CN107701121B - Exempt to bore and exempts to fish out solid completion integral tubing string - Google Patents

Exempt to bore and exempts to fish out solid completion integral tubing string Download PDF

Info

Publication number
CN107701121B
CN107701121B CN201711070853.2A CN201711070853A CN107701121B CN 107701121 B CN107701121 B CN 107701121B CN 201711070853 A CN201711070853 A CN 201711070853A CN 107701121 B CN107701121 B CN 107701121B
Authority
CN
China
Prior art keywords
tubing string
exempts
out solid
external seal
fish out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711070853.2A
Other languages
Chinese (zh)
Other versions
CN107701121A (en
Inventor
高彦才
程文佳
董社霞
刘刚芝
李良庆
梁月松
刘明娟
王东
周欢
仲晔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Original Assignee
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Oilfield Services Ltd, China National Offshore Oil Corp CNOOC filed Critical China Oilfield Services Ltd
Priority to CN201711070853.2A priority Critical patent/CN107701121B/en
Publication of CN107701121A publication Critical patent/CN107701121A/en
Priority to PCT/CN2018/089733 priority patent/WO2019085472A1/en
Priority to CA3080647A priority patent/CA3080647C/en
Application granted granted Critical
Publication of CN107701121B publication Critical patent/CN107701121B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B34/00Valve arrangements for boreholes or wells
    • E21B34/06Valve arrangements for boreholes or wells in wells
    • E21B34/14Valve arrangements for boreholes or wells in wells operated by movement of tools, e.g. sleeve valves operated by pistons or wire line tools
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/12Packers; Plugs
    • E21B33/122Multiple string packers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B34/00Valve arrangements for boreholes or wells
    • E21B34/06Valve arrangements for boreholes or wells in wells
    • E21B34/08Valve arrangements for boreholes or wells in wells responsive to flow or pressure of the fluid obtained

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Exempt to bore disclosed herein is one kind and exempt to fish out solid completion integral tubing string, including casing tubing string and is mounted in casing tubing string and the closed setting tool string tubing string of lower section;Casing tubing string includes being sequentially connected ON/OFF formula cementing device, external packer of pipe and the interior Sealing connect from top to bottom, is provided with pressure transmission hole on external packer of pipe;Setting tool string tubing string includes being sequentially connected external seal short circuit, impacting seat and the sealed device connect from top to bottom, external seal is provided with flowing hole on being shorted, flowing hole is between ON/OFF formula cementing device and interior Sealing, ON/OFF formula cementing device is mutually sealed with external seal short circuit, interior Sealing is mutually sealed with sealed device, and has the anchor mechanism for slipping out of the hand between ON/OFF formula cementing device and external seal short circuit.This, which exempts to bore to exempt to fish out solid completion integral tubing string and well solved circulation port, is not closed completely, returns the problem for taking rubber plug difficulty etc..

Description

Exempt to bore and exempts to fish out solid completion integral tubing string
Technical field
Present document relates to but be not limited to stowage unit field, espespecially one kind exempt from bore exempt to fish out solid completion integral tubing string.
Background technique
Under normal conditions, offshore oilfield well cementing operation and completion practice adhere to two different construction technologies separately, and construction exists The problems such as construction time is long, casing program is complicated.Land, which is being applied, at present exempts to bore solid completion integral technique and is applied with shortening Between working hour, casing program is reduced.
Land application at present exempts from that bore solid completion integral process flow as follows:
One, pipe string structure forms: guide shoe+screen casing+exempts from drill tools+casing.
Two, pipe string in place after, well head is suppressed, and envelope swollen first exempts from the external packer of pipe on drill tools, insulates annular space, continues to beat Pressure, opening exempt from drill tools stage cementing device, establish circulation, normal procedure well cementation, and the later period throws rubber plug bruising, and well cementation terminates.
Three, after Hou Ning, drill tools internal structure, and milling drifting are exempted from the lower macaroni with fishing tool, salvaging, whole A complete well construction terminates.
But there are biggish hidden danger and deficiency for current solid completion integral technique of exempting to bore:
Casing cementing and rubber plug is needed to replace cement 1. exempting from drill tools, it is endless there may be replacing that rubber plug replaces cement Entirely, the case where internal surface of sleeve pipe residual cement;
2. the technique closes cementing device circulation port using hydraulic open cementing device circulation port, rubber plug bruising, actually apply It is easy to appear circulation port in work and opens the case where fitting badly, influences cementing quality;
3. after well cementation, needing lower fishing tool salvaging to exempt from drill tools internal structure, salvaging back and take difficulty.
Summary of the invention
At least one of in order to solve the above-mentioned technical problem, exempt to bore there is provided herein one kind and exempts to fish out solid completion integral pipe Column has well solved circulation port and has been not closed completely, returns the problem for taking rubber plug difficulty etc..Setting tool string tubing string is installed in place recoil Sealing tube external packer pushes setting tool string tubing string and opens ON/OFF formula cementing device, and cementing and bottom plug replace in drilling rod, It above mentions setting tool string tubing string closing ON/OFF formula cementing device time and takes rubber plug, entire construction process is coherent, when Hou Ning being avoided to wait Between.
In order to reach this paper purpose, exempts to bore there is provided herein one kind and exempt to fish out solid completion integral tubing string, including casing tubing string Be mounted in described sleeve pipe tubing string and the closed setting tool string tubing string of lower section;Described sleeve pipe tubing string includes from top to bottom successively ON/OFF formula cementing device, external packer of pipe and the interior Sealing being connected are provided with pressure transmission hole on the external packer of pipe; The setting tool string tubing string includes being sequentially connected external seal short circuit, impacting seat and the sealed device connect from top to bottom, described outer Flowing hole is provided on Sealing, the flowing hole is described between the ON/OFF formula cementing device and interior Sealing ON/OFF formula cementing device is mutually sealed with external seal short circuit, and the interior Sealing is mutually sealed with the sealed device, and institute State the anchor mechanism having between ON/OFF formula cementing device and external seal short circuit for slipping out of the hand.
Optionally, the setting tool string tubing string further include: drilling rod, positioned at the top that the external seal is shorted, the brill The lower end of bar is connected with the upper end that the external seal is shorted.
Optionally, the setting tool string tubing string further include: the interior guide shoe of lower end closed, under the sealed device Side, the upper end of the interior guide shoe is connected with the lower end of the sealed device.
Optionally, the setting tool string tubing string further include: rubber plug, the rubber plug can be launched in the external seal short circuit And it is sealed on the impacting seat.
Optionally, described sleeve pipe tubing string further include: screen casing, positioned at the lower section of the interior Sealing, the screen casing it is upper End is connected with the lower end of the interior Sealing.
Optionally, described sleeve pipe tubing string further include: the outer guide shoe of lower end perforation, it is described outer positioned at the lower section of the screen casing The upper end of guide shoe is connected with the lower end of the screen casing.
Optionally, described sleeve pipe tubing string further include: casing is generated, it is described positioned at the top of the ON/OFF formula cementing device The lower end for generating casing is connected with the upper end of the ON/OFF formula cementing device.
Optionally, the ON/OFF formula cementing device is mechanical ON/OFF formula cementing device.
Optionally, the mechanical ON/OFF formula cementing device includes: inner cylinder, is provided with first through hole;And outer cylinder Body, lower end are connected with the external packer of pipe, and the second through-hole is provided on the outer barrel, and the first through hole is in institute The top of the second through-hole is stated, the inner cylinder can be installed on up or down in the outer barrel, and the side wall of the inner cylinder covers Cover second through-hole.
Optionally, the anchor mechanism include be set to screw buckle that the external seal is shorted and be set to it is described open/ Barb on the formula cementing device of pass.
Compared with prior art, brill provided by the invention of exempting from exempts to fish out solid completion integral tubing string, has well solved circulation Bore closure is not tight, returns the problem for taking rubber plug difficulty etc..Setting tool string tubing string is installed in place recoil sealing tube external packer, pushes and sits It seals tool string tubing string and opens ON/OFF formula cementing device, cementing and bottom plug replace in drilling rod, above mention setting tool string tubing string pass It closes ON/OFF formula cementing device time and takes rubber plug, entire construction process is coherent, avoids the Hou Ning waiting time.
The other feature and advantage of this paper will illustrate in the following description, also, partly become from specification It is clear that by implementing to understand herein.The purpose of this paper and other advantages can be by specifications, claims And specifically noted structure is achieved and obtained in attached drawing.
Detailed description of the invention
Attached drawing is used to provide to further understand this paper technical solution, and constitutes part of specification, with this Shen Embodiment please is used to explain the technical solution of this paper together, does not constitute the limitation to this paper technical solution.
Fig. 1 to Fig. 5 is to exempt to bore described in one embodiment of the invention to exempt to fish out solid completion integral tubing string different working condition Schematic cross-sectional view.
Wherein, corresponding relationship of the Fig. 1 into Fig. 5 between appended drawing reference and component names are as follows:
1 stratum, 2 outer layer sleeves, 3 outer layer cement, 4 generate casing, and 5 external seals are shorted, 6 mechanical ON/OFF formula cementing devices, 7 impacting seats, 8 external packer of pipe, Sealing in 9,10 drilling rods, guide shoe in 11 sealed devices 12,13 outer guide shoes, 14 screen casings, 15 Rubber plug, 16 oil pipes, 17 flowing holes, 18 first through hole, 19 second through-holes.
Specific embodiment
For the purposes, technical schemes and advantages of this paper are more clearly understood, below in conjunction with attached drawing to the reality of this paper Example is applied to be described in detail.It should be noted that in the absence of conflict, the spy in embodiment and embodiment in the application Sign can mutual any combination.
Many details are explained in the following description in order to fully understand herein, still, can also be adopted herein Implemented with other than the one described here mode, therefore, the protection scope of this paper is not by following public specific implementation The limitation of example.
The brill of exempting from for describing some embodiments herein with reference to the accompanying drawing exempts to fish out solid completion integral tubing string.
Brill provided by the invention of exempting from exempts to fish out solid completion integral tubing string, as shown in Figures 1 to 5, including casing tubing string and peace In described sleeve pipe tubing string and the closed setting tool string tubing string of lower section;Described sleeve pipe tubing string includes being sequentially connected from top to bottom ON/OFF formula cementing device, external packer of pipe 8 and the interior Sealing 9 connect is provided with pressure transmission hole on the external packer of pipe 8;Institute Stating setting tool string tubing string includes being sequentially connected the external seal connect from top to bottom to be shorted 5, impacting seat 7 and sealed device 11, described External seal is shorted on 5 and is provided with flowing hole 17, and the flowing hole 17 is located at the ON/OFF formula cementing device and interior Sealing 9 Between, the ON/OFF formula cementing device is shorted the sealing of 5 phases, the interior Sealing 9 and the sealed device with the external seal The sealing of 11 phases, and the ON/OFF formula cementing device and the external seal are shorted between 5 the anchor mechanism having for slipping out of the hand.
It is provided by the invention exempt from bore exempt to fish out solid completion integral tubing string, well solved circulation port be not closed completely, return take The problem of 15 difficulty of rubber plug etc..Setting tool string tubing string is installed in place recoil sealing tube external packer 8, pushes setting tool string tubing string ON/OFF formula cementing device is opened, cementing and bottom plug 15 replace in drilling rod 10, above mention setting tool string tubing string and close ON/OFF Formula cementing device, which returns, takes rubber plug 15, and entire construction process is coherent, avoids the Hou Ning waiting time.
Specifically, the setting tool string tubing string further include: drilling rod 10 is shorted 5 top positioned at the external seal, described The lower end of drilling rod 10 is connected with the upper end that the external seal is shorted 5;The interior guide shoe 12 of lower end closed is located at the sealed device The upper end of 11 lower section, the interior guide shoe 12 is connected with the lower end of the sealed device 11;With rubber plug 15, the rubber plug 15 can The external seal is launched to be shorted in 5 and be sealed on the impacting seat 7.
Specifically, described sleeve pipe tubing string further include: screen casing 14, positioned at the lower section of the interior Sealing 9, the screen casing 14 Upper end be connected with the lower end of the interior Sealing 9;The outer guide shoe 13 of lower end perforation, positioned at the lower section of the screen casing 14, The upper end of the outer guide shoe 13 is connected with the lower end of the screen casing 14;With generation casing 4, it is located at the ON/OFF formula cementing The top of device, the lower end for generating casing 4 are connected with the upper end of the ON/OFF formula cementing device.
Wherein, the ON/OFF formula cementing device is mechanical ON/OFF formula cementing device 6, the machinery ON/OFF formula cementing Device 6 includes: inner cylinder, is provided with first through hole 18;And outer barrel, lower end are connected with the external packer of pipe 8, institute It states and is provided with the second through-hole 19 on outer barrel, the first through hole 18 is in the top of second through-hole 19, the inner cylinder It can be installed on up or down in the outer barrel, the side wall of the inner cylinder covers second through-hole 19, and inner cylinder is opposite When outer barrel is moved down into maximum position, first through hole 18 and the coincidence of the second through-hole 19 are conducted.
Specifically, the anchor mechanism include be set to screw buckle that the external seal is shorted on 5 and be set to it is described open/ Barb on the formula cementing device of pass, to realize setting tool string tubing string and casing pipe by rotating backward setting tool string tubing string Column is given up.
Five implementation processes are described below:
One, well head elder generation tripping in casing tubing string, then tripping in setting tool string tubing string.As shown in Figure 1
In well head according to above-mentioned order of connection tripping in casing tubing string, casing tubing string is suspended from well with slips after the completion of tripping in Mouthful, then (pass through hook or top drive) tripping in setting tool string tubing string has suspending weight anomalous variation until hook or top are driven, then sets work The tubing string tripping in of tool string is in place.
Two, well head, which is suppressed, sets external packer of pipe 8.As shown in Figure 2
Casing tubing string and setting tool string tubing string are by external seal pipe nipple and mechanical ON/OFF formula cementing device 6 and interior sealing Device 11 and interior packoff nipple are realized and are sealed at two.The sealing space of formation is connected with the pressure transmission hole of external packer of pipe 8, presses from well head It is pumped according to ladder pressure into drilling rod 10, pressure enters pressure transmission hole and successively cuts the multiple groups shear pin of external packer of pipe 88, completes External packer of pipe 8 is set.
Three, mechanical cementing device is opened, by design flow cementing.As shown in Figure 3
It pushes drilling rod 10 and arrives certain tonnage, cut the shear pin of mechanical ON/OFF formula cementing device 6, open circulation port (i.e. inner cylinder Body moves down conducting first through hole and the second through-hole), circulation port is connected in casing tubing string and outside casing tubing string, injects water by design flow Mud.
Four, rubber plug 15 replaces cement, bruising.As shown in Figure 4
Rubber plug 15 is put into setting tool string tubing string by cementing head and is injected displacement fluid, displacement fluid replaces rubber plug 15 So that cement is passed through the circulation port of mechanical ON/OFF formula cementing device 6, be injected into inside casing tubing string and open hole well, rubber plug 15 with touch Bruising is realized in the contact of wedge 7.
Five, it slips out of the hand setting tool string tubing string, Hou Ning completes integrated solid well operations.As shown in Figure 5
After bruising, rotation setting tool string tubing string is above mentioned and be buckled to, is closed by anchor mechanism (driving in-migration on inner cylinder) The circulation port of mechanical ON/OFF formula cementing device 6 is closed, casing tubing string is completed and slips out of the hand with setting tool string tubing string, take out setting tool String tubing string, Hou Ning complete integrated solid well operations.
Wherein, structure includes: stratum 1, outer layer sleeve 2, outer layer cement 3 and oil pipe 16 in well.
In conclusion brill provided by the invention of exempting from exempts to fish out solid completion integral tubing string, circulation bore closure has been well solved It is not tight, return the problem for taking rubber plug difficulty etc..Setting tool string tubing string is installed in place recoil sealing tube external packer, pushes setting tool Tubing string of going here and there opens ON/OFF formula cementing device, and cementing and bottom plug replace in drilling rod, above mention the closing of setting tool string tubing string open/ Pass formula cementing device, which returns, takes rubber plug, and entire construction process is coherent, avoids the Hou Ning waiting time.
In description herein, term " installation ", " connected ", " connection ", " fixation " etc. be shall be understood in a broad sense, for example, " connection " may be fixed connection or may be dismantle connection, or integral connection;It can be directly connected, can also lead to Intermediary is crossed to be indirectly connected.For the ordinary skill in the art, above-mentioned term can be understood as the case may be Concrete meaning herein.
In the description of this specification, the description of term " one embodiment ", " some embodiments ", " specific embodiment " etc. Mean that particular features, structures, materials, or characteristics described in conjunction with this embodiment or example are contained at least one implementation of this paper In example or example.In the present specification, schematic expression of the above terms are not necessarily referring to identical embodiment or example. Moreover, the particular features, structures, materials, or characteristics of description can be in any one or more of the embodiments or examples with suitable Mode combine.
Although embodiment disclosed herein is as above, the content only implementation of use herein for ease of understanding Mode is not limited to herein.Technical staff in any this paper fields, do not depart from spirit disclosed herein and Under the premise of range, any modification and variation, but the patent protection model of this paper can be carried out in the form and details of implementation It encloses, still should be subject to the scope of the claims as defined in the appended claims.

Claims (10)

1. one kind is exempted to bore and exempts to fish out solid completion integral tubing string, which is characterized in that including casing tubing string and be mounted on described sleeve pipe pipe In column and the closed setting tool string tubing string of lower section;
Described sleeve pipe tubing string include be sequentially connected from top to bottom the ON/OFF formula cementing device connect, external packer of pipe and it is interior sealing it is short It connects, is provided with pressure transmission hole on the external packer of pipe;
The setting tool string tubing string includes being sequentially connected external seal short circuit, impacting seat and the sealed device connect, institute from top to bottom State external seal be shorted on be provided with flowing hole, the flowing hole between the ON/OFF formula cementing device and interior Sealing, The ON/OFF formula cementing device is mutually sealed with external seal short circuit, and the interior Sealing is mutually sealed with the sealed device, And with the anchor mechanism for slipping out of the hand between the ON/OFF formula cementing device and external seal short circuit.
2. brill according to claim 1 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that the setting tool string pipe Column further include:
Drilling rod, positioned at the top that the external seal is shorted, the lower end of the drilling rod is connected with the upper end that the external seal is shorted.
3. brill according to claim 2 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that the setting tool string pipe Column further include:
The interior guide shoe of lower end closed, positioned at the lower section of the sealed device, upper end and the sealed device of the interior guide shoe Lower end is connected.
4. brill according to claim 3 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that the setting tool string pipe Column further include:
Rubber plug, the rubber plug launch the external seal and are shorted interior and are sealed on the impacting seat.
5. brill according to claim 1 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that described sleeve pipe tubing string also wraps It includes:
Screen casing, positioned at the lower section of the interior Sealing, the upper end of the screen casing is connected with the lower end of the interior Sealing.
6. brill according to claim 5 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that described sleeve pipe tubing string also wraps It includes:
The outer guide shoe of lower end perforation, positioned at the lower section of the screen casing, the upper end of the outer guide shoe is connected with the lower end of the screen casing It connects.
7. brill according to claim 6 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that described sleeve pipe tubing string also wraps It includes:
Casing is generated, positioned at the top of the ON/OFF formula cementing device, the lower end for generating casing and the ON/OFF formula are infused The upper end of cement device is connected.
8. brill according to any one of claim 1 to 7 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that described ON/OFF formula cementing device is mechanical ON/OFF formula cementing device.
9. brill according to claim 8 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that the machinery ON/OFF formula Cementing device includes:
Inner cylinder is provided with first through hole;With
Outer barrel, lower end are connected with the external packer of pipe, and the second through-hole is provided on the outer barrel, and described first is logical Hole is in the top of second through-hole, and the inner cylinder can be installed on up or down in the outer barrel, the inner cylinder Side wall cover second through-hole.
10. brill according to any one of claim 1 to 7 of exempting from exempts to fish out solid completion integral tubing string, which is characterized in that described Anchor mechanism includes being set to the screw buckle that the external seal is shorted and the barb being set on the ON/OFF formula cementing device.
CN201711070853.2A 2017-11-03 2017-11-03 Exempt to bore and exempts to fish out solid completion integral tubing string Active CN107701121B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201711070853.2A CN107701121B (en) 2017-11-03 2017-11-03 Exempt to bore and exempts to fish out solid completion integral tubing string
PCT/CN2018/089733 WO2019085472A1 (en) 2017-11-03 2018-06-04 Tubular column for drill-free and catch-free integrated well cementing and well completion and application thereof
CA3080647A CA3080647C (en) 2017-11-03 2018-06-04 Tubular column for drill-free and catch-free integrated well cementing and well completion and application thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711070853.2A CN107701121B (en) 2017-11-03 2017-11-03 Exempt to bore and exempts to fish out solid completion integral tubing string

Publications (2)

Publication Number Publication Date
CN107701121A CN107701121A (en) 2018-02-16
CN107701121B true CN107701121B (en) 2019-05-28

Family

ID=61177815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711070853.2A Active CN107701121B (en) 2017-11-03 2017-11-03 Exempt to bore and exempts to fish out solid completion integral tubing string

Country Status (3)

Country Link
CN (1) CN107701121B (en)
CA (1) CA3080647C (en)
WO (1) WO2019085472A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107701121B (en) * 2017-11-03 2019-05-28 中国海洋石油集团有限公司 Exempt to bore and exempts to fish out solid completion integral tubing string
CN112443289B (en) * 2019-08-27 2023-01-20 中国石油化工股份有限公司 Packing type stage cementing device
CN115247545A (en) * 2021-04-27 2022-10-28 中国石油化工股份有限公司 Pressure transmission tool and method for drilling-plug-free cementing completion
CN113803020B (en) * 2021-10-18 2023-04-07 中国石油化工股份有限公司 Rapid leaking stoppage and production recovery method for horizontal well
CN114016977B (en) * 2021-10-29 2024-06-11 德州众凯石油科技有限公司 Well control type hanging screen pipe and well completion process
CN113863893B (en) * 2021-11-23 2023-10-20 北京泊溪科技有限责任公司 Drilling-free stage cementing device

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2625571Y (en) * 2003-05-30 2004-07-14 中国石化胜利油田有限公司采油工艺研究院 Impacting seat for well cementing
CN2653119Y (en) * 2003-09-18 2004-11-03 杜晓瑞 Bottom structure of self filling self seal casing
CN201050332Y (en) * 2007-05-22 2008-04-23 辽河石油勘探局 Cement injection switch device for drillable segmental cementing
CN101187300A (en) * 2007-11-29 2008-05-28 中国石油天然气集团公司 Rotary hydraulic machinery double function expansion type tail pipe hanger
CN101614117A (en) * 2009-07-30 2009-12-30 中国石油天然气股份有限公司 A kind of expansion tube type liner hanger
CN201396090Y (en) * 2009-05-06 2010-02-03 中国石油集团西部钻探工程有限公司克拉玛依钻井工艺研究院 Multi-stage separator packing means outside tube for underbalance well cementation and completion
CN201924878U (en) * 2011-01-21 2011-08-10 中国石油化工股份有限公司 Half-cementing well completion pipe string
CN102606107A (en) * 2011-01-21 2012-07-25 中国石油化工股份有限公司 Halfway cementing well completion tube column and halfway cementing method
CN202914027U (en) * 2012-11-26 2013-05-01 中国石油集团长城钻探工程有限公司 Salvage type drilling-free plug hydraulic grading cementing device and special spear thereof
CN202946100U (en) * 2012-12-07 2013-05-22 中国石油集团西部钻探工程有限公司 Halfway well cementation self-grouting float collar
CN203130037U (en) * 2013-03-20 2013-08-14 中国石油化工股份有限公司 Ball seat type rubber plug system
CN203239276U (en) * 2013-03-04 2013-10-16 中国石油天然气股份有限公司 Well completion bump pressure combined device for coupling-free reinforcing tube
CN105604508A (en) * 2015-12-18 2016-05-25 中国石油天然气股份有限公司 Liner hanger
CN205669389U (en) * 2016-02-02 2016-11-02 德州隆科石油装备有限公司 One exempts from brill formula cementing device
CN206554872U (en) * 2017-01-13 2017-10-13 中国石油天然气集团公司 A kind of pitching builds the pressure device and the well shaft fixing technology tubing string with the device

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080029269A1 (en) * 2006-05-24 2008-02-07 Martin Thomas B Jr Method and system for installing equipment for production and injection operations
CN101725330B (en) * 2009-11-03 2013-06-19 山东普瑞思德石油技术有限公司 Drilling-and-plugging-free well fixing method and tool
CN101979821B (en) * 2010-11-13 2013-11-13 中国石油集团西部钻探工程有限公司 Self-locking cementing stopper combination device
CN103775015B (en) * 2012-10-18 2016-11-16 中国石油化工股份有限公司 Expand instrument under cased well and use its expansion sleeve method
CN103835677B (en) * 2014-03-21 2016-08-17 青岛吉安泰耐磨密封材料有限公司 A kind of horizontal well two-stage sealing bruising salvagable completion system
CN104110234B (en) * 2014-07-31 2017-06-30 于世江 Horizontal cementing exempts to bore blind plate circulation cementing method
CN106812478B (en) * 2015-12-01 2019-02-15 中国石油天然气股份有限公司 Tubing string and completion method
CN106555566A (en) * 2016-12-07 2017-04-05 中国石油集团西部钻探工程有限公司 Frangible stratum or the cementing method on broken stratum
CN107701121B (en) * 2017-11-03 2019-05-28 中国海洋石油集团有限公司 Exempt to bore and exempts to fish out solid completion integral tubing string
CN207420469U (en) * 2017-11-03 2018-05-29 中国海洋石油总公司 Exempt to bore and exempt to drag for solid completion integral tubing string

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2625571Y (en) * 2003-05-30 2004-07-14 中国石化胜利油田有限公司采油工艺研究院 Impacting seat for well cementing
CN2653119Y (en) * 2003-09-18 2004-11-03 杜晓瑞 Bottom structure of self filling self seal casing
CN201050332Y (en) * 2007-05-22 2008-04-23 辽河石油勘探局 Cement injection switch device for drillable segmental cementing
CN101187300A (en) * 2007-11-29 2008-05-28 中国石油天然气集团公司 Rotary hydraulic machinery double function expansion type tail pipe hanger
CN201396090Y (en) * 2009-05-06 2010-02-03 中国石油集团西部钻探工程有限公司克拉玛依钻井工艺研究院 Multi-stage separator packing means outside tube for underbalance well cementation and completion
CN101614117A (en) * 2009-07-30 2009-12-30 中国石油天然气股份有限公司 A kind of expansion tube type liner hanger
CN201924878U (en) * 2011-01-21 2011-08-10 中国石油化工股份有限公司 Half-cementing well completion pipe string
CN102606107A (en) * 2011-01-21 2012-07-25 中国石油化工股份有限公司 Halfway cementing well completion tube column and halfway cementing method
CN202914027U (en) * 2012-11-26 2013-05-01 中国石油集团长城钻探工程有限公司 Salvage type drilling-free plug hydraulic grading cementing device and special spear thereof
CN202946100U (en) * 2012-12-07 2013-05-22 中国石油集团西部钻探工程有限公司 Halfway well cementation self-grouting float collar
CN203239276U (en) * 2013-03-04 2013-10-16 中国石油天然气股份有限公司 Well completion bump pressure combined device for coupling-free reinforcing tube
CN203130037U (en) * 2013-03-20 2013-08-14 中国石油化工股份有限公司 Ball seat type rubber plug system
CN105604508A (en) * 2015-12-18 2016-05-25 中国石油天然气股份有限公司 Liner hanger
CN205669389U (en) * 2016-02-02 2016-11-02 德州隆科石油装备有限公司 One exempts from brill formula cementing device
CN206554872U (en) * 2017-01-13 2017-10-13 中国石油天然气集团公司 A kind of pitching builds the pressure device and the well shaft fixing technology tubing string with the device

Also Published As

Publication number Publication date
WO2019085472A1 (en) 2019-05-09
CN107701121A (en) 2018-02-16
CA3080647A1 (en) 2019-05-09
CA3080647C (en) 2022-05-31

Similar Documents

Publication Publication Date Title
CN107701121B (en) Exempt to bore and exempts to fish out solid completion integral tubing string
CN202900205U (en) Multifunctional formation testing well completion integral pipe column
DK200900764A (en) A completion assembly for stimulating segmenting and controlling ERD wells
CN111119784B (en) Suspension plugging device for open hole well and using method
CA2437678A1 (en) Apparatus and method for wellbore isolation
NO302046B1 (en) Underwater brönninjiseringssystem
CN202914027U (en) Salvage type drilling-free plug hydraulic grading cementing device and special spear thereof
CN207437005U (en) Band centering edge formula delayed start-up well cementation sliding sleeve
GB2565098A (en) Work string for a borehole
BR112020006363A2 (en) method, electronic initiator glove, and system
US4834176A (en) Well valve
CN109025915A (en) A kind of full-bore under across returning combined operation of perforation and testing tubing string and its operating method
CN205605156U (en) Workover device is pressed in oil gas field area
CN207420469U (en) Exempt to bore and exempt to drag for solid completion integral tubing string
CN202788741U (en) Completion tool free of drilling and plugging
CN202194613U (en) Hydraulic drilling-free suspension packer
CN101839117B (en) Annulus safety valve
CN202140062U (en) Hydraulic drilling-free tail pipe hanging packer
CN108979583A (en) A kind of sidetracked hole layer and section cementing unit and application method
CN109989725A (en) Exempt from brill formula blind plate and exempts to bore plug well shaft fixing technology
RU2438007C1 (en) Procedure for completion of gas well (versions)
CN105625979B (en) Chute type gradually deblocking packer
RU2626108C2 (en) Method of well casing by tail pipe with bottomhole screen
CN209704526U (en) A kind of naked eye plugging device
CN201202429Y (en) Expansion tube hanging seal device for open hole section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Applicant after: China Offshore Oil Group Co., Ltd.

Applicant after: China Oilfield Services Limited

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Applicant before: China National Offshore Oil Corporation

Applicant before: China Oilfield Services Limited

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant