CN107679687A - A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure - Google Patents

A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure Download PDF

Info

Publication number
CN107679687A
CN107679687A CN201710761852.6A CN201710761852A CN107679687A CN 107679687 A CN107679687 A CN 107679687A CN 201710761852 A CN201710761852 A CN 201710761852A CN 107679687 A CN107679687 A CN 107679687A
Authority
CN
China
Prior art keywords
photovoltaic
sample
formula
fuzzy
day
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710761852.6A
Other languages
Chinese (zh)
Inventor
关志坚
归三荣
韩俊
吴垠
陈曦
陈皓菲
袁越
杨苏
吴涵
凌开元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
State Grid Corp of China SGCC
Hohai University HHU
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
State Grid Corp of China SGCC
Hohai University HHU
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd, State Grid Corp of China SGCC, Hohai University HHU, Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
Priority to CN201710761852.6A priority Critical patent/CN107679687A/en
Publication of CN107679687A publication Critical patent/CN107679687A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F18/00Pattern recognition
    • G06F18/20Analysing
    • G06F18/23Clustering techniques
    • G06F18/232Non-hierarchical techniques
    • G06F18/2321Non-hierarchical techniques using statistics or function optimisation, e.g. modelling of probability density functions
    • G06F18/23213Non-hierarchical techniques using statistics or function optimisation, e.g. modelling of probability density functions with fixed number of clusters, e.g. K-means clustering
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Data Mining & Analysis (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Artificial Intelligence (AREA)
  • Evolutionary Computation (AREA)
  • Evolutionary Biology (AREA)
  • Game Theory and Decision Science (AREA)
  • Bioinformatics & Computational Biology (AREA)
  • Bioinformatics & Cheminformatics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Probability & Statistics with Applications (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of photovoltaic output modeling method, including:1)The year sequential of sample is contributed using Fisher optimal segmentations algorithm according to effective output photovoltaic day, length time and carries out optimal segmentation, forms the data set of day part;2)Fuzzy c-Means Clustering Algorithm model is built, and cluster analysis is carried out one by one to the day part data set using the Fuzzy c-Means Clustering Algorithm model, until the Euclidean distance of data set and corresponding cluster centre is minimum.Have the beneficial effect that:Using Fisher optimal segmentations method to the piecewise fine modeling of photovoltaic output sequence, the local sequential feature of this area's photovoltaic power can be more embodied, there is stronger practicality and specific aim;Using FCM multidimensional clustering algorithms, cluster analysis is carried out to day part photovoltaic power and workload demand, this method simple and highly efficient the characteristics of simulating the randomness and timing that stochastic variable has.

Description

A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure
Technical field
The present invention relates to the grid-connected reliability consideration of renewable energy power, more particularly to a kind of photovoltaic output modeling method with And Generation System Reliability appraisal procedure.
Background technology
With the rapid development of economy, electricity needs is continuously increased, and the large-scale application of regenerative resource meets society Requirement to environmental protection, energy-saving and emission-reduction and sustainable development.After rational planning, they can postpone transmission & distribution The construction or upgrading of electric network, reduce network outages and strengthening system safety in operation and reliability, improve system electricity Energy quality etc. produces beneficial effect.Wherein, photovoltaic generation is quickly grown in recent years, system of the accurate evaluation containing photovoltaic generation Reliability becomes particularly significant, has research to predict, 2 000MWp are up to China's Photovoltaic generation installed capacity in 2020, counts Draw and increase by more than 15% in year.
In the reliability consideration containing photovoltaic generating system, the modeling that photovoltaic is contributed is the focus studied instantly.At present, state The inside and outside research for going out force modeling to photovoltaic can be divided into two classes:One kind is the physical modeling based on solar energy resources.Such In model, based on analysis irradiation intensity, the factor such as temperature and photovoltaic array angle, by photoelectric conversion process, photovoltaic is finally given The power output of system.The data volume that its modeling process needs is big, calculates more complicated;Another kind of is to be contributed with photovoltaic history as base The statistical modeling of plinth, directly by the statistical analysis to photovoltaic plant history power output, utilize Monte-Carlo step technology mould Photovoltaic plant power output is drawn up, this method enormously simplify opto-electronic conversion model.Document one《Photovoltaic based on Markov chain Electricity generation system power output short term prediction method》(electric power network technique, 2011, volume 35, the 1st phase, page 152 to page 157) adopt Statistical modeling, document two have been carried out with being contributed based on the clustering technique of Markov Process as Applied to photovoltaic generation《Based on neutral net Photovoltaic array generating forecast model design》(electrotechnics journal, 2009, volume 24, the 9th phase, page 153 to 158 Page) use the clustering technique of neutral net, above method is relatively cumbersome.Document three《A time-dependent approach to evaluate capacity value of wind and solar PV generation》(IEEE Transactions on Sustainable Energy, 2016, volume 7, the 1st phase, page 129 to page 138) in consider The characteristic and correlation diurnal periodicity that photovoltaic is contributed and load has, using a kind of technology of cluster, analyzes photovoltaic generating system Confidence capacity.But the reliability index of the use of document three can only reflect the average level of annual time scale, it is impossible to accurate to carve Influence of the day part photovoltaic to electricity generation system in drawing 1 year, its reliability index are excessively coarse, it is impossible to reflect that photovoltaic is contributed season Characteristic.
In to the system Reliability Research containing photovoltaic plant, generally directed to be a year and a day photovoltaic and load data, The result of calculating can only also characterize comprehensive contribution of the photovoltaic generation to system whole year abundant intensity, the application of the reliability assessment It is narrower, it is limited to actual production directive function.But inherently differed for different regions, its photovoltaic power producing characteristics.Only From the time scale of whole year, it is difficult to do the research to become more meticulous to influence of the photovoltaic generation to system reliability.It is therefore necessary to grind Various Seasonal and in a few days influence of the different periods photovoltaic generation to system reliability are studied carefully, to reach in shorter time dimension On, the influence of finer consideration photovoltaic resources characteristic and part throttle characteristics to system reliability.And the most frequently used segmentation side Method is the dividing mode according to season, i.e., annual time scale is divided into 4 periods, corresponded to respectively:Spring, summer, autumn and winter.But should Method is a kind of fuzzy, segmentation for being manually set, without the foundation of reality, it is impossible to for somewhere actual photovoltaic contribute it is special Property carry out that there is targetedly optimal segmentation.
The content of the invention
Present invention aims to overcome that the deficiency of above-mentioned prior art, there is provided a kind of photovoltaic output modeling method and hair Electric system reliability estimation method, specifically there is following technical scheme realization:
The photovoltaic output modeling method, including:
The year sequential of sample is gone out using Fisher optimal segmentations algorithm according to effective output photovoltaic day, length time
Power carries out optimal segmentation, forms the data set of day part;
Fuzzy c-Means Clustering Algorithm model is built, and using the Fuzzy c-Means Clustering Algorithm model to the day part Data set carries out cluster analysis one by one, carries out building object function first during cluster analysis, then straight to object function iteration optimizing It is minimum to the Euclidean distance of data set and corresponding cluster centre.
The further design of the photovoltaic output modeling method is, the structure of the Fisher optimal segmentations algorithm model Including:
Set { X1,X2,…,XnIt is n ordered sample, each sample is m dimensional vectors, and the sample is divided, record A certain section of sample be:
G (i, j)={ Xi,Xi+1,…,Xj} (1)
Using description of the sum of squares of deviations as this section of diameter, i.e.,:
In formula, D (i, j) is the ordered sample from i-th of sample to the sum of squares of deviations of j-th of sample;For the section The average of ordered sample;
The ordered sample is divided into k sections, every section of sample index is designated as Bj={ ij,ij+1,…,ij+1- 1 }, j ∈ 1, 2 ..., k }, quantile therein meets:1=i1< i2< ... < ik< n=ik+1, total object function is obtained, such as formula (4):
In formula, L is each section of deviation total sum of squares, and L values are smaller, and segmentation is more reasonable.
The further design of the photovoltaic output modeling method is, the target of the Fuzzy c-Means Clustering Algorithm model Function such as formula (5):
In formula, U is subordinated-degree matrix;C is cluster centre matrix;M is weighting multiple;dijFor ith cluster center and jth Euclidean distance between individual data point.
3rd, photovoltaic output modeling method according to claim 1, it is characterised in that the Fuzzy c-Means Clustering Algorithm For iteration searching process, cluster centre battle array and degree of membership battle array are updated by formula (7), formula (8):
If front and rear iterative process twice, the knots modification of object function is less than some threshold value, then cluster process terminates:
||J(U(z+1), C(z+1))-J(U(z), C(z)) | | < 9 (9)
In formula:J(U(z),C(z)) for the target function value of the z times iteration, threshold epsilon typically take 10-4
A kind of Generation System Reliability appraisal procedure is provided according to the photovoltaic output modeling method, based on optimal segmentation It is as follows with multidimensional clustering algorithm, step:
Step 1) recombinates to photovoltaic output sequence, forms with the data mode of arrangement in 24 hours one day, forms matrix Form is the photovoltaic output battle array P of 365 row * 24 rowpv
Step 2) statistics obtains photovoltaic effective output time series Tpv, according to the original of the daily effective output time length of photovoltaic Then, using Fisher optimal segmentation algorithms, force data progress sequential segmentation is gone out to the photovoltaic history of year simulation cycle, obtained optimal Waypoint;
Step 3) is in each period, respectively to photovoltaic power and workload demand data, when determining each by FCM clustering procedures The cluster centre and fuzzy membership matrix of section photovoltaic power, the cluster centre and fuzzy membership matrix of day part load;
Step 4) is simulated to the running status of the photovoltaic power of each period, workload demand and conventional power unit, system The reliability index of meter systems.
The further design of the Generation System Reliability appraisal procedure is that the step 4) passes through Monte Carlo state The methods of sampling is, it is specified that frequency in sampling is 105It is secondary.
The further design of the Generation System Reliability appraisal procedure is, expected energy not supplied is used in step 4) LOEE is as reliability index, LOEE expression formula such as formula (10):
In formula:S is the iterations in sampled analog;T is moment point, h;N is the iteration total degree of setting;TdayFor this The number of days of period;G is the quantity of whole conventional power units;Ds,tAnd Ps,tIn respectively the s times iteration, needed in moment t load The amount of asking and photovoltaic power.
Beneficial effects of the present invention:
1st, photovoltaic output modeling method, it is characterised in that including:
According to effective output photovoltaic day, length time using Fisher optimal segmentations algorithm the year sequential of sample is contributed into Row optimal segmentation, form the data set of day part;
Fuzzy c-Means Clustering Algorithm model is built, and using the Fuzzy c-Means Clustering Algorithm model to the day part Data set carries out cluster analysis one by one, until the Euclidean distance of data set and corresponding cluster centre is minimum.
Embodiment
The present invention program is described in detail below.
The photovoltaic output modeling method of the present embodiment, including two steps are respectively:1) when according to photovoltaic day effective output Between length the year sequential of sample contributed using Fisher optimal segmentations algorithm carry out optimal segmentation, form the data of day part Collection.2) Fuzzy c-Means Clustering Algorithm model is built, and using the Fuzzy c-Means Clustering Algorithm model to the day part number Cluster analysis is carried out one by one according to collection, until the Euclidean distance of data set and corresponding cluster centre is minimum.Fisher optimal segmentations are calculated Method model:
Assuming that { X1,X2,…,XnIt is n ordered sample, each sample is m dimensional vectors.The sample is divided, recorded A certain section of sample be:
G (i, j)={ Xi,Xi+1,…,Xj} (1)
Using description of the sum of squares of deviations as this section of diameter, i.e.,:
In formula:D (i, j) is the ordered sample from i-th of sample to the sum of squares of deviations of j-th of sample;For the section The average of ordered sample.
When having obtained every section of sum of squares of deviations, if the ordered sample is divided into k sections, every section of sample index is designated as Bj ={ ij,ij+1,…,ij+1- 1 }, j ∈ { 1,2 ..., k }, quantile therein meet:1=i1< i2< ... < ik< n=ik+1。 So as to obtain total object function, as shown in formula (4).
In formula:L is each section of deviation total sum of squares, and L values are smaller, and segmentation is more reasonable.
There are some researches show linear relation is presented in sunshine-duration of the illumination irradiation level of, given area often with this area. I.e. in certain time period, sunshine-duration of one day grow section substantially reflect irradiation level power.And for photovoltaic generating system, light Volt is contributed directly to be influenceed by irradiation level again, so the length of sunshine-duration embodies the power of photovoltaic output indirectly.Based on this, The present invention discloses a kind of new segmented mode, i.e., according to the principle of photovoltaic effective output time length in one day, photovoltaic year is gone out Power carries out ordered section.
Fuzzy c-Means Clustering Algorithm model:
The target of the algorithm is so that the Euclidean distance of data set and corresponding cluster centre is minimum, and object function is as follows:
In formula:U is subordinated-degree matrix;C is cluster centre matrix;M is weighting multiple;dijFor ith cluster center and jth Euclidean distance between individual data point.
The algorithm is an iteration searching process, cluster centre battle array and degree of membership battle array can be carried out by following two formula Renewal.
If front and rear iterative process twice, the knots modification of object function is less than some threshold value, then cluster process terminates:
||J(U(z+1), C(z+1))-J(U(z), C(z)) | | < ε (9)
In formula:J(U(z),C(z)) for the target function value of the z times iteration, threshold epsilon typically take 10-4
The present invention is used as reliability index using expected energy not supplied (loss of energy expection, LOEE), The index not only preferably reflects the size of system short of electricity amount, the system reliability that can be more reflected in each period.
In formula:S is the iterations in sampled analog;T is moment point, h;N is the iteration total degree of setting; TdayFor this The number of days of period;G is the quantity of whole conventional power units;Ds,tAnd Ps,tIn respectively the s times iteration, needed in moment t load The amount of asking and photovoltaic power.
The present embodiment is according to the method for above-mentioned photovoltaic output Series Modeling, there is provided one kind is based on optimal segmentation and multidimensional clustering Reliability Modeling.This method is contributed to photovoltaic carry out sequential segment processing first;Then cluster analysis is carried out to every section, Sampled analog obtains the reliability index value of system.Specific calculation procedure is as follows:
Step 1) recombinates to photovoltaic output sequence, forms with the data mode of arrangement in 24 hours one day, forms matrix Form is the photovoltaic output battle array P of 365 row * 24 rowpv
Step 2) statistics obtains photovoltaic effective output time series Tpv, according to the original of the daily effective output time length of photovoltaic Then, using Fisher optimal segmentation algorithms, force data progress sequential segmentation is gone out to the photovoltaic history of year simulation cycle, obtained optimal Waypoint.
Step 3) is in each period, respectively to photovoltaic power and workload demand data, when determining each using FCM clustering procedures Between section cluster numbers, cluster centre and fuzzy membership battle array.It should be noted that cluster analysis and the photovoltaic power of workload demand Analysis method is identical, repeats no more here.
In summary 3 steps obtain step 4):The cluster centre and fuzzy membership matrix of each period photovoltaic power, respectively The cluster centre and fuzzy membership matrix of individual period load, the capacity and fault rate of the conventional power unit of RTS test systems.Utilize Monte Carlo state sampling technology is, it is specified that frequency in sampling is 105It is secondary, to the photovoltaic power of each period, workload demand and often The running status of rule unit is simulated, the reliability index of statistical system.
Compared with prior art, the advantages of present invention is prominent includes:First, in reliability assessment containing photovoltaic generating system The date periodicity round the clock and season timing cycles of photovoltaic output are considered, photovoltaic is contributed using Fisher optimal segmentations method The piecewise fine modeling of sequence, the local sequential feature of this area's photovoltaic power can be more embodied, there is stronger practicality and be directed to Property;Secondly, using FCM multidimensional clustering algorithms, cluster analysis is carried out to day part photovoltaic power and workload demand, this method is simple And the characteristics of efficiently simulating the randomness and timing that stochastic variable has;Finally, with reference to Monte Carlo state sampling side Method to carrying out fail-safe analysis containing photovoltaic generating system, institute's extracting method can effective lifting system reliability assessment precision, quantization After analysis access photovoltaic plant, system is in the situation of change of different time sections reliability, the grid connection capacity planning to photovoltaic plant With great importance.
Photovoltaic output modeling method provided by the invention and Generation System Reliability appraisal procedure have been carried out in detail above It is thin to introduce, in order to understand the present invention and its core concept., in the specific implementation, can for those of ordinary skill in the art A variety of modifications and deduction are carried out according to the core concept of the present invention.In summary, this specification is not construed as the limit to the present invention System.

Claims (7)

  1. A kind of 1. photovoltaic output modeling method, it is characterised in that including:
    The year sequential of sample is contributed using Fisher optimal segmentations algorithm according to effective output photovoltaic day, length time and carried out most Optimal sorting section, form the data set of day part;
    Fuzzy c-Means Clustering Algorithm model is built, and using the Fuzzy c-Means Clustering Algorithm model to the day part data Collection carries out cluster analysis one by one, carries out building object function during cluster analysis first, then to the optimizing of object function iteration until number Euclidean distance according to collection and corresponding cluster centre is minimum.
  2. 2. photovoltaic output modeling method according to claim 1, it is characterised in that the Fisher optimal segmentations algorithm mould The structure of type includes:
    Set { X1,X2,…,XnIt is n ordered sample, each sample is m dimensional vectors, and the sample is divided, and records sample A certain section be:
    G (i, j)={ Xi,Xi+1,…,Xj} (1)
    Using description of the sum of squares of deviations as this section of diameter, i.e.,:
    In formula, D (i, j) is the ordered sample from i-th of sample to the sum of squares of deviations of j-th of sample;It is orderly for the section The average of sample;
    The ordered sample is divided into k sections, every section of sample index is designated as Bj={ ij,ij+1,…,ij+1- 1 }, j ∈ 1,2 ..., K }, quantile therein meets:1=i1< i2< ... < ik< n=ik+1, total object function is obtained, such as formula (4):
    In formula, L is each section of deviation total sum of squares, and L values are smaller, and segmentation is more reasonable.
  3. 3. photovoltaic output modeling method according to claim 1, it is characterised in that the Fuzzy c-Means Clustering Algorithm model Object function such as formula (5):
    In formula:U is subordinated-degree matrix;C is cluster centre matrix;M is weighting multiple;dijFor ith cluster center and j-th of number Euclidean distance between strong point, μijFor j-th of data point and the degree of membership at ith cluster center.
  4. 4. photovoltaic output modeling method according to claim 1, it is characterised in that the Fuzzy c-Means Clustering Algorithm is repeatedly For searching process, cluster centre battle array and degree of membership battle array are updated by formula (7), formula (8):
    If front and rear iterative process twice, the knots modification of object function is less than some threshold value and (is generally less than 10-3), then cluster process knot Beam:
    ||J(U(z+1),C(z+1))-J(U(z),C(z)) | | < ε (9)
    In formula:J(U(z),C(z)) for the target function value of the z times iteration.
  5. 5. the Generation System Reliability appraisal procedure of the photovoltaic output modeling method as described in claim any one of 1-4, it is special Sign is as follows based on optimal segmentation and multidimensional clustering algorithm, step:
    Step 1) recombinates to photovoltaic output sequence, forms with the data mode of arrangement in 24 hours one day, forms matrix form For the photovoltaic output battle array P of 365 row * 24 rowpv
    Step 2) statistics obtains photovoltaic effective output time series Tpv, according to the principle of the daily effective output time length of photovoltaic, Using Fisher optimal segmentation algorithms, force data progress sequential segmentation is gone out to the photovoltaic history of year simulation cycle, obtains most optimal sorting Duan Dian;
    Respectively to photovoltaic power and workload demand data, day part light is determined by FCM clustering procedures in each period for step 3) Lie prostrate the cluster centre and fuzzy membership matrix of power, the cluster centre and fuzzy membership matrix of day part load;
    Step 4) is simulated to the running status of the photovoltaic power of each period, workload demand and conventional power unit, department of statistic The reliability index of system.
  6. 6. Generation System Reliability appraisal procedure according to claim 5, it is characterised in that the step 4) is special by covering Caro state sampling method is, it is specified that frequency in sampling is 105It is secondary.
  7. 7. Generation System Reliability appraisal procedure according to claim 5, it is characterised in that in step 4) using electricity not Foot it is expected LOEE as reliability index, LOEE expression formula such as formula (10):
    In formula:S is the iterations in sampled analog;T is moment point, h;N is the iteration total degree of setting;TdayFor the time The number of days of section;G is the quantity of whole conventional power units;Ds,tAnd Ps,tIn respectively the s times iteration, in moment t workload demand amount And photovoltaic power.
CN201710761852.6A 2017-08-29 2017-08-29 A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure Pending CN107679687A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710761852.6A CN107679687A (en) 2017-08-29 2017-08-29 A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710761852.6A CN107679687A (en) 2017-08-29 2017-08-29 A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure

Publications (1)

Publication Number Publication Date
CN107679687A true CN107679687A (en) 2018-02-09

Family

ID=61134856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710761852.6A Pending CN107679687A (en) 2017-08-29 2017-08-29 A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure

Country Status (1)

Country Link
CN (1) CN107679687A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108376262A (en) * 2018-02-23 2018-08-07 新疆大学 A kind of analysis model construction method of wind power output typical characteristics
CN109494792A (en) * 2018-11-21 2019-03-19 国网青海省电力公司 Method and device for determining light abandoning electric quantity of photovoltaic power station
CN111090926A (en) * 2019-11-14 2020-05-01 远景智能国际私人投资有限公司 Photovoltaic power curve modeling method and device, computer equipment and storage medium
CN111293681A (en) * 2020-01-22 2020-06-16 重庆大学 Photovoltaic station output fluctuation quantitative evaluation method based on RankBoost
CN112381409A (en) * 2020-11-16 2021-02-19 江西电力交易中心有限公司 Dynamic adjustment method for peak time period
CN113659631A (en) * 2021-08-09 2021-11-16 大连理工大学 Wind-solar power station group output description method considering time-varying characteristics
CN114398493A (en) * 2021-12-29 2022-04-26 中国人民解放军92728部队 Unmanned aerial vehicle type spectrum construction method based on fuzzy clustering and cost-effectiveness value
CN114896871A (en) * 2022-04-22 2022-08-12 国网江苏省电力有限公司电力科学研究院 Photovoltaic output decomposition method based on minimum mutual information

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105931134A (en) * 2016-04-25 2016-09-07 华北电力大学 Method for evaluating reliability of system with grid-connected photovoltaic power station
CN106096753A (en) * 2016-05-30 2016-11-09 北京中电普华信息技术有限公司 A kind of photovoltaic power generation output forecasting method and apparatus
CN106779175A (en) * 2016-11-28 2017-05-31 西安交通大学 It is a kind of to consider that non-linear photovoltaic at times is exerted oneself Forecasting Methodology

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105931134A (en) * 2016-04-25 2016-09-07 华北电力大学 Method for evaluating reliability of system with grid-connected photovoltaic power station
CN106096753A (en) * 2016-05-30 2016-11-09 北京中电普华信息技术有限公司 A kind of photovoltaic power generation output forecasting method and apparatus
CN106779175A (en) * 2016-11-28 2017-05-31 西安交通大学 It is a kind of to consider that non-linear photovoltaic at times is exerted oneself Forecasting Methodology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨苏等: "含光伏电站发电系统可靠性评估方法研究", 《电力需求侧管理》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108376262B (en) * 2018-02-23 2021-08-10 新疆大学 Analytical model construction method for typical characteristics of wind power output
CN108376262A (en) * 2018-02-23 2018-08-07 新疆大学 A kind of analysis model construction method of wind power output typical characteristics
CN109494792A (en) * 2018-11-21 2019-03-19 国网青海省电力公司 Method and device for determining light abandoning electric quantity of photovoltaic power station
CN109494792B (en) * 2018-11-21 2022-05-13 国网青海省电力公司 Method and device for determining light abandoning electric quantity of photovoltaic power station
CN111090926A (en) * 2019-11-14 2020-05-01 远景智能国际私人投资有限公司 Photovoltaic power curve modeling method and device, computer equipment and storage medium
WO2021096432A1 (en) * 2019-11-14 2021-05-20 Envision Digital International Pte. Ltd. Method and apparatus for modeling photovoltaic power curve, and computer device and storage medium thereof
CN111090926B (en) * 2019-11-14 2023-09-12 远景智能国际私人投资有限公司 Photovoltaic power curve modeling method and device, computer equipment and storage medium
CN111293681B (en) * 2020-01-22 2023-04-25 重庆大学 Photovoltaic field station output fluctuation quantitative evaluation method based on RankBoost
CN111293681A (en) * 2020-01-22 2020-06-16 重庆大学 Photovoltaic station output fluctuation quantitative evaluation method based on RankBoost
CN112381409A (en) * 2020-11-16 2021-02-19 江西电力交易中心有限公司 Dynamic adjustment method for peak time period
CN113659631A (en) * 2021-08-09 2021-11-16 大连理工大学 Wind-solar power station group output description method considering time-varying characteristics
CN113659631B (en) * 2021-08-09 2022-07-26 大连理工大学 Wind-solar power station group output description method considering time-varying characteristics
CN114398493A (en) * 2021-12-29 2022-04-26 中国人民解放军92728部队 Unmanned aerial vehicle type spectrum construction method based on fuzzy clustering and cost-effectiveness value
CN114398493B (en) * 2021-12-29 2022-12-16 中国人民解放军92728部队 Unmanned aerial vehicle type spectrum construction method based on fuzzy clustering and cost-effectiveness value
CN114896871A (en) * 2022-04-22 2022-08-12 国网江苏省电力有限公司电力科学研究院 Photovoltaic output decomposition method based on minimum mutual information
CN114896871B (en) * 2022-04-22 2023-12-22 国网江苏省电力有限公司电力科学研究院 Photovoltaic output decomposition method based on minimum mutual information

Similar Documents

Publication Publication Date Title
CN107679687A (en) A kind of photovoltaic output modeling method and Generation System Reliability appraisal procedure
Liu et al. Random forest solar power forecast based on classification optimization
CN110070226A (en) Photovoltaic power prediction technique and system based on convolutional neural networks and meta learning
CN102184337B (en) Dynamic combination analysis method of new energy generating capacity influenced by meteorological information
CN108376262B (en) Analytical model construction method for typical characteristics of wind power output
CN106251001A (en) A kind of based on the photovoltaic power Forecasting Methodology improving fuzzy clustering algorithm
CN105184678A (en) Method for constructing photovoltaic power station generation capacity short-term prediction model based on multiple neural network combinational algorithms
CN104200032B (en) Based on period horizontal time shafts clustering method in broad sense load modeling
CN104899665A (en) Wind power short-term prediction method
CN104978611A (en) Neural network photovoltaic power generation output prediction method based on grey correlation analysis
CN111754037B (en) Long-term load hybrid prediction method for regional terminal integrated energy supply system
CN105069521A (en) Photovoltaic power plant output power prediction method based on weighted FCM clustering algorithm
CN109376951A (en) A kind of photovoltaic probability forecasting method
CN112186761B (en) Wind power scene generation method and system based on probability distribution
CN111859283B (en) Scene generation method considering multi-energy charge time sequence and correlation
CN109272258B (en) Regional wind and solar power generation resource evaluation method based on K-means clustering
CN109255728A (en) The photovoltaic generation power neural network prediction method of chaos phase space optimal reconfiguration
CN111709109A (en) Photovoltaic absorption capacity calculation method and device considering source-load time sequence correlation
CN115829126A (en) Photovoltaic power generation power prediction method based on multi-view self-adaptive feature fusion
CN113516271A (en) Wind power cluster power day-ahead prediction method based on space-time neural network
CN106611243A (en) Residual correction method for wind speed prediction based on GARCH (Generalized ARCH) model
CN116894504A (en) Wind power cluster power ultra-short-term prediction model establishment method
Meng et al. A new PV generation power prediction model based on GA-BP neural network with artificial classification of history day
Jin et al. Wind and photovoltaic power time series data aggregation method based on an ensemble clustering and Markov chain
CN112836876B (en) Power distribution network line load prediction method based on deep learning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180209