CN107780893A - A kind of Shallow Heavy Oil Reservoir completion tubular column - Google Patents

A kind of Shallow Heavy Oil Reservoir completion tubular column Download PDF

Info

Publication number
CN107780893A
CN107780893A CN201610722272.1A CN201610722272A CN107780893A CN 107780893 A CN107780893 A CN 107780893A CN 201610722272 A CN201610722272 A CN 201610722272A CN 107780893 A CN107780893 A CN 107780893A
Authority
CN
China
Prior art keywords
screen casing
casing
tube
section
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201610722272.1A
Other languages
Chinese (zh)
Inventor
王磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610722272.1A priority Critical patent/CN107780893A/en
Publication of CN107780893A publication Critical patent/CN107780893A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B37/00Methods or apparatus for cleaning boreholes or wells
    • E21B37/08Methods or apparatus for cleaning boreholes or wells cleaning in situ of down-hole filters, screens, e.g. casing perforations, or gravel packs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/02Subsoil filtering
    • E21B43/08Screens or liners
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/14Obtaining from a multiple-zone well

Abstract

The present invention discloses a kind of Shallow Heavy Oil Reservoir completion tubular column, including production casing, the horizontal segment of production casing is connected with two primary screen casings, oil pick-up tube is fixed with by packer in production casing vertical section, the horizontal ends of oil pick-up tube freely extend in the net horizontal section that two primary screen casings and sleeve pipe are formed, and two level screen casing is provided with the horizontal segment of oil pick-up tube;The sieve aperture of two level screen casing includes reducing section, flat segments and impact section, reduces section internal diameter and radially outward successively decreases along two level screen casing, impact section internal diameter radially outward successively decreases along two level screen casing.In horizontal well, it is divided into three parts by two external packer of pipe bore holes, i.e., the fluid in horizontal well is entered around oil pick-up tube by two primary screen casings respectively;Now, it is transported to respectively by the two level screen casing on oil pumping pipe end and oil pick-up tube horizontal segment in production casing vertical section top by the fluid entered in two primary screen casings, and then completes the segmentation exploitation of horizontal well.

Description

A kind of Shallow Heavy Oil Reservoir completion tubular column
Technical field
The invention belongs to horizontal well production technical field, more particularly to a kind of Shallow Heavy Oil Reservoir completion tubular column.
Background technology
Viscous crude is the important component in the petroleum hydrocarbon energy, and its feature is as follows:
(1)Colloid in viscous crude is high with bitumen content, and light fraction is seldom.And with resin and asphalt
Content increases the relative density of viscous crude and viscosity and also accordingly increased.
(2)The viscosity of viscous crude is for very temperature sensitive, and with the increase of temperature, viscosity drastically declines.And
Viscosity of crude is bigger, and this change is more obvious.
(3)The hetero atom such as sulphur, oxygen, nitrogen is more in viscous crude.
(4)Paraffin content is typically relatively low in viscous crude, but it is " double high oil fields ", i.e. asphalt content also to have only a few oil field Height, paraffin content are also high, are characterized as the high condensation point crude oil of high viscosity.
(5)Same heavy crude reservoir, oil property usually have very in the different well sections and plane of vertical oil reservoir between each well Big difference.
With horizontal well drilling completion and the constantly improve of production technique, horizontal well be advantageous to improve well yield, increase can Adopt reserves and improve oil recovery rate, horizontal well development technology is applied to various types of oil reservoirs at present.For the sandstone of homogeneous Or for Carbonate Reservoir, traditional barefoot completion, primary sieve tube completion, perforation completion mode can give horizontal well development band Carry out some problems.Because level of production section is longer, being influenceed by pit shaft friction drag, the producing pressure differential of whole horizontal segment is different, Heel end producing pressure differential is maximum, and toe-end producing pressure differential is minimum, and it is uneven to ultimately result in horizontal segment production liquid, or even toe-end occurs and do not produce liquid Situation, significantly impact the development effectiveness of horizontal well.
The content of the invention
The invention reside in a kind of Shallow Heavy Oil Reservoir completion tubular column is provided, reduce the producing pressure differential of heel end, amplify toe-end Producing pressure differential, horizontal segment relatively evenly output is realized, so as to realize that horizontal well in segments is exploited.
The present invention's is achieved through the following technical solutions:
A kind of Shallow Heavy Oil Reservoir completion tubular column, includes the production casing of L-shaped, and the horizontal segment of the production casing is connected with two Primary screen casing, sleeve pipe are arranged between two primary screen casings, and L-shaped is fixed with by packer in the production casing vertical section Oil pick-up tube, packer in pipe is installed in sleeve pipe, the horizontal ends of the oil pick-up tube are in two the primary screen casings and set The net horizontal section that pipe is formed freely extends, and two level screen casing, the two level screen casing face end are provided with the horizontal segment of oil pick-up tube The primary screen casing being connected with production casing horizontal segment, two external packer of pipe, and two pipe coverings are installed outside sleeve pipe Bore hole is separated into three parts every device;The sieve aperture of the two level screen casing includes the diminution being radially outward sequentially connected along two level screen casing Section, flat segments and impact section, the diminution section internal diameter radially outward successively decrease along two level screen casing, and the impact section internal diameter sieves along two level Pipe radially outward successively decreases, and the primary screen casing includes the base tube that multiple fuel feed holes are provided with outer wall, along the base tube axially at it Be provided with multiple ribs on outer circle wall, and along base tube circle on multiple ribs interval be wound with wrapping wire, it is adjacent Two ribs between be filled with the block foamed iron of triangle, it is and solid being welded with the middle part of the isometrical conveyor screw on inwall It is fixed to enclose, rotated on retainer plate inner peripheral wall and be provided with multiple balls, include the guide rail of annular, the guide rail circumferentially passes through along base tube Wear in the middle part of multiple ribs, and the annular groove with multiple ball engagements is provided with guide rail outer circle wall.
In the prior art, in the thermal process of viscous crude, the horizontal segment of horizontal well is longer, the friction drag of horizontal well toe-end It is bigger, ultimately result in that the production liquid of horizontal segment is uneven, i.e., the heel end of horizontal segment differs with toe-end producing pressure differential, has a strong impact on water The oil recovery efficiency of horizontal well, for this problem, the present invention is divided into horizontal well by two external packer of pipe bore holes Three parts, i.e., the fluid in horizontal well are entered around oil pick-up tube by two primary screen casings respectively;Now, by two primary sieves The fluid entered in pipe is transported to production casing by the two level screen casing on oil pumping pipe end and oil pick-up tube horizontal segment respectively In vertical section top, and then complete the segmentation exploitation of horizontal well.The present invention utilizes segmentation exploitation so that is produced positioned at horizontal well toe-end The frictional resistance of liquid reduces, and is exaggerated the producing pressure differential of toe-end, while increases the frictional resistance of horizontal well heel end production liquid, reduces heel end Producing pressure differential, horizontal segment production liquid relatively evenly output is realized, caused by efficiently solving conventional horizontal well completion mode Horizontal segment production liquid is uneven, the problem of toe-end does not produce liquid even occurs, realizes the balanced production liquid of horizontal segment, the exploitation for well of improving the standard Effect.And the filtering that the fluid in the bore hole of production casing end passes through primary screen casing and two level screen casing so that most The solid concentration for entering fluid in oil pick-up tube eventually minimizes, and when carrying out clean-out service to horizontal completion in the later stage of recovering the oil, Flushing fluid is injected in production casing, oil pick-up tube, primary screen casing and two level screen casing are cleaned by flushing fluid, ensures water Oil recovery efficiency of the flat completion in later stage recovery process;
Wherein, flushing fluid by production casing when being entered in oil pick-up tube, because formation pressure is larger, the flushing fluid in oil pick-up tube The resistance outwards sprayed is accordingly larger, for two primary screen casings, secondary sieve of the flushing fluid on by oil pick-up tube horizontal segment Pipe is injected into the primary screen casing of production casing side, now by flushing fluid to outside the primary screen casing of secondary screen casing face Spray to realize that the effect for the sieve aperture dredged on primary screen casing is difficult to realize, therefore, inventor is carried out to the sieve aperture of two level screen casing Improve, i.e., the sieve aperture of two level screen casing includes the diminution section, flat segments and the impact section that are sequentially connected, and reduces section and impact section Internal diameter radially outward successively decreasing along two level screen casing, and the internal diameter of flat segments then keeps constant, when flushing fluid in oil pick-up tube by overflowing When going out, flushing fluid after the diminishing of flow cross suddenly, and its flow velocity can be continuously increased, by gentle in flat segments Transition, accelerated again in impact section, at the same time, in horizontal well oil reservoir it is relative to the pressure in two level screen casing with it is general It is low for logical sieve aperture, i.e., finally primary screen casing is carried out being kept its fast state by the flushing fluid overflowed in impact section Wash away, while the solid phase particles being blocked on two level screen casing and primary screen casing are then rushed by the flushing fluid with powerful impact dynamics Walk so that two level screen casing and primary screen casing keep the unobstructed of its sieve aperture.
During work, base tube is placed in the horizontal segment of horizontal completion, and viscous crude enters wrapping wire by wire spacing and formed with sleeve pipe Gap in, after the filtration by foamed iron, substrate tube is entered by fuel feed hole, to realize the pumping of fluid; In the prior art, steam flooding technology is used when being exploited to viscous crude, i.e., steam injection well and producing well are set above oil reservoir, Constantly passing through steam in steam injection well so that steam constantly heats the stratum around pit shaft, while the crude oil in stratum is also heated, The steam zone progressively extended with the continuous injection of steam is formed in the stratum of near wellbore, steam can be by containing in steam zone Saturation degree drops to relatively low degree, and by flowable crude oil(That is the difference of initial oil saturation and residual oil saturation)Displace Steam zone;At the same time, in the horizontal segment of horizontal completion, steam consumingly moves to updip direction, and under the force of gravity, Heated crude oil is driven onto and had a down dip reversely, and the increase of the temperature with crude oil, profit and gravel in horizontal completion horizontal segment It will be seethed with excitement Deng mixture, and cause crude oil to be degraded(Disturbance caused by the boiling of mixture), the mixing of profit and solid phase Thing starts by entering substrate tube in horizontal completion horizontal segment, and wrapping wire is a complete metal bar and is wound on by interval On multiple ribs, the primary filter unit to the major diameter solid phase such as gravel in profit is formed, and foam iron rule is formed to small straight The secondary filter unit of footpath solid phase, to realize the sand control purpose of base tube;Also, when in horizontal completion horizontal segment by liquid pressure When power and the self-contained heat of profit influence and cause to produce pressure change, formed between adjacent two ribs Secondary filter section is compressed, but filled with multiple foamed irons block in triangle, foamed iron in the secondary filter section After stress deforms upon, the runner of multiple irregular geometric figures can be still formed in secondary filter section for oil mixing with water Thing is by the way that and foamed iron inner duct stress occurs minor variations and being not easy and is blocked dead, while foamed iron has certain bullet Property, the duct in elasticity recovery deformation in foamed iron resets, and to maintain the percolation ability in secondary filter section, ensures viscous crude Smooth exploitation.
Further, when oil water mixture enters in base tube, because the whole level that oil water mixture moves and drives is complete The motion of fluid in well horizontal segment, and by horizontal segment fluid apply the isometrical spiral shell formed to wrapping wire in all directions The pressure revolved on body is different, when isometrical conveyor screw both sides discontinuity equalization, passes through the mutual cunning between ball and annular groove It is dynamic to coordinate so that isometrical conveyor screw starts slow rotation outside base tube, and is now partly connected in isometrical conveyor screw gap The solid phases such as sand grains can directly drop with the rotation and washing away for oil water mixture of isometrical conveyor screw, avoid on isometrical conveyor screw There is serious clogging, ensure the stability of oil-feed in base tube.
It is incremented by successively in the length of the diminution section, flat segments and impact section in two level screen casing radially.Reduce section, put down The length of straight section and impact section in two level screen casing radially is directly connected to jet velocity of the flushing fluid on two level screen casing, i.e., Flushing fluid speed acceleration in sieve aperture is more, and the impact dynamics to primary screen casing is then bigger, and section, flat segments are reduced in the present invention And radially outward increasing of the length of impact section along two level screen casing so that acceleration time of the flushing fluid in sieve aperture extends, and ensures The momentum during injection of flushing fluid can be fully erased by the solid phase particles on primary screen casing and two level screen casing, ensures in level The stable output of completion later stage exploitation production liquid.
Also include giving up, described give up is connected by screw thread with packer upper end.Giving up can be direct after being connected with packer Docked with the pumping pipe string in protective casing, while packer insulates the vertical portion of first paragraph oil pipe into upper and lower two Part, and oilhole is opened in bottom, gives up positioned at top so that oilhole is being flowed into by the production liquid flowed into first paragraph primary screen casing Afterwards, directly mixed with by the production liquid phase flowed into second segment oil pipe, concentrate on give up it is interior after be extracted outside well.
Also include multiple reinforcements, multiple reinforcements axially and are distributed on wrapping wire in a ring along the base tube. In the horizontal segment of horizontal completion, wrapping wire is not only by the pressure of oil reservoir, and pressure moment change with the change of reservoir temperature, I.e. during the abrupt change of pressure, wrapping wire is highly prone to damage, and the present invention by set on wrapping wire it is multiple in a ring The reinforcement of distribution so that the first filter element that wrapping wire is formed stably is supported, to tackle in horizontal completion in horizontal segment Continually changing production pressure, while extend the service life of its own.
TiALN-WC/C layers are scribbled on the wrapping wire outer wall.Preferably, TiALN-WC/C is set to apply in wrapping wire outer wall Layer, and the coefficient of friction of TiALN-WC/C coatings only has 0.1, when the solid phases such as sand grains constantly contact with wrapping wire, can greatly drop Low frictional dissipation between the two, and self lubricity is carried, greatly ensure service life of the wrapping wire in horizontal completion.
Also include connector, the both ends of the base tube are connected by connector with blind pipe respectively.Preferably, according to reality The needs of oil recovery, base tube is connected by connector with blind pipe, facilitates the pumping of crude oil, and the abandoning tradition blind pipe in laying The mode directly welded with base tube, wrapping wire is directly changed when wrapping wire damages and without being carried out integrally to base tube, wrapping wire to facilitate Change, reduce the production cost of thickened oil recovery.
Multiple balls are rounded and array distribution is on the inner peripheral wall of the retainer plate.Preferably, multiple rollings Pearl is evenly distributed on the inner peripheral wall of retainer plate, i.e., more balanced in the support of the isometrical conveyor screw formed to wrapping wire, and And when isometrical conveyor screw freely rotates outside base tube, isometrical conveyor screw will not be caused stress raisers occur, reduce wrapping wire While damage, ensure the oil-feed efficiency in base tube.
The present invention compared with prior art, has the following advantages and advantages:
The filtering that fluid of the present invention in the bore hole of production casing end passes through primary screen casing and two level screen casing so that most The solid concentration for entering fluid in oil pick-up tube eventually minimizes, and when carrying out clean-out service to horizontal completion in the later stage of recovering the oil, Flushing fluid is injected in production casing, oil pick-up tube, primary screen casing and two level screen casing are cleaned by flushing fluid, ensures water Oil recovery efficiency of the flat completion in later stage recovery process.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the embodiment of the present invention, forms one of the application Point, do not form the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention;
Fig. 2 is the structural representation of two level screen casing sieve aperture;
Fig. 3 is the structural representation of primary screen casing;
Fig. 4 is the longitdinal cross-section diagram of primary screen casing.
Mark and corresponding parts title in accompanying drawing:
1- production casings, 2- sleeve pipes, 3- external packer of pipe, 4- primary screen casing, 5- give up, in 6- packers, 7- oil pick-up tubes, 8- pipes Packer, 9- bore holes, 10- protective casings, 11- two levels screen casing, 111- impact sections, 112- flat segments, 113- reduce section, A- with End, B- toe-ends, 12- reinforcements, 13- wrapping wires, 14- ribs, 15- base tubes, 16- fuel feed holes, 17- connectors, 18- blind pipes, 19- Foamed iron, 20- retainer plates, 21- guide rails, 22- balls.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment and accompanying drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment 1
As shown in Figures 1 to 4, the present embodiment includes the production casing 2 of L-shaped, and the horizontal segment of the production casing 2 is connected with two Primary screen casing, sleeve pipe 2 are arranged between two primary screen casings, are fixed with the vertical section of production casing 2 by packer 6 The oil pick-up tube 7 of L-shaped, packer 8 in pipe are installed in sleeve pipe 2, the horizontal ends of the oil pick-up tube 7 are in two primary screen casings And the net horizontal section that sleeve pipe 2 is formed freely extends, two level screen casing 11, the two level sieve are provided with the horizontal segment of oil pick-up tube 7 The primary screen casing that the face end of pipe 11 is connected with the horizontal segment of production casing 2, two external packer of pipe 3 are installed outside sleeve pipe 2, and Bore hole 9 is separated into three parts by two external packer of pipe 3;The sieve aperture of the two level screen casing 11 is included along the footpath of two level screen casing 11 To the diminution section 113, flat segments 112 and impact section 111 being outwards sequentially connected, the internal diameter of section 113 that reduces is along two level screen casing 11 Radially outward successively decrease, the internal diameter of impact section 111 radially outward successively decreases along two level screen casing 11, and the primary screen casing 4 includes outer wall On be provided with the base tubes 15 of multiple fuel feed holes 16, multiple ribs 14 are axially provided with its outer circle wall along the base tube 15, And along base tube 15 justify on multiple ribs 14 interval be wound with wrapping wire 13, filled between adjacent two ribs 14 Have in the block foamed iron 19 of triangle, and be welded with retainer plate 20 in the middle part of the isometrical conveyor screw on inwall, in retainer plate 20 Rotated in circumferential wall and be provided with multiple balls 22, include the guide rail 21 of annular, the guide rail 21 is circumferential through multiple along base tube 4 The middle part of ribs 3, and the annular groove coordinated with multiple balls 22 is provided with the outer circle wall of guide rail 21.
In the prior art, in the thermal process of viscous crude, the horizontal segment of horizontal well is longer, and horizontal well toe-end B's rubs along journey Resistance is bigger, ultimately results in that the production liquid of horizontal segment is uneven, i.e. the heel end A of horizontal segment differs with toe-end B producing pressure differentials, serious shadow The oil recovery efficiency of Xiangshui County's horizontal well, for this problem, the present invention passes through two quilts of 3 bore hole of external packer of pipe 9 in horizontal well Three parts are divided into, i.e., the fluid in horizontal well is entered around oil pick-up tube 7 by two primary screen casings respectively;Now, by two The fluid entered in individual primary screen casing is defeated by the two level screen casing 11 on the end of oil pick-up tube 7 and the horizontal segment of oil pick-up tube 7 respectively Deliver in the vertical section top of production casing 2, and then complete the segmentation exploitation of horizontal well.The present invention utilizes segmentation exploitation so that position Reduce in the frictional resistance of horizontal well toe-end B production liquid, be exaggerated toe-end B producing pressure differential, while increase horizontal well heel end A production liquid Frictional resistance, heel end A producing pressure differential is reduced, realize horizontal segment production liquid relatively evenly output, efficiently solve conventional levels Horizontal segment production liquid caused by well completion mode is uneven, the problem of toe-end B does not produce liquid even occurs, realizes the balanced production of horizontal segment Liquid, the development effectiveness for well of improving the standard.And the fluid in the bore hole 9 of the end of production casing 2 by primary screen casing and The filtering of two level screen casing 11 so that the solid concentration for entering eventually into fluid in oil pick-up tube 7 minimizes, and in the later stage pair of recovering the oil When horizontal completion carries out clean-out service, the injection flushing fluid in the production casing 2, by flushing fluid to oil pick-up tube 7, primary screen casing with And two level screen casing 11 is cleaned, ensure oil recovery efficiency of the horizontal completion in later stage recovery process;
Wherein, flushing fluid by production casing 2 when being entered in oil pick-up tube 7, because formation pressure is larger, washing in oil pick-up tube 7 The resistance that well liquid outwards sprays is accordingly larger, for two primary screen casings, flushing fluid on by the horizontal segment of oil pick-up tube 7 two Secondary screen casing is injected into the primary screen casing of the side of production casing 2, now the primary by flushing fluid to secondary screen casing face Sprayed outside screen casing to realize that the effect for the sieve aperture dredged on primary screen casing is difficult to realize, therefore, inventor is to two level screen casing 11 Sieve aperture is improved, i.e., the sieve aperture of two level screen casing 11 includes diminution section 113, flat segments 112 and the impact section 111 being sequentially connected, And internal diameter radially outward the successively decreasing along two level screen casing 11 of section 113 and impact section 111 is reduced, and the internal diameter of flat segments 112 Then keep constant, when flushing fluid is by overflowing in oil pick-up tube 7, after the diminishing suddenly of flow cross, it flows flushing fluid Speed can be continuously increased, and by the gentle transition in flat segments 112, be accelerated again in impact section 111, same with this When, oil reservoir is relative to the pressure in two level screen casing 11 low with for common sieve aperture in horizontal well, i.e., finally by impact section 111 The flushing fluid of spilling keep its fast state start to wash away primary screen casing, while be blocked in two level screen casing 11 and just Solid phase particles on level screen casing are then washed away by the flushing fluid with powerful impact dynamics so that two level screen casing 11 and primary screen casing Keep the unobstructed of its sieve aperture.
During work, base tube 15 is placed in the horizontal segment of horizontal completion, and viscous crude enters wrapping wire 13 and set by the gap of wrapping wire 13 In the gap that pipe is formed, after the filtration of foamed iron 19, entered by fuel feed hole 16 inside base tube 15, to realize The pumping of fluid;In the prior art, steam flooding technology is used when being exploited to viscous crude, i.e., steam injection well is set above oil reservoir And producing well, constantly pass through steam in steam injection well so that steam constantly heats the stratum around pit shaft, while the original in stratum Oil is also heated, and the steam zone progressively extended with the continuous injection of steam is formed in the stratum of near wellbore, and steam can incite somebody to action Relatively low degree is dropped to containing saturation degree in steam zone, and by flowable crude oil(That is initial oil saturation and residual oil saturation The difference of degree)Displace steam zone;At the same time, in the horizontal segment of horizontal completion, steam consumingly moves to updip direction, and Under the force of gravity, heated crude oil is driven onto and had a down dip reversely, and the increase of the temperature with crude oil, in horizontal completion horizontal segment The mixture such as profit and gravel will seethe with excitement, and cause crude oil to be degraded(Disturbance caused by the boiling of mixture), profit with And the mixture of solid phase starts by being entered in horizontal completion horizontal segment inside base tube 15, wrapping wire 13 is a complete metal bar And be wound on by interval on multiple ribs 14, the primary filter unit to the major diameter solid phase such as gravel in profit is formed, and Foamed iron 19 then forms the secondary filter unit to minor diameter solid phase, to realize the sand control purpose of base tube 15;Also, when level It is adjacent when being influenceed in completion horizontal segment by fluid pressure and the self-contained heat of profit and causing to produce pressure change Two ribs 14 between the secondary filter section that is formed compressed, but be in filled with multiple in the secondary filter section The block foamed iron 19 of triangle, foamed iron 19 can still be formed in secondary filter section and multiple do not advised after stress deforms upon Then the runner of geometric figure for oil water mixture by, and the inner duct stress of foamed iron 19 occur minor variations and be not easy Blocked, while foamed iron 19 has certain elasticity, the duct in elasticity recovery deformation in foamed iron 19 resets, to maintain Percolation ability in secondary filter section, ensure the smooth exploitation of viscous crude.
Further, when oil water mixture enters in base tube 4, because the whole level that oil water mixture moves and drives is complete The motion of fluid in well horizontal segment, and by horizontal segment fluid apply in all directions to wrapping wire 2 formed it is isometrical Pressure on conveyor screw is different, when isometrical conveyor screw both sides discontinuity equalization, passes through the phase between ball 22 and annular groove Mutually it is slidably matched so that isometrical conveyor screw starts slow rotation outside base tube 4, and is now partly connected to isometrical conveyor screw gap The solid phases such as interior sand grains can directly drop with the rotation and washing away for oil water mixture of isometrical conveyor screw, avoid isometrical spiral Occur serious clogging on body, ensure the stability of oil-feed in base tube 4.
Preferably, in the length of the diminution section 113, flat segments 112 and impact section 111 in two level screen casing 11 radially Spend incremented by successively.The length of section 113, flat segments 112 and impact section 111 in two level screen casing 11 radially is reduced to be directly connected to Jet velocity of the flushing fluid on two level screen casing 11, i.e. the flushing fluid speed in sieve aperture accelerate more, the impact to primary screen casing Dynamics is then bigger, and radial direction of the length of section 113, flat segments 112 and impact section 111 along two level screen casing 11 is reduced in the present invention Outwards increase so that acceleration time of the flushing fluid in sieve aperture extends, and ensures that the momentum during injection of flushing fluid can sieve primary Solid phase particles on pipe and two level screen casing 11 are fully erased, ensure to exploit the stable output of production liquid in the horizontal completion later stage.
The present embodiment also includes giving up 5, and described give up 5 is connected by screw thread with the upper end of packer 6.Give up 5 with packer 6 Directly it can be docked after connection with the post of oil pick-up tube 7 in protective casing 10, while packer 6 is by the vertical portion of first paragraph oil pipe Upper and lower two parts are insulated into, and oilhole is opened in bottom, giving up 5 is located at top so that by being flowed into first paragraph primary screen casing Production liquid after oilhole is flowed into, directly mixed with by the production liquid phase flowed into second segment oil pipe, concentrate on after giving up in 5 and be extracted Outside well.
The present embodiment also includes multiple reinforcements 12, and multiple reinforcements 12 divide axially and in a ring along the base tube 15 Cloth is on wrapping wire 13.In the horizontal segment of horizontal completion, wrapping wire 13 is not only by the pressure of oil reservoir, and the pressure is with reservoir temperature Change and the moment change, i.e., during the abrupt change of pressure, wrapping wire 13 is highly prone to damage, and the present invention by around Multiple reinforcements 12 being distributed in a ring are set on silk 13 so that the first filter element that wrapping wire 13 is formed stably is supported, To tackle in horizontal completion continually changing production pressure in horizontal segment, while extend the service life of its own.
Preferably, TiALN-WC/C coatings are set in the outer wall of wrapping wire 13, and the coefficient of friction of TiALN-WC/C coatings is only Have 0.1, when the solid phases such as sand grains constantly contact with wrapping wire 13, can greatly reduce frictional dissipation between the two, and with certainly Lubricity, greatly ensure service life of the wrapping wire 13 in horizontal completion.
Preferably, according to the needs actually to recover the oil, base tube 15 is connected by connector 17 with blind pipe 18, facilitates crude oil Pumping, and the mode that abandoning tradition blind pipe 18 directly welds with base tube 15 in laying, to facilitate when wrapping wire 13 damages Wrapping wire 13 is directly changed without carrying out integral replacing to base tube 15, wrapping wire 13, reduces the production cost of thickened oil recovery.
Preferably, multiple balls 22 are rounded and array distribution is on the inner peripheral wall of the retainer plate 20.It is more Individual ball 22 is evenly distributed on the inner peripheral wall of retainer plate 20, i.e., the isometrical conveyor screw formed to wrapping wire 2 support more Add equilibrium, and when isometrical conveyor screw freely rotates outside base tube 4, isometrical conveyor screw will not be caused local stress collection occur In, while reducing the damage of wrapping wire 2, ensure the oil-feed efficiency in base tube 4.
Above-described embodiment, the purpose of the present invention, technical scheme and beneficial effect are carried out further Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc., all should include Within protection scope of the present invention.

Claims (7)

1. a kind of Shallow Heavy Oil Reservoir completion tubular column, include the production casing of L-shaped(1), it is characterised in that:The production casing (1)Horizontal segment be connected with two primary screen casings(4), sleeve pipe(2)It is arranged on two primary screen casings(4)Between, in the production Sleeve pipe(1)Pass through packer in vertical section(6)It is fixed with the oil pick-up tube of L-shaped(7), in sleeve pipe(2)Packer in pipe is inside installed (8), the oil pick-up tube(7)Horizontal ends in two primary screen casings(4)And sleeve pipe(2)The net horizontal section of composition freely prolongs Stretch, oil pick-up tube(7)Horizontal segment on be provided with two level screen casing(11), the two level screen casing(11)Face end and production casing (1)The primary screen casing of horizontal segment connection(4), in sleeve pipe(2)Two external packer of pipe are installed outside(3), and outside two pipes Packer(3)By bore hole(9)It is separated into three parts;The two level screen casing(11)Sieve aperture include along two level screen casing(11)Radially to The diminution section being sequentially connected outside(113), flat segments(112)And impact section(111), the diminution section(113)Internal diameter sieves along two level Pipe(11)Radially outward successively decrease, the impact section(111)Internal diameter is along two level screen casing(11)Radially outward successively decrease, the primary screen casing (4)Including being provided with multiple fuel feed holes on outer wall(16)Base tube(15), along the base tube(15)Axially set on its outer circle wall It is equipped with multiple ribs(14), and along base tube(15)Circle is in multiple ribs(14)Upper interval is wound with wrapping wire(13), Two adjacent ribs(14)Between be filled with the block foamed iron of triangle(19), and it is interior in the middle part of the isometrical conveyor screw Retainer plate is welded with wall(20), retainer plate(20)Rotated on inner peripheral wall and be provided with multiple balls(22), in addition to annular Guide rail(21), the guide rail(21)Along base tube(4)It is circumferential to run through multiple ribs(3)Middle part, and in guide rail(21)Outer circle wall On be provided with and multiple balls(22)The annular groove of cooperation.
A kind of 2. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:The diminution section(113)、 Flat segments(112)And impact section(111)In two level screen casing(11)Length radially is incremented by successively.
A kind of 3. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:Also include giving up(5), institute State and give up(5)Pass through screw thread and packer(6)Upper end connects.
A kind of 4. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:Also include multiple reinforcements (12), multiple reinforcements(12)Along the base tube(15)It is distributed in axially and in a ring wrapping wire(13)On.
A kind of 5. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:In the wrapping wire(13)Outside TiALN-WC/C layers are scribbled on wall.
A kind of 6. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:Also include connector (17), the base tube(15)Both ends pass through connector respectively(17)With blind pipe(18)Connection.
A kind of 7. Shallow Heavy Oil Reservoir completion tubular column according to claim 1, it is characterised in that:Multiple balls(22) Rounded and array distribution is in the retainer plate(20)Inner peripheral wall on.
CN201610722272.1A 2016-08-25 2016-08-25 A kind of Shallow Heavy Oil Reservoir completion tubular column Withdrawn CN107780893A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610722272.1A CN107780893A (en) 2016-08-25 2016-08-25 A kind of Shallow Heavy Oil Reservoir completion tubular column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610722272.1A CN107780893A (en) 2016-08-25 2016-08-25 A kind of Shallow Heavy Oil Reservoir completion tubular column

Publications (1)

Publication Number Publication Date
CN107780893A true CN107780893A (en) 2018-03-09

Family

ID=61389137

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610722272.1A Withdrawn CN107780893A (en) 2016-08-25 2016-08-25 A kind of Shallow Heavy Oil Reservoir completion tubular column

Country Status (1)

Country Link
CN (1) CN107780893A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309460A (en) * 2021-05-18 2021-08-27 中国地质大学(武汉) Oil-gas well fracturing filling well reconstruction drilling method and device
CN113464100A (en) * 2021-08-02 2021-10-01 山东科技大学 Deep sea hydrate exploitation sand control screen pipe blocking improvement system and application method
US11898421B2 (en) * 2022-04-27 2024-02-13 Southwest Petroleum University Sand control device for marine hydrate production

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309460A (en) * 2021-05-18 2021-08-27 中国地质大学(武汉) Oil-gas well fracturing filling well reconstruction drilling method and device
CN113464100A (en) * 2021-08-02 2021-10-01 山东科技大学 Deep sea hydrate exploitation sand control screen pipe blocking improvement system and application method
US11898421B2 (en) * 2022-04-27 2024-02-13 Southwest Petroleum University Sand control device for marine hydrate production

Similar Documents

Publication Publication Date Title
CN105863578A (en) Horizontal well completion string capable of achieving subsection exploiting
CN103189596B (en) Upgoing drainholes for reducing liquid-loading in gas wells
US7621326B2 (en) Petroleum extraction from hydrocarbon formations
US9022119B2 (en) Steam distribution apparatus and method for enhanced oil recovery of viscous oil
CA2913140C (en) Radial fishbone sagd
CN204283379U (en) Screen casing completes oil well intelligent water control pipe post
CN108708700A (en) A kind of method of SAGD technology application effects in improvement heterogeneous reservoir
CN101821476A (en) Flow restriction device
CN107780893A (en) A kind of Shallow Heavy Oil Reservoir completion tubular column
CN103939071A (en) Horizontal well steam flooding well network structure and steam flooding method
CA2749437A1 (en) Harvesting resource from variable pay intervals
US4124074A (en) Method for forming a gravel pack in tar sands
US20100326656A1 (en) Pattern steamflooding with horizontal wells
CN105927164A (en) Completion pipe string of shallow viscous crude oil reservoir
CN206753554U (en) One kind can sand control become a mandarin Balance route surely oily device
CN105863590A (en) Anti-sand pipe column for shallow heavy oil reservoir
CN105863579A (en) Production tubular column adopted for thermal recovery of heavy oil in horizontal well
CN105863576A (en) Sand-preventing pipe column capable of achieving subsection exploiting
CN107780899A (en) A kind of sand control pipe of achievable segmentation exploitation
CN107780895A (en) Sand control pipe for Shallow Heavy Oil Reservoir
CN105971568A (en) Screen pipe used for horizontal completed well thickened oil thermal recovery
CN105971567A (en) Screen pipe used for shallow thickened oil horizontal completed well
CN105756626A (en) Anti-damage screen pipe for horizontal well completion of shallow oil reservoir
CN107780896A (en) A kind of horizontal well completion tubular pile of achievable segmentation exploitation
CN105952388A (en) Heavy oil horizontal well completion pipe string realizing subsection mining

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180309

WW01 Invention patent application withdrawn after publication