CN107688877A - A kind of load distribution method based on new self-organizing grid dynamic base - Google Patents

A kind of load distribution method based on new self-organizing grid dynamic base Download PDF

Info

Publication number
CN107688877A
CN107688877A CN201710807936.9A CN201710807936A CN107688877A CN 107688877 A CN107688877 A CN 107688877A CN 201710807936 A CN201710807936 A CN 201710807936A CN 107688877 A CN107688877 A CN 107688877A
Authority
CN
China
Prior art keywords
unit
mrow
msub
load
coal consumption
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710807936.9A
Other languages
Chinese (zh)
Other versions
CN107688877B (en
Inventor
朱誉
周建新
范伟
司风琪
谭力强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Original Assignee
Southeast University
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University, Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd filed Critical Southeast University
Priority to CN201710807936.9A priority Critical patent/CN107688877B/en
Publication of CN107688877A publication Critical patent/CN107688877A/en
Application granted granted Critical
Publication of CN107688877B publication Critical patent/CN107688877B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Feedback Control In General (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention discloses a kind of load distribution method based on new self-organizing grid dynamic base, including:(1) initial grid dynamic base is established;(2) dynamic library searching positioning is carried out according to the instruction of full factory's total load and current complete each unit operation situation of factory, obtains sharing of load reference record;(3) assigned references are recorded with progress deviation to set to obtain new allocation result and send instruction;(4) each unit coal consumption and full factory's total consumption of coal are calculated according to final allocation result, and calculates corresponding coal consumption bias factor, record renewal grid dynamic base.On the premise of the present invention overcomes the shortcomings of the laod sharing modes such as existing intelligent optimization algorithm, take into full account the different operation characteristic of each unit, on the basis of guaranteeing safety, rational full factory laod sharing mode is provided, meet power plant safety, high-quality, economical operation needs, reach the effect of energy-saving and emission-reduction.

Description

一种基于新型自组织格栅动态库的负荷分配方法A load distribution method based on a new self-organizing grid dynamic library

技术领域technical field

本发明涉及节能调度领域,更具体地,涉及一种基于新型自组织格栅动态库的负荷分配方法。The invention relates to the field of energy-saving scheduling, and more specifically, relates to a load distribution method based on a novel self-organizing grid dynamic library.

背景技术Background technique

节能调度系统的核心思想在于:摆脱传统的调度方式,以电厂各机组能耗特性为基础,借助各种人工智能优化方法,达到全厂各机组以总能耗最低的方式运行的目标。与传统调度方式相比,节能调度系统改变了点对点直控机组的调度方式,由调度中心下发全厂负荷指令,系统自动合理地进行全厂机组的负荷优化分配,实现总体煤耗降低,从而有效降低发电成本,并且有利于提高机组的稳定性和安全性,精简电力调度控制对象。The core idea of the energy-saving dispatching system is to get rid of the traditional dispatching method, based on the energy consumption characteristics of each unit in the power plant, and with the help of various artificial intelligence optimization methods, to achieve the goal of operating the units in the whole plant with the lowest total energy consumption. Compared with the traditional dispatching method, the energy-saving dispatching system has changed the dispatching method of point-to-point direct control units. The dispatching center issues the load command of the whole plant, and the system automatically and rationally optimizes the load distribution of the units of the whole plant to reduce the overall coal consumption, thereby effectively Reduce the cost of power generation, and help to improve the stability and safety of the unit, and simplify the control objects of power dispatching.

基于上述思想,研究者们提出了大量的智能优化算法,包括神经网络、遗传算法以及粒子群算法等。Based on the above ideas, researchers have proposed a large number of intelligent optimization algorithms, including neural networks, genetic algorithms, and particle swarm optimization algorithms.

首先,由于电厂各机组负荷调度是高维度、多约束,且动态响应能力要求较高的复杂工业问题,现有提出的智能算法虽然对大规模参量优化问题具有很强的计算能力,但由于过于依赖所建立的固有模型而忽略了机组特性变化等要素,且部分算法容易陷入局部最优,故会导致优化结果与现场实际情况不符合。其次,在多约束、多目标条件下,优化算法计算过程复杂,不仅容易陷入局部最优,且往往需要大量的计算时间,无法满足较高的动态响应要求。First of all, since the load scheduling of each unit in a power plant is a complex industrial problem with high dimensions, multiple constraints, and high requirements for dynamic response capabilities, although the existing intelligent algorithms have strong computing power for large-scale parameter optimization problems, they are too Relying on the established inherent model ignores factors such as unit characteristic changes, and some algorithms are prone to fall into local optimum, so the optimization results will not conform to the actual situation on site. Secondly, under the multi-constraint and multi-objective conditions, the calculation process of the optimization algorithm is complex, not only easy to fall into local optimum, but also often requires a lot of calculation time, which cannot meet the high dynamic response requirements.

发明内容Contents of the invention

本发明为克服上述现有技术所述的至少一种缺陷(不足),提供一种基于新型自组织格栅动态库的负荷分配方法。该方法充分考虑各机组不同的运行特性,在保障安全性的基础上,提供合理的全厂负荷分配方式,满足电厂安全、优质、经济运行的需要,达到节能减排的效果。In order to overcome at least one defect (deficiency) of the above-mentioned prior art, the present invention provides a load distribution method based on a novel self-organizing grid dynamic library. This method fully considers the different operating characteristics of each unit, and provides a reasonable load distribution method for the entire plant on the basis of ensuring safety, meeting the needs of safe, high-quality, and economical operation of the plant, and achieving the effect of energy saving and emission reduction.

为解决上述技术问题,本发明的技术方案如下:In order to solve the problems of the technologies described above, the technical solution of the present invention is as follows:

一种基于新型自组织格栅动态库的负荷分配方法,包括以下步骤:A load distribution method based on a novel self-organizing grid dynamic library, comprising the following steps:

(1)建立初始格栅动态库;(1) Establish an initial grid dynamic library;

(2)根据全厂总负荷指令及当前全厂各机组运行情况进行动态库搜索定位,获取负荷分配参考记录;(2) Search and locate the dynamic library according to the total load command of the whole plant and the current operation status of each unit in the whole plant, and obtain the reference records of load distribution;

(3)对分配参考记录进行偏差设置得到新的分配结果并发出指令;(3) Perform deviation setting on the allocation reference record to obtain a new allocation result and issue an instruction;

(4)根据最终分配结果计算各机组煤耗及全厂总煤耗,并计算相应的煤耗偏置因子,记录更新格栅动态库。(4) Calculate the coal consumption of each unit and the total coal consumption of the whole plant according to the final distribution results, and calculate the corresponding coal consumption bias factor, record and update the grid dynamic library.

优选的,步骤(1)的初始格栅动态库的建立过程为:Preferably, the establishment process of the initial grid dynamic library of step (1) is:

(1a)通过机组热力试验得到实测数据,计算不同负荷段锅炉效率与煤耗特性关系,同时分析汽机热耗特性、单因素变化特性,获得各台机组发电煤耗、厂用电率;获取DCS/SIS历史数据,分析获得基于数据驱动的各台机组煤耗特性;进一步结合运行经验与上述热力试验分析结果及历史数据分析结果进行相互验证,最终拟合出机组煤耗特性关系;(1a) Obtain the measured data through the thermal test of the unit, calculate the relationship between boiler efficiency and coal consumption characteristics in different load segments, and analyze the heat consumption characteristics of the steam turbine and the single factor change characteristics at the same time, and obtain the coal consumption and plant power consumption rate of each unit; obtain DCS/SIS Historical data, analyzing and obtaining the coal consumption characteristics of each unit based on the data drive; further combining the operation experience with the above thermal test analysis results and historical data analysis results for mutual verification, and finally fitting the coal consumption characteristic relationship of the unit;

(1b)按照主要辅机运行情况的外部条件对各机组工况点进行分割,其中主要辅机运行情况包括环境温度、煤热值及给水泵(具体是采用控制变量的方式,将各主要辅机的历史运行情况进行区间划分,考虑主要辅机有三个,将环境温度,煤热值,给水泵耗功剔除异常值后,按照历史最大值/最小值分别划分成C1,C2,C3个区间,进行排列组合,共得到C1*C2*C3个工况);(1b) Divide the operating points of each unit according to the external conditions of the operation of the main auxiliary machines. The historical operating conditions of the machine are divided into intervals. Considering that there are three main auxiliary machines, after removing the abnormal values of ambient temperature, coal calorific value, and power consumption of the feed water pump, they are divided into C1, C2, and C3 intervals according to the historical maximum/minimum values. , permutation and combination, a total of C1*C2*C3 working conditions are obtained);

(1c)依次计算各机组不同工况条件下的机组煤耗,形成初始记录群;(1c) Calculate the coal consumption of each unit under different working conditions in turn to form an initial record group;

(1d)将各机组分割后的不同工况进行组合,并计算所有组合方式下全厂总煤耗bcp,按照煤耗由低到高,总负荷由低到高排列形成初始动态库;(1d) Combine the different working conditions of each unit, and calculate the total coal consumption b cp of the whole plant under all combinations, and form the initial dynamic library according to the coal consumption from low to high and the total load from low to high;

(1e)进一步从DCS/SIS运行数据中提取历史运行工况,筛选出各工况下单机及全厂煤耗最低的负荷分配方式,按照时间先后顺序补充至初始动态库,形成初始格栅动态库。(1e) Further extract the historical operating conditions from the DCS/SIS operating data, screen out the load distribution mode with the lowest coal consumption for a single machine and the whole plant under each operating condition, and add them to the initial dynamic library in chronological order to form the initial grid dynamic library .

优选的,步骤(2)中根据全厂总负荷指令及当前全厂各机组运行情况进行动态库搜索定位的具体过程为:Preferably, in step (2), the specific process of performing dynamic library search and positioning according to the total load order of the whole plant and the operating conditions of each unit of the current whole plant is:

(2a)依据负荷总指令搜索动态库,获得满足条件的所有M条记录,构造记录矩阵A:(2a) Search the dynamic library according to the total command of the load, obtain all M records that meet the conditions, and construct the record matrix A:

其中:Pij为第i台机组第j条记录,ζij为第i台机组第j条记录偏置因子;Among them: P ij is the jth record of the i-th unit, ζ ij is the offset factor of the j-th record of the i-th unit;

相应地构造所有记录的时间向量T=[t1,t2,…tM]及煤耗矩阵B:Correspondingly construct all recorded time vector T=[t 1 ,t 2 ,…t M ] and coal consumption matrix B:

其中:bij为第i台机组第j条记录煤耗;Among them: b ij is the coal consumption recorded in item j of unit i;

再构造所有记录全厂总煤耗向量Bcp=[b1,cp,b2,cp,…bM,cp];Reconstruct all the records of the total plant coal consumption vector B cp =[b 1,cp ,b 2,cp ,...b M , cp ];

其中tj为第j条记录的时间,bj,cp为第j条记录分配方式全厂总煤耗;Where t j is the time of the jth record, b j , cp is the total coal consumption of the whole plant according to the distribution method of the jth record;

(2b)根据所有M条记录按照煤耗由低到高排序,选择煤耗最低的记录进行结果分配,煤耗相同时,将记录按照时间先后进行排序,选择最近的记录作为负荷分配参考记录(从所有M条记录中筛选出负荷分配参考记录,该条记录中包括全厂所有机组的煤耗,bij表示煤耗矩阵B中的第i台机组第j条记录煤耗。)。(2b) According to all M records sorted by coal consumption from low to high, select the record with the lowest coal consumption to distribute the results. The reference record of load distribution is screened out from the record, which includes the coal consumption of all units in the whole plant, and b ij represents the coal consumption recorded in item j of unit i in the coal consumption matrix B.).

优选的,步骤(3)中对分配参考记录进行偏差设置的具体过程为:Preferably, in step (3), the specific process of setting the deviation to the allocation reference record is:

(3a)设定初始动态库各工况下不同机组的煤耗偏置因子为0;(3a) Set the coal consumption bias factor of different units under each working condition of the initial dynamic library to be 0;

(3b)在分配参考记录的基础上考虑机组动态特性变化情况,同时在保证总负荷不变的情况下,对每台机组进行负荷偏置;若偏置因子为0,则随机确定偏置因子正负情况,并对参考记录各机组负荷按照偏置因子调节;若偏置因子为正,则增大该机组的负荷,反之减小,确保偏置后总负荷不变,以此作为结果下达机组负荷指令;若偏置因子已知,则按照当前偏置因子方向按比例调节各机组负荷,确保调节后总负荷不变,下达分配指令。(3b) On the basis of allocating reference records, consider the change of unit dynamic characteristics, and at the same time, under the condition that the total load remains unchanged, carry out load bias for each unit; if the bias factor is 0, then randomly determine the bias factor In the case of positive or negative, adjust the load of each unit according to the reference record according to the offset factor; if the offset factor is positive, then increase the load of the unit, otherwise decrease, to ensure that the total load remains unchanged after the offset, and issue it as a result Unit load command; if the bias factor is known, adjust the load of each unit proportionally according to the direction of the current bias factor to ensure that the total load remains unchanged after adjustment, and issue a distribution command.

优选的,步骤(4)中根据最终分配结果计算各机组煤耗bi,new及全厂总煤耗bcp,new,并计算各机组当前工况下煤耗偏置因子:Preferably, in step (4), the coal consumption b i,new of each unit and the total coal consumption b cp , new of the whole plant are calculated according to the final distribution results, and the coal consumption bias factor of each unit under the current working condition is calculated:

再根据负荷分配结果、单机组煤耗、全厂总煤耗、煤耗偏置因子以及各机组当前运行状态,更新动态库,备下次调用。Then, according to the load distribution results, coal consumption of a single unit, the total coal consumption of the whole plant, the offset factor of coal consumption, and the current operating status of each unit, the dynamic library is updated for the next call.

与现有技术相比,本发明技术方案的有益效果是:本发明根据环境温度等边界条件对工况点进行分割,从历史数据中提取相最优负荷分配方式补充进动态库,取最近的记录作为负荷分配参考记录。考虑机组动态特性变化情况,对每台机组负荷进行偏置,偏置后的结果作为负荷分配指令。本发明克服现有智能优化算法等负荷分配方式的不足的前提下,充分考虑各机组不同的运行特性,在保障安全性的基础上,提供合理的全厂负荷分配方式,满足电厂安全、优质、经济运行的需要,达到节能减排的效果。Compared with the prior art, the beneficial effect of the technical solution of the present invention is: the present invention divides the operating point according to the boundary conditions such as ambient temperature, extracts the optimal load distribution mode from the historical data and supplements it into the dynamic library, and takes the nearest record as a load distribution reference record. Considering the change of the dynamic characteristics of the unit, the load of each unit is biased, and the result after the bias is used as the load distribution command. On the premise of overcoming the shortcomings of the existing intelligent optimization algorithm and other load distribution methods, the present invention fully considers the different operating characteristics of each unit, and provides a reasonable load distribution method for the whole plant on the basis of ensuring safety to meet the safety, quality, and The needs of economic operation, to achieve the effect of energy saving and emission reduction.

附图说明Description of drawings

图1为本发明的流程示意图。Fig. 1 is a schematic flow chart of the present invention.

具体实施方式detailed description

附图仅用于示例性说明,不能理解为对本专利的限制;为了更好说明本实施例,附图某些部件会有省略、放大或缩小,并不代表实际产品的尺寸;The drawings are for illustrative purposes only, and should not be construed as limitations on this patent; in order to better illustrate this embodiment, some parts in the drawings will be omitted, enlarged or reduced, and do not represent the size of the actual product;

对于本领域技术人员来说,附图中某些公知结构及其说明可能省略是可以理解的。下面结合附图和实施例对本发明的技术方案做进一步的说明。For those skilled in the art, it is understandable that some well-known structures and descriptions thereof may be omitted in the drawings. The technical solutions of the present invention will be further described below in conjunction with the accompanying drawings and embodiments.

如图1,本发明提出的一种基于新型自组织格栅动态库的负荷分配方法,其实现过程为:As shown in Fig. 1, a kind of load distribution method based on novel self-organizing grid dynamic library proposed by the present invention, its realization process is:

S1、建立初始格栅动态库:S1. Establish an initial grid dynamic library:

11)基于发电过程获取数据,构造数据源;其数据源包括:DCS/SIS历史数据、机组热力试验数据、煤质等离线数据和机组运行人员的经验数据;11) Obtain data based on the power generation process and construct data sources; the data sources include: DCS/SIS historical data, unit thermal test data, offline data such as coal quality, and experience data of unit operators;

11)基于数据源分析获得机组煤耗特性关系,具体是:通过机组热力试验得到实测数据,计算不同负荷段锅炉效率与煤耗特性关系,同时分析汽机热耗特性、单因素变化特性,获得各台机组发电煤耗、厂用电率;获取DCS/SIS历史数据,挖局获得基于数据驱动的各台机组煤耗特性。进一步结合机组运行人员的经验数据与上述热力试验分析结果及历史数据挖局结果进行相互验证,最终拟合出机组煤耗特性关系;11) Based on the analysis of data sources, the coal consumption characteristic relationship of the unit is obtained, specifically: the measured data is obtained through the thermal test of the unit, the relationship between the boiler efficiency and the coal consumption characteristic of different load segments is calculated, and the heat consumption characteristics of the steam turbine and the single factor change characteristics are analyzed at the same time, to obtain the characteristics of each unit Coal consumption for power generation and plant power consumption rate; obtain DCS/SIS historical data, and dig out to obtain the data-driven coal consumption characteristics of each unit. Further combine the experience data of unit operators with the above thermal test analysis results and historical data excavation results for mutual verification, and finally fit the coal consumption characteristic relationship of the unit;

热力试验条件下,获取多个试验工况下的实测数据及DCS运行数据,系统运行前预先将其拟合成二次多项式。Under the thermal test conditions, the measured data and DCS operation data under multiple test conditions are obtained, and the system is pre-fitted into a quadratic polynomial before the system runs.

数据挖掘方法拟合煤耗特性步骤如下:The steps of data mining method for fitting coal consumption characteristics are as follows:

Step1:获取DCS历史数据Step1: Obtain DCS historical data

Step2:进行稳定工况判断及筛选Step2: Judgment and screening of stable working conditions

Step3:对不同负荷段下的样本点进行处理分析。对样本点进行有效性分析,去除无效工况;判断各负荷段有效工况点个数,若工况点数不满足要求,则去除该负荷段;Step3: Process and analyze the sample points under different load segments. Perform validity analysis on sample points to remove invalid working conditions; determine the number of valid working condition points for each load segment, and remove the load segment if the number of working condition points does not meet the requirements;

Step4:将上述稳定数据拟合成二次曲线Step4: Fit the above stable data into a quadratic curve

Step5:根据当前计算工况点或近时间段内的多个稳定工况点,修改约束条件,修正煤耗曲线。Step5: Modify the constraint conditions and correct the coal consumption curve according to the current calculated working condition point or multiple stable working condition points in the near time period.

最后根据现场运行人员的运行经验,观察上述煤耗特性与现场运行结果的偏差,进行曲线修正,通过不断修正确保煤耗特性曲线总是符合当前设备状态的。Finally, according to the operation experience of the on-site operators, observe the deviation between the above-mentioned coal consumption characteristics and the on-site operation results, and perform curve correction. Through continuous correction, it is ensured that the coal consumption characteristic curve always conforms to the current equipment status.

13)按照环境温度、煤热值及给水泵等主要辅机运行情况等外部条件对各机组工况点进行分割。以第i台机组为例,给定工况点下,机组负荷上下限区间[Pi,min,Pi,max]、负荷变动速率[vi,min,vi,max]、负荷裕量限制ΔPi,limit、临界负荷约束Pi,critical,通过煤耗特性关系计算机组煤耗bi,condition13) According to external conditions such as ambient temperature, coal calorific value, and operation of main auxiliary machines such as feed water pumps, the operating point of each unit is divided. Taking unit i as an example, under a given working condition point, the unit load upper and lower limit range [P i,min ,P i,max ], load change rate [v i,min ,v i,max ], load margin Limit ΔP i,limit , critical load constraint P i,critical , and calculate group coal consumption b i,condition through coal consumption characteristic relationship;

14)依次计算各机组不同工况条件下的机组煤耗,形成初始记录群。14) Calculate the coal consumption of each unit under different working conditions in turn to form an initial record group.

15)将各机组分割后的不同工况进行组合,并计算所有组合方式下全厂总煤耗bcp,按照煤耗由低到高,总负荷由低到高排列形成初始动态库。15) Combine the different working conditions of each unit, and calculate the total coal consumption b cp of the whole plant under all combinations, and form the initial dynamic library according to the coal consumption from low to high and the total load from low to high.

16)进一步从DCS/SIS运行数据中提取历史运行工况,筛选出各工况下单机及全厂煤耗最低的负荷分配方式,按照时间先后顺序补充至初始动态库。16) Further extract the historical operating conditions from the DCS/SIS operating data, screen out the load distribution mode with the lowest coal consumption of the single machine and the whole plant under each operating condition, and add them to the initial dynamic library in chronological order.

S2、根据全厂总负荷指令及当前全厂机组运行情况进行动态库搜索定位,获取负荷分配参考记录;S2. Search and locate the dynamic library according to the total load command of the whole plant and the current operating conditions of the units of the whole plant, and obtain the load distribution reference records;

21)依据负荷总指令搜索动态库,获得满足条件的所有M条记录,构造记录矩阵A:21) Search the dynamic library according to the total command of the load, obtain all M records that meet the conditions, and construct the record matrix A:

其中:Pij为第i台机组第j条记录,ζij为第i台机组第j条记录偏置因子;Among them: P ij is the jth record of the i-th unit, ζ ij is the offset factor of the j-th record of the i-th unit;

相应地构造所有记录的时间向量T=[t1,t2,…tM]及煤耗矩阵B:Correspondingly construct all recorded time vector T=[t 1 ,t 2 ,…t M ] and coal consumption matrix B:

其中:bij为第i台机组第j条记录煤耗;Among them: b ij is the coal consumption recorded in item j of unit i;

再构造所有记录全厂总煤耗向量Bcp=[b1,cp,b2,cp,…bM,cp];Reconstruct all the records of the total plant coal consumption vector B cp =[b 1,cp ,b 2,cp ,...b M , cp ];

其中tj为第j条记录的时间,bj,cp为第j条记录分配方式全厂总煤耗;Where t j is the time of the jth record, b j , cp is the total coal consumption of the whole plant according to the distribution method of the jth record;

22)根据所有M条记录按照煤耗由低到高排序,选择煤耗最低的记录进行结果分配,煤耗相同时,将记录按照时间先后进行排序,选择最近的记录作为负荷分配参考记录。22) According to all M records sorted from low to high coal consumption, select the record with the lowest coal consumption to distribute the results.

S3、对分配参考记录进行偏差设置得到新的分配结果并发出指令;S3. Perform deviation setting on the allocation reference record to obtain a new allocation result and issue an instruction;

31)设定初始动态库各工况下不同机组的煤耗偏置因子为0;31) Set the coal consumption bias factor of different units under each working condition of the initial dynamic library to be 0;

32)在分配参考记录的基础上考虑机组动态特性变化情况,同时在保证总负荷不变的情况下,对每台机组进行负荷偏置;若偏置因子为0,则随机确定偏置因子正负情况,并对参考记录各机组负荷按照偏置因子调节;若偏置因子为正,则增大该机组的负荷,反之减小,确保偏置后总负荷不变,以此作为结果下达机组负荷指令;若偏置因子已知,则按照当前偏置因子方向按比例调节各机组负荷,确保调节后总负荷不变,下达分配指令32) On the basis of allocating reference records, consider the change of unit dynamic characteristics, and at the same time ensure that the total load remains unchanged, carry out load bias for each unit; if the bias factor is 0, randomly determine the bias factor positive Negative situation, and adjust the load of each unit according to the reference record according to the offset factor; if the offset factor is positive, then increase the load of the unit, otherwise decrease, to ensure that the total load remains unchanged after the offset, and use this as a result to issue the unit Load command; if the bias factor is known, adjust the load of each unit proportionally according to the direction of the current bias factor to ensure that the total load remains unchanged after adjustment, and issue a distribution command

S4、根据最终分配结果计算各机组煤耗bi,new及全厂总煤耗bcp,new,并基于公式(1)计算各机组当前工况下煤耗偏置因子,再根据负荷分配结果、单机组煤耗、全厂总煤耗、煤耗偏置因子以及各机组当前运行状态,更新动态库,备下次调用:S4. Calculate the coal consumption b i,new of each unit and the total coal consumption b cp,new of the whole plant according to the final distribution results, and calculate the coal consumption bias factor of each unit under the current working condition based on the formula (1), and then according to the load distribution results, single unit Coal consumption, total coal consumption of the whole plant, coal consumption bias factor, and the current operating status of each unit, update the dynamic library, and prepare for the next call:

以某电厂四台机组为例,选择一个月的网调AGC指令数据进行实时的优化分配,选取覆盖全工况范围的典型工况数据列于表1和表2。Taking four units of a certain power plant as an example, one month's network dispatching AGC instruction data is selected for real-time optimal distribution, and the typical working condition data covering the whole working condition range are selected and listed in Table 1 and Table 2.

表1:优化前负荷及煤耗Table 1: Optimal preload and coal consumption

表2:优化后负荷及煤耗Table 2: Load and coal consumption after optimization

表3:优化前后煤耗对比Table 3: Comparison of coal consumption before and after optimization

负荷指令(MW)Load command (MW) 1329.391329.39 1550.521550.52 1773.131773.13 1975.401975.40 2207.832207.83 2409.462409.46 优化前煤耗(g/kWh)Coal consumption before optimization (g/kWh) 344.48344.48 334.62334.62 330.62330.62 329.10329.10 328.07328.07 326.52326.52 优化后煤耗(g/kWh)Coal consumption after optimization (g/kWh) 343.08343.08 333.95333.95 329.10329.10 327.15327.15 326.60326.60 326.07326.07 节省煤耗(g/kWh)Save coal consumption (g/kWh) 1.401.40 0.670.67 1.521.52 1.951.95 1.481.48 0.460.46 节省煤耗率/%Coal saving rate/% 0.4060.406 0.1940.194 0.4600.460 0.5930.593 0.4510.451 0.1410.141

根据表1、表2,对比了典型负荷段优化分配前煤耗和优化分配后的煤耗率,并结合表3所示的节省煤耗率,可见优化分配后的煤耗明显优于电厂单机AGC控制下的煤耗,达到了节约燃料的优化效果。According to Table 1 and Table 2, the coal consumption before optimal distribution and the coal consumption rate after optimal distribution are compared in typical load segments, and combined with the coal consumption rate shown in Table 3, it can be seen that the coal consumption after optimal distribution is significantly better than that under the control of a single AGC in a power plant Coal consumption has achieved the optimization effect of saving fuel.

显然,本发明的上述实施例仅仅是为清楚地说明本发明所作的举例,而并非是对本发明的实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明权利要求的保护范围之内。Apparently, the above-mentioned embodiments of the present invention are only examples for clearly illustrating the present invention, rather than limiting the implementation of the present invention. For those of ordinary skill in the art, other changes or changes in different forms can be made on the basis of the above description. It is not necessary and impossible to exhaustively list all the implementation manners here. All modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included within the protection scope of the claims of the present invention.

Claims (5)

1. a kind of load distribution method based on new self-organizing grid dynamic base, it is characterised in that comprise the following steps:
(1) initial grid dynamic base is established;
(2) dynamic library searching positioning is carried out according to the instruction of full factory's total load and current complete each unit operation situation of factory, obtains load Assigned references record;
(3) assigned references are recorded with progress deviation to set to obtain new allocation result and send instruction;
(4) each unit coal consumption and full factory's total consumption of coal are calculated according to final allocation result, and calculates corresponding coal consumption bias factor, remembered Record renewal grid dynamic base.
2. a kind of load distribution method based on new self-organizing grid dynamic base according to claim 1, its feature exist In the process of establishing of the initial grid dynamic base of step (1) is:
(1a) obtains measured data by unit thermal test, calculates different load section boiler efficiency and coal consumption characteristic relation, together When analyze turbine heat rate characteristic, single factor test variation characteristic, obtain each unit generation coal consumption, station service power consumption rate;DCS/SIS is obtained to go through History data, analysis obtain each unit coal consumption characteristic based on data-driven;Tried further combined with operating experience and above-mentioned heating power Test analysis result and historical data analysis result is mutually authenticated, finally fit unit coal consumption characteristic relation;
(1b) is split according to the external condition of major pant item running situation to each unit operating point, and wherein major pant item is run Situation includes environment temperature, coal calorific value and feed pump;
(1c) calculates the unit coal consumption under each unit difference working condition successively, forms original records group;
Different operating modes after (1d) splits each unit are combined, and calculate all combination Xia Quan factories total consumption of coal bcp, press According to coal consumption from low to high, the total load initial dynamic base of arrangement form from low to high;
(1e) extracts history run operating mode from DCS/SIS service datas, and it is minimum to filter out unit and full factory's coal consumption under each operating mode Laod sharing mode, be supplemented to initial dynamic base according to time order and function order, form initial grid dynamic base.
3. a kind of load distribution method based on new self-organizing grid dynamic base according to claim 2, its feature exist According to the tool of each unit operation situation progress dynamic library searching positioning of the instruction of full factory's total load and current full factory in step (2) Body process is:
(2a) always instructs search dynamic base according to load, obtains all M bars record for the condition that meets, construction record matrix A:
Wherein:PijRecorded for i-th unit j-th strip, ζijBias factor is recorded for i-th unit j-th strip;
Correspondingly construct the time arrow T=[t of all records1,t2,…tM] and coal consumption matrix B:
Wherein:bijCoal consumption is recorded for i-th unit j-th strip;
Reconstruct and all record full factory's total consumption of coal vector Bcp=[b1,cp,b2,cp,…bM,cp];
Wherein tjFor the time of j-th strip record, bj,cpThe full factory's total consumption of coal of the method for salary distribution is recorded for j-th strip;
(2b) is recorded according to all M bars and sorted from low to high according to coal consumption, selects the minimum record of coal consumption to carry out result distribution, coal When consuming identical, record is ranked up according to time order and function, selects nearest record as sharing of load reference record.
4. a kind of load distribution method based on new self-organizing grid dynamic base according to claim 3, its feature exist In the detailed process that in step (3) assigned references are recorded with progress deviation setting is:
(3a) sets the coal consumption bias factor of different units under each operating mode of initial dynamic base as 0;
(3b) considers unit dynamic characteristic situation of change on the basis of assigned references record, while is ensureing that total load is constant In the case of, load biasing is carried out to every unit;It is random to determine the positive and negative situation of bias factor if bias factor is 0, and to ginseng Examine and record each unit load and adjusted according to bias factor;If bias factor reduces just, to increase the load of the unit, Total load is constant after ensuring biasing, and unit load instruction is assigned in this, as result;If bias factor, it is known that if according to it is current partially Put factor direction and adjust each unit load in proportion, it is ensured that total load is constant after regulation, assigns distribution instruction.
5. a kind of load distribution method based on new self-organizing grid dynamic base according to claim 4, its feature exist According to each unit coal consumption b of final allocation result calculating in step (4)i,newAnd full factory total consumption of coal bcp,new, and calculate each unit Coal consumption bias factor under current working:
<mrow> <mi>Z</mi> <mo>=</mo> <mo>&amp;lsqb;</mo> <msub> <mi>&amp;zeta;</mi> <mn>1</mn> </msub> <mo>,</mo> <mo>...</mo> <mo>,</mo> <msub> <mi>&amp;zeta;</mi> <mi>i</mi> </msub> <mo>,</mo> <mo>...</mo> <mo>,</mo> <msub> <mi>&amp;zeta;</mi> <mi>N</mi> </msub> <mo>&amp;rsqb;</mo> <mo>=</mo> <mo>&amp;lsqb;</mo> <mfrac> <mrow> <msub> <mi>b</mi> <mrow> <mn>1</mn> <mo>,</mo> <mi>n</mi> <mi>e</mi> <mi>w</mi> </mrow> </msub> <mo>-</mo> <msub> <mi>b</mi> <mrow> <mn>1</mn> <mi>j</mi> </mrow> </msub> </mrow> <msub> <mi>b</mi> <mrow> <mn>1</mn> <mi>j</mi> </mrow> </msub> </mfrac> <mo>,</mo> <mo>...</mo> <mo>,</mo> <mfrac> <mrow> <msub> <mi>b</mi> <mrow> <mi>i</mi> <mo>,</mo> <mi>n</mi> <mi>e</mi> <mi>w</mi> </mrow> </msub> <mo>-</mo> <msub> <mi>b</mi> <mrow> <mi>i</mi> <mi>j</mi> </mrow> </msub> </mrow> <msub> <mi>b</mi> <mrow> <mi>i</mi> <mi>j</mi> </mrow> </msub> </mfrac> <mo>,</mo> <mo>...</mo> <mo>,</mo> <mfrac> <mrow> <msub> <mi>b</mi> <mrow> <mi>N</mi> <mo>,</mo> <mi>n</mi> <mi>e</mi> <mi>w</mi> </mrow> </msub> <mo>-</mo> <msub> <mi>b</mi> <mrow> <mi>N</mi> <mi>j</mi> </mrow> </msub> </mrow> <msub> <mi>b</mi> <mrow> <mi>N</mi> <mi>j</mi> </mrow> </msub> </mfrac> <mo>&amp;rsqb;</mo> <mo>;</mo> </mrow>
Shape is currently run further according to sharing of load result, single fighter coal consumption, full factory's total consumption of coal, coal consumption bias factor and each unit State, dynamic base is updated, called standby next time.
CN201710807936.9A 2017-09-08 2017-09-08 A load distribution method based on a novel self-organizing grid dynamic library Active CN107688877B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710807936.9A CN107688877B (en) 2017-09-08 2017-09-08 A load distribution method based on a novel self-organizing grid dynamic library

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710807936.9A CN107688877B (en) 2017-09-08 2017-09-08 A load distribution method based on a novel self-organizing grid dynamic library

Publications (2)

Publication Number Publication Date
CN107688877A true CN107688877A (en) 2018-02-13
CN107688877B CN107688877B (en) 2020-09-25

Family

ID=61156138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710807936.9A Active CN107688877B (en) 2017-09-08 2017-09-08 A load distribution method based on a novel self-organizing grid dynamic library

Country Status (1)

Country Link
CN (1) CN107688877B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114722599A (en) * 2022-03-31 2022-07-08 浙江中控信息产业股份有限公司 Water plant grating operation optimization control method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101206754A (en) * 2006-12-21 2008-06-25 北京华电天仁电力控制技术有限公司 Plant-level Load Optimal Distribution Method of Thermal Power Plants Based on Multiple Constraint Rules
CN102622530A (en) * 2012-04-24 2012-08-01 华电能源股份有限公司哈尔滨第三发电厂 Improved genetic algorithm-based method for distributing and optimizing thermal and electrical load of steam extraction and heating unit
CN103440535A (en) * 2013-09-02 2013-12-11 华北电力大学 Multi-target plant level load optimization method based on immune optimization and fuzzy decision
CN106372756A (en) * 2016-09-07 2017-02-01 南京工程学院 Thermal power plant load optimization distribution method based on breeding particle swarm optimization

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101206754A (en) * 2006-12-21 2008-06-25 北京华电天仁电力控制技术有限公司 Plant-level Load Optimal Distribution Method of Thermal Power Plants Based on Multiple Constraint Rules
CN102622530A (en) * 2012-04-24 2012-08-01 华电能源股份有限公司哈尔滨第三发电厂 Improved genetic algorithm-based method for distributing and optimizing thermal and electrical load of steam extraction and heating unit
CN103440535A (en) * 2013-09-02 2013-12-11 华北电力大学 Multi-target plant level load optimization method based on immune optimization and fuzzy decision
CN106372756A (en) * 2016-09-07 2017-02-01 南京工程学院 Thermal power plant load optimization distribution method based on breeding particle swarm optimization

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
YU,ZHU 等: "Hierarchical Economic Load Dispatch Based on Chaotic-particle Swarm Optimization", 《2013 NINTH INTERNATIONAL CONFERENCE ON NATURAL COMPUTATION (ICNC)》 *
管益斌 等: "江苏电网节能发电调度分析与对策", 《中国电力》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114722599A (en) * 2022-03-31 2022-07-08 浙江中控信息产业股份有限公司 Water plant grating operation optimization control method

Also Published As

Publication number Publication date
CN107688877B (en) 2020-09-25

Similar Documents

Publication Publication Date Title
CN106356856B (en) A kind of Security corrective computational methods based on partition load control
CN103903073B (en) A kind of micro-capacitance sensor Method for optimized planning containing distributed power source and energy storage and system
CN102508474B (en) Circulated cooling water operation optimization control system for industrial enterprise
CN102013699B (en) Method for distributing active power of wind power station
CN112000075B (en) Coke dry quenching optimization control method and system
CN104571068A (en) Optimized operation control method and system of distributed energy system
Gao et al. Technologies in smart district heating system
CN103248056A (en) Reactive voltage emergency control method in concentrated grid connecting area of wind power plant
CN115640982B (en) Pumped storage priority regulation-based day-ahead optimal scheduling method for multi-energy complementary system
CN103056016A (en) Energy-saving optimization method for output of coal pulverizer in power station
CN104467028A (en) Method for automatically distributing load to units of thermal power plant
CN103150686B (en) Network and province integrated plan establishment method based on distributed preprocessing and hierarchical coordination
CN116760060A (en) A two-layer optimization method for frequency modulation power of fire-multi-storage system
CN103617455A (en) Power network and plant two-stage optimal load scheduling method based on virtual machine set subgroup
Cheng et al. Bi-level expansion planning of multiple energy systems under carbon emission constraints
CN112288170A (en) Optimization analysis method of power plant unit operating conditions based on big data analysis
CN112217197A (en) Optimization method for economic dispatch of double-layer distributed multi-region power distribution network
CN103345713A (en) Method for designing super-large scale power network synchronization security correction system
CN111598348A (en) A method, system, medium and electronic equipment for optimization of uniformity planning of transmission network
CN115933398A (en) Air compression system linkage control energy-saving method and system based on Internet of things
CN107688877A (en) A kind of load distribution method based on new self-organizing grid dynamic base
CN105958535A (en) Distributed power supply cluster control system and control method thereof
CN118378750A (en) Carbon-electricity cooperative low-carbon scheduling optimization decision method
CN112949892A (en) Regional power grid new energy power generation consumption optimization method, system, equipment and medium
CN116068890A (en) Cooperation optimization scheduling method and device for furnace-machine network of cogeneration district heating

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant