CN107678848A - Repeater satellite task scheduling constrains the construction method and device of plan model - Google Patents

Repeater satellite task scheduling constrains the construction method and device of plan model Download PDF

Info

Publication number
CN107678848A
CN107678848A CN201710967156.0A CN201710967156A CN107678848A CN 107678848 A CN107678848 A CN 107678848A CN 201710967156 A CN201710967156 A CN 201710967156A CN 107678848 A CN107678848 A CN 107678848A
Authority
CN
China
Prior art keywords
task
formula
repeater satellite
time
satellite
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710967156.0A
Other languages
Chinese (zh)
Other versions
CN107678848B (en
Inventor
胡欣岳
马楠
开彩虹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei University of Technology
Original Assignee
Hefei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei University of Technology filed Critical Hefei University of Technology
Priority to CN201710967156.0A priority Critical patent/CN107678848B/en
Publication of CN107678848A publication Critical patent/CN107678848A/en
Application granted granted Critical
Publication of CN107678848B publication Critical patent/CN107678848B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/46Multiprogramming arrangements
    • G06F9/48Program initiating; Program switching, e.g. by interrupt
    • G06F9/4806Task transfer initiation or dispatching
    • G06F9/4843Task transfer initiation or dispatching by program, e.g. task dispatcher, supervisor, operating system
    • G06F9/485Task life-cycle, e.g. stopping, restarting, resuming execution

Landscapes

  • Engineering & Computer Science (AREA)
  • Software Systems (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radio Relay Systems (AREA)

Abstract

The embodiments of the invention provide the construction method and device of a kind of repeater satellite task scheduling constraint plan model,This method is when building model,For the forward link of space-based backbone network relay satellite system,That is earth station --- repeater satellite --- user spacecraft,Or earth station --- repeater satellite --- repeater satellite --- user spacecraft,More repeater satellites be present,And in the case of between repeater satellite communication link being present,SEE time window is considered,Task attribute,The constraintss such as the propagation delay of resource-constrained scheduling user task is limited and communication delay is limited,So that the planning of repeater satellite task can be completed in the case where meeting above-mentioned constraints based on the task scheduling approach that the model obtains,Ensure that the higher task of priority can be by successful dispatch as much as possible,And then improve the efficiency of task scheduling.

Description

Repeater satellite task scheduling constrains the construction method and device of plan model
Technical field
The present embodiments relate to communication technical field, and in particular to a kind of repeater satellite task scheduling constrains plan model Construction method and device.
Background technology
Due to repeater satellite limited amount, data service capabilities are limited, and with needing the user of repeater satellite service to navigate The constraint of SEE time window between its device be present, therefore how the mission planning of rational layout dispatching of relays satellite is in raising After satellite utilization rate, and then improve the key technology of the efficiency of whole Information Network.Existing relay satellite system task is adjusted The main object of degree research is reservation type task, due to the complexity of repeater satellite Mission Scheduling, existing repeater satellite Most of mathematical modeling of task scheduling is NP-hard problems, therefore existing solution party's fado is heuritic approach.The first Algorithm solves the problems, such as mission planning using artificial bee colony algorithm, and it has initially set up the mathematical modeling of repeater satellite scheduling, provides Fitness function and various constraintss, and using artificial bee colony algorithm search for and obtain preferably task scheduling side Case.Second algorithm establishes the Task Scheduling Model existed under the conditions of more repeater satellites, and using based on population combine into The resource allocation algorithm of change is solved.
However, during innovation and creation are realized, inventor has found that original repeater satellite dispatching algorithm is in modeling Scene when only considering to have single repeater satellite mostly, such as the first algorithm.Second algorithm considers that more relayings be present defends The scene of star, but communication link be present between have ignored repeater satellite in it, actually due to existing between repeater satellite Communication link, therefore when some user spacecraft task needs some given trunk satellite to be serviced for it, it not only can be straight Connect and contacted with this repeater satellite, and can indirectly be contacted with this repeater satellite by the method that repeater satellite relays.
Equally, in existing modeling (such as above-mentioned the first and second algorithm) considers that the time delay of task will Ask, because between repeater satellite, repeater satellite and user's interstellar distance are very long, therefore data transmission delay is obvious, and many time delays are quick Feel generic task, such as the transmission of measurement and control signal has strict requirements to data transmission delay, this make it that existing model can not Meet this requirement.
The content of the invention
The purpose of the embodiment of the present invention is to provide a kind of structure for repeater satellite task scheduling constraint plan model Method and device.
In a first aspect, the embodiments of the invention provide a kind of structure side of repeater satellite task scheduling constraint plan model Method, including:
Obtain the priority of default each scheduler task, the earliest start time that each task is successfully executed, all tasks Maximum delay time and each repeater satellite on be each task service pot life window;
The earliest start time that is successfully executed according to the priority of each scheduler task, each task, all tasks Maximum propagation time delay and pot life window, build the fitness function and constraints of the model;
Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, meets and hold The period of row preset task;The fitness function of the model, for in the specified priority, the early start The target letter of optimal task schedule scheme is obtained under time and the maximum propagation time delay, under the constraint of the constraints Number;The optimal task schedule scheme is that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Scheme.
Second aspect, the embodiments of the invention provide a kind of structure dress of repeater satellite task scheduling constraint plan model Put, including:
Acquiring unit, obtain earliest start time that priority, each task of default each scheduler task be successfully executed, It is the pot life window of each task service on the maximum delay time of all tasks and each repeater satellite;
Construction unit, during the early start being successfully executed for the priority according to each scheduler task, each task Between, the maximum propagation time delay of all tasks and pot life window, build the fitness function and constraints of the model;
Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, meets and hold The period of row preset task;The fitness function of the model, for in the specified priority, the early start The target letter of optimal task schedule scheme is obtained under time and the maximum propagation time delay, under the constraint of the constraints Number;The optimal task schedule scheme is that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Scheme.
The third aspect, another embodiment of the present invention provide a kind of computer equipment, including memory, processor and Storage is realized above-mentioned on a memory and the computer program that can run on a processor, during the computing device described program The step of first aspect methods described.
Fourth aspect, another embodiment of the present invention provide a kind of computer-readable recording medium, are stored thereon with meter Calculation machine program, when the program is executed by processor realize as described in relation to the first aspect method the step of.
The embodiments of the invention provide a kind of construction method of repeater satellite task scheduling constraint plan model, this method exists When building model, --- repeater satellite --- user for the forward link of space-based backbone network relay satellite system, i.e. earth station Spacecraft, or earth station --- repeater satellite --- repeater satellite --- user spacecraft, more repeater satellites be present, and In the case of communication link being present between repeater satellite, SEE time window, task attribute, resource-constrained user have been considered The constraintss such as the propagation delay of task scheduling is limited and communication delay is limited, so that being obtained based on the model for task Scheduling scheme can complete the planning of repeater satellite task in the case where meeting above-mentioned constraints, ensure as much as possible preferential The higher task of level can be by successful dispatch, and then improves the efficiency of task scheduling.
Brief description of the drawings
By reading the detailed description of hereafter preferred embodiment, it is various other the advantages of and benefit it is common for this area Technical staff will be clear understanding.Accompanying drawing is only used for showing the purpose of preferred embodiment, and is not considered as to the present invention Limitation.And in whole accompanying drawing, identical part is denoted by the same reference numerals.In the accompanying drawings:
Fig. 1 is a kind of construction method flow of repeater satellite task scheduling constraint plan model provided in an embodiment of the present invention Figure;
Fig. 2 is a kind of construction device example structure of repeater satellite task scheduling constraint plan model provided by the invention Schematic diagram;
Fig. 3 is a kind of computer equipment example structure block diagram provided by the invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
In a first aspect, the embodiments of the invention provide a kind of structure side of repeater satellite task scheduling constraint plan model Method, as shown in figure 1, including:
S101, obtain earliest start time that priority, each task of default each scheduler task be successfully executed, be all It is the pot life window of each task service on the maximum delay time of task and each repeater satellite;
S102, the earliest start time being successfully executed according to priority, each task of each scheduler task, Suo Youren The maximum propagation time delay and pot life window of business, build the fitness function and constraints of the model;
Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, meets and hold The period of row preset task;The fitness function of the model, for in the specified priority, the early start The target letter of optimal task schedule scheme is obtained under time and the maximum propagation time delay, under the constraint of the constraints Number;The optimal task schedule scheme is that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Scheme.
The embodiments of the invention provide a kind of construction method of repeater satellite task scheduling constraint plan model, this method exists When building model, --- repeater satellite --- user for the forward link of space-based backbone network relay satellite system, i.e. earth station Spacecraft, or earth station --- repeater satellite --- repeater satellite --- user spacecraft, more repeater satellites be present, and In the case of communication link being present between repeater satellite, SEE time window, task attribute, resource-constrained user have been considered The constraintss such as the propagation delay of task scheduling is limited and communication delay is limited, so that being obtained based on the model for task Scheduling scheme can complete the planning of repeater satellite task in the case where meeting above-mentioned constraints, ensure as much as possible preferential The higher task of level can be by successful dispatch, and then improves the efficiency of task scheduling.
In the specific implementation, it is to be understood that fitness function and the constraint of model are built in above-mentioned steps S102 Condition can be implemented in several ways, and the optional embodiment of one of which is introduced below.
(1) structure of the fitness function of model
The fitness function expression formula of model is:
Wherein, ρi=Pmax-pi, piThe task i specified for user priority, PmaxRepresent task priority weighted value Maximum adds one, takes Pmax=11, pi∈ { 1,2,3 ..., 10 }, then ρiThe weighted value of expression task i priority, user specify Task i priority it is higher, i.e. piρ that is smaller, then obtainingiBigger, i.e. the weighted value of task i priority is bigger.As user refers to The priority for determining task i is pi=1, then the weighted value of task i priority is ρi=11-1=10.Weighted value ρiIt is bigger, represent Task i priority is higher.
βi=Dmax-|Ti-ei|, DmaxRepresent the maximum delay of all tasks specified in advance, TiExpression task i is scheduled to The Starting Executing Time of work(, eiThe earliest start time that the task i that user specifies is successfully executed is represented, | Ti-ei| represent task I delay, the Starting Executing Time of task perform the time closer to the task early start that user specifies, i.e., | Ti-ei| it is smaller, Then postpone smaller, weighted value βiIt is bigger.
χim={ 0,1 }, i ∈ J, m ∈ M, if χim=1, show that task i is dispatched successfully by repeater satellite m;Otherwise, show to adjust Degree failure.
The target of the fitness function expression formula is to make higher priority, smaller, the more tasks of delay by success Perform.(2) structure of model constraint function
The constraint equation of model is:
(6)
I, j ∈ J and i ≠ j, wherein i, j ∈ J and i ≠ j, δij=1
Wherein, if representing a task scheduling success, the task can only be scheduled to formula (2) on a repeater satellite Work(, otherwise it is assumed that the task scheduling fails.
In formula (3), χijm={ 0,1 }, i, j ∈ J, m ∈ M, if χijm=1, show that repeater satellite m is stood after having performed task i Perform task j.If showing, any two task is being dispatched to user spacecraft to constraint equation (3) by a repeater satellite On, then execution sequence must one in front and one in back, that is, show that a repeater satellite is at most only a task clothes in the same time Business.
Formula (4) be in order to ensure that being performed on same repeater satellite for task can line up an ordered sequence, while It ensure that a repeater satellite can only at most perform a task in synchronization.
In formula (5), Wim=Bi∩Aim, BiRepresent earliest start time that the task i that specifies of user is successfully executed with most The time window that the late end time is formed, AimRepresent to be the set of the repeater satellite m of task i services SEE time window, Wim Represent on repeater satellite m to be the set of all pot life windows of task i services.So-called pot life window, is exactly meeting On the basis of the observability of repeater satellite and user spacecraft, meet the task execution time section that user specifies.IfThen show task i in repeater satellite m pot life window w.Constraint Conditional (5) task of indicating must is fulfilled for the constraint of SEE time window, is only possible to be scheduled successfully, and dispatches successful task It is only capable of carrying out in an available time windows during execution.
In formula (6), diExpression task i duration, di=d0+di', d0For repeater satellite service beginning and termination phase It is the time of consumption, relevant with the soft hardware equipment of space-based backbone network relay satellite system, such as needed in service preparatory stage, earth station Connection is established, while is configured between star, star ground communication link device and data server system, in the end of service stage, ground Needs of standing disconnect, and discharge and remove link, while discharge satellite resource, di' it is the actual data communication times of task i, Submitted by user according to being actually needed.εijmRepresent that repeater satellite m has been performed when being immediately performed task j exchange after task i Between.I, j ∈ J and i ≠ j, it is earliest to represent that task j is successfully executed Period between the end time the latest that time started and task i are successfully executed.TiExpression task i scheduling successfully starts Perform the time.If showing, two task i, j (j is performed after i) perform constraint equation (6) on same repeater satellite When, task j Starting Executing Time TjT must have been performed in task ii+diijmAfterwards, a repeater satellite is further emphasized A task can only be performed in synchronization.
In formula (7), οij={ 0,1 }, i, j ∈ J, if οij=1, then show that task i is performed before task j.Constraints Formula (7) represents two task i on a repeater satellite, and when resource contention occurs for j, task i, j the execution time are that to have It is overlapping, i.e., must be one previous in rear execution, also show a repeater satellite and be only one in synchronization Task service.
In formula (8),For task i on repeater satellite m pot life window w at the beginning of between, in formula (9),To appoint It is engaged in end times of the i on repeater satellite m pot life window w, wherein, i ∈ J, m ∈ M, w ∈ Wim.Constraint equation (8) and Formula (9) expression task wants to be scheduled successfully, must just be performed in a pot life window, wherein constraint equation (8) table Show task Starting Executing Time have to be larger than or equal to the pot life window at the beginning of between;Constraint equation (9) represents to appoint The end time of business is necessarily less than or the end time equal to the pot life window.
In formula (10), tiRepresent that the task i that user specifies is scheduled for the maximum propagation time delay that user spacecraft is undergone. V represents the speed of Electromagnetic Wave Propagation, gives tacit consent to v=3.0 × 108km/s。siExpression task i is scheduled for user spacecraft and undergone Total propagation distance,Wherein, snRepresent the distance between earth station and repeater satellite n, smnIn expression After the distance between satellite m and n,Represent distances of the repeater satellite m on pot life window w with user spacecraft.φi= { 0,1 }, i ∈ J, if φi=1, then show that task i meets propagation delay requirement.Constraint equation (10) represents that task i is scheduled The maximum propagation time delay undergone to user spacecraft is not more than the maximum propagation time delay that user specifies, that is, meets that propagation delay will Ask.
In formula (11),The task of further demonstrating that wants holding by successful dispatch The row time must be in the pot life window between a certain repeater satellite and user spacecraft, also only in pot life window Task can be performed.
The step of by above-mentioned structure fitness function and constraint function, you can obtain in the case where various current conditions constrain More relay satellite system scheduling models.It must be gone out on missions point by appropriate optimized algorithm (such as the optimized algorithm such as genetic algorithm) With scheme, the optimal solution of the model can be obtained.Wherein the optimal solution is make it that model fitness function (1) value is maximum, together When meet (2) arrive (11) constraints optimal solution.The optimal solution may act as optimal task schedule scheme, applied to reality In the case of task scheduling in.
Second aspect, the embodiments of the invention provide a kind of structure dress of repeater satellite task scheduling constraint plan model Put, as shown in Fig. 2 including:
