CN107732947A - A kind of demand response system and method for energy internet - Google Patents

A kind of demand response system and method for energy internet Download PDF

Info

Publication number
CN107732947A
CN107732947A CN201711163288.4A CN201711163288A CN107732947A CN 107732947 A CN107732947 A CN 107732947A CN 201711163288 A CN201711163288 A CN 201711163288A CN 107732947 A CN107732947 A CN 107732947A
Authority
CN
China
Prior art keywords
demand response
electrical equipment
demand
energy
regulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711163288.4A
Other languages
Chinese (zh)
Inventor
杜强
沈煜
张晋茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG ENERGY AND NUCLEAR TECHNOLOGY APPLICATION RESEARCH INSTITUTE
Original Assignee
ZHEJIANG ENERGY AND NUCLEAR TECHNOLOGY APPLICATION RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG ENERGY AND NUCLEAR TECHNOLOGY APPLICATION RESEARCH INSTITUTE filed Critical ZHEJIANG ENERGY AND NUCLEAR TECHNOLOGY APPLICATION RESEARCH INSTITUTE
Priority to CN201711163288.4A priority Critical patent/CN107732947A/en
Publication of CN107732947A publication Critical patent/CN107732947A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J13/0062
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/40Bus networks
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/40Bus networks
    • H04L2012/40208Bus networks characterized by the use of a particular bus standard
    • H04L2012/40221Profibus
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/14Energy storage units
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of demand response system and method for energy internet, demand response compensation device is set in mechanical floor power demand side, and demand response regulates and controls terminal and sends regulating command to demand response electrical equipment and demand response compensation device according to regulation and control demand;Demand response compensation device is used to carry out charge or discharge according to regulating command, to adjust the energy difference between electrical equipment practical adjustments to power network compensation power network target during electrical equipment performs electricity consumption regulation.Using technical scheme, compensated by setting demand response compensation device in mechanical floor power demand side and participating in power grid regulation, so as to allow possess be unsatisfactory on regulating power but regulating time require electrical equipment can participate in the automatic demand response system of energy internet, the equipment range of choice for making it possible to participate in automatic demand response is greatly widened, and also makes the ability of regulation and control of energy internet be strengthened.

Description

A kind of demand response system and method for energy internet
Technical field
The present invention relates to energy Internet technical field, more particularly to a kind of demand response system for energy internet And method.
Background technology
Energy internet is a kind of internet and production of energy, transmission, storage, consumption and energy market depth integration Energy industry develops neomorph, has device intelligence, multipotency collaboration, information symmetrical, supply and demand is scattered, system is flat, transaction opening Etc. principal character.Energy internet is the grand strategy support for promoting China's energy revolution, to improving regenerative resource proportion, is promoted Enter fossil clean energy efficiently to utilize, lift Integrated Energy efficiency, promote energy market opening and industrial upgrading, form new warp Ji growth point, lifting energy international cooperation level are significant.
The automatic demand response of user side is the important component of energy internet.It is mainly carried out to industry and commerce user Flexible load regulates and controls, and it is actively engaged in power network peak load shifting, and balances and fluctuated caused by renewable energy power generation.To industry and commerce User and resident carry out flexible load regulation and control, realize automatic demand response, can give full play to Demand-side interactive resources and exist Peak load shifting, the balance intermittent renewable energy bring the effect in the fluctuation of power network.Using market mechanism, build with load The automatic demand response system of integrator's pattern, by disposing automatic demand response main website and terminal, carry out power consumer industry Non-core production auxiliary device, such as motor, blower fan, the modification of pump electrical equipment and communication system construction, gather user With energy data, the service such as energy monitor, analysis and diagnosis for providing personalization for power consumer;Data mining, policy of regulation and control point Analysis, realize that electric load participates in power network peak load shifting, realize that interconnecting for a variety of distributed energy resources is allocated with flexibility Transaction.But many industrial equipments possess regulating power, but load reduction can not be quickly completed in a short time.In order to ensure Production, the regulation processes of these energy consumption equipments may be from several minutes to dozens of minutes;And the signal of power network regulation needs Feedback is made in several seconds to tens seconds.According to prior art, such equipment is not meet automatic demand response energy internet The condition of transformation.The allowance that this kind equipment of industry and commerce user can not enjoy demand response is used, the operator of virtual plant Ability of regulation and control is also greatly affected.
Therefore for drawbacks described above present in currently available technology, it is necessary to be studied in fact, to provide a kind of scheme, Solves defect present in prior art.
The content of the invention
In view of this, it is necessory to provide a kind of demand response system and method for energy internet, by setting Standby layer power demand side sets demand response compensation device and participates in power grid regulation compensation, possesses regulating power but regulation so as to allow The electrical equipment for being unsatisfactory for requiring on time can be participated in the automatic demand response system of energy internet.
The defects of in order to overcome prior art, technical scheme are as follows:
A kind of demand response system for energy internet, using four-layer structure, including demand response electrical equipment, use In the demand response regulation and control terminal that controls multiple demand response electrical equipment power demands and more by Internet remote control The virtual plant operation platform of individual demand response regulation and control terminal, sets at least one demand response to mend in mechanical floor power demand side Device is repaid, demand response regulates and controls terminal and sends tune to demand response electrical equipment and demand response compensation device according to regulation and control demand Section instruction;Demand response electrical equipment performs electricity consumption regulation according to regulating command, and the demand response compensation device is used for basis Regulating command carries out charge or discharge, to adjust and use to power network compensation power network target during electrical equipment performs electricity consumption regulation Energy difference between electric equipment practical adjustments;
The demand response compensation device include two way convertor (PCS), battery management unit (BMS), energy-storage battery group, Control unit, detection metering units and communication unit, wherein, the two way convertor is used for energy conversion;The battery management Unit is used for the electric current, voltage, temperature information for detecting every group of monomer of battery pack, and sends the data to control unit, while Ensure that every group of monomer flows, pressed during charge/discharge;The detection metering units are used for real-time voltage, the electricity for detecting electrical equipment The parameters such as stream, power simultaneously measure electricity;The communication unit be used for receive demand response regulation and control terminal regulating command or to its Send data;Described control unit collects various data messages, and the mode of operation of decision systems is operating power.
Preferably, cooperate with and enter to power network by communication unit cascade network between multiple demand response compensation devices Row ability compensation.
The invention also discloses a kind of demand response method for energy internet, comprise the following steps:
Step S1:In mechanical floor power demand side, at least one demand response compensation device is set;
Step S2:Demand response regulates and controls terminal and filled according to regulation and control demand to demand response electrical equipment and demand response compensation Put transmission regulating command;
Step S3:Demand response compensation device carries out charge or discharge according to regulating command, to perform use in electrical equipment To the energy difference between the regulation of power network compensation power network target and electrical equipment practical adjustments during electricity regulation.
Preferably, the demand response compensation device includes two way convertor (PCS), battery management unit (BMS), energy storage Battery pack, control unit, detection metering units and communication unit, wherein, the two way convertor is used for energy conversion;The electricity Pond administrative unit is used for the electric current, voltage, temperature information for detecting every group of monomer of battery pack, and sends the data to control unit, Ensure that every group of monomer flows, pressed in charge/discharge simultaneously;The detection metering units are used for the real-time electricity for detecting electrical equipment The parameters such as pressure, electric current, power simultaneously measure electricity;The communication unit be used for receive demand response regulation and control terminal regulating command or It is sent to data;Described control unit collects various data messages, and the mode of operation of decision systems is operating power.
The present invention is compensated by setting demand response compensation device to participate in power grid regulation in mechanical floor power demand side, so as to Allow and possess the automatic demand that the electrical equipment for being unsatisfactory for requiring on regulating power but regulating time can participate in energy internet In Response System.This equipment range of choice for making it possible to participate in automatic demand response is greatly widened, and also makes energy internet Ability of regulation and control is strengthened.
Brief description of the drawings
Fig. 1 is the demand response system general frame schematic diagram that the present invention is used for energy internet.
Fig. 2 is the structural representation of demand response compensation device in the present invention.
Fig. 3 is the FB(flow block) for the demand response method for being used for energy internet in the present invention.
Specific examples below will combine above-mentioned accompanying drawing and further illustrate the present invention.
Embodiment
Technical scheme provided by the invention is described further below with reference to accompanying drawing.
In the prior art, the user of energy internet is participated in, if electrical equipment receives the demand that operating service business is assigned Response signal is controlled, and realizes the demand of spatial load forecasting or peak clipping at the appointed time, then operating service business, which needs to pay, to be used The corresponding expense in family.Meanwhile the energy expenditure of reduction is also a part for income.This is that automatic demand response can use contract The premise of energy management.
But it is different from air-conditioning, heat pump, illumination or household electrical appliance, many industrial equipments can not quickly complete in a short time Load reduction, unexpected regulation may be produced to production procedure and had a strong impact on.In order to ensure to produce, the regulation of these energy consumption equipments Process may be from several minutes to dozens of minutes;And the signal of power network regulation needs to make feedback within the several seconds to tens seconds. According to routine, such equipment is not meet the condition of automatic demand response transformation.This kind equipment of industry and commerce user can not be enjoyed Used by the allowance of demand response, the ability of regulation and control of the operator of virtual plant is also greatly affected.
The present invention allows aiming at this kind of application scenario and possesses regulating power, but desired consumption is unsatisfactory on regulating time Energy equipment is participated in the automatic demand response system of energy internet.Adjusted with compensation device to fill up power network regulation and equipment Between time difference caused by energy difference.Before demand response electrical equipment completes regulation, provided and lacked by compensation device Mouth energy.In the meantime, compensation device is in short time high power discharge state, and its power is equal to the regulated value of operator requirement With the difference of equipment real time energy consumption value.When equipment completes regulation or receives the termination signal of operator transmission, compensation equipment stops Discharged to power network, into reverse small-power charged state;High-power quick charge can also be carried out in the paddy electricity period, to reduce Overall energy expense.
Referring to Fig. 1, the demand response system general frame schematic diagram that the present invention is used for energy internet is shown, demand is rung Compensation device is answered to use four coating systems frameworks, respectively mechanical floor, measurement with the integrated of virtual plant comprehensive operation service platform Layer, Internet and main website layer, major function are as follows:
(1) mechanical floor
It is made up of user side adjustable apparatus and demand response compensation device.The former include electric motor system, blower fan system, Pumping system etc..
(2) layer is measured
It is made up of automatic demand response regulation and control terminal, non-intruding measuring equipment and various intelligent meters, is responsible for compensation device The transmission of collection, remote control command with user side equipment information and the communication with main website.
(3) Internet
Internet is made up of equipment such as 4G communication equipments, data encryption equipment and interchangers, is mounted in user side oneself The hinge that dynamic demand response terminal and non-intruding measuring equipment communicate with main station system.
(4) main website layer
Main website layer is made up of front-collection equipment, database server and application server, is responsible for compensation device and use Family equipment carries out Data Collection, processing, analysis and storage, while issues control command to demand response regulation and control terminal.
As shown in Figure 1, the present invention sets at least one demand response compensation device in mechanical floor power demand side, and demand is rung Terminal should be regulated and controled regulating command is sent to demand response electrical equipment and demand response compensation device according to regulation and control demand;Demand is rung Electricity consumption regulation is performed according to regulating command using electric equipment, the demand response compensation device is used to be filled according to regulating command Electricity or electric discharge, to be performed in electrical equipment during electricity consumption is adjusted to the regulation of power network compensation power network target and electrical equipment practical adjustments Between energy difference.
Compensation device of the present invention can several parallel connections, the ac bus of access demand response energy consumption equipment side; To meet the requirement of different capacity.Automatic network-building between each compensation device, receive the instruction of demand response regulation and control terminal, according to every The surplus of energy-storage units in platform compensation device, determine respective discharge capacity or charge volume.In Regional Energy overall well-to-do period, As wind energy or luminous energy are more abundant, the not high spring and autumn of total load, compensation device can also be by the pattern of peak-trough electricity energy-accumulating power station Work, to make full use of equipment, allow maximum revenue.
Referring to Fig. 2, the structural representation of demand response compensation device in the present invention, demand response compensation device bag are shown Include two way convertor (PCS), battery management unit (BMS), energy-storage battery group, control unit, detection metering units and communication unit Member, wherein, PCS is responsible for energy conversion, both can with battery to grid transmission, can also power network charged to battery.BMS is responsible for detection The key messages such as the electric current of every group of monomer of battery pack, voltage, temperature, and control unit is sent the data to, while in charge/discharge When ensure that every group of monomer flows, pressed.Energy-storage battery group must be low capacity, the motive-power battery of high-discharge-rate, with lithium from Based on sub- battery.General stored energy capacitance selection is discharged 20~30 minutes in full power.Detection metering units effect is detection power consumption The parameters such as the real-time voltage of equipment, electric current, power, while measure electricity.Communication unit is responsible for receiving, sends data to demand sound Should regulate and control terminal, and with other compensation device group-net communications.Control unit collects various data messages, the Working mould of decision systems The parameters such as formula, watt level.
