CN107730034A - A kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted planing method - Google Patents

A kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted planing method Download PDF

Info

Publication number
CN107730034A
CN107730034A CN201710903919.5A CN201710903919A CN107730034A CN 107730034 A CN107730034 A CN 107730034A CN 201710903919 A CN201710903919 A CN 201710903919A CN 107730034 A CN107730034 A CN 107730034A
Authority
CN
China
Prior art keywords
station
node
distant
type
nodes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710903919.5A
Other languages
Chinese (zh)
Other versions
CN107730034B (en
Inventor
张铭泽
李亦农
宋若晨
王伊晓
仇成
李新聪
秦旷宇
徐涛
邵捷
费斐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Online Extra Large Electric Design Co Ltd
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Online Extra Large Electric Design Co Ltd
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Online Extra Large Electric Design Co Ltd, State Grid Shanghai Electric Power Co Ltd filed Critical State Online Extra Large Electric Design Co Ltd
Priority to CN201710903919.5A priority Critical patent/CN107730034B/en
Publication of CN107730034A publication Critical patent/CN107730034A/en
Application granted granted Critical
Publication of CN107730034B publication Critical patent/CN107730034B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

Layout planing method, comprise the following steps the present invention relates to a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV:1) the typical rack type and node-classification of aerial net are determined;2) " three is distant " node is set by node-classification;3) terminal is carried out at " three is distant " node to layout;4) Calculation of Reliability check is powered to result of layouting;5) optimize terminal according to check result to layout.Compared with prior art, the present invention has the advantages that reasonable reliable, shortening fault location time of layouting.

Description

A kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted planing method
Technical field
It is automatic more particularly, to a kind of distribution of the aerial nets of A+ regions 10kV the present invention relates to the field of power distribution of typical rack Change terminal to layout planing method.
Background technology
According to current overall present situation, the power supply reliability of aerial net is significantly lower than cable system.Therefore, from reliability requirement Speech, the distribution power automation terminal configuration standard of aerial net should be higher than that cable system.
On the other hand, because " three is distant " terminal typically uses fiber optic communication mode, aerial net fibre optic installations can use peg Mode realizes that enforcement difficulty and cost are relatively low, and cable system fibre optic installations are then frequently necessary in no comb and hole position resource Shi Caiyong digging direct-buried modes, enforcement difficulty and cost are higher (containing engineering cost and damages), and fibre optic installations expense accounts for total cost Ratio is high.Accordingly, with respect to cable system, net configuration " three is distant " terminal is maked somebody a mere figurehead, is advantageously for input-output efficiency 's.
For interconnection switch, when its position is closer to backbone end, after by block switch isolated fault, by closing It is then more to close the load that the interconnection switch can turn to supply.By taking more segmentation appropriateness contacts as an example, if as shown in figure 1,3 interconnection switches In only select configuration " three is a distant " terminal, then configuration end QS9 switch when, backbone optional position failure, can pass through After block switch isolated fault section, recover the power supply of all non-faulting sections by QF1 and QS9 closures;If configuration is in head end QS7 switch when, QS2 to the line failure between QS9, then the non-faulting section after trouble point can not be closed by QS7 Restore electricity rapidly, it is necessary to which manually closing QS9 switches can just recover.Therefore, difficulty and appropriation budget bar are being built on an equal basis Under part, and offside circuit turn energy supply power it is enough when, should preferentially choose the interconnection switch close to backbone end and carry out terminal cloth Point.
To sum up, aerial net should consider Distribution Automation Construction transformation difficulty and capital budgeting situation, to interconnection switch The distribution power automation terminal covering based on " three is distant " terminal is carried out with block switch.For interconnection switch, difficulty is built on an equal basis Under the conditions of appropriation budget, when offside circuit turn energy supply power is enough, the interconnection switch closer to backbone end is layouted preferentially Level is higher.
Load saturation value, which is organized, for A+ classes region, between any 2 adjacent " three is distant " nodes must not exceed 2MW." three It is distant " node is set, and it is the main contents of A+ classes region Distribution Automation Construction;" two is distant " node can according to the actual requirements, in line with Economical and practical principle sets (if desired primary equipment is changed, then should not be used as " two is distant " node), further reduces monitoring blind spot, Shorten fault location time.
The content of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of A+ regions 10kV framves The distribution power automation terminal of abortive haul is layouted planing method.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted planing method, is comprised the following steps:
1) the typical rack type and node-classification of aerial net are determined;
2) " three is distant " node is set by node-classification;
3) terminal is carried out at " three is distant " node to layout;
4) Calculation of Reliability check is powered to result of layouting;
5) optimize terminal according to check result to layout.
Preferably, described typical rack type includes transformer station's Firsthand Users, transformer station supplies p-type for K-type station, transformer station Stand Single-ring network, WX types station Single-ring network, transformer station supplies the looped network pattern of P/W types station 1.5 for the looped network pattern one of P/W types station 1.5, transformer station 2nd, transformer station supplies P/W types station Single-ring network or double for p-type station dual-ring network, more segmentation appropriateness contacts, K-type station Firsthand Users, K-type station Looped network, K-type station overhead outlet Connection Mode, p-type station outlet Connection Mode.
Preferably, described transformer station includes 1 node, 2 nodes, 3 nodes, 4 sections for the node type of p-type station Single-ring network Point, 5 nodes;1 node is using first p-type station as " three is distant " node;2 nodes are using first and second p-type station as " three It is distant " node;3 nodes using first and the 3rd p-type station as " three is distant " node, do not layout terminal by remaining node;4 nodes are by Two and the 4th p-type station conduct " three is distant " node;5 nodes save at first, the 3rd, the 5th p-type station as " three is distant " Point.
Preferably, the node type of described WX types station Single-ring network is included no more than 14 nodes and more than 14 nodes, remaining Node is not layouted terminal;No more than 14 nodes using both sides first and last WX types station as " three is distant " node, more than 14 Node is using both sides first and last WX types station as " three is distant " node, then with equal separated time road and any two " three is distant " It is that principle sets up " three is distant " node that load saturation value is organized between node no more than 2MW, and remaining node is not layouted terminal.
Preferably, the node type of described WH types station Single-ring network is included no more than 16 nodes and more than 16 nodes;Do not surpass 16 nodes are crossed using last WH types station of both sides and the WH types station among the circuit of both sides as " three is distant " node, remaining node Do not layout terminal;More than 16 nodes by both sides using last WH types station of both sides as " three is distant " node, then with equal separated time road And it is that principle sets up " three is distant " node that load saturation value is organized between any two " three is distant " node no more than 2MW, remaining node not cloth Point terminal.
Preferably, described transformer station's Firsthand Users, K-type station Firsthand Users are not provided with " three is distant ", " two is distant " node.
Preferably, described more segmentations are moderately got in touch with using backbone interconnection switch as " three is distant ", node.
Preferably, described K-type station includes for P/W types station Single-ring network or dual-ring network:
1) the stand erectly terminal p-type station of confession of K-type is not provided with " three is distant " node, the p-type station or WX, WH type station two that K-type station is confessed Level looped network interior joint quantity is less than or equal to 3, is not provided with " three is distant " node;
