CN107809066B CN201710868032.7A CN201710868032A CN107809066B CN 107809066 B CN107809066 B CN 107809066B CN 201710868032 A CN201710868032 A CN 201710868032A CN 107809066 B CN107809066 B CN 107809066B
Authority
CN
China
Prior art keywords
module
main body
prefabricated cabin
cabinet mounting
installation panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710868032.7A
Other languages
Chinese (zh)
Other versions
CN107809066A (en
Inventor
丁丽平
闫建华
韩付申
窦辉
王树勋
胡丙群
李承光
谢润哲
张永峰
朱凤玲
李振兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xuji Group Co Ltd
XJ Electric Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xuji Group Co Ltd
XJ Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xuji Group Co Ltd, XJ Electric Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710868032.7A priority Critical patent/CN107809066B/en
Publication of CN107809066A publication Critical patent/CN107809066A/en
Application granted granted Critical
Publication of CN107809066B publication Critical patent/CN107809066B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/20Bus-bar or other wiring layouts, e.g. in cubicles, in switchyards
    • H02B1/202Cable lay-outs

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Patch Boards (AREA)
  • Wind Motors (AREA)

Abstract

The present invention relates to the concentration router module of the prefabricated cabin in prefabricated cabin field and use the prefabricated cabin of the module;Prefabricated cabin concentration router module includes main body module, main body module includes installation panel and the column for connecting with prefabricated cabin, the main body module is an integral structure, the installation panel is formed by plate, installation panel is equipped with the cabinet mounting hole installed for box module, installs and is equipped with the cabinet mounting structure being fixedly mounted for box module in the position close to cabinet mounting hole on panel.Main body module is arranged to integral structure, panel is installed and column is formed by the different piece on main body module, when router module is concentrated in installation, directly main body module can be installed in the cabin of prefabricated cabin, electrical equipment is installed on main body module;Compared with the prior art, the negligible amounts for the components for needing to assemble, improve installation effectiveness.

Description

Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module
Technical field
The present invention relates to one of prefabricated cabin field prefabricated cabin concentration router module and use the prefabricated cabin of the module.
Background technique
With the fast development of power grid, it is widely popularized at home as a kind of novel intelligent prefabricated cabin formula substation Using instead of the superiority that old-fashioned substation has it brilliant in all various aspects, but there are in secondary decoration inside prefabricated cabin The traditional work mode of in disorder cabling on bulkhead is carried out, the later period is all inconvenient to the maintenance of electric components and O&M, to entire The normal operation of power grid, which causes, cannot be neglected influence, and be unfavorable for intelligent substation widelys popularize application.To adapt to intelligence The allegro modularization construction process of substation guarantees that beautiful prefabricated cabin interior cabling, safe and reliable, maintenance and O&M are convenient, right The integrated modular alignment system research of prefabricated cabin is very important.
The Chinese invention patent that notification number is CN104917087B, the day for announcing is 2017.07.04 discloses a kind of prefabricated cabin Interlayer module, prefabricated cabin interlayer module include the equipment sandwich portion for installing equipment and the cabling interlayer for laying cable Part;Equipment sandwich portion is main module, and main body module includes left interlayer side plate, right interlayer side plate, reinforces transverse slat and installation Panel;Left and right interlayer side plate forms column at being used to connect with the cabin of prefabricated cabin every setting between left and right;Installation panel has The multiple of setting are vertically alternatively arranged, installation panel is horizontally set between left and right column;It can be reserved between two adjacent installation panels The mounting hole of electric elements installation, the digital and analog hole of power supply component installation is respectively equipped on left and right column.
Cabling sandwich portion includes cabling interlayer side plate, door-plate, top cover and bottom cover, and cabling interlayer side plate is mounted on side by side to be set For the side of the width direction of sandwich portion, cable-through hole is offered on the column of the close cabling sandwich portion of main body module, is walked Cable in line sandwich portion connects the correspondence electric elements on main body module by cable-through hole.Existing concentration router module, energy Enough realize the concentration arrangement of cable in prefabricated cabin.But concentrate router module whole using assembled structure, components compared with For dispersion and quantity it is more, prefabricated cabin assemble when, concentrate the installation effectiveness of router module lower.
Summary of the invention
The purpose of the present invention is to provide a kind of prefabricated cabins with router module is concentrated, and is deposited with solving existing concentration router module Components it is more, assembly time is longer, the problem of influencing production efficiency;The object of the invention is also to provide a kind of uses The prefabricated cabin of the router module.
To achieve the above object, the scheme 1 of prefabricated cabin of the invention concentration router module is: prefabricated cabin concentrates cabling Module includes main body module, and main body module includes installation panel and the column for connecting with prefabricated cabin, the main body module are Integral structure, the installation panel are formed by plate, and installation panel is equipped with the cabinet mounting hole installed for box module, peace The cabinet mounting structure being fixedly mounted for box module is equipped in the position close to cabinet mounting hole on dress panel.
Scheme 2 is concentration router module according to scheme 1, the one pair of them relative side phase of the installation panel To fold, fold part forms the column.
Scheme 3 is concentration router module according to scheme 1, there is towards opposite bending and molding on the installation panel Two groove structures;One of groove structure charger equipment installation, forms the main body module.
Scheme 4 is the concentration router module according to scheme 2 or 3, and the installation panel is vertically arranged, and installs panel On in the position at the two vertical holes edges close to cabinet mounting hole be respectively equipped with L shape connection frame, L shape connection frame be equipped with for The equipment connecting hole of electrical equipment connection, L shape connection frame form the cabinet mounting structure.
Scheme 5 is concentration router module according to scheme 4, close to cabinet mounting hole on the installation panel The position at lower horizontal hole edge is equipped with the L shape support bracket for carrying out support to electrical equipment.
The scheme 1 of prefabricated cabin of the invention is: prefabricated cabin, including cabin and the concentration router module that is arranged in cabin, Concentrating router module includes main body module, and main body module includes installation panel and the column for connecting with prefabricated cabin, the master Module is an integral structure, and the installation panel is formed by plate, and installation panel is equipped with the cabinet installed for box module Mounting hole is installed and is equipped with the cabinet mounting structure being fixedly mounted for box module in the position close to cabinet mounting hole on panel.
Scheme 2 is prefabricated cabin according to scheme 1, and the one pair of them relative side of the installation panel turns down in opposite directions, Fold part forms the column.
Scheme 3 is prefabricated cabin according to scheme 1, there is recessed towards opposite two bending and molding on the installation panel Slot structure;One of groove structure charger equipment installation, forms the main body module.
Scheme 4 is the prefabricated cabin according to scheme 2 or 3, and the installation panel is vertically arranged, and installs and is leaning on panel The position at two vertical holes edges of nearly cabinet mounting hole is respectively equipped with L shape connection frame, and L shape connection frame is equipped with for setting with electric appliance The equipment connecting hole of standby connection, L shape connection frame form the cabinet mounting structure.
Scheme 5 is prefabricated cabin according to scheme 4, in the downside water close to cabinet mounting hole on the installation panel The position at flat hole edge is equipped with the L shape support bracket for carrying out support to electrical equipment.
The beneficial effects of the present invention are: main body module is arranged to integral structure, panel and column are installed by main body mould Different piece on block is formed, and when router module is concentrated in installation, directly main body module can be installed in the cabin of prefabricated cabin, Electrical equipment is installed on main body module;Compared with the prior art, the negligible amounts for the components for needing to assemble improve peace Fill efficiency.
Detailed description of the invention
Fig. 1 is the perspective view of the embodiment one of the prefabricated cabin in the present invention;
Fig. 2 is the enlarged drawing in Fig. 1 at A;
Fig. 3 is the front perspective view of the concentration router module in Fig. 1;
Fig. 4 is the rear perspective figure of the concentration router module in Fig. 1;
Fig. 5 is the cross-sectional view of the embodiment two of the prefabricated cabin in the present invention.
Specific embodiment
Embodiments of the present invention are described further with reference to the accompanying drawing.
The embodiment one of prefabricated cabin of the invention, as shown in Figures 1 to 4, including cabin 1 and the use being arranged in cabin 1 In the concentration router module 2 for concentrating cabling, concentrate router module 2 that the corner inside cabin 1 is set;Cabin 1 is pushed up with cabin Part 3, cabin top part 3 are equipped with wiring casing 31, and circumferential edge of the wiring casing 31 along cabin top part 3 is arranged;Each electric appliance in cabin 1 Cable in equipment is pooled in wiring casing 31, and the cable in wiring casing 31 is concentrated to be connected to again and be concentrated in router module 2.
As shown in Figure 3 and Figure 4, it concentrates router module 2 that there is main body module 21 and router module 22, main body module 21 and walks Wire module 22 is formed by corresponding frame structure respectively, and router module 22 is disposed in parallel in the one of the width direction of main body module 21 Side.The installation of the operating elements such as 21 power supply and distribution case of main body module, service chamber, switch, router module 22 is for concentrating cabling, cabin top Divide the cable in 3 cable box that can enter in router module 22.
The frame structure that main body module 21 is vertically arranged, the front panel of main body module 21 form installation panel, mounting surface The two opposite sides side of the width direction of plate turns down in opposite directions, and fold part forms the column for connecting with cabin 1.It installs on panel Equipped with the cabinet mounting hole 211 installed for box module, the operation component such as distribution box, service chamber can insert cabinet mounting hole In 211;Position on the inner wall of panel on the hole edge close to cabinet mounting hole 211 is installed to be equipped with for the fixed peace of corresponding box module The cabinet mounting structure of dress.
In the present embodiment, cabinet mounting structure includes two vertical holes close to cabinet mounting hole 211 along the L shape connection being arranged Frame further includes the L shape support bracket close to the lower horizontal hole of cabinet mounting hole 211 along setting;L shape connection frame and L shape support bracket It is formed by angle steel, L shape connection frame is equipped with the equipment connecting hole 213 for corresponding box module connection.
The top of main body module 21 is blocked by top plate 217, and the back and bottom of main body module 21 are hatch frame, back The vertical edges of the separate router module 22 of hatch frame are equipped with towards the in-flanges 214 turned down on the inside of main body module 21;Bottom Portion's hatch frame is brought up in main body module 21 for the cable in the bottom plate interlayer of cabin 1.
It is respectively provided on in-flanges 214 and on the backboard of router module 22 and is connected to equipment mounting hole with cabin 1 215, the equipment mounting hole 215 on each component has the two or more being spaced along the vertical direction.Main body module 21 with cabling mould The adjacent side plate of block 22 is equipped with cable-through hole 216, and the cable on router module 22 and main body module 21 can be mutual by cable-through hole 216 Logical, cable-through hole 216 has the two or more for the setting that is arranged above and below.
Router module 22 is formed by side plate 221, two end plates 222 and revolving door 223, and side plate 221 is surrounded with main body module 21 Cavity body structure with front openings, two end plates 222 are separately positioned on the top and bottom of cavity body structure, in two end plates 222 Equipped with cable hole 224, two end plates 222 are respectively provided with towards the fold part turned down on the inside of front openings, fold part for pair Spinning door 223 carries out block;Revolving door 223 is equipped with lockset 225.
When assembling prefabricated cabin, router module 2 will be concentrated to be fixed on the inner wall of cabin by equipment mounting hole 215, cabin The cable on electric elements in body 1 enters router module 22 from cable hole 224, and the cable in router module 22 passes through cable-through hole 216 connect with the corresponding equipment on main body module 21, and that installs on main body module 21 has distribution box, service chamber, switch, socket etc. Operating element.
Wherein, the inlet wire in distribution box is drawn from the alternating current-direct current screen in prefabricated cabin, is pressed from both sides by the antistatic floor of the bilge 1 Layer enters in router module 22.Compared with the prior art, the better tightness of router module 2 is concentrated, anti-dust performance has larger It improves, and needs components to be mounted less, installation effectiveness is higher.
Embodiment two, embodiment two and embodiment one the difference is that, concentrating router module 2 by cross section is " 5 " The frame structure of font is formed;" 5 " cabinet frame body has towards two opposite groove body parts, and groove body part 21 forms charger and sets The main body module of standby installation, groove body part 22 form router module;Revolving door is rotatably equipped at the notch of groove body part 22 223.The groove bottom of groove body part 21 is equipped with the equipment mounting hole installed for box module, and groove bottom forms installation panel, slot Body portion 21 is used to connect with prefabricated cabin in the opposite cell wall of its groove width direction separately, forms column.21 He of groove body part Partition between groove body part 22 is equipped with cable-through hole 216.Concentration router module 2 is integral type bending and molding, reduces and concentrates The manufacture difficulty of wire module improves the integral strength for concentrating router module.In other embodiments, " 5 " character form structure can also be with By being formed towards two opposite U-shaped bending part weldings.
In other embodiments, the integral structure of main body module can also use welding procedure welding shape by different piece At.
The prefabricated cabin of the invention embodiment for concentrating router module concentrates the structure and aforementioned present invention of router module The structure of router module in any embodiment of prefabricated cabin is identical;Therefore, it is not repeated to illustrate.

Claims (6)

1. prefabricated cabin is with router module, including main body module and router module is concentrated, main body module includes installation panel and is used for The column being connect with prefabricated cabin, it is characterised in that: the main body module is an integral structure, and the installation panel is by plate shape At installation panel is equipped with the cabinet mounting hole installed for box module, installs on panel in the position close to cabinet mounting hole Equipped with the cabinet mounting structure being fixedly mounted for box module, the one pair of them relative side of the installation panel turns down in opposite directions, Fold part form the column, the installation panel is vertically arranged, install panel on close to cabinet mounting hole two vertically The position at hole edge is respectively equipped with L shape connection frame, and L shape connection frame is equipped with the equipment connecting hole for connecting with electrical equipment, L Shape connection frame forms the cabinet mounting structure;Router module is disposed in parallel in the side of the width direction of main body module.
2. prefabricated cabin according to claim 1 concentration router module, it is characterised in that: be bent on the installation panel Type has towards two opposite groove structures;One of groove structure charger equipment installation, forms the main body module.
3. prefabricated cabin according to claim 1 or 2 is with concentrating router module, it is characterised in that: on the installation panel The L shape support bracket for carrying out support to electrical equipment is equipped with close to the position at the lower horizontal hole edge of cabinet mounting hole.
4. prefabricated cabin, including cabin and the concentration router module being arranged in cabin, concentrate router module include main body module and Router module, main body module include installation panel and the column for connecting with prefabricated cabin, it is characterised in that: the main body module It being an integral structure, the installation panel is formed by plate, and installation panel is equipped with the cabinet mounting hole installed for box module, The cabinet mounting structure being fixedly mounted for box module, the installation are equipped in the position close to cabinet mounting hole on installation panel The one pair of them relative side of panel turns down in opposite directions, and fold part forms the column, and the installation panel is vertically arranged, installation It is respectively equipped with L shape connection frame in the position at the two vertical holes edges close to cabinet mounting hole on panel, L shape connection frame, which is equipped with, to be used In the equipment connecting hole connecting with electrical equipment, L shape connection frame forms the cabinet mounting structure;Router module is disposed in parallel in The side of the width direction of main body module.
5. prefabricated cabin according to claim 4, it is characterised in that: there is towards opposite bending and molding on the installation panel Two groove structures;One of groove structure charger equipment installation, forms the main body module.
6. prefabricated cabin according to claim 4 or 5, it is characterised in that: close to cabinet mounting hole on the installation panel Lower horizontal hole edge position be equipped with for electrical equipment carry out support L shape support bracket.
CN201710868032.7A 2017-09-22 2017-09-22 Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module Expired - Fee Related CN107809066B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710868032.7A CN107809066B (en) 2017-09-22 2017-09-22 Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710868032.7A CN107809066B (en) 2017-09-22 2017-09-22 Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module

Publications (2)

Publication Number Publication Date
CN107809066A CN107809066A (en) 2018-03-16
CN107809066B true CN107809066B (en) 2019-08-27

Family

ID=61584394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710868032.7A Expired - Fee Related CN107809066B (en) 2017-09-22 2017-09-22 Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module

Country Status (1)

Country Link
CN (1) CN107809066B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108493782B (en) * 2018-04-02 2023-10-20 深圳市怡富通讯科技有限公司 Prefabricated cabin
CN112653036B (en) * 2021-01-13 2021-12-14 中国科学院高能物理研究所 Processing and assembling method of payload structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104362517A (en) * 2014-10-31 2015-02-18 许继集团有限公司 Prefabricated ceiling and secondary device prefabricating bin using same
CN105392311A (en) * 2015-11-06 2016-03-09 许继集团有限公司 Cabinet pedestal and modularized combined equipment using the same
CN106088703A (en) * 2016-07-27 2016-11-09 国家电网公司 A kind of assembled transformer station using modularity base

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104917087B (en) * 2015-07-01 2017-07-04 许继集团有限公司 Prefabricated interlayer module and the interlayer preparation method and prefabricated cabin using the module
CN204795914U (en) * 2015-07-17 2015-11-18 温州电力设计有限公司 Prefabricated cabin of integration rack -type equipment body
CN105576574B (en) * 2016-01-07 2018-02-16 许继集团有限公司 A kind of frame and the secondary device prefabricated cabin using the frame
CN206490919U (en) * 2017-02-17 2017-09-12 上海奔鼎机电设备制造有限公司 A kind of upward wiring groove network cabinet

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104362517A (en) * 2014-10-31 2015-02-18 许继集团有限公司 Prefabricated ceiling and secondary device prefabricating bin using same
CN105392311A (en) * 2015-11-06 2016-03-09 许继集团有限公司 Cabinet pedestal and modularized combined equipment using the same
CN106088703A (en) * 2016-07-27 2016-11-09 国家电网公司 A kind of assembled transformer station using modularity base

Also Published As

Publication number Publication date
CN107809066A (en) 2018-03-16

Similar Documents

Publication Publication Date Title
CN107809066B (en) Prefabricated cabin, which is used, concentrates router module and the prefabricated cabin using the module
WO2019237431A1 (en) Power battery group structure capable of freely assembling hidden wiring
CN207365332U (en) A kind of air conditioner electric-controlled box
CN211774823U (en) Assembled light partition wall
CN203233609U (en) An electric control box and a cabinet air conditioner
CN115347681A (en) Energy storage system is with converging control cabinet
CN208149046U (en) The water-proof type of battery flat slides cabin door structure on a kind of passenger-car roof
CN203937794U (en) The lower pipe battery assembly of Electrical Bicycle
CN203942737U (en) A kind of communication cabinet
CN201463453U (en) Structure for installing glass door of refrigerator
CN205944752U (en) Apron that cubical switchboard was used
CN205883749U (en) Outdoor equipment cabinet
CN213584673U (en) Component mounting rack for pluggable standard modular power distribution cabinet
CN201360107Y (en) Draw-out low-pressure switch cabinet with fixed partitions
CN203839753U (en) Indoor concealed installation distribution box
CN201298676Y (en) Low-voltage electrical control cabinet provided with ventilating window
CN208890447U (en) A kind of indoor box body of split type direct-current charging post
CN216040288U (en) Washing machine
CN206180866U (en) Photovoltaic inverter machine case and photovoltaic inverter
CN212738075U (en) Multi-functional portable dado structure in EMUs sightseeing area
CN204538963U (en) A kind of high power D C-DC conversion equipment
CN217087221U (en) Fixed separated centralized cabinet
CN202310339U (en) Electric cabinet structure of diesel locomotive
CN216738965U (en) Display plate mounting structure of clothes nursing machine
CN218683785U (en) Water dispenser shell frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827

Termination date: 20200922