The demand response compensation device designed using the present invention, can be operated in different mode of operations, various to be applicable Different application scenarios.
1st, compensation model
When demand response regulation and control terminal receives the startup order that main station system is sent, energy consumption equipment and compensation device are same Shi Qidong.The energy consumption equipment power at metering units record current time, the reduction that control unit instructs according to main website are detected first Value and the time for completing response, current time PCS compensation power is calculated, and start to discharge to ac bus.Set in power consumption During standby progressively regulation, PCS compensation power is also accordingly made adjustment.When equipment completion regulation, or the deadline is reached, Or when receiving the termination signal of main website transmission, compensation equipment stops electric discharge.
2nd, rectification mode
After compensation model terminates, just into rectification mode.Now PCS charges from ac bus power taking to energy-storage battery.Root According to the plan of main website, there can be two kinds of rectification modes.As main website determines capacity may be arranged to regulate and control in following 8 hours, then mend System is repaid to charge using 1/4C~1/6C;As main website did not arranged capacity to regulate and control in following 8 hours, then compensation system according to when Between, at peak, electricity choosing period of time is charged using 1/15~1/20C, is charged in the paddy electricity period using 1C~1/4C.
3rd, backup mode
If power distribution network catastrophic failure, compensation device can quickly identify and be switched to backup mode.Now first confirm that automatic Shearing device has disconnected ac bus, and PCS carries out DC/AC inversions afterwards, is discharged to the demand response electrical equipment of the access point, Drop power regulating signals are sent to it simultaneously.After power system restoration is normal, backup mode, and incoming transport bus again are exited. As energy-storage battery group has consumed more than 90%, when power network does not recover yet, then sent to the demand response electrical equipment of the access point Soft-off signal, power-off suddenly is avoided to cause bigger loss.
4th, energy storage pattern
In Regional Energy overall well-to-do period, main station system, which sends instruction, can make compensation device be operated in energy-accumulating power station mould Formula.Now, compensation device can use as a small-sized energy-accumulating power station., can according to the short-term scene of main website and load prediction The generation schedule of whole plant area's whole day each micro battery of 24 hours, load electricity consumption plan are arranged with reasonable plan ahead, energy storage is filled Electric discharge plan, generation schedule and power demand is set to reach balance generally.It is small that compensation device can be arranged in load power consumption, Charged when electricity price is low;It is big in load power consumption, discharged when electricity price is high.Realize that paddy electricity peak is used, reduce electric cost.Compensation system has The charging interval of body, charge power, discharge time, discharge power are planned as a whole to determine by main website.
5th, communication modes
To realize the purpose of main website carries out automatic demand response control, operational monitoring to user power utilization equipment, main website needs By automatic demand response terminal, real-time information communication, transmission regulation are carried out with compensation device and the main electrical equipment of user Instruction, real-time collecting device running status, environment parameter and with can situation.Communication modes mainly include following several classes:
Sent in live real time data:Support by DLT645, MODBUS, OPC and BACnet agreement collecting device energy and Running status, and uniformly switch to IEC60870-5-104 teletransmission stipulations, sent in remote signalling amount displacement in real time, on remote measurement quantitative change bit timing Send, meet to monitor and call together in real time to survey adjustable requirement.
Demand response instruction issuing:Demand response control instruction, using compatible GDW376.1 communications protocol, can and electricity consumption Information acquisition system slitless connection.
Control instruction forwards:Demand response instruction translation is the control to equipment according to preset control strategy by terminal Instruction, and can be communicated by MODBUS agreements with device controller.It can also be led to by OPC or BACnet with BAS system News, then pass through BAS system control device state.
Referring to Fig. 3, a kind of FB(flow block) of demand response method for energy internet in the present invention is shown, including Following steps:
Step S1:In mechanical floor power demand side, at least one demand response compensation device is set;
Step S2:Demand response regulates and controls terminal and filled according to regulation and control demand to demand response electrical equipment and demand response compensation Put transmission regulating command;
Step S3:Demand response compensation device carries out charge or discharge according to regulating command, to perform use in electrical equipment To the energy difference between the regulation of power network compensation power network target and electrical equipment practical adjustments during electricity regulation.
Using above-mentioned technical proposal, the present invention in mechanical floor power demand side by setting demand response compensation device to participate in Power grid regulation compensate, so as to allow possess be unsatisfactory on regulating power but regulating time require electrical equipment can participate in the energy In the automatic demand response system of internet.This equipment range of choice for making it possible to participate in automatic demand response is greatly widened, Also the ability of regulation and control of energy internet is made be strengthened.
The explanation of above example is only intended to help the method and its core concept for understanding the present invention.It should be pointed out that pair For those skilled in the art, under the premise without departing from the principles of the invention, the present invention can also be carried out Some improvement and modification, these are improved and modification is also fallen into the protection domain of the claims in the present invention.
The foregoing description of the disclosed embodiments, professional and technical personnel in the field are enable to realize or using the present invention. A variety of modifications to these embodiments will be apparent for those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one The most wide scope caused.

Claims (4)

1. a kind of demand response system for energy internet, using four-layer structure, including demand response electrical equipment, it is used for The demand response of multiple demand response electrical equipment power demands is controlled to regulate and control terminal and multiple by Internet remote control Demand response regulates and controls the virtual plant operation platform of terminal, it is characterised in that is set in mechanical floor power demand side at least one Demand response compensation device, demand response regulate and control terminal and compensated according to regulation and control demand to demand response electrical equipment and demand response Device sends regulating command;Demand response electrical equipment performs electricity consumption regulation, the demand response compensation dress according to regulating command Put for carrying out charge or discharge according to regulating command, to be performed in electrical equipment during electricity consumption is adjusted to power network compensation power network mesh Energy difference between mark regulation and electrical equipment practical adjustments;
The demand response compensation device includes two way convertor (PCS), battery management unit (BMS), energy-storage battery group, control Unit, detection metering units and communication unit, wherein, the two way convertor is used for energy conversion;The battery management unit For detecting the electric current, voltage, temperature information of every group of monomer of battery pack, and control unit is sent the data to, while in discharge charge Ensure that every group of monomer flows, pressed when electric;The detection metering units are used for the real-time voltage, electric current, work(for detecting electrical equipment The parameters such as rate simultaneously measure electricity;The communication unit is used to receive the regulating command of demand response regulation and control terminal or is sent to count According to;Described control unit collects various data messages, and the mode of operation of decision systems is operating power.
2. the demand response system according to claim 1 for energy internet, it is characterised in that multiple demands By communication unit cascade network between response compensation device, cooperate with to power network and carry out ability compensation.
A kind of 3. demand response method for energy internet, it is characterised in that comprise the following steps:
Step S1:In mechanical floor power demand side, at least one demand response compensation device is set;
Step S2:Demand response regulates and controls terminal and sent out according to regulation and control demand to demand response electrical equipment and demand response compensation device Send regulating command;
Step S3:Demand response compensation device carries out charge or discharge according to regulating command, is adjusted with performing electricity consumption in electrical equipment To the energy difference between the regulation of power network compensation power network target and electrical equipment practical adjustments during section.
4. the demand response method according to claim 4 for energy internet, it is characterised in that the demand response Compensation device includes two way convertor (PCS), battery management unit (BMS), energy-storage battery group, control unit, detection metering list Member and communication unit, wherein, the two way convertor is used for energy conversion;The battery management unit is every for detecting battery pack Electric current, voltage, the temperature information of group monomer, and control unit is sent the data to, while ensure every group of monomer in charge/discharge Flow, press;The detection metering units are used to detect the parameters such as the real-time voltage, electric current, power of electrical equipment and measure electricity Amount;The communication unit is used to receive the regulating command of demand response regulation and control terminal or is sent to data;Described control unit Collect various data messages, the mode of operation of decision systems is operating power.
CN201711163288.4A 2017-11-21 2017-11-21 A kind of demand response system and method for energy internet Pending CN107732947A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711163288.4A CN107732947A (en) 2017-11-21 2017-11-21 A kind of demand response system and method for energy internet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711163288.4A CN107732947A (en) 2017-11-21 2017-11-21 A kind of demand response system and method for energy internet

Publications (1)

Publication Number Publication Date
CN107732947A true CN107732947A (en) 2018-02-23

Family

ID=61216485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711163288.4A Pending CN107732947A (en) 2017-11-21 2017-11-21 A kind of demand response system and method for energy internet

Country Status (1)

Country Link
CN (1) CN107732947A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110048513A (en) * 2019-02-28 2019-07-23 深圳市科陆电子科技股份有限公司 Echelon utilizes Vehicular dynamic battery energy-storage system
CN110298594A (en) * 2019-07-04 2019-10-01 北京华建网源电力设计研究院有限公司 A kind of the load automatic regulating system and method for virtual plant
EP4089871A1 (en) * 2021-05-14 2022-11-16 Huawei Digital Power Technologies Co., Ltd. Energy storage system and related method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120123604A1 (en) * 2010-11-12 2012-05-17 Nathan Bowman Littrell Systems, methods, and apparatus for demand response of battery-powered devices
CN106099962A (en) * 2016-08-22 2016-11-09 国网江苏省电力公司盐城供电公司 A kind of electric automobile charging station is actively engaged in the system and method for electrical network regulation
CN106655243A (en) * 2016-08-12 2017-05-10 浙江工业大学 Electric vehicle's automatic demand responding method aiming to maintain the supply-and-demand balance of a micro power grid
CN106786542A (en) * 2017-01-04 2017-05-31 国家电网公司 A kind of demand response system
CN106950840A (en) * 2017-05-11 2017-07-14 山东理工大学 Towards the integrated energy system layered distribution type control method for coordinating of power network peak clipping
CN107230984A (en) * 2017-07-26 2017-10-03 杭州电子科技大学 A kind of electricity needs response participates in the method and control system of distribution network voltage regulation
CN107332266A (en) * 2017-08-25 2017-11-07 浙江南都电源动力股份有限公司 User side energy-accumulating power station and its application model
CN207459740U (en) * 2017-11-21 2018-06-05 浙江省能源与核技术应用研究院 A kind of demand response system for energy internet

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120123604A1 (en) * 2010-11-12 2012-05-17 Nathan Bowman Littrell Systems, methods, and apparatus for demand response of battery-powered devices
CN106655243A (en) * 2016-08-12 2017-05-10 浙江工业大学 Electric vehicle's automatic demand responding method aiming to maintain the supply-and-demand balance of a micro power grid
CN106099962A (en) * 2016-08-22 2016-11-09 国网江苏省电力公司盐城供电公司 A kind of electric automobile charging station is actively engaged in the system and method for electrical network regulation
CN106786542A (en) * 2017-01-04 2017-05-31 国家电网公司 A kind of demand response system
CN106950840A (en) * 2017-05-11 2017-07-14 山东理工大学 Towards the integrated energy system layered distribution type control method for coordinating of power network peak clipping
CN107230984A (en) * 2017-07-26 2017-10-03 杭州电子科技大学 A kind of electricity needs response participates in the method and control system of distribution network voltage regulation
CN107332266A (en) * 2017-08-25 2017-11-07 浙江南都电源动力股份有限公司 User side energy-accumulating power station and its application model
CN207459740U (en) * 2017-11-21 2018-06-05 浙江省能源与核技术应用研究院 A kind of demand response system for energy internet

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘东旗;王连成;庞金海;吴玉光;: "智能电网自动需求响应技术系统的研究", 自动化仪表, vol. 34, no. 11, pages 76 - 79 *
石怀德;李德智;高峰;袁静伟;郭炳庆;王永雷;: "能源互联网中用电与需求侧管理商业模式研究", 电源技术, vol. 40, no. 11, pages 2288 - 2291 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110048513A (en) * 2019-02-28 2019-07-23 深圳市科陆电子科技股份有限公司 Echelon utilizes Vehicular dynamic battery energy-storage system
CN110048513B (en) * 2019-02-28 2023-08-18 深圳市科陆电子科技股份有限公司 Power battery energy storage system for gradient utilization vehicle
CN110298594A (en) * 2019-07-04 2019-10-01 北京华建网源电力设计研究院有限公司 A kind of the load automatic regulating system and method for virtual plant
EP4089871A1 (en) * 2021-05-14 2022-11-16 Huawei Digital Power Technologies Co., Ltd. Energy storage system and related method
US11757285B2 (en) 2021-05-14 2023-09-12 Huawei Digital Power Technologies Co., Ltd. Energy storage system and related method

Similar Documents

Publication Publication Date Title
CN109713712B (en) Optical storage intelligent management integrated machine and optical storage intelligent management method
CN103001225B (en) MAS-based (multi-agent system) multi-microgrid energy management system simulation method
CN110190597B (en) Distributed power management system
CN103400205B (en) A kind of power distribution network energy efficiency management system and method for coordinating control based on idle work optimization
CN104716693B (en) The energy management method and controller, system of a kind of distributed energy storage battery
CN109409702A (en) A kind of operation of power networks index analysing system
CN103208809A (en) Regulating device and control method for balance of demand side battery pack
CN105743111A (en) Energy storage system of power battery for echelon utilization vehicle
CN107732947A (en) A kind of demand response system and method for energy internet
CN114285159B (en) Energy control system for transformer area
CN105515110A (en) Electric automobile ordered charging real-time control system
CN109193723B (en) Combined base station backup energy storage power supply and control method
CN113263938A (en) Intelligent ordered charging system and method based on edge calculation
CN104158187A (en) Control method and system for secondary allocation of local power grid energy and power
CN110061565A (en) A kind of energy storage charge/discharge capacity control system and method based on wind-driven generator
CN103580052B (en) A kind of composite energy storage power station for active distribution network and distribution method thereof
CN111610361A (en) Electric power Internet of things random measurement system and method
CN207249427U (en) A kind of electric meter system applied to family's photovoltaic generation
CN113098042A (en) Base station distributed energy storage power-saving control method based on user power utilization prediction
CN110867934A (en) Commercial power solar charging module sharing system
CN204190487U (en) For the load data collect and transmit analytical equipment in rural power dispensing table district
CN207459740U (en) A kind of demand response system for energy internet
CN109004641A (en) A kind of microgrid source net lotus control method for coordinating based on energy source optimization scheduling
CN117057547A (en) Method, device and storage medium for constructing multi-form load resource scheduling model of intelligent energy service platform
CN216530731U (en) Synthesize green energy efficiency intelligence management and control system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination