04-27 1992-04-27 Steel ball heat treatment process

Publications (1)

Publication Number Publication Date
CN1078265A true CN1078265A (en) 1993-11-10

Family

ID=4943241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 92108118 Pending CN1078265A (en) 1992-04-27 1992-04-27 Steel ball heat treatment process

Country Status (1)

Country Link
CN (1) CN1078265A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1044389C (en) * 1996-03-28 1999-07-28 刘机 Steel ball making process
CN1063364C (en) * 1994-08-16 2001-03-21 托比工业株式会社 Method for producing a vehicular endless track link
CN100509209C (en) * 2008-05-08 2009-07-08 刘机 Steel-forged ball processing technique
CN101307799B (en) * 2007-05-18 2010-09-29 上海钢球厂 Blast engine steel ball
CN102848155A (en) * 2012-09-24 2013-01-02 椿中岛机械(太仓)有限公司 Production process of bearing steel balls of high speed spinner
CN104109810A (en) * 2014-08-01 2014-10-22 宁国市南方耐磨材料有限公司 High-C abrasion-resistant steel ball
CN107186447A (en) * 2017-07-15 2017-09-22 芜湖市宇恒特种钢球有限公司 A kind of processing method of bearing steel ball

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1063364C (en) * 1994-08-16 2001-03-21 托比工业株式会社 Method for producing a vehicular endless track link
CN1044389C (en) * 1996-03-28 1999-07-28 刘机 Steel ball making process
CN101307799B (en) * 2007-05-18 2010-09-29 上海钢球厂 Blast engine steel ball
CN100509209C (en) * 2008-05-08 2009-07-08 刘机 Steel-forged ball processing technique
CN102848155A (en) * 2012-09-24 2013-01-02 椿中岛机械(太仓)有限公司 Production process of bearing steel balls of high speed spinner
CN102848155B (en) * 2012-09-24 2015-03-18 椿中岛机械(太仓)有限公司 Production process of bearing steel balls of high speed spinner
CN104109810A (en) * 2014-08-01 2014-10-22 宁国市南方耐磨材料有限公司 High-C abrasion-resistant steel ball
CN107186447A (en) * 2017-07-15 2017-09-22 芜湖市宇恒特种钢球有限公司 A kind of processing method of bearing steel ball

Similar Documents

Publication Publication Date Title
CN109082587A (en) The manufacturing method of high-carbon high nickel steel ring forging used for wind power generation
US4933024A (en) Method for manufacturing a high strength rail with good toughness
CN103643143B (en) A kind of 600MPa level Green heat treatment high strength cast iron and working method thereof
US4221612A (en) Grinding members
CA2195287A1 (en) Railway Wheel and Manufacturing Method of the Railway Wheel
CN1078265A (en) Steel ball heat treatment process
CN103451398A (en) Manufacture method of 50CrVA alloy structural steel type hot rolled round steel bar
CN112301193B (en) Thermomechanical treatment method for preparing rare earth bearing steel
JPS5773132A (en) Production of cold rolled mild steel plate of superior deep drawability and aging resistance by continuous annealing
US4108695A (en) Steel wire
US4180418A (en) Method of making a steel wire adapted for cold drawing
US3904446A (en) Process of making high strength cold rolled steel having excellent bake-hardening properties
JPS5818966B2 (en) Rail manufacturing method
CN1044389C (en) Steel ball making process
JPS629162B2 (en)
CN101058148A (en) Processing technology for steel ball
CN1068906C (en) Heat treatment process of cutter for stone work
CN1056716A (en) A kind of high strength cold-rolled dual phase sheet steel and manufacture method
CN1027652C (en) Heat-cutting hardening process for bainite steel workpiece
CN1463899A (en) High-strength packaging steel band and thermal treatment process thereof
US4592788A (en) Method for pressurized water quenching of rolled steel products
CN1158362A (en) Multicomponent alloyed cast and forged wearing, corrosion resistant and high toughness grinding balls and its prodn. method
JPH0219175B2 (en)
CN1044723C (en) Heat treatment method for vanadium-contained alloy steel rail
CN1087783C (en) Heat treatment for martensitic stainless steel sheet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C01 Deemed withdrawal of patent application (patent law 1993)
WD01 Invention patent application deemed withdrawn after publication