2) P, WX, WH type station second-class loop that K-type station is confessed, monocyclic p-type station or WX, WH type tiny node quantity are more than or equal to 4, if looped network group load saturation value reaches 2MW, " three is distant " node is set;When looped network group load saturation value is less than 2MW, no " three is distant " node is set.
Preferably for K-type station overhead outlet Connection Mode, if at least one block switch on circuit be present, contact is opened Close and be used as " three is distant " node;For p-type station outlet Connection Mode, subordinate's outlet that the p-type station in non-one-level looped network is confessed is not set Put " three is distant " and " two is distant " node.
Preferably, scheme of the described transformer station for the looped network pattern one of P/W types station 1.5 with reference to p-type station Single-ring network;Described Scheme of the transformer station for the looped network pattern two of P/W types station 1.5 with reference to WH types station Single-ring network;Described transformer station is bicyclic for P/W types station Scheme of the net with reference to p-type station Single-ring network.
Compared with prior art, the present invention is equipped with difference for the type of the different typical racks of the aerial net in A+ regions Terminal sensor distributing, meet Q/GDW 11184-2014《Distribution automation planning designing technique directive/guide》Related request it is same When, pass through power supply reliability check, reached higher AFset values, shortened fault location time, planning more adduction of layouting Reason, enhance the safety and reliability of region distribution.
Brief description of the drawings
Fig. 1 is to be segmented the exemplary block diagram moderately got in touch with more;
Fig. 2 is flow chart of the method for the present invention;
Fig. 3 is the aerial net electricity system figure in A+ regions of an embodiment of the present invention;
Fig. 4 is that network termination sensor distributing figure is maked somebody a mere figurehead in the A+ regions of an embodiment of the present invention;
Fig. 5 is that network termination sensor distributing figure is maked somebody a mere figurehead in the A+ regions after the optimization of an embodiment of the present invention.
Embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
Embodiment
Layouted planing method the present invention relates to a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV, as shown in Fig. 2 Comprise the following steps:
1) the typical rack type and node-classification of aerial net are determined;
2) " three is distant " node is set by node-classification;
3) terminal is carried out at " three is distant " node to layout;
4) Calculation of Reliability check is powered to result of layouting;
5) optimize terminal according to check result to layout.
According to above-mentioned steps, the typical rack of the aerial nets of A+ regions 10kV is analyzed, the setting of its " three is distant " node And the programme that terminal is layouted is as shown in table 1.
Table 1
The rack of the present embodiment comes from Shanghai Electric Power Co urban district electric company area under one's jurisdiction, belongs to A+ classes region.The region Electricity system as shown in figure 3, being aerial backbone from loyal station from 11 outlets, sharing 1131 Zhao Zhoudongtaidong and 1044 on backbone starts 2 block switches in Zhou Hefei south, and 3 connection such as south, 0912 Hefei Ji Nanxi, 0745 Zhao Zhoujianguobei are revived by 0822 Jinan Network switch is got in touch with other 10kV overhead lines respectively.From being stood outlet since loyalty, first backbone is segmented non-branch extension bar and become, the Branch meets 4 bars changes and 1 user altogether for two backbone segmentations, and branch connects 4 bars changes altogether for the 3rd backbone segmentation.
According to the planing method of the present invention, 2 block switch conducts such as 1131 Zhao Zhoudongtaidong and 1044 Zhao Zhouhefeinan " three is distant " node, 0745, which starts Zhou Jianguo north interconnection switch, is used as " three is distant " node, and south, 0912 Hefei Ji Nanxi are revived in 0822 Jinan Deng 2 interconnection switches depending on offside line condition determine whether carry out terminal layout.Aid in " two is distant " node true by site inspection It is fixed whether to need to add, as shown in Figure 4.
It is the aerial backbone that transformer station confesses from 11 circuits according to the planing method of the present invention, only 2 segmentations are opened Close, therefore all as " three is distant " node.0745 to start Zhou Jianguo north interconnection switch be line end interconnection switch, therefore preferential is made For " three is distant " node, 2 interconnection switches such as south, 0912 Hefei Jinan west are revived in 0822 Jinan to be determined depending on offside line requirements Terminal whether is carried out to layout.If, can in addition, find that circuit has cross a river road or building etc. to make an inspection tour difficult situation by site inspection Suitably set up auxiliary " two is distant " node.
Power supply reliability after planning is checked, the present embodiment, which is taken, calculates AFset (only consideration fault outage factors Average power supply availability) calculate power supply reliability, design conditions are as follows:
Overhead line fault rate:0.07 times/year of .km (presses Guo Wang companies《Distribution automation planning designing technique directive/guide》Appendix B Insulating frame ceases to be busy fault rate consider);
ASAI3 (availability of averagely powering) desired value:99.999%;
T1 (fault zone positioning time):1h;
T2 (by the time required to manually carrying out fault section isolation under fault location guide):1h;
T3 (the time required to fault restoration):4h;
Number of users:According to rack actual conditions, each bar, which becomes to become with a user, is used as an equivalent user, totally 9 etc. Effectiveness family;
Line length:According to rack actual conditions, each section of line length has been shown on Fig. 3.
It is computed, it is 99.9985972% to make somebody a mere figurehead backbone bulk supply reliability AFset values, when not considering scheduled outage 99.999% desired value has been unable to reach, therefore " three is distant " segmentation for this circuit, should be set up in conditions permit and is opened Close.Assuming that " three is a distant " block switch is set up, as shown in Figure 5.
Calculated again, it is 99.9991317% to make somebody a mere figurehead backbone bulk supply reliability AFset values, to reach 99.999% desired value can be that scheduled outage per family leaves 0.692min, meet Q/GDW 11184-2014《Distribution is automatic Change planning and designing fire protection technology》Related request, thus optimize after terminal layout programme power supply reliability check pass through.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any Be familiar with the staff of the art the invention discloses technical scope in, various equivalent modifications can be readily occurred in or replaced Change, these modifications or substitutions should be all included within the scope of the present invention.Therefore, protection scope of the present invention should be with power It is required that protection domain be defined.

Claims (10)

  1. The planing method 1. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted, it is characterised in that this method includes Following steps:
    1) the typical rack type and node-classification of aerial net are determined;
    2) " three is distant " node is set by node-classification;
    3) terminal is carried out at " three is distant " node to layout;
    4) Calculation of Reliability check is powered to result of layouting;
    5) optimize terminal according to check result to layout.
  2. The planing method 2. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 1 is layouted, its It is characterised by, described typical rack type includes transformer station's Firsthand Users, transformer station supplies p-type station monocyclic for K-type station, transformer station Net, WX types station Single-ring network, transformer station are for the looped network pattern one of P/W types station 1.5, transformer station for the looped network pattern two of P/W types station 1.5, change Power station supplies P/W types station Single-ring network or dual-ring network, K for p-type station dual-ring network, more segmentation appropriateness contacts, K-type station Firsthand Users, K-type station Type station overhead outlet Connection Mode, p-type station outlet Connection Mode.
  3. The planing method 3. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, described transformer station includes 1 node, 2 nodes, 3 nodes, 4 nodes, 5 sections for the node type of p-type station Single-ring network Point;1 node is using first p-type station as " three is distant " node;2 nodes save first and second p-type station as " three is distant " Point;3 nodes using first and the 3rd p-type station as " three is distant " node, do not layout terminal by remaining node;4 nodes are by second " three is distant " node is used as with the 4th p-type station;5 nodes are using first, the 3rd, the 5th p-type station as " three is distant " node.
  4. The planing method 4. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, the node type of described WX types station Single-ring network is included no more than 14 nodes and more than 14 nodes, and remaining node is not Layout terminal;, will more than 14 nodes no more than 14 nodes using both sides first and last WX types station as " three is distant " node Both sides first and last WX types station are used as " three is distant " node, then between equal separated time road and any two " three is distant " node Group load saturation value is that principle sets up " three is distant " node no more than 2MW, and remaining node is not layouted terminal.
  5. The planing method 5. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, the node type of described WH types station Single-ring network is included no more than 16 nodes and more than 16 nodes;No more than 16 sections Point does not layout at last WH types station of both sides and the WH types station among the circuit of both sides as " three is distant " node, remaining node Terminal;More than 16 nodes by both sides using last WH types station of both sides as " three is distant " node, then with equal separated time road and arbitrarily It is that principle sets up " three is distant " node that load saturation value is organized between two " three is distant " nodes no more than 2MW, and remaining node is not layouted terminal.
  6. The planing method 6. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, described transformer station's Firsthand Users, K-type station Firsthand Users are not provided with " three is distant ", " two is distant " node.
  7. The planing method 7. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, described more segmentations are moderately got in touch with using backbone interconnection switch as " three is distant ", node.
  8. The planing method 8. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, described K-type station includes for P/W types station Single-ring network or dual-ring network:
    1) the stand erectly terminal p-type station of confession of K-type is not provided with " three is distant " node, the p-type station or WX, WH type station two-stage ring that K-type station is confessed Net interior joint quantity is less than or equal to 3, is not provided with " three is distant " node;
    2) P, WX, WH type station second-class loop that K-type station is confessed, monocyclic p-type station or WX, WH type tiny node quantity are more than or equal to 4 , if looped network group load saturation value reaches 2MW, " three is distant " node is set;When looped network group load saturation value is less than 2MW, do not set Put " three is distant " node.
  9. The planing method 9. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 2 is layouted, its It is characterised by, for K-type station overhead outlet Connection Mode, if at least one block switch on circuit be present, interconnection switch conduct " three is distant " node;For p-type station outlet Connection Mode, subordinate's outlet that the p-type station in non-one-level looped network is confessed is not provided with " three It is distant " and " two is distant " node.
  10. The planning side 10. a kind of distribution power automation terminal of the aerial nets of A+ regions 10kV according to claim 3 or 5 is layouted Method, it is characterised in that scheme of the described transformer station for the looped network pattern one of P/W types station 1.5 with reference to p-type station Single-ring network;Described Scheme of the transformer station for the looped network pattern two of P/W types station 1.5 with reference to WH types station Single-ring network;Described transformer station is bicyclic for P/W types station Scheme of the net with reference to p-type station Single-ring network.
CN201710903919.5A 2017-09-29 2017-09-29 Distribution automation terminal distribution planning method for A + region 10kV overhead network Active CN107730034B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710903919.5A CN107730034B (en) 2017-09-29 2017-09-29 Distribution automation terminal distribution planning method for A + region 10kV overhead network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710903919.5A CN107730034B (en) 2017-09-29 2017-09-29 Distribution automation terminal distribution planning method for A + region 10kV overhead network

Publications (2)

Publication Number Publication Date
CN107730034A true CN107730034A (en) 2018-02-23
CN107730034B CN107730034B (en) 2022-01-28

Family

ID=61208807

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710903919.5A Active CN107730034B (en) 2017-09-29 2017-09-29 Distribution automation terminal distribution planning method for A + region 10kV overhead network

Country Status (1)

Country Link
CN (1) CN107730034B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203166550U (en) * 2013-03-28 2013-08-28 国家电网公司 Cable ring network structure of power distribution network
CN103840439A (en) * 2014-03-31 2014-06-04 国网上海市电力公司 Power distribution automation protecting method achieved by matching of master station and distributed terminals
CN104484712A (en) * 2014-11-24 2015-04-01 国家电网公司 Optimization configuration method for three-remote power distribution terminal
CN105404967A (en) * 2015-11-09 2016-03-16 广东电网有限责任公司惠州供电局 Power distribution network automatic planning method and system
US20160239032A1 (en) * 2013-10-30 2016-08-18 Jiangsu Electric Power Company Nanjing Power Supply Company A progressive optimization dispatching method of smart distribution system
WO2016141683A1 (en) * 2015-03-10 2016-09-15 中国电力科学研究院 Implementation method for energy internet absorbing large-scale distributed power supply
CN106505738A (en) * 2016-11-29 2017-03-15 国网上海市电力公司 A kind of distribution power automation terminal method for arranging based on power supply reliability
CN107147111A (en) * 2017-05-19 2017-09-08 上海电力设计院有限公司 The distribution power automation terminal points distributing method analyzed based on power supply reliability

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203166550U (en) * 2013-03-28 2013-08-28 国家电网公司 Cable ring network structure of power distribution network
US20160239032A1 (en) * 2013-10-30 2016-08-18 Jiangsu Electric Power Company Nanjing Power Supply Company A progressive optimization dispatching method of smart distribution system
CN103840439A (en) * 2014-03-31 2014-06-04 国网上海市电力公司 Power distribution automation protecting method achieved by matching of master station and distributed terminals
CN104484712A (en) * 2014-11-24 2015-04-01 国家电网公司 Optimization configuration method for three-remote power distribution terminal
WO2016141683A1 (en) * 2015-03-10 2016-09-15 中国电力科学研究院 Implementation method for energy internet absorbing large-scale distributed power supply
CN105404967A (en) * 2015-11-09 2016-03-16 广东电网有限责任公司惠州供电局 Power distribution network automatic planning method and system
CN106505738A (en) * 2016-11-29 2017-03-15 国网上海市电力公司 A kind of distribution power automation terminal method for arranging based on power supply reliability
CN107147111A (en) * 2017-05-19 2017-09-08 上海电力设计院有限公司 The distribution power automation terminal points distributing method analyzed based on power supply reliability

Also Published As

Publication number Publication date
CN107730034B (en) 2022-01-28

Similar Documents

Publication Publication Date Title
CN103840439B (en) Main website coordinates the power distribution automation guard method realized with distributed terminal
Suslov et al. Flexible Power Distribution Networks: New Opportunities and Applications.
CN101505065B (en) Energy management system and control method using the same
CN103457262B (en) Energy-saving and cost-reducing power source double-loop grid knot line system
CN106208391B (en) A kind of centralization based on distribution CPS with distribution FA cooperates with fault handling method
CN105306328B (en) A kind of secondary equipment of intelligent converting station looped network distributed structure/architecture method and system
CN107332217B (en) The co-architecture and Synergistic method of the power distribution protection of the device containing flexible interconnection
CN102611107A (en) Urban medium-voltage power distribution network closed-loop power supply system based on annular net rack
CN104882883A (en) 10 KV power distribution network system
CN102386614A (en) Method for sharing standby protecting device by power equipment in intelligent transformer substation
CN103812041A (en) Method for overhauling ring main unit of 10kV cable circuit without switching power supply off
CN105375465A (en) City center area power distribution network and load transfer method
CN202840533U (en) Flexible direct current closed loop type power distribution network system converter station with bypass direct current buses
CN106505738A (en) A kind of distribution power automation terminal method for arranging based on power supply reliability
CN202917958U (en) Bus differential protection system for high-voltage direct-current flexible closed-loop intelligent power distribution network
CN111082422A (en) Composite grid structure capable of reliably supplying power
CN103001191B (en) Busbar differential protection method and system for flexible direct-current closed-loop intelligent distribution network
CN105576811A (en) Power distribution network adopting four-loop-one-group crossed connection wiring
CN106608269A (en) Turnout control system
CN107730034A (en) A kind of distribution power automation terminal of the aerial nets of A+ regions 10kV is layouted planing method
CN201985614U (en) Multi-way automatic switching device for standby power supply
CN103414242B (en) A kind of electrified railway in-phase power supply method and standby host structure
CN104333031B (en) The current conversion station stoppage in transit control method of Multi-end flexible direct current transmission system and device thereof
CN204184214U (en) A kind of contact system online combined switch cabinet device
CN103258301A (en) Power supply reliability evaluating method applicable to county power grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant