CN107815979A - A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method - Google Patents

A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method Download PDF

Info

Publication number
CN107815979A
CN107815979A CN201711033723.1A CN201711033723A CN107815979A CN 107815979 A CN107815979 A CN 107815979A CN 201711033723 A CN201711033723 A CN 201711033723A CN 107815979 A CN107815979 A CN 107815979A
Authority
CN
China
Prior art keywords
tensioning
wire
anchoring part
compressor wire
box beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711033723.1A
Other languages
Chinese (zh)
Inventor
王双其
张健
王丽健
王剑琳
叶李水
王飞
闻人霞
梁小光
赵慧君
李丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xu Jian Engineering Science And Technology Development Co Ltd
Original Assignee
Beijing Xu Jian Engineering Science And Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Xu Jian Engineering Science And Technology Development Co Ltd filed Critical Beijing Xu Jian Engineering Science And Technology Development Co Ltd
Priority to CN201711033723.1A priority Critical patent/CN107815979A/en
Publication of CN107815979A publication Critical patent/CN107815979A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Abstract

The invention discloses a kind of box beam beam bottom prestressing force to strengthen bracing means, set including mirror image and be fixed on two tensioning anchoring parts at box beam beam bottom, for installing the installation crab-bolt of tensioning anchoring part, it is separately positioned on two anchor slabs of two tensioning anchoring parts away from plane of symmetry side, connect the compressor wire of two tensioning anchoring parts, the steel wire being arranged between two tensioning anchoring parts, and any one tensioning anchoring part is arranged on away from plane of symmetry side and the stretch-draw jack that is connected with compressor wire.For the present invention due to carrying out prestressed stretch-draw, small volume using high tensile steel wire, anchoring position requires relatively low;The prestressing force dispersed distribution of compressor wire is in embedded high-strength and high-ductility epoxy concrete, so as to alleviate the stress concentration of the anchored end of compressor wire, reaches the purpose for improving bridge prestress well, so as to ensure that the consolidation effect of bridge.Present invention also offers the construction method of the bracing means.

Description

A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method
Technical field
The present invention relates to engineer applied Bridge technical field of structural reinforcement, and in particular to be a kind of box beam beam bottom in advance should Power strengthens bracing means and its construction method.
Background technology
Bridge is the important component of Modern Traffic net, and many bridges are in overload operation state for a long time at present, Many bridges cause the quantity of disease bridge, unsafe bridge more next because prestressed loss causes Lack of support and downwarp phenomenon occurs It is more, it is difficult to meet the requirement of communications and transportation development.Adopt an effective measure in time and sick bridge, unsafe bridge are repaired and conserved and can be had Effect ground strengthens the ability to work of existing bridge, extends the service life of bridge.Typically use for external prestress strengthening method (tensioning cable wire etc.) but its anchored end volume are big, are not fixed easily, and the intensity requirement to anchoring position is high.Pine occurs for a long time Relax.
To sum up, how to design a kind of a kind of box beam beam bottom prestressing force enhancing that can effectively solve prior art deficiency and reinforce dress Put, become for those skilled in the art's urgent need to resolve the problem of one of.
The content of the invention
For above-mentioned the deficiencies in the prior art, the invention provides a kind of box beam beam bottom prestressing force to strengthen bracing means.
To achieve the above object, the technical solution adopted by the present invention is as follows:
A kind of box beam beam bottom prestressing force strengthens bracing means, including mirror image sets and is fixed on two tensioning at box beam beam bottom Anchoring part, for installing the installation crab-bolt of tensioning anchoring part, it is separately positioned on two anchors of two tensioning anchoring parts away from plane of symmetry side Plate, the compressor wire of two tensioning anchoring parts, the steel wire being arranged between two tensioning anchoring parts are connected, and be arranged on any Individual tensioning anchoring part is away from plane of symmetry side and the stretch-draw jack that is connected with compressor wire;The tensioning anchoring part includes being used to pacify Anchoring part bottom plate mounted in box beam beam bottom, and the anchoring part riser being fixedly connected vertical with anchoring part bottom plate one end, the installation crab-bolt Be arranged on anchoring part bottom plate, be provided with the through hole that compressor wire passes through on the anchoring part riser, described two anchor slabs respectively with Two anchoring part riser fittings are set, and the compressor wire is being worn through through hole and the mounting hole of anchor slab, the compressor wire Cross and intermediate plate is provided with anchor slab, space pours in the compressor wire and steel wire is used for filled with high-strength and high-ductility epoxy concrete The prestressing force of compressor wire is scattered in high-strength and high-ductility epoxy concrete, anchor slab and the tensioning thousand of the stretch-draw jack side Jin is provided with limiting plate between top.
Preferably, the compressor wire is high tensile steel wire.
Preferably, the installation crab-bolt is chemical anchor bolts.
Specifically, the chemical anchor bolts are four and are uniformly arranged into square on anchoring part bottom plate.
Specifically, the compressor wire is four and is arranged side by side, the through hole on the anchoring part riser is four And be arranged side by side, the anchor slab is the four hole anchor slabs matched with anchoring part riser, and the limiting plate is four matched with four hole anchor slabs Hole limiting plate.
Based on foregoing teachings, present invention also offers the construction method of box beam beam bottom prestressing force enhancing bracing means, its It is characterised by, comprises the following steps:
(1) first rule and slot at box beam beam bottom, bury two tensioning anchoring parts;
(2) two anchor slabs are fitted on the outside of two anchoring part risers, passed through through compressor wire and in compressor wire Intermediate plate is set at two anchor slabs;
(3) limiting plate is set stretch-draw jack side need to be installed, then stretch-draw jack is connected with compressor wire;
(4) slowly oil-feed tensioning stretch-draw jack to design pulling force, cuts off unnecessary compressor wire;
(5) after compressor wire completes tensioning, steel wire is inserted between compressor wire and box beam beam bottom;
(6) epoxy concrete form erection is carried out;
(7) after the completion of epoxy concrete form is set up, high-strength and high-ductility epoxy concrete is inserted, to empty in compressor wire and steel wire Between carry out cast closing;
(8) after the completion of the high-strength high viscous high tenacity epoxy concrete construction in box beam beam bottom, age reaches progress pine after design load.
Compared with prior art, the invention has the advantages that:
For the present invention due to carrying out prestressed stretch-draw, small volume using high tensile steel wire, anchoring position requires relatively low;Tensioning is complete Steel wire is set between compressor wire afterwards, then with high-strength and high-ductility epoxy concrete, to empty in all compressor wires and steel wire Between carry out cast closing, because high-strength and high-ductility epoxy concrete and concrete and steel have a superpower adhesive property, and its own Good compression strength and tensile strength, it with the solidification of high-strength and high-ductility epoxy concrete, can divide the prestressing force of compressor wire Dissipate and be distributed in embedded high-strength and high-ductility epoxy concrete, so as to alleviate the stress concentration of the anchored end of compressor wire, reach The purpose of bridge prestress is improved well, so as to ensure that the consolidation effect of bridge.
Brief description of the drawings
Fig. 1 is the use state diagram of the present invention.
Fig. 2 is the tensioning anchoring part schematic diagram of the present invention.
Fig. 3 is the tensioning anchoring part sectional view of the present invention.
Fig. 4 is the anchored framework schematic diagram of the present invention.
Fig. 5 is the spacing plate structure schematic diagram of the present invention.
Wherein, it is entitled corresponding to reference:
1- tensioning anchoring parts, 2- installation crab-bolts, 3- anchor slabs, 4- compressor wires, 5- steel wires, 6- stretch-draw jacks, 7- anchors Seat bottom plate, 8- anchoring part risers, 9- intermediate plates, 10- limiting plates.
Embodiment
The invention will be further described with embodiment for explanation below in conjunction with the accompanying drawings, and embodiments of the present invention are included but not It is only limitted to following examples.
As shown in Fig. 1~5, a kind of box beam beam bottom prestressing force strengthens bracing means, including two tensioning anchoring parts 1, installation anchor Bolt 2, two anchor slabs 3, compressor wire 4, steel wire 5, stretch-draw jacks 6;Wherein, tensioning anchoring part 1 includes being used to be arranged on case The anchoring part bottom plate 7 at Liang Liang bottoms, the anchoring part riser 8 being fixedly connected vertical with the one end of anchoring part bottom plate 7.
Two tensioning anchoring parts 1 are oppositely arranged and are fixed on box beam beam bottom, and installation crab-bolt 2 is used to install tensioning anchoring part 1, two Anchor slab 3 is separately positioned on two 1 outer sides of tensioning anchoring part, and compressor wire 4 connects two tensioning anchoring parts 1, steel Silk screen 5 is arranged between two tensioning anchoring parts 1, and stretch-draw jack 6 is arranged on any one tensioning anchoring part 1 away from plane of symmetry side simultaneously It is connected with compressor wire 4;Installation crab-bolt 2 is arranged on anchoring part bottom plate 7, and compressor wire 4 is provided with anchoring part riser 8 and is passed through Through hole, two anchor slabs 3 are bonded setting with two anchoring part risers 8 respectively, installation of the compressor wire 4 through through hole and anchor slab 3 Hole, compressor wire 4 is through intermediate plate 9 is provided with anchor slab 3, and space is poured filled with height in compressor wire 4 and steel wire 5 Strong high tenacity epoxy concrete is used to the prestressing force of compressor wire 4 being scattered in high-strength and high-ductility epoxy concrete, stretch-draw jack 6 one Limiting plate 10 is provided between the anchor slab 3 and stretch-draw jack 6 of side, compressor wire 4 is high tensile steel wire, and installation crab-bolt 2 is change Crab-bolt is learned, chemical anchor bolts are four and to be uniformly arranged into square on anchoring part bottom plate 7, and compressor wire 4 is four and side by side Set, the through hole on anchoring part riser 8 is four and is arranged side by side, and anchor slab 3 is the four hole anchor slabs matched with anchoring part riser 8, spacing Plate 10 is the four hole limiting plates matched with four hole anchor slabs.
The construction method of the present embodiment box beam beam bottom prestressing force enhancing bracing means, comprises the following steps:
(1) first rule and slot at box beam beam bottom, bury two tensioning anchoring parts 1;
(2) two anchor slabs 3 are fitted in two outsides of anchoring part riser 8, through compressor wire 4 and in compressor wire 4 Intermediate plate 9 is set at through two anchor slabs 3;
(3) limiting plate 10 is set the side of stretch-draw jack 6 need to be installed, then by stretch-draw jack 6 and compressor wire 4 Connection;
(4) slowly oil-feed tensioning stretch-draw jack 6 to design pulling force, cuts off unnecessary compressor wire 4;
(5) after compressor wire 4 completes tensioning, steel wire 5 is inserted between compressor wire 4 and box beam beam bottom;
(6) epoxy concrete form erection is carried out;
(7) after the completion of epoxy concrete form is set up, high-strength and high-ductility epoxy concrete is inserted, in compressor wire 4 and steel wire 5 Space carries out cast closing;
(8) after the completion of the high-strength high viscous high tenacity epoxy concrete construction in box beam beam bottom, age reaches progress pine after design load.
Should misplace progress when Specific construction engineering central sill bottom tensioning anchoring part is embedded, avoid stress concentration as far as possible;Tensioning anchor Stretching construction can be carried out after intensity is up to standard after seat is embedded, stretching force is determined by designing to calculate according to bridge actual conditions;Tensioning When, answering slow oil-feed tensioning, people forbids station to fly to hurt sb.'s feelings to prevent anchor slab or top are de- at anchor slab both ends during tensioning to design pulling force;Excision Sufficiently long active length should be reserved during unnecessary compressor wire;Must not should be noted that when closing mould to the compressor wire after tensioning Cause to damage, need to check one by one, the construction of epoxy concrete can be carried out after need to being rectified and improved if any damage.
Above-described embodiment is only one of the preferred embodiment of the present invention, should not be taken to limit the protection model of the present invention Enclose, all body design thought in the present invention and that mentally makes have no the change of essential meaning or polishing, what it was solved Technical problem is still consistent with the present invention, should be included within protection scope of the present invention.

Claims (6)

1. a kind of box beam beam bottom prestressing force strengthens bracing means, it is characterised in that is set including mirror image and is fixed on box beam beam bottom Two tensioning anchoring parts (1), for installing the installation crab-bolt (2) of tensioning anchoring part, be separately positioned on two tensioning anchoring parts away from right Two anchor slabs (3) of title face side, the compressor wire (4) of two tensioning anchoring parts is connected, is arranged between two tensioning anchoring parts Steel wire (5), and be arranged on any one tensioning anchoring part away from plane of symmetry side and the tensioning thousand that is connected with compressor wire Jin top (6);The tensioning anchoring part includes being used for the anchoring part bottom plate (7) installed in box beam beam bottom, and is hung down with anchoring part bottom plate one end The anchoring part riser (8) being directly fixedly connected, the installation crab-bolt are arranged on anchoring part bottom plate, and pre- answer is provided with the anchoring part riser The through hole that power steel wire passes through, described two anchor slabs are bonded setting with two anchoring part risers respectively, and the compressor wire passes through logical Hole and the mounting hole of anchor slab, the compressor wire is through being provided with intermediate plate (9), the compressor wire and steel wire at anchor slab Space pours in net is used to the prestressing force of compressor wire being scattered in high-strength and high-ductility ring filled with high-strength and high-ductility epoxy concrete In oxygen concrete, limiting plate (10) is provided between the anchor slab and stretch-draw jack of the stretch-draw jack side.
A kind of 2. box beam beam bottom prestressing force enhancing bracing means according to claim 1, it is characterised in that the prestressing force Steel wire is high tensile steel wire.
A kind of 3. box beam beam bottom prestressing force enhancing bracing means according to claim 2, it is characterised in that the installation anchor Bolt is chemical anchor bolts.
A kind of 4. box beam beam bottom prestressing force enhancing bracing means according to claim 3, it is characterised in that the chemical anchors Bolt is four and is uniformly arranged into square on anchoring part bottom plate.
5. a kind of box beam beam bottom prestressing force enhancing bracing means according to claim 4, it is characterised in that described pre- Stress wire is four and to be arranged side by side, and the through hole on the anchoring part riser is four and is arranged side by side, and the anchor slab is and anchor Four hole anchor slabs of seat riser matching, the limiting plate are the four hole limiting plates matched with four hole anchor slabs.
6. the construction method of the box beam beam bottom prestressing force enhancing bracing means described in any one of Claims 1 to 5, its feature exist In comprising the following steps:
(1) first rule and slot at box beam beam bottom, bury two tensioning anchoring parts;
(2) two anchor slabs are fitted on the outside of two anchoring part risers, two is passed through through compressor wire and in compressor wire Intermediate plate is set at anchor slab;
(3) limiting plate is set stretch-draw jack side need to be installed, then stretch-draw jack is connected with compressor wire;
(4) slowly oil-feed tensioning stretch-draw jack to design pulling force, cuts off unnecessary compressor wire;
(5) after compressor wire completes tensioning, steel wire is inserted between compressor wire and box beam beam bottom;
(6) epoxy concrete form erection is carried out;
(7) after the completion of epoxy concrete form is set up, high-strength and high-ductility epoxy concrete is inserted, space in compressor wire and steel wire is entered Row cast closing;
(8) after the completion of the high-strength high viscous high tenacity epoxy concrete construction in box beam beam bottom, age reaches progress pine after design load.
CN201711033723.1A 2017-10-30 2017-10-30 A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method Pending CN107815979A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711033723.1A CN107815979A (en) 2017-10-30 2017-10-30 A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711033723.1A CN107815979A (en) 2017-10-30 2017-10-30 A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method

Publications (1)

Publication Number Publication Date
CN107815979A true CN107815979A (en) 2018-03-20

Family

ID=61604456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711033723.1A Pending CN107815979A (en) 2017-10-30 2017-10-30 A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method

Country Status (1)

Country Link
CN (1) CN107815979A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854024A (en) * 2021-01-10 2021-05-28 山西省交通新技术发展有限公司 Construction method of bonded prestressed structure for reinforcing hollow slab bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100328318B1 (en) * 1998-10-22 2002-07-03 구민세 Stiffness improvement of inner support section area by filling concrete in steel box girder bridge.
CN201184016Y (en) * 2008-03-21 2009-01-21 四川省交通厅公路规划勘察设计研究院 Low retracting amount steel hinge line anchorage
CN102900200A (en) * 2012-10-09 2013-01-30 东南大学 Intelligent FRP (Fiber Reinforce Plastic)-concrete composite structure and manufacturing method thereof
CN105887702A (en) * 2016-04-20 2016-08-24 武汉理工大学 Method for reinforcing concrete beam by prestressed carbon fiber plate and steel-concrete
CN106245540A (en) * 2016-08-30 2016-12-21 河南省交通科学技术研究院有限公司 A kind of based on retarded adhesive prestressed bridge strengthening system and reinforcement means
CN206070381U (en) * 2016-08-31 2017-04-05 襄阳创天机械有限公司 Beam body tension tool

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100328318B1 (en) * 1998-10-22 2002-07-03 구민세 Stiffness improvement of inner support section area by filling concrete in steel box girder bridge.
CN201184016Y (en) * 2008-03-21 2009-01-21 四川省交通厅公路规划勘察设计研究院 Low retracting amount steel hinge line anchorage
CN102900200A (en) * 2012-10-09 2013-01-30 东南大学 Intelligent FRP (Fiber Reinforce Plastic)-concrete composite structure and manufacturing method thereof
CN105887702A (en) * 2016-04-20 2016-08-24 武汉理工大学 Method for reinforcing concrete beam by prestressed carbon fiber plate and steel-concrete
CN106245540A (en) * 2016-08-30 2016-12-21 河南省交通科学技术研究院有限公司 A kind of based on retarded adhesive prestressed bridge strengthening system and reinforcement means
CN206070381U (en) * 2016-08-31 2017-04-05 襄阳创天机械有限公司 Beam body tension tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854024A (en) * 2021-01-10 2021-05-28 山西省交通新技术发展有限公司 Construction method of bonded prestressed structure for reinforcing hollow slab bridge

Similar Documents

Publication Publication Date Title
CN106677070A (en) Construction support and method for overhead large-span heavy-duty cross beam
WO2019149270A1 (en) Assembled pier for mixed reinforcement of normal steel rebar and finished threaded steel bar
CN107386127A (en) A kind of bridge pier assembly device
CN110847044A (en) Semi-prefabricated assembled bent cap construction method
CN103556749A (en) Hanging flexible connection of precast concrete infill wall
CN102535504A (en) Seismic isolation foundation for bridge
CN110886201A (en) Prefabricated assembled concrete-filled steel tube self-resetting pier with earthquake damage replaceable components
CN108411769A (en) A kind of assembled device of prefabricated pier shaft and prefabricated bent cap
CN107815979A (en) A kind of box beam beam bottom prestressing force enhancing bracing means and its construction method
CN211689864U (en) Prefabricated assembled concrete-filled steel tube self-resetting pier with earthquake damage replaceable components
CN108442236A (en) Assembled bridge pier and construction method, prefabricated assembled beam bridge
CN103195183A (en) Standard unit assembled shock isolating and damping structure system
CN207846427U (en) A kind of upper and lower walkway of assembled foundation pit
CN108086481B (en) A kind of metro depot upper cover Estate Development Self-resetting integral structure and method
CN103790230B (en) Novel post-earthquake self-reset concrete framework structural system
CN110158475A (en) A kind of prefabricated assembled bridge substructure and its construction method
CN212336567U (en) Large-span split type prefabricated staircase
CN109898860A (en) A kind of fabricated assembly overall shear wall formwork bracket reducing fracture width
CN208122299U (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type tub system
CN210712562U (en) Tower crane system for construction of cast-in-situ tower column of cable-stayed bridge
CN212611921U (en) Prefabricated assembled concrete-filled steel tube self-resetting pier with box-type earthquake damage replaceable components
CN106481109B (en) A kind of cooling tower X inclined struts segmentation self-balancing construction method
CN209538521U (en) One kind, which is casted anchor, applies prestressed girder with rolled steel section en cased in concrete
CN209145319U (en) Structure construction protective device is got rid of after a kind of building
CN208072458U (en) A kind of pier sheet-pile engaging portion structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180320

RJ01 Rejection of invention patent application after publication