CN107705146A - Data processing method, device, storage medium and the computer equipment of subdivisional work - Google Patents

Data processing method, device, storage medium and the computer equipment of subdivisional work Download PDF

Info

Publication number
CN107705146A
CN107705146A CN201710795272.9A CN201710795272A CN107705146A CN 107705146 A CN107705146 A CN 107705146A CN 201710795272 A CN201710795272 A CN 201710795272A CN 107705146 A CN107705146 A CN 107705146A
Authority
CN
China
Prior art keywords
subdivisional work
data
valuation model
price
quantities
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710795272.9A
Other languages
Chinese (zh)
Inventor
罗寒旭
陈思远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Hai Shi Bao Technology Co Ltd
Original Assignee
Beijing Hai Shi Bao Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Hai Shi Bao Technology Co Ltd filed Critical Beijing Hai Shi Bao Technology Co Ltd
Priority to CN201710795272.9A priority Critical patent/CN107705146A/en
Publication of CN107705146A publication Critical patent/CN107705146A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Development Economics (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Primary Health Care (AREA)
  • Tourism & Hospitality (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of data processing method of subdivisional work, device, storage medium and computer equipment.Wherein, this method includes:Obtain the engineering characteristics data of subdivisional work;Obtain the valuation model with the engineering characteristics data match in default valuation model library;Search the Pricedata corresponding with the engineering characteristics data;Price data in the Pricedata is filled into the valuation model;The computation rule included according to the valuation model, calculates the comprehensive unit price for generating the subdivisional work;Bill of quantities is generated according to the comprehensive unit price.By the data processing method of above-mentioned subdivisional work, device, storage medium and computer equipment, the efficiency of the data processing of subdivisional work is improved.

Description

Data processing method, device, storage medium and the computer equipment of subdivisional work
Technical field
The present invention relates to areas of information technology, more particularly to a kind of data processing method of subdivisional work, device, storage Medium and computer equipment.
Background technology
Price Method of Bill of Quantities refers in bidding on construction project, bid inviter according to unification of the motherland quantities Inventory computation rule provides quantities number, is independently offered according to bill of quantities by bidder, and according to through evaluating reasonably low price A kind of construction cost account method that middle target rule is carried out.Subdivisional work refers to the part of partitioned project, is construction drawing Most basic unit of account in budget, it is the determination such as different size according to different construction methods, different materials.Engineering Bill of quantities row in amount inventory can represent a subdivisional work.The comprehensive unit price of subdivisional work mainly includes labour cost, material Material takes, machinery cost, measure expense, administration fee and profit etc..
However, in the data processing method of traditional subdivisional work, the intricate operation of the comprehensive unit price of subdivisional work is calculated Complexity, easily cause mistakes and omissions occur or calculate inaccurate situation, and need the judgement of authorized personnel and practical experience for many years Accumulation, so that the data processing of subdivisional work is less efficient.
The content of the invention
Based on this, it is necessary to for subdivisional work data processing it is less efficient the problem of, there is provided a kind of subdivisional work Data processing method, device, storage medium and computer equipment.
A kind of data processing method of subdivisional work, methods described include:Obtain the engineering characteristics data of subdivisional work;Obtain Take the valuation model with the engineering characteristics data match in default valuation model library;Search and the engineering characteristics data Corresponding Pricedata;Price data in the Pricedata is filled into the valuation model;According to described The computation rule that valuation model includes, calculates the comprehensive unit price for generating the subdivisional work;Work is generated according to the comprehensive unit price Journey amount inventory.
In one of the embodiments, the engineering characteristics data include project content and engineering attribute;It is described to obtain in advance If valuation model library in valuation model with the engineering characteristics data match, including:Obtain default valuation model library In the valuation model that matches with the project content and engineering attribute of the subdivisional work.
In one of the embodiments, the price data includes labour cost, fee of material and machinery cost;Described in the basis The computation rule that valuation model includes, the comprehensive unit price for generating the subdivisional work is calculated, including:To labour cost, fee of material and Machinery cost is summed, and obtains the direct total cost of the subdivisional work;The directly total cost is multiplied by multiple predetermined coefficients, Obtain multiple indirect expenses of the subdivisional work;To the directly total cost and the summation of the multiple indirect expense, institute is obtained State the comprehensive unit price of subdivisional work.
In one of the embodiments, the engineering characteristics data include quantities;It is described to be given birth to according to the comprehensive unit price Into bill of quantities, including:The comprehensive unit price is multiplied with the quantities, it is corresponding to obtain the subdivisional work data Subdivisional work subitem total price;According to the subitem total price generation bill of quantities.
In one of the embodiments, the engineering characteristics data of the subdivisional work are the data that terminal is sent;Described After bill of quantities being generated according to the comprehensive unit price, in addition to:The bill of quantities is sent to the terminal and opened up Show.
A kind of data processing equipment of subdivisional work, described device include:Engineering characteristics data acquisition module, for obtaining The engineering characteristics data of subdivisional work;Valuate model acquisition module, for obtain it is default valuation model library in the engineering The valuation model that characteristic matches;Pricedata searching modul, it is corresponding with the engineering characteristics data for searching Pricedata;Price data fills module, for the price data in the Pricedata to be filled to the valuation In model;Comprehensive unit price computing module, for the computation rule included according to the valuation model, calculate and generate the subitem work The comprehensive unit price of journey;Bill of quantities generation module, for generating bill of quantities according to the comprehensive unit price.
In one of the embodiments, the engineering characteristics data include project content and engineering attribute;The valuation mould Type acquisition module is additionally operable to obtain the project content and engineering attribute phase in default valuation model library with the subdivisional work The valuation model matched somebody with somebody.
In one of the embodiments, the price data includes labour cost, fee of material and machinery cost;The comprehensive unit price Computing module is additionally operable to sum to labour cost, fee of material and machinery cost, obtains the direct total cost of the subdivisional work;Will The directly total cost is multiplied by multiple predetermined coefficients, obtains multiple indirect expenses of the subdivisional work;Directly total take to described With and the multiple indirect expense sum, obtain the comprehensive unit price of the subdivisional work.
A kind of computer-readable recording medium, is stored thereon with computer program, and the program is realized when being executed by processor Described in above-mentioned each embodiment the step of the data processing method of subdivisional work.
A kind of computer equipment, including memory, processor and storage can be run on a memory and on a processor Computer program, the data processing of subdivisional work described in above-mentioned each embodiment is realized during the computing device described program The step of method.
Data processing method, device, storage medium and the computer equipment of above-mentioned subdivisional work, pass through default valuation model Storehouse and Pricedata, and be associated Pricedata and valuation model library according to the engineering characteristics data of subdivisional work, Comprehensive unit price is calculated by the computation rule included in model of valuating, reduces the data processing complex of subdivisional work.And Price data in Pricedata can be updated according to demand, improve the accurate fixed and timely of comprehensive unit price calculating Property, so as to improve the efficiency of the data processing of subdivisional work.
Brief description of the drawings
Fig. 1 is the application scenarios of the data processing method of subdivisional work in one embodiment;
Fig. 2 is the cut-away view of the data processing method Computer equipment of subdivisional work in one embodiment;
Fig. 3 is the flow chart of the data processing method of subdivisional work in one embodiment;
Fig. 4 is the flow chart of the data processing method of subdivisional work in another embodiment;
Fig. 5 is the flow chart of the data processing method of subdivisional work in another embodiment;
Fig. 6 is the structured flowchart of the data processing equipment of subdivisional work in one embodiment.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
The data processing method of subdivisional work provided in the embodiment of the present invention, it can be applied to application as shown in Figure 1 In environment.With reference to figure 1, terminal 110 can be established by network and server 120 and communicated to connect.Terminal 110 includes but is not limited to hand Machine, tablet personal computer, personal digital assistant or desktop computer etc..Server 120 can use independent server either multiple things Manage server group into server cluster.Terminal 110 can receive the related data of subdivisional work, such as the engineering of subdivisional work Characteristic, and related data is sent to server 120 by communicating to connect.It can be stored in server 120 and subdivisional work Data processing method association database, such as valuation model library and Pricedata etc..Server 120 can also be from terminal Engineering characteristics data are obtained in 110 related datas sent, according to what is matched in engineering characteristics data search valuation model library Valuation model and corresponding Pricedata etc..
As shown in Fig. 2 in one embodiment, there is provided a kind of computer equipment, the computer equipment can by with It is set to server 120.Wherein, the computer equipment include by system bus connection processor, non-volatile memory medium, Built-in storage and network interface.Wherein, the processor of the server is used to provide calculating and control ability, supports whole terminal Operation.The non-volatile memory medium of the server is stored with operating system and computer executable instructions, and the computer can be held Row instruction can be performed by processor, for realizing a kind of data processing side of subdivisional work of following embodiment offer Method.The built-in storage provides the fortune of cache for the operating system in non-volatile memory medium, computer executable instructions Row environment.The network interface of the server is used to carry out network service with terminal 110, the engineering number sent such as receiving terminal 110 According to.
It will be understood by those skilled in the art that the structure shown in Fig. 2, the only part related to application scheme knot The block diagram of structure, does not form the restriction for the server being applied thereon to application scheme, and specific server can include Than more or less parts shown in figure, either combine some parts or arranged with different parts.
In one embodiment, as shown in Figure 3, there is provided a kind of data processing method of subdivisional work, this method application Come in the server shown in Fig. 1 for example, including:
Step S302, obtain the engineering characteristics data of subdivisional work.
In the present embodiment, subdivisional work refers to unit of account most basic in working drawing budget, is according to different constructions The determination such as different size of method, different materials.For example in bill of quantities, often row bill of quantities row can represent one Individual subdivisional work.Wherein, the content of bill of quantities include but is not limited to project code, project name, item characteristic, in work Appearance, measurement unit, work load evaluation and the combination by one or more of which such as the regular quantities being calculated.Engineering Characteristic refers to the data that the subdivisional work is can be identified for that in the content of bill of quantities, and can according to engineering characteristics data It is determined that the valuation model to match with the subdivisional work.Wherein, it is special to include but is not limited to project name, project for engineering characteristics data Sign, action and measurement unit.Specifically, after the whole related datas for receiving subdivisional work, whole phases be can extract Close keyword and corresponding numeric data in data.Further, predeterminable keyword database, the related data that will be received Matched with the keyword in keyword database, by number associated with keyword in the keyword of matching and related data Value Data is as engineering characteristics data.
In one embodiment, before the engineering characteristics data of subdivisional work are obtained, user can be according in construction drawing Demand is by the corresponding unfilled bill of quantities of terminal searching, including but not limited to from local cache or from server It is upper to obtain related bill of quantities.For example, construction drawing, which is shown, needs flooring cement mortar screeding, then user can basis The demand searches for corresponding bill of quantities, and further, user can be according in the bill of quantities row in bill of quantities Content inputs specific character numerical value.For example showing that item characteristic includes screed-coat thickness in bill of quantities row, then user can Specifically levelling thickness value, such as 20mm are inputted according to the actual requirements.
Step S304, obtain the valuation model with engineering characteristics data match in default valuation model library.
In the present embodiment, multiple valuation models can be included in default valuation model library.Wherein, model of valuating refers to can root According to the engineering characteristics data of the subdivisional work got, the model of the subdivisional work comprehensive unit price is calculated.Valuating model can Represented in the form of by excel, but not limited to this.Multiple price numbers for not being filled concrete numerical value are included in valuation model According to the including but not limited to one of which such as labour cost, fee of material, machinery cost, measure expense, administration fee, profit and value-added tax or more The combination of kind.Wherein, the content of each single item price data includes but is not limited to specifications and models, unit, net use, the proportion of goods damageds and unit price Etc. the combination of one or more of which.For example fee of material may include the price data of one or more materials, the price data Content may also include the combination of the one or more of which such as material specification model, basic unit, technique, product category, intensity and thickness. Specifically, can according to engineering characteristics data, including but not limited to project name, item characteristic, action, measurement unit etc., Search the valuation model to match in default valuation model library.
In one embodiment, engineering characteristics data include project content and engineering attribute.Wherein, project content refers to reality The means or way of the subdivisional work are applied, engineering attribute refers to the concrete numerical value for weighing the means or way.Such as in engineering It can be that flooring layer is levelling to hold, and engineering attribute can be levelling thickness 20mm.Specifically, obtain it is default valuation model library in work The valuation model that journey characteristic matches, including:Obtain in default valuation model library with the project content of subdivisional work and The valuation model that engineering attribute matches.
In one embodiment, can not be in default valuation mould when engineering characteristics data are not accurate enough or sufficiently complete The valuation model with engineering characteristics data match is found in type storehouse, then returns to the prompting letter for supplementing detailed engineering characteristics data Cease to terminal.Further, the engineering characteristics data that this can not match can be stored and form synonym dictionary database, as under Once reference data during renewal valuation model.Such as the project name of user's input is " flooring mortar is levelling ", due to " sand " of " sand " and project name in valuation model is inconsistent, can not be found and " flooring in default valuation model library Mortar is levelling " the valuation model that matches.A predeterminable non-matched data storehouse, " flooring mortar is levelling " is stored to this not Matching database,, can be by " building when detecting " flooring mortar is levelling " as reference when searching valuation model thereafter Valuation model of the ground mortar levelling " as matching.
Step S306, search the Pricedata corresponding with engineering characteristics data.
In the present embodiment, Pricedata refers to include, for calculating the comprehensive unit price relative costs data of subdivisional work Database.Wherein, the subdivisional work is corresponding with engineering characteristics data, accordingly, Pricedata also with it is all possible Engineering characteristics data are corresponding.Pricedata includes but is not limited to labour cost database, fee of material database, proportion of goods damageds data The combination of the one or more of which such as storehouse and net usage data storehouse.Further, the Pricedata can be it is default, or It is updated according to default time interval, or real-time update can also be carried out by network connection.
In one embodiment, engineering characteristics data also include regionalism, and accordingly, Pricedata also can be according to ground Area's feature is classified.Such as engineering characteristics data are Shenzhen also including area, then can search price number corresponding with Shenzhen According to storehouse.
Step S308, the price data in Pricedata is filled into valuation model.
Specifically, by one of which such as the net dosage in Pricedata, the proportion of goods damageds, labour cost unit price and fee of material unit prices Or a variety of price datas is filled into valuation model.Price data has with the empty data item not being filled in valuation model to be reflected Penetrate relation
Step S310, the computation rule included according to valuation model, calculates the comprehensive unit price for generating subdivisional work.
In the present embodiment, the computation rule that valuation model includes refers to the price data filled in model of valuating calculating life Into the mathematical formulae of comprehensive unit price.Comprehensive unit price refers to the artificial completion expense to be paid of per unit this subdivisional work of submitting a tender With, including labour cost, fee of material, machinery cost, measure expense, administration fee, profit, value-added tax and input tax etc. can also be included wherein One or more combinations.
In one embodiment, when the measurement unit and the inconsistent unit of price data in engineering characteristics data, also Numerical value in price data can be made to corresponding conversion, it is consistent and then will to be converted to measurement unit in engineering characteristics data Price data is inserted valuation model and calculated.Wherein, measurement unit can be marked for the legal measurement unit of country, or the world Quasi- unit.
Step S312, bill of quantities is generated according to comprehensive unit price.
In the present embodiment, bill of quantities refers to the inventory being made up of the related data of multiple subdivisional works.Quantities is clear Single content class includes the preset content arrived according to engineering characteristics data search.For example project code, project name, project are special Sign, action, measurement unit and quantities etc., may also include be calculated according to specifically engineering characteristics value data it is comprehensive Close unit price and/or subitem total price etc..
In above-described embodiment, by default valuation model library and Pricedata, and according to the engineering characteristics of subdivisional work Pricedata and valuation model library are associated by data, are calculated by the computation rule included in model of valuating comprehensive single Valency, reduce the data processing complex of subdivisional work.And the price data in Pricedata can be carried out more according to demand Newly, the accurate fixed and promptness of comprehensive unit price calculating is improved, so as to improve the efficiency of the data processing of subdivisional work.
In one embodiment, as shown in figure 4, price data includes labour cost, fee of material and machinery cost;According to valuation mould The computation rule that type includes, the comprehensive unit price of generation subdivisional work is calculated, including:
Step S402, labour cost, fee of material and machinery cost are summed, obtain the direct total cost of subdivisional work.
In the present embodiment, direct total cost refers to implement direct cost sum caused by subdivisional work, and direct cost includes But it is not limited to labour cost, fee of material and machinery cost etc..Wherein, labour cost, fee of material and machinery cost can be directly from Pricedatas Middle acquisition, also generation can be calculated according to the price data in Pricedata.
In one embodiment, before being summed to labour cost, fee of material and machinery cost, in addition to according to price number Generation labour cost, fee of material and machinery cost are calculated according to the price data in storehouse.The engineering characteristics number of different subdivisional works can be directed to According to default corresponding labour cost database, fee of material database and machinery cost database, also predeterminable corresponding proportion of goods damageds data Storehouse and net usage data storehouse.Specifically, the price in labour cost database, loss rate database and net usage data storehouse can be combined The labour cost that subdivisional work is calculated in data closes valency.It may also be combined with fee of material database, loss rate database and net dosage number The fee of material that subdivisional work is calculated according to the price data in storehouse closes valency.Further, can to net dosage corresponding to labour cost, Actual consumption rate and unit price are multiplied, and are obtained labour cost and are closed valency.Can also be to net dosage, actual consumption corresponding to individual event fee of material Rate and unit price are multiplied, and are obtained individual event fee of material and are closed valency, can be by the list of multiple material if subdivisional work corresponds to multiple material Item fee of material closes valency and is added, and obtains total fee of material and closes valency.Wherein, actual consumption rate is that the proportion of goods damageds add 100%.
Step S404, direct total cost is multiplied by multiple predetermined coefficients, obtains multiple indirect expenses of subdivisional work.
In the present embodiment, indirect expense refers to implement subdivisional work caused expense indirectly, for example, measure expense, administration fee, Profit, set-fee and value-added tax etc..Predetermined coefficient refers to the coefficient for calculating indirect expense, including but not limited to overhead cost rate And discount tax rate etc..The predetermined coefficient can be that national regulation is default or default according to the market demand.Specifically, may be used To set the coefficient data storehouse for including all predetermined coefficients, when detecting indirect expense to be calculated, from coefficient data storehouse Transfer corresponding predetermined coefficient.Further, each coefficient has corresponding geographic area, can be according to the ground in engineering characteristics data Area's feature transfers corresponding predetermined coefficient from coefficient data storehouse.
In one embodiment, price data includes multiple overhead cost rates, and overhead cost rate is to be used for and direct total expense The rate of corresponding indirect expense is obtained with being multiplied.Specifically, the indirect expense to be calculated in valuation model, matches phase The overhead cost rate answered, each overhead cost rate is multiplied with direct total cost to obtain corresponding indirect expense.
In one embodiment, price data includes multiple discount tax rates, and indirect expense may also include input tax.Wherein, The discount tax rate is that the tax rate of material labor service income tax amount is reduced for calculating.Specifically, can by each direct cost with it is corresponding The discount tax rate is multiplied to obtain corresponding input tax deduction, and all input tax deductions are added and can obtain total input tax.
Step S406, direct total cost and multiple indirect expenses are summed, obtain the comprehensive unit price of subdivisional work.
In the present embodiment, direct total cost plus or minus each indirect expense can be obtained final comprehensive unit price, also Indirect expense can directly be filled in the form of positive number or negative into valuation model, directly by direct total cost plus between each The expense of connecing obtains comprehensive unit price.For example, indirect expense may also include input tax, wherein, input tax is to reduce material labor service The amount of tax to be paid of income, comprehensive list can be obtained with after other indirect expense sums, subtracting the number of input tax calculating direct total cost Valency, or, the numerical value of input tax can be represented in the form of negative in model of valuating, by direct total cost and all overhead costs With being added so that comprehensive unit price is calculated.
In one embodiment, engineering characteristics data include quantities, and bill of quantities, bag are generated according to comprehensive unit price Include:Comprehensive unit price is multiplied with quantities, obtains the subitem total price of subdivisional work corresponding to subdivisional work data;According to point Item total price generation bill of quantities.
In the present embodiment, quantities refers to each subitem or son point represented by natural measurement unit or physics measurement unit The quantity of item engineering and component and fitting.The subitem total price of subdivisional work refers to the total cost to be paid of this subdivisional work, can table It is shown as the product of comprehensive unit price and quantities.The subitem total price of this subdivisional work can be shown in bill of quantities.
In one embodiment, the engineering characteristics data of subdivisional work are the data that terminal is sent;Given birth to according to comprehensive unit price Into after bill of quantities, in addition to:Bill of quantities is sent to terminal and is shown.
In the present embodiment, user can input one or more bill of quantities rows for needing to be calculated by terminal, eventually End can send the data in the bill of quantities row to server, server by the data processing of the subdivisional work of reception it Afterwards, complete bill of quantities can be generated, and the bill of quantities is sent to terminal, to show user.Wherein, terminal bag Include but be not limited to mobile phone, tablet personal computer, personal digital assistant or desktop computer etc..Specifically, one or more points are calculated After the comprehensive unit price and subitem total price of item engineering, work can be generated according to the bill of quantities row of one or more subdivisional works Journey amount inventory.
In one embodiment, as shown in Figure 5, there is provided a kind of data processing method of subdivisional work.Can be applied to as In application environment shown in Fig. 1, including:
Step S501, obtain the engineering characteristics data of subdivisional work.
In the present embodiment, engineering characteristics data include but is not limited to project name, item characteristic and measurement unit etc. wherein One or more combinations.For example, the content of the bill of quantities of reception includes:Project code is 011101006, project Entitled flooring mortar levelling and surface layer, item characteristic is levelling thickness 20mm and mortar mix ratio is dry-mixed ground mortar M20, action for cleaning basic unit, allocation and transportation mortar and it is floating, compacting, measurement unit for square metre, then can be by flooring mortar Levelling, levelling thickness 20mm and dry-mixed ground mortar M20 are as engineering characteristics data.
Step S502, obtain what is matched in default valuation model library with the project content and engineering attribute of subdivisional work Valuation model.
In the present embodiment, project content may include project name, and engineering attribute may include item characteristic.For example, root According to the project name " flooring sand is levelling " in engineering characteristics data, the valuation mould related to " flooring sand is levelling " can be found Type, valuate model in can be preset with corresponding parameter, such as, " flooring sand is levelling (40mm) " valuation model in " (40mm) " represents that levelling thickness is 40mm.Further, the levelling parameter of user's input can also be received, such as, flooring Sand is levelling " 20mm ".The levelling parameter that can be inputted according to user performs step S503.
Step S503, search the Pricedata corresponding with engineering characteristics data.
In the present embodiment, Pricedata includes but is not limited to labour cost database, fee of material database, proportion of goods damageds data Storehouse and net usage data storehouse etc..For example, in labour cost database corresponding to " flooring cement mortar screeding ", " flooring In mortar levelling 40mm " unit price be 13 yuan every square metre;In corresponding fee of material database, " cement mortar material, M20 " Unit price is 544 yuan;In corresponding net usage data storehouse, " the net dosages of flooring mortar surface layer 20mm " are 0.025 cubic metre and often put down Square rice;In corresponding loss rate database, " mortar " proportion of goods damageds are 2%.
Step S504, the price data in Pricedata is filled into valuation model.
Step S505, labour cost, fee of material and machinery cost are summed, obtain the direct total cost of subdivisional work.
In the present embodiment, the product of net dosage, active loss rate and unit price is calculated, the conjunction valency of this expense can be obtained.Its In, actual consumption rate is that the proportion of goods damageds add 100%.For example, " in flooring mortar levelling 40mm " corresponding to labour cost Unit price be 13, artificial net dosage is 1, and the artificial proportion of goods damageds are 0%, then calculate the product of 1,100% and 13 threes, obtain It is 13 that labour cost corresponding to subdivisional work " in flooring mortar levelling 40mm ", which closes valency,.For another example, " flooring cement mortar is looked for The unit price of cement mortar material corresponding to flat, dry-mixed ground mortar M20 " is 544, and the net dosage of material is 0.025, material The proportion of goods damageds are 2%, and the actual consumption rate of material is 102%, then calculates the product of 0.025,102% and 544 threes, itemized " fee of material of the cement mortar material corresponding to flooring cement mortar screeding, dry-mixed ground mortar M20 " closes valency to engineering 13.87。
Step S506, direct total cost is multiplied by multiple predetermined coefficients, obtains multiple indirect expenses of subdivisional work.
In the present embodiment, predetermined coefficient includes but is not limited to overhead cost rate and the discount tax rate.Specifically, predetermined coefficient can To be fixed, can also be adjusted according to demand.Such as different coefficients is preset according to different regions.For example, if directly It is 28.66 to connect total cost, and in Beijing, the overhead cost rate of measure expense is 2.44%, then it is 0.7 that administration fee, which can be calculated, Hebei, the overhead cost rate of measure expense is 1.98%, then administration fee can be calculated as 0.57.
Step S507, direct total cost and multiple indirect expenses are summed, obtain the comprehensive unit price of subdivisional work.
In the present embodiment, the numerical value of input tax can be represented in the form of negative in model of valuating, by direct total cost It is added with all indirect expenses so that comprehensive unit price is calculated.
Step S508, comprehensive unit price is multiplied with quantities, obtains subdivisional work corresponding to subdivisional work data Subitem total price, according to subitem total price generation bill of quantities.
In the present embodiment, multiple bill of quantities rows of reception can be performed with the data processing method of above-mentioned subdivisional work Step, the bill of quantities row after multiple processing is obtained, the bill of quantities row after the plurality of processing can be generated to one completely Inventory.Specifically, the comprehensive unit price and subitem total price of each subdivisional work are may include in bill of quantities.Further, may be used The bill of quantities of generation is sent to terminal and is shown.
In above-described embodiment, by default valuation model library and Pricedata, and according to the engineering characteristics of subdivisional work Pricedata and valuation model library are associated by data, are calculated by the computation rule included in model of valuating comprehensive single Valency, reduce the data processing complex of subdivisional work.Direct cost and indirect expense, and default system are calculated by model of valuating Number can upgrade in time, the accuracy for calculating subdivisional work comprehensive unit price be improved, so as to improve the data processing of subdivisional work Efficiency.
In one embodiment, as shown in Figure 6, there is provided a kind of data processing equipment 600 of subdivisional work, the device bag Include:Engineering characteristics data acquisition module 602, for obtaining the engineering characteristics data of subdivisional work;Valuation model acquisition module 604, for obtaining the valuation model in default valuation model library with engineering characteristics data match;Price data library lookup mould Block 606, for searching the Pricedata corresponding with engineering characteristics data;Price data fills module 608, for by price Price data in database is filled into valuation model;Comprehensive unit price computing module 610, for what is included according to valuation model Computation rule, calculate the comprehensive unit price of generation subdivisional work;Bill of quantities generation module 612, for being given birth to according to comprehensive unit price Into bill of quantities.
In above-described embodiment, by default valuation model library and Pricedata, and according to the engineering characteristics of subdivisional work Pricedata and valuation model library are associated by data, are calculated by the computation rule included in model of valuating comprehensive single Valency, reduce the data processing complex of subdivisional work.And the price data in Pricedata can be carried out more according to demand Newly, the accurate fixed and promptness of comprehensive unit price calculating is improved, so as to improve the efficiency of the data processing of subdivisional work.
In one embodiment, engineering characteristics data include project content and engineering attribute;Valuation model acquisition module 604 It is additionally operable to obtain the valuation model with the project content and engineering attribute of subdivisional work to match in default valuation model library.
In one embodiment, price data includes labour cost, fee of material and machinery cost;Comprehensive unit price computing module 610 It is additionally operable to sum to labour cost, fee of material and machinery cost, obtains the direct total cost of subdivisional work;Direct total cost is multiplied With multiple predetermined coefficients, multiple indirect expenses of subdivisional work are obtained;Direct total cost and multiple indirect expenses are summed, obtained The comprehensive unit price of subdivisional work.
In one embodiment, engineering characteristics data include quantities;Bill of quantities generation module 612 is additionally operable to comprehensive Close unit price to be multiplied with quantities, obtain the subitem total price of subdivisional work corresponding to subdivisional work data;According to subitem total price Generate bill of quantities.
In one embodiment, the engineering characteristics data of subdivisional work are the data that terminal is sent;Bill of quantities generates Module 612 is additionally operable to send bill of quantities to terminal and is shown.
Modules in the data processing equipment of above-mentioned subdivisional work can be fully or partially through software, hardware and its group Close to realize.Above-mentioned each module can in the form of hardware be embedded in or independently of in the memory of terminal, can also be in a software form It is stored in the memory of terminal, operation corresponding to above modules is performed in order to which processor calls.The processor can be with For CPU (CPU), microprocessor, single-chip microcomputer etc..
In one embodiment, there is provided a kind of computer-readable recording medium, be stored thereon with computer program, the journey Following steps are realized when sequence is executed by processor:Obtain the engineering characteristics data of subdivisional work;Obtain default valuation model library In valuation model with engineering characteristics data match;Search the Pricedata corresponding with engineering characteristics data;By price Price data in database is filled into valuation model;The computation rule included according to valuation model, calculate generation subitem work The comprehensive unit price of journey;Bill of quantities is generated according to comprehensive unit price.
In one embodiment, engineering characteristics data include project content and engineering attribute, and the program is executed by processor When, realize obtain in default valuation model library the step with the valuation model of engineering characteristics data match when, including reality Existing following steps:Obtain the valuation mould to match in default valuation model library with the project content and engineering attribute of subdivisional work Type.
In one embodiment, price data includes labour cost, fee of material and machinery cost, and the program is executed by processor When, in the computation rule that realization includes according to valuation model, the step of the comprehensive unit price of calculating generation subdivisional work, including reality Existing following steps:Labour cost, fee of material and machinery cost are summed, obtain the direct total cost of subdivisional work;To be directly total Expense is multiplied by multiple predetermined coefficients, obtains multiple indirect expenses of subdivisional work;Direct total cost and multiple indirect expenses are asked With obtain the comprehensive unit price of subdivisional work.
In one embodiment, engineering characteristics data include quantities, when the program is executed by processor, are realizing basis When comprehensive unit price generates the step of bill of quantities, including realize following steps:Comprehensive unit price is multiplied with quantities, obtained To the subitem total price of subdivisional work corresponding to subdivisional work data;According to subitem total price generation bill of quantities.
In one embodiment, the engineering characteristics data of subdivisional work are the data that terminal is sent, and the program is by processor During execution, in addition to realize following steps:Bill of quantities is sent to terminal and is shown.
In one embodiment, there is provided a kind of computer equipment, including memory, processor and storage are on a memory And the computer program that can be run on a processor, during the computing device program, realize following steps:Obtain subdivisional work Engineering characteristics data;Obtain the valuation model with engineering characteristics data match in default valuation model library;Lookup and engineering The corresponding Pricedata of characteristic;Price data in Pricedata is filled into valuation model;According to valuation The computation rule that model includes, calculate the comprehensive unit price of generation subdivisional work;Bill of quantities is generated according to comprehensive unit price.
In one embodiment, engineering characteristics data include project content and engineering attribute, during the computing device program, Realize obtain it is default valuation model library in engineering characteristics data match valuation model step when, including realize with Lower step:Obtain the valuation model to match in default valuation model library with the project content and engineering attribute of subdivisional work.
In one embodiment, price data includes labour cost, fee of material and machinery cost, during the computing device program, In the computation rule that realization includes according to valuation model, when calculating the step for the comprehensive unit price for generating subdivisional work, including realize Following steps:Labour cost, fee of material and machinery cost are summed, obtain the direct total cost of subdivisional work;Directly total it will take With multiple predetermined coefficients are multiplied by, multiple indirect expenses of subdivisional work are obtained;Direct total cost and multiple indirect expenses are summed, Obtain the comprehensive unit price of subdivisional work.
In one embodiment, engineering characteristics data include quantities, during the computing device program, are realizing according to comprehensive When closing the step of unit price generation bill of quantities, including realize following steps:Comprehensive unit price is multiplied with quantities, obtained The subitem total price of subdivisional work corresponding to subdivisional work data;According to subitem total price generation bill of quantities.
In one embodiment, the data that the engineering characteristics data of subdivisional work send for terminal, the computing device journey During sequence, in addition to realize following steps:Bill of quantities is sent to terminal and is shown.
One of ordinary skill in the art will appreciate that realize all or part of flow in above-described embodiment method, being can be with The hardware of correlation is instructed to complete by computer program, described program can be stored in a non-volatile computer and can be read In storage medium, the program is upon execution, it may include such as the flow of the embodiment of above-mentioned each method.Wherein, described storage is situated between Matter can be magnetic disc, CD, read-only memory (Read-Only Memory, ROM) etc..
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, the scope that this specification is recorded all is considered to be.
Embodiment described above only expresses the several embodiments of the present invention, and its description is more specific and detailed, but simultaneously Can not therefore it be construed as limiting the scope of the patent.It should be pointed out that come for one of ordinary skill in the art Say, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the protection of the present invention Scope.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (10)

1. a kind of data processing method of subdivisional work, methods described include:
Obtain the engineering characteristics data of subdivisional work;
Obtain the valuation model with the engineering characteristics data match in default valuation model library;
Search the Pricedata corresponding with the engineering characteristics data;
Price data in the Pricedata is filled into the valuation model;
The computation rule included according to the valuation model, calculates the comprehensive unit price for generating the subdivisional work;
Bill of quantities is generated according to the comprehensive unit price.
2. according to the method for claim 1, it is characterised in that the engineering characteristics data include project content and engineering category Property;
The valuation model obtained in default valuation model library with the engineering characteristics data match, including:
Obtain the valuation model to match in default valuation model library with the project content and engineering attribute of the subdivisional work.
3. according to the method for claim 1, it is characterised in that the price data includes labour cost, fee of material and machinery Take;
The computation rule included according to the valuation model, calculates the comprehensive unit price for generating the subdivisional work, including:
Labour cost, fee of material and machinery cost are summed, obtain the direct total cost of the subdivisional work;
The directly total cost is multiplied by multiple predetermined coefficients, obtains multiple indirect expenses of the subdivisional work;
To the directly total cost and the summation of the multiple indirect expense, the comprehensive unit price of the subdivisional work is obtained.
4. according to the method for claim 1, it is characterised in that the engineering characteristics data include quantities;
It is described that bill of quantities is generated according to the comprehensive unit price, including:
The comprehensive unit price is multiplied with the quantities, obtains point of subdivisional work corresponding to the subdivisional work data Item total price;
According to the subitem total price generation bill of quantities.
5. according to the method for claim 1, it is characterised in that the engineering characteristics data of the subdivisional work send for terminal Data;
After the generation bill of quantities according to the comprehensive unit price, in addition to:
The bill of quantities is sent to the terminal and is shown.
6. a kind of data processing equipment of subdivisional work, it is characterised in that described device includes:
Engineering characteristics data acquisition module, for obtaining the engineering characteristics data of subdivisional work;
Valuation model acquisition module, for obtaining the valuation in default valuation model library with the engineering characteristics data match Model;
Pricedata searching modul, for searching the Pricedata corresponding with the engineering characteristics data;
Price data fills module, for the price data in the Pricedata to be filled into the valuation model;
Comprehensive unit price computing module, for the computation rule included according to the valuation model, calculate and generate the subdivisional work Comprehensive unit price;
Bill of quantities generation module, for generating bill of quantities according to the comprehensive unit price.
7. device according to claim 6, it is characterised in that the engineering characteristics data include project content and engineering category Property;
The valuation model acquisition module is additionally operable to obtain the project content in default valuation model library with the subdivisional work And the valuation model that engineering attribute matches.
8. device according to claim 6, it is characterised in that the price data includes labour cost, fee of material and machinery Take;
The comprehensive unit price computing module is additionally operable to sum to labour cost, fee of material and machinery cost, obtains the subitem work The direct total cost of journey;The directly total cost is multiplied by multiple predetermined coefficients, obtains multiple overhead costs of the subdivisional work With;To the directly total cost and the summation of the multiple indirect expense, the comprehensive unit price of the subdivisional work is obtained.
9. a kind of computer-readable recording medium, is stored thereon with computer program, it is characterised in that the program is held by processor The step of data processing method of subdivisional work described in any one in claim 1 to 5 is realized during row.
10. a kind of computer equipment, including memory, processor and storage are on a memory and the meter that can run on a processor Calculation machine program, it is characterised in that realize during the computing device described program in claim 1 to 5 and divide described in any one The step of data processing method of item engineering.
CN201710795272.9A 2017-09-06 2017-09-06 Data processing method, device, storage medium and the computer equipment of subdivisional work Pending CN107705146A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710795272.9A CN107705146A (en) 2017-09-06 2017-09-06 Data processing method, device, storage medium and the computer equipment of subdivisional work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710795272.9A CN107705146A (en) 2017-09-06 2017-09-06 Data processing method, device, storage medium and the computer equipment of subdivisional work

Publications (1)

Publication Number Publication Date
CN107705146A true CN107705146A (en) 2018-02-16

Family

ID=61172044

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710795272.9A Pending CN107705146A (en) 2017-09-06 2017-09-06 Data processing method, device, storage medium and the computer equipment of subdivisional work

Country Status (1)

Country Link
CN (1) CN107705146A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108921459A (en) * 2018-08-31 2018-11-30 北京海数宝科技有限公司 Index generates method, apparatus, computer equipment and storage medium
CN108960933A (en) * 2018-07-19 2018-12-07 北京中电普华信息技术有限公司 A kind of method for computing data, device and electronic equipment
CN109389330A (en) * 2018-11-21 2019-02-26 广州供电局有限公司 Power distribution network infrastructure project analysis of prices method, apparatus, computer equipment and storage medium
CN109493158A (en) * 2018-09-26 2019-03-19 平安国际融资租赁有限公司 Products quotation measuring method, device, computer equipment and storage medium
CN109492853A (en) * 2018-09-17 2019-03-19 北京海数宝科技有限公司 Model engineering amount calculates method, apparatus, storage medium and computer equipment
CN109783445A (en) * 2018-12-27 2019-05-21 北京海数宝科技有限公司 Date storage method, device, computer equipment and storage medium
CN109918401A (en) * 2019-01-25 2019-06-21 北京海数宝科技有限公司 Bill of quantities data processing method, device, storage medium and computer equipment
CN110413597A (en) * 2019-07-30 2019-11-05 广联达科技股份有限公司 Digital engineering cost inventory constructs the method, system and medium of main material list automatically
CN111598604A (en) * 2020-03-27 2020-08-28 广联达科技股份有限公司 Imported equipment unit price calculating system and method
CN112307098A (en) * 2020-10-15 2021-02-02 上海东方投资监理有限公司 Cost consultation management method, system, electronic equipment and computer readable storage medium
CN112734392A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 BIM project cost rapid calculation system and method
CN112861500A (en) * 2021-01-14 2021-05-28 佛山轨道交通设计研究院有限公司 Engineering pricing table generation method and device based on engineering quantity list
CN113643064A (en) * 2021-08-13 2021-11-12 大地仁工程咨询有限公司 Integrated pricing system and method for general engineering contract
CN113987644A (en) * 2021-10-26 2022-01-28 广东天元建筑设计有限公司 Engineering quantity list generation method, device, equipment and storage medium
CN117474583A (en) * 2023-11-07 2024-01-30 北京梦诚科技有限公司 Construction project yield measuring and calculating method and device based on price system
CN117541289A (en) * 2023-11-21 2024-02-09 佛山轨道交通设计研究院有限公司 Full-flow automatic pricing method, device, equipment and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008033101A1 (en) * 2006-09-13 2008-03-20 National University Of Singapore System and method for generating a bill of quantities
CN103295104A (en) * 2013-06-13 2013-09-11 深圳市加斯特工程咨询有限公司 Quota design management method and project investment service platform for cost accounting
CN106447405A (en) * 2016-10-25 2017-02-22 国网浙江省电力公司 Automatic pricing method for electric power marketing project bidding and system thereof
CN107038603A (en) * 2017-03-17 2017-08-11 东易日盛家居装饰集团股份有限公司 A kind of engineering quotation generation method and system based on BIM softwares

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008033101A1 (en) * 2006-09-13 2008-03-20 National University Of Singapore System and method for generating a bill of quantities
CN103295104A (en) * 2013-06-13 2013-09-11 深圳市加斯特工程咨询有限公司 Quota design management method and project investment service platform for cost accounting
CN106447405A (en) * 2016-10-25 2017-02-22 国网浙江省电力公司 Automatic pricing method for electric power marketing project bidding and system thereof
CN107038603A (en) * 2017-03-17 2017-08-11 东易日盛家居装饰集团股份有限公司 A kind of engineering quotation generation method and system based on BIM softwares

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108960933A (en) * 2018-07-19 2018-12-07 北京中电普华信息技术有限公司 A kind of method for computing data, device and electronic equipment
CN108921459B (en) * 2018-08-31 2020-12-11 北京海数宝科技有限公司 Index generation method and device, computer equipment and storage medium
CN108921459A (en) * 2018-08-31 2018-11-30 北京海数宝科技有限公司 Index generates method, apparatus, computer equipment and storage medium
CN109492853A (en) * 2018-09-17 2019-03-19 北京海数宝科技有限公司 Model engineering amount calculates method, apparatus, storage medium and computer equipment
CN109493158A (en) * 2018-09-26 2019-03-19 平安国际融资租赁有限公司 Products quotation measuring method, device, computer equipment and storage medium
CN109389330A (en) * 2018-11-21 2019-02-26 广州供电局有限公司 Power distribution network infrastructure project analysis of prices method, apparatus, computer equipment and storage medium
CN109783445A (en) * 2018-12-27 2019-05-21 北京海数宝科技有限公司 Date storage method, device, computer equipment and storage medium
CN109918401B (en) * 2019-01-25 2021-10-19 北京海数宝科技有限公司 Building engineering list data processing method and device, storage medium and computer equipment
CN109918401A (en) * 2019-01-25 2019-06-21 北京海数宝科技有限公司 Bill of quantities data processing method, device, storage medium and computer equipment
CN110413597A (en) * 2019-07-30 2019-11-05 广联达科技股份有限公司 Digital engineering cost inventory constructs the method, system and medium of main material list automatically
CN111598604A (en) * 2020-03-27 2020-08-28 广联达科技股份有限公司 Imported equipment unit price calculating system and method
CN112307098A (en) * 2020-10-15 2021-02-02 上海东方投资监理有限公司 Cost consultation management method, system, electronic equipment and computer readable storage medium
CN112861500A (en) * 2021-01-14 2021-05-28 佛山轨道交通设计研究院有限公司 Engineering pricing table generation method and device based on engineering quantity list
CN112734392A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 BIM project cost rapid calculation system and method
CN112734392B (en) * 2021-01-15 2023-09-01 广州市新誉工程咨询有限公司 BIM engineering project cost rapid calculation system and method
CN113643064A (en) * 2021-08-13 2021-11-12 大地仁工程咨询有限公司 Integrated pricing system and method for general engineering contract
CN113987644A (en) * 2021-10-26 2022-01-28 广东天元建筑设计有限公司 Engineering quantity list generation method, device, equipment and storage medium
CN117474583A (en) * 2023-11-07 2024-01-30 北京梦诚科技有限公司 Construction project yield measuring and calculating method and device based on price system
CN117541289A (en) * 2023-11-21 2024-02-09 佛山轨道交通设计研究院有限公司 Full-flow automatic pricing method, device, equipment and storage medium
CN117541289B (en) * 2023-11-21 2024-07-23 佛山轨道交通设计研究院有限公司 Full-flow automatic pricing method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN107705146A (en) Data processing method, device, storage medium and the computer equipment of subdivisional work
Robson et al. A review of computable general equilibrium models for transport and their applications in appraisal
Torre et al. Reconsidering the estimation of the economic impact of cultural tourism
Bergstrom et al. Multi-item production planning—an extension of the HMMS rules
Capros et al. GEM-E3 model documentation
Weidema et al. Guidelines for application of deepened and broadened LCA
Arslan et al. E-bidding proposal preparation system for construction projects
CN109034505A (en) Metering table demand on-line prediction method and terminal device
CN107563828A (en) Full statement of expense generation method, device, storage medium and computer equipment
CN102222285B (en) Multi-dimensional data linkage computing device and multi-dimensional data linkage computing method
Zhan et al. Formulating systemic construction productivity enhancement strategies
CN110287250A (en) User gradation quantization method and device
de Joode et al. Demand for seasonal gas storage in northwest Europe until 2030: Simulation results with a dynamic model
CN108132777A (en) Across the table exploitation system and method for one kind
von Geibler et al. Forming the nucleus of a novel ecological accounting system: The myEcoCost approach
Benetti et al. Transmission pricing: right insights for suitable cost allocation methods
Patil Analysis of Cost over run in construction Projects
Marshall Economic efficiency implications of federal‐local cost sharing in water resource development
Lawrence et al. Simulating contestability in freight transportation: the canadian grain handling and transportation system
Lee et al. Characteristics of public–private partnerships for municipal wastewater treatment in Taiwan
CN113095296A (en) Civil engineering material calculation system and method based on Internet of things
Castellano et al. Estimating a socially optimal water price for irrigation versus an environmentally optimal water price through the use of Geographical Information Systems and Social Accounting Matrices
Davidson et al. Optimization of investments in natural gas distribution networks
Pinto et al. Proposed smart market design for sediment discharge
Tirkaso et al. Evaluation of cost efficiency in hydropower-related biodiversity restoration projects in Sweden–a stochastic frontier approach

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180216