Acquiring unit 201, when obtaining the early start that priority, each task of default each scheduler task are successfully executed Between, on the maximum delay time of all tasks and each repeater satellite be each task service pot life window;
Construction unit 202, the early start being successfully executed for the priority according to each scheduler task, each task Time, the maximum propagation time delay of all tasks and pot life window, build the fitness function and constraints of the model;
Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, meets and hold The period of row preset task;The fitness function of the model, for in the specified priority, the early start The target letter of optimal task schedule scheme is obtained under time and the maximum propagation time delay, under the constraint of the constraints Number;The optimal task schedule scheme is that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Scheme.
Wherein, here fitness function and the structure of constraints is referred in first aspect for fitness letter The detailed process of number and constraints construction step, will not be repeated here.
In the specific implementation, described device also includes:
Optimize unit 203, for based on the obtained model, the model to be asked for most using default optimized algorithm Excellent solution, wherein the optimal solution is make it that the fitness function value is maximum and meets the solution of the constraints, and by institute Optimal solution is stated to export as the optimal task schedule scheme.
By the construction device that the repeater satellite task scheduling that the present embodiment is introduced constrains plan model is to perform The device of the construction method of repeater satellite task scheduling constraint plan model in the embodiment of the present invention, so it is real based on the present invention The method for applying the structure of the repeater satellite task scheduling constraint plan model described in example, those skilled in the art can Understand the embodiment of the construction device of the repeater satellite task scheduling constraint plan model of the present embodiment and its is various Version, so how the construction device for constraining plan model for the repeater satellite task scheduling herein realizes that the present invention is real The construction method for applying the constraint plan model of the repeater satellite task scheduling in example is no longer discussed in detail.As long as the affiliated technology in this area Device used by the construction method of repeater satellite task scheduling constraint plan model, all belongs in personnel's implementation embodiment of the present invention In the scope that the application to be protected.
Fig. 3 shows the structured flowchart of computer equipment provided in an embodiment of the present invention.
Reference picture 3, the computer equipment, including processor (processor) 301, memory (memory) 302, bus 303 and EBI 304;
Wherein, the processor 301 and memory 302 complete mutual communication by the bus 303, and bus connects Mouth 304 is used for and external device carries out information exchange;
The processor 301 is used to call the programmed instruction in the memory 302, to perform above-mentioned each method embodiment Method described in middle first aspect.
A kind of computer program product is also disclosed in the embodiment of the present invention, and the computer program product is non-temporary including being stored in Computer program on state computer-readable recording medium, the computer program include programmed instruction, when described program instructs When being computer-executed, computer is able to carry out the method described in above-mentioned each method embodiment first aspect.
The embodiment of the present invention also provides a kind of non-transient computer readable storage medium storing program for executing, and the non-transient computer is readable to deposit Storage media stores computer instruction, and the computer instruction makes the computer perform above-mentioned each method embodiment first aspect institute The method stated.
In the specification that this place provides, numerous specific details are set forth.It is to be appreciated, however, that the implementation of the present invention Example can be put into practice in the case of these no details.In some instances, known method, structure is not been shown in detail And technology, so as not to obscure the understanding of this description.
Similarly, it will be appreciated that in order to simplify the disclosure and help to understand one or more of each inventive aspect, Above in the description to the exemplary embodiment of the present invention, each feature of the invention is grouped together into single implementation sometimes In example, figure or descriptions thereof.However, the method for the disclosure should be construed to reflect following intention:I.e. required guarantor The application claims of shield features more more than the feature being expressly recited in each claim.It is more precisely, such as following Claims reflect as, inventive aspect is all features less than single embodiment disclosed above.Therefore, Thus the claims for following embodiment are expressly incorporated in the embodiment, wherein each claim is in itself Separate embodiments all as the present invention.
Those skilled in the art, which are appreciated that, to be carried out adaptively to the module in the equipment in embodiment Change and they are arranged in one or more equipment different from the embodiment.Can be the module or list in embodiment Member or component be combined into a module or unit or component, and can be divided into addition multiple submodule or subelement or Sub-component.In addition at least some in such feature and/or process or unit exclude each other, it can use any Combination is disclosed to all features disclosed in this specification (including adjoint claim, summary and accompanying drawing) and so to appoint Where all processes or unit of method or equipment are combined.Unless expressly stated otherwise, this specification (including adjoint power Profit requires, summary and accompanying drawing) disclosed in each feature can be by providing the alternative features of identical, equivalent or similar purpose come generation Replace.
In addition, it will be appreciated by those of skill in the art that although some embodiments in this include institute in other embodiments Including some features rather than further feature, but the combination of the feature of different embodiments means to be in the scope of the present invention Within and form different embodiments.For example, in the following claims, embodiment claimed it is any it One mode can use in any combination.
Some unit embodiments of the present invention can be realized with hardware, or to be run on one or more processor Software module realize, or realized with combinations thereof.It will be understood by those of skill in the art that it can use in practice Microprocessor or digital signal processor (DSP) are realized in gateway according to embodiments of the present invention, proxy server, system Some or all parts some or all functions.The present invention is also implemented as being used to perform side as described herein The some or all equipment or program of device (for example, computer program and computer program product) of method.It is such Realizing the program of the present invention can store on a computer-readable medium, or can have the shape of one or more signal Formula.Such signal can be downloaded from internet website and obtained, and either be provided or with any other shape on carrier signal Formula provides.
It should be noted that the present invention will be described rather than limits the invention for above-described embodiment, and ability Field technique personnel can design alternative embodiment without departing from the scope of the appended claims.In the claims, Any reference symbol between bracket should not be configured to limitations on claims.Word "comprising" does not exclude the presence of not Element or step listed in the claims.Word "a" or "an" before element does not exclude the presence of multiple such Element.The present invention can be by means of including the hardware of some different elements and being come by means of properly programmed computer real It is existing.In if the unit claim of equipment for drying is listed, several in these devices can be by same hardware branch To embody.The use of word first, second, and third does not indicate that any order.These words can be explained and run after fame Claim.

Claims (10)

  1. A kind of 1. construction method of repeater satellite task scheduling constraint plan model, it is characterised in that including:
    Obtain the priority of default each scheduler task, the earliest start time that each task is successfully executed, all tasks most It is the pot life window of each task service on big time delay and each repeater satellite;
    Earliest start time, the maximum of all tasks being successfully executed according to the priority of each scheduler task, each task Propagation delay and pot life window, build the fitness function and constraints of the model;
    Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, it is pre- meets execution If the period of task;The fitness function of the model, for in the specified priority, the earliest start time And the object function of optimal task schedule scheme is obtained under the maximum propagation time delay, under the constraint of the constraints; The optimal task schedule scheme is the side that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Case.
  2. 2. according to the method for claim 1, it is characterised in that the fitness function is as shown in formula one:
    Max f=∑ ∑s (ρiβiimFormula one
    Wherein, ρiThe weighted value of expression task i priority;ρi=Pmax-pi, piThe task i specified for user priority, Pmax Maximum for the priority of all tasks adds 1;
    βiThe weighted value of expression task i delay time;βi=Dmax-|Ti-ei|, DmaxRepresent that the maximum of default all tasks is prolonged Late, TiExpression task i dispatches successful Starting Executing Time, eiWhen representing the early start that default task i is successfully executed Between, | Ti-ei| represent task i time delay;
    χimThe situation that expression task i is performed;χim={ 0,1 }, i ∈ J, m ∈ M;If χim=1, show task i by repeater satellite m Dispatch successfully;Otherwise, task i scheduling failures are shown.
  3. 3. according to the method for claim 2, it is characterised in that the constraints includes:
    And i ≠ j formula three
    And i ≠ j, j ≠ z formula four
    Formula six
    And i ≠ j, wherein i, j ∈ J and i ≠ j, δij=1
    Wherein, if formula two is used to constrain a task scheduling success, the task can only be scheduled on a repeater satellite Work(, otherwise it is assumed that the task scheduling fails;
    In formula three, χijm={ 0,1 }, i, j ∈ J, m ∈ M, if χijm=1, show that repeater satellite m is held immediately after having performed task i Row task j;If formula three is used for constraint, any two task is being dispatched to user spacecraft by a repeater satellite, relays Satellite is only a task service in the same time;
    Formula four can perform in order for constraining on same repeater satellite performing for task, while also constrain a relaying Satellite can only perform a task in synchronization;
    In formula five, Wim=Bi∩Aim, BiThe earliest start time that the task i that expression user specifies is successfully executed with tying the latest The time window that the beam time is formed, AimRepresent to be the set of the repeater satellite m of task i services SEE time window, WimRepresent It can be the set of all pot life windows of task i services on repeater satellite m;Expression task i whether in repeater satellite m can With in time window w,i∈J,m∈M,w∈WimIfThen show task i repeater satellite m it is available when Between in window w;Formula five is used to constrain task only when meeting the constraint of SEE time window, is only possible to be scheduled successfully, and dispatch It is only capable of carrying out in an available time windows during successful tasks carrying;
    In formula six, diExpression task i duration, di=d0+d′i, d0Disappear for repeater satellite service beginning and termination phase The time of consumption, d 'iFor the actual data communication times of task i;εijmRepresent that repeater satellite m has been performed to be immediately performed after task i times Business j swap time;I, j ∈ J and i ≠ j, represent task j by success Period between the end time the latest that the earliest start time and task i of execution are successfully executed;TiExpression task i is dispatched Successful Starting Executing Time;If formula six is used to constrain task i, task j when being performed on same repeater satellite, and task J is performed after task i, then task j Starting Executing Time TjT must have been performed in task ii+diijmAfterwards;
    In formula seven, οijExpression task i and task j execution sequence, οij={ 0,1 }, i, j ∈ J, if οij=1, then show to appoint Business i is performed before task j;Two task i that formula seven is used to constrain on a repeater satellite, when resource contention occurs for j, appoint Be engaged in i, and the j execution time can not be overlapping;
    In formula eight and formula nine,For task i on repeater satellite m pot life window w at the beginning of between,For task End times of the i on repeater satellite m pot life window w, wherein, i ∈ J, m ∈ M, w ∈ Wim.Formula eight and formula nine are used Want to be scheduled successfully in constraint task, must just be performed in a pot life window, wherein formula eight represents opening for task Begin perform the time have to be larger than or equal to the pot life window at the beginning of between;Formula nine represents that the end time of task must be small In or equal to the pot life window end time;
    In formula ten, tiRepresent that the task i that user specifies is scheduled for the maximum propagation time delay that user spacecraft is undergone;V is represented The speed of Electromagnetic Wave Propagation, v=3.0 × 108km/s;siExpression task i is scheduled for total propagation that user spacecraft is undergone Distance,Wherein, snRepresent the distance between earth station and repeater satellite n, smnRepresent repeater satellite m and n The distance between,Represent distances of the repeater satellite m on pot life window w with user spacecraft;φiWhether expression task i Meet the situation of propagation delay, φi={ 0,1 }, i ∈ J, if φi=1, then show that task i meets propagation delay requirement;Formula ten When being scheduled for maximum propagation time delay that user spacecraft undergone no more than the maximum propagation that user specifies for constraining task i Prolong;
    In formula 11,Showing that task wants must by the executable time of successful dispatch Must be in the pot life window between a certain repeater satellite and user spacecraft.
  4. 4. according to the method for claim 1, it is characterised in that methods described also includes:
    Based on the obtained model, the optimal solution of the model is asked for using default optimized algorithm, wherein the optimal solution Make it that the fitness function value is maximum and meets the solution of the constraints, and using the optimal solution as described optimal Task scheduling approach exports.
  5. A kind of 5. construction device of repeater satellite task scheduling constraint plan model, it is characterised in that including:
    Acquiring unit, obtain earliest start time that priority, each task of default each scheduler task be successfully executed, all It is the pot life window of each task service on the maximum delay time of task and each repeater satellite;
    Construction unit, the earliest start time being successfully executed for the priority according to each scheduler task, each task, institute There are the maximum propagation time delay and pot life window of task, build the fitness function and constraints of the model;
    Wherein, the pot life window, it is on the basis of the observability of repeater satellite and user spacecraft is met, it is pre- meets execution If the period of task;The fitness function of the model, for in the specified priority, the earliest start time And the object function of optimal task schedule scheme is obtained under the maximum propagation time delay, under the constraint of the constraints; The optimal task schedule scheme is the side that the most tasks for enabling higher priority, propagation delay smaller are successfully executed Case.
  6. 6. device according to claim 5, it is characterised in that the fitness function is as shown in formula one:
    Max f=∑ ∑s (ρiβiimFormula one
    Wherein, ρiThe weighted value of expression task i priority;ρi=Pmax-pi, piThe task i specified for user priority, Pmax Maximum for the priority of all tasks adds 1;
    βiThe weighted value of expression task i delay time;βi=Dmax-|Ti-ei|, DmaxRepresent that the maximum of default all tasks is prolonged Late, TiExpression task i dispatches successful Starting Executing Time, eiWhen representing the early start that default task i is successfully executed Between, | Ti-ei| represent task i time delay;
    χimThe situation that expression task i is performed;χim={ 0,1 }, i ∈ J, m ∈ M;If χim=1, show task i by repeater satellite m Dispatch successfully;Otherwise, task i scheduling failures are shown.
  7. 7. device according to claim 6, it is characterised in that the constraints includes:
    And i ≠ j formula three
    And i ≠ j, j ≠ z formula four
    Formula six
    And i ≠ j, wherein i, j ∈ J and i ≠ j, δij=1
    Wherein, if formula two is used to constrain a task scheduling success, the task can only be scheduled on a repeater satellite Work(, otherwise it is assumed that the task scheduling fails;
    In formula three, χijm={ 0,1 }, i, j ∈ J, m ∈ M, if χijm=1, show that repeater satellite m is held immediately after having performed task i Row task j;If formula three is used for constraint, any two task is being dispatched to user spacecraft by a repeater satellite, relays Satellite is only a task service in the same time;
    Formula four can perform in order for constraining on same repeater satellite performing for task, while also constrain a relaying Satellite can only perform a task in synchronization;
    In formula five, Wim=Bi∩Aim, BiThe earliest start time that the task i that expression user specifies is successfully executed with tying the latest The time window that the beam time is formed, AimRepresent to be the set of the repeater satellite m of task i services SEE time window, WimRepresent It can be the set of all pot life windows of task i services on repeater satellite m;Expression task i whether in repeater satellite m can With in time window w,i∈J,m∈M,w∈WimIfThen show task i repeater satellite m it is available when Between in window w;Formula five is used to constrain task only when meeting the constraint of SEE time window, is only possible to be scheduled successfully, and dispatch It is only capable of carrying out in an available time windows during successful tasks carrying;
    In formula six, diExpression task i duration, di=d0+d′i, d0Disappear for repeater satellite service beginning and termination phase The time of consumption, d 'iFor the actual data communication times of task i;εijmRepresent that repeater satellite m has been performed to be immediately performed after task i times Business j swap time;I, j ∈ J and i ≠ j, represent task j by into Period between the end time the latest that the earliest start time and task i that work(performs are successfully executed;TiExpression task i is adjusted Spend successful Starting Executing Time;If formula six is used to constrain task i, task j when being performed on same repeater satellite, and appoints Business j is performed after task i, then task j Starting Executing Time TjT must have been performed in task ii+diijmAfterwards;
    In formula seven, οijExpression task i and task j execution sequence, οij={ 0,1 }, i, j ∈ J, if οij=1, then show to appoint Business i is performed before task j;Two task i that formula seven is used to constrain on a repeater satellite, when resource contention occurs for j, appoint Be engaged in i, and the j execution time can not be overlapping;
    In formula eight and formula nine,For task i on repeater satellite m pot life window w at the beginning of between,For task End times of the i on repeater satellite m pot life window w, wherein, i ∈ J, m ∈ M, w ∈ Wim.Formula eight and formula nine are used Want to be scheduled successfully in constraint task, must just be performed in a pot life window, wherein formula eight represents opening for task Begin perform the time have to be larger than or equal to the pot life window at the beginning of between;Formula nine represents that the end time of task must be small In or equal to the pot life window end time;
    In formula ten, tiRepresent that the task i that user specifies is scheduled for the maximum propagation time delay that user spacecraft is undergone;V is represented The speed of Electromagnetic Wave Propagation, v=3.0 × 108km/s;siExpression task i is scheduled for total propagation that user spacecraft is undergone Distance,Wherein, snRepresent the distance between earth station and repeater satellite n, smnRepresent repeater satellite m and n The distance between,Represent distances of the repeater satellite m on pot life window w with user spacecraft;φiWhether expression task i Meet the situation of propagation delay, φi={ 0,1 }, i ∈ J, if φi=1, then show that task i meets propagation delay requirement;Formula ten When being scheduled for maximum propagation time delay that user spacecraft undergone no more than the maximum propagation that user specifies for constraining task i Prolong;
    In formula 11,Showing that task wants must by the executable time of successful dispatch Must be in the pot life window between a certain repeater satellite and user spacecraft.
  8. 8. device according to claim 5, it is characterised in that described device also includes:
    Optimize unit, for based on the obtained model, asking for the optimal solution of the model using default optimized algorithm, its Described in optimal solution make it that the fitness function value is maximum and meets the solution of the constraints, and by the optimal solution Exported as the optimal task schedule scheme.
  9. 9. a kind of computer equipment, including memory, processor and storage can be run on a memory and on a processor Computer program, it is characterised in that realized during the computing device described program such as any methods describeds of claim 1-4 Step.
  10. 10. a kind of computer-readable recording medium, is stored thereon with computer program, it is characterised in that the program is by processor The step of methods described as any such as claim 1-4 is realized during execution.
CN201710967156.0A 2017-10-17 2017-10-17 Method and device for constructing relay satellite task scheduling constraint planning model Expired - Fee Related CN107678848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710967156.0A CN107678848B (en) 2017-10-17 2017-10-17 Method and device for constructing relay satellite task scheduling constraint planning model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710967156.0A CN107678848B (en) 2017-10-17 2017-10-17 Method and device for constructing relay satellite task scheduling constraint planning model

Publications (2)

Publication Number Publication Date
CN107678848A true CN107678848A (en) 2018-02-09
CN107678848B CN107678848B (en) 2020-07-07

Family

ID=61140649

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710967156.0A Expired - Fee Related CN107678848B (en) 2017-10-17 2017-10-17 Method and device for constructing relay satellite task scheduling constraint planning model

Country Status (1)

Country Link
CN (1) CN107678848B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108510125A (en) * 2018-04-11 2018-09-07 北京航空航天大学 Satellite task reliability-based optimization method, apparatus and electronic equipment
CN108832993A (en) * 2018-06-22 2018-11-16 西安电子科技大学 Online relay satellite system communication resource allocation method towards hybrid task
CN109946713A (en) * 2019-04-02 2019-06-28 上海微小卫星工程中心 A kind of restructural satellite system of distribution and remote sensing technique
CN111124633A (en) * 2019-12-06 2020-05-08 上海交通大学 Earth-moon relay satellite task scheduling method considering storage limit of detector
CN111211943A (en) * 2020-01-03 2020-05-29 中国人民解放军63920部队 Method and device for determining instruction sending time delay of spacecraft and storage medium
CN111600643A (en) * 2020-04-09 2020-08-28 中国电子科技集团公司电子科学研究院 Satellite communication resource scheduling method and device storage medium
CN111812966A (en) * 2020-07-02 2020-10-23 北京航天飞行控制中心 Multi-spacecraft-based time difference between heaven and earth determining method, determining device and processor
CN112529317A (en) * 2020-12-17 2021-03-19 中国科学院空天信息创新研究院 Satellite imaging task planning method and device, electronic equipment and storage medium
CN113095578A (en) * 2021-04-16 2021-07-09 广东电网有限责任公司电力调度控制中心 Design method, device, terminal and medium for optimal communication path of transformer substation
CN113852406A (en) * 2021-08-24 2021-12-28 合肥工业大学 Multi-beam relay satellite task scheduling method and device
CN113852405A (en) * 2021-08-24 2021-12-28 合肥工业大学 Method and device for constructing multi-beam relay satellite task scheduling model
CN114612019A (en) * 2022-05-12 2022-06-10 北京开运联合信息技术集团股份有限公司 Multi-satellite task overall planning method and device
CN115441936A (en) * 2022-09-02 2022-12-06 合肥工业大学 Heuristic relay satellite task scheduling method based on variable neighborhood search
CN116760454A (en) * 2023-08-09 2023-09-15 中国科学院空天信息创新研究院 Relay satellite resource allocation method and device

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107070534A (en) * 2017-01-26 2017-08-18 清华大学 The dynamic preemptive type method for scheduling task and system of a kind of repeater satellite load balancing

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107070534A (en) * 2017-01-26 2017-08-18 清华大学 The dynamic preemptive type method for scheduling task and system of a kind of repeater satellite load balancing

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
开彩红等: "一种中继卫星任务调度约束规划模型的构建方法", 《电子与信息学报2015年》 *
林鹏等: "中继卫星系统的多星多天线动态调度方法", 《清华大学学报(自然科学版)2015年》 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108510125A (en) * 2018-04-11 2018-09-07 北京航空航天大学 Satellite task reliability-based optimization method, apparatus and electronic equipment
CN108832993A (en) * 2018-06-22 2018-11-16 西安电子科技大学 Online relay satellite system communication resource allocation method towards hybrid task
CN108832993B (en) * 2018-06-22 2020-09-18 西安电子科技大学 Hybrid task-oriented online relay satellite system communication resource allocation method
CN109946713A (en) * 2019-04-02 2019-06-28 上海微小卫星工程中心 A kind of restructural satellite system of distribution and remote sensing technique
CN111124633B (en) * 2019-12-06 2023-05-30 上海交通大学 Ground-month relay satellite task scheduling method considering detector storage limit
CN111124633A (en) * 2019-12-06 2020-05-08 上海交通大学 Earth-moon relay satellite task scheduling method considering storage limit of detector
CN111211943A (en) * 2020-01-03 2020-05-29 中国人民解放军63920部队 Method and device for determining instruction sending time delay of spacecraft and storage medium
CN111600643A (en) * 2020-04-09 2020-08-28 中国电子科技集团公司电子科学研究院 Satellite communication resource scheduling method and device storage medium
CN111812966A (en) * 2020-07-02 2020-10-23 北京航天飞行控制中心 Multi-spacecraft-based time difference between heaven and earth determining method, determining device and processor
CN112529317A (en) * 2020-12-17 2021-03-19 中国科学院空天信息创新研究院 Satellite imaging task planning method and device, electronic equipment and storage medium
CN113095578A (en) * 2021-04-16 2021-07-09 广东电网有限责任公司电力调度控制中心 Design method, device, terminal and medium for optimal communication path of transformer substation
CN113095578B (en) * 2021-04-16 2022-09-23 广东电网有限责任公司电力调度控制中心 Design method, device, terminal and medium for optimal communication path of transformer substation
CN113852405B (en) * 2021-08-24 2024-03-05 合肥工业大学 Construction method and device of multi-beam relay satellite task scheduling model
CN113852406A (en) * 2021-08-24 2021-12-28 合肥工业大学 Multi-beam relay satellite task scheduling method and device
CN113852405A (en) * 2021-08-24 2021-12-28 合肥工业大学 Method and device for constructing multi-beam relay satellite task scheduling model
CN113852406B (en) * 2021-08-24 2024-04-30 合肥工业大学 Multi-beam relay satellite task scheduling method and device
CN114612019A (en) * 2022-05-12 2022-06-10 北京开运联合信息技术集团股份有限公司 Multi-satellite task overall planning method and device
CN115441936A (en) * 2022-09-02 2022-12-06 合肥工业大学 Heuristic relay satellite task scheduling method based on variable neighborhood search
CN115441936B (en) * 2022-09-02 2023-09-26 合肥工业大学 Relay satellite task scheduling method based on variable neighborhood search heuristic
CN116760454B (en) * 2023-08-09 2023-10-13 中国科学院空天信息创新研究院 Relay satellite resource allocation method and device
CN116760454A (en) * 2023-08-09 2023-09-15 中国科学院空天信息创新研究院 Relay satellite resource allocation method and device

Also Published As

Publication number Publication date
CN107678848B (en) 2020-07-07

Similar Documents

Publication Publication Date Title
CN107678848A (en) Repeater satellite task scheduling constrains the construction method and device of plan model
CN107678850A (en) Repeater satellite method for scheduling task and device
US10432537B2 (en) Service function chaining based on resource availability in the time dimension
CN108062246B (en) Resource regulating method and device for deep learning frame
Ni et al. Resource allocation strategy in fog computing based on priced timed petri nets
US10402227B1 (en) Task-level optimization with compute environments
Aburukba et al. A heuristic scheduling approach for fog-cloud computing environment with stationary IoT devices
CN102760074B (en) Method and its system for high load capacity operation flow scalability
CN108961033A (en) Multiservice system exchange method and device, storage medium, electric terminal
CN109034396A (en) Method and apparatus for handling the deep learning operation in distributed type assemblies
Epstein et al. Virtual appliance content distribution for a global infrastructure cloud service
CN110008015B (en) Online task dispatching and scheduling method with bandwidth limitation in edge computing system
CN113760488B (en) Method, apparatus, device and computer readable medium for scheduling tasks
CN113033814A (en) Method, apparatus and storage medium for training machine learning model
CN109634764A (en) Work-flow control method, apparatus, equipment, storage medium and system
US12095659B2 (en) Service chain instance pool sizing
KR20200136468A (en) Job scheduling
Deniziak et al. Cost optimization of real-time cloud applications using developmental genetic programming
CN108134851B (en) The method for controlling quality of service and device of data transmission
CN109858782A (en) Dispatching method, device and the electronic equipment of service role
EP3783547B1 (en) System and methods for reply date response and due date management in manufacturing
Truong-Huu et al. Dynamic embedding of workflow requests for bandwidth efficiency in data centers
CN116611783A (en) Method and device for automatically realizing business process links and circulation thereof
US11803420B1 (en) Execution of replicated tasks using redundant resources
CN111178823B (en) Method and device for canceling residence related transaction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Hu Xinyue

Inventor after: Ma Nan

Inventor after: Bright red

Inventor before: Hu Xinyue

Inventor before: Ma Nan

Inventor before: Open rainbow

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200707

CF01 Termination of patent right due to non-payment of annual fee