CN107675175A - A kind of multi-functional laser melting coating processing factory building - Google Patents

A kind of multi-functional laser melting coating processing factory building Download PDF

Info

Publication number
CN107675175A
CN107675175A CN201711153970.5A CN201711153970A CN107675175A CN 107675175 A CN107675175 A CN 107675175A CN 201711153970 A CN201711153970 A CN 201711153970A CN 107675175 A CN107675175 A CN 107675175A
Authority
CN
China
Prior art keywords
factory building
laser melting
melting coating
garbage collection
coating processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711153970.5A
Other languages
Chinese (zh)
Inventor
毛桂林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Purple Light Great Achievement Laser Science And Technology Ltd
Original Assignee
Suzhou Purple Light Great Achievement Laser Science And Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Purple Light Great Achievement Laser Science And Technology Ltd filed Critical Suzhou Purple Light Great Achievement Laser Science And Technology Ltd
Priority to CN201711153970.5A priority Critical patent/CN107675175A/en
Publication of CN107675175A publication Critical patent/CN107675175A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C24/00Coating starting from inorganic powder
    • C23C24/08Coating starting from inorganic powder by application of heat or pressure and heat
    • C23C24/10Coating starting from inorganic powder by application of heat or pressure and heat with intermediate formation of a liquid phase in the layer

Abstract

The invention discloses a kind of multi-functional laser melting coating processing factory building, including factory building, solar power supply apparatus, driving, laser melting coating process equipment, side door, waste material collection device, radiation ventilator and opposite opened sliding door, described solar power supply apparatus are welded on the top of factory building;Inner upper of the described driving installed in factory building;Described laser melting coating process equipment is arranged on the bosom position of factory building.Bearer network plate weld of the present invention is advantageous to convenient dust in factory building or liquid be imported into garbage collection bucket on the top of base;Regulating valve is arranged on liquid discharge pipe, is advantageous to the convenient liquid by garbage collection bucket and is discharged;Handle is welded on the right side of garbage collection bucket, is advantageous in chute extract garbage collection bucket out, further facilitates and pours out dust trash on the inside of garbage collection bucket;The setting of solar panel and photovoltaic controller, be advantageous to conveniently convert light energy into electric energy, further improve energy-saving effect.

Description

A kind of multi-functional laser melting coating processing factory building
Technical field
The invention belongs to laser process equipment technical field, more particularly to a kind of multi-functional laser melting coating processing factory building.
Background technology
Laser melting coating refers to place selected coating material warp on by cladding matrix surface with different adding material modes Laser irradiation is allowed to and matrix surface a thin layer while melted, and formation dilution factor is extremely low after quickly solidifying, with matrix into metallurgy With reference to face coat, significantly improve wear-resisting, anti-corrosion, heat-resisting, anti-oxidant and electrical characteristic the process of substrate surface, from And reach the purpose that surface is modified or repairs, the requirement to material surface particular characteristic had both been met, had been saved again substantial amounts of expensive Heavy element.
But existing laser melting coating processing factory building also there is in-convenience in use, energy-saving effect difference and be inconvenient to discharge and gives up The problem of expecting waste water.
Therefore, invent a kind of multi-functional laser melting coating processing factory building and seem very necessary.
The content of the invention
In order to solve the above-mentioned technical problem, the present invention provides a kind of multi-functional laser melting coating processing factory building, existing to solve Some laser melting coatings processing factory building in-convenience in use, energy-saving effect is poor and the problem of inconvenient wastage waste water.A kind of more work( The laser melting coating processing factory building of energy, including factory building, solar power supply apparatus, driving, laser melting coating process equipment, side door, waste material Collection device, radiation ventilator and opposite opened sliding door, described solar power supply apparatus are welded on the top of factory building;It is described Driving installed in factory building inner upper;Described laser melting coating process equipment is arranged on the bosom position of factory building;Institute The side door stated is arranged on the right side of factory building;Described waste material collection device is welded on factory building installed in described radiation ventilator Left side;Described opposite opened sliding door is arranged on the front portion of factory building;Described waste material collection device includes base, chute, gives up Expect collection bucket, carry web plate, baffle plate, handle, liquid discharge pipe and regulating valve, described chute are laterally opened in the inside of base Centre position;Described garbage collection bucket is plugged in chute;Described baffle plate is welded on the right-hand member of garbage collection bucket;Described Liquid discharge pipe is opened in the lower right side of garbage collection bucket.
Preferably, described solar power supply apparatus includes solar panel, battery board bracket, protective frame, battery And photovoltaic controller, described battery board bracket are arranged at left and right sides of the bottom of solar panel;Described protective frame peace Mounted in the middle and lower part of solar panel;Described battery and photovoltaic controller is separately mounted to the inside of protective frame;It is described Solar panel and photovoltaic controller be electrically connected with;Described photovoltaic controller is electrically connected with battery.
Preferably, described radiation ventilator includes fixed frame, fixed plate, blower fan frame, ventilation blower, Air Filter, fixes Neck and fixing bolt, described fixed plate are welded on the both sides up and down of fixed frame;Described blower fan frame is plugged in fixed frame; Described ventilation blower is arranged on the inner right side of blower fan frame;Described Air Filter is arranged on the left side of blower fan frame.
Preferably, described battery board bracket uses two-stage stainless steel stent.
Preferably, described blower fan frame is fixed on the inner side of fixed plate by fixing bolt plugged and fixed neck.
Preferably, described carrying web plate uses stainless steel web plate, and described bearer network plate weld is on the top of base.
Preferably, described regulating valve is arranged on liquid discharge pipe.
Preferably, described handle is welded on the right side of garbage collection bucket.
Compared with prior art, beneficial effects of the present invention are:
1st, in the present invention, described battery board bracket uses two-stage stainless steel stent, is advantageous to convenient regulation solar-electricity The height of pond plate.
2nd, in the present invention, described blower fan frame is fixed on the inner side of fixed plate by fixing bolt plugged and fixed neck, has Blower fan frame is dismantled beneficial to convenient so that use is more convenient.
3rd, in the present invention, described bearer network plate weld on the top of base, be advantageous to it is convenient by the dust in factory building or Liquid is imported into garbage collection bucket.
4th, in the present invention, described regulating valve is arranged on liquid discharge pipe, and it is convenient by garbage collection bucket to be advantageous to Liquid is discharged.
5th, in the present invention, described handle is welded on the right side of garbage collection bucket, is advantageous to garbage collection bucket in chute Interior extraction, further facilitate and pour out dust trash on the inside of garbage collection bucket.
6th, in the present invention, the setting of described solar panel and photovoltaic controller, be advantageous to conveniently convert luminous energy For electric energy, energy-saving effect is further improved.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the structural representation of the solar power supply apparatus of the present invention.
Fig. 3 is the structural representation of the waste material collection device of the present invention.
Fig. 4 is the structural representation of the radiation ventilator of the present invention.
In figure:
1st, factory building;2nd, solar power supply apparatus;21st, solar panel;22nd, battery board bracket;23rd, protective frame;24th, store Battery;25th, photovoltaic controller;3rd, drive a vehicle;4th, laser melting coating process equipment;5th, side door;6th, waste material collection device;61st, base; 62nd, chute;63rd, garbage collection bucket;64th, web plate is carried;65th, baffle plate;66th, handle;67th, liquid discharge pipe;68th, regulating valve;7、 Radiation ventilator;71st, fixed frame;72nd, fixed plate;73rd, blower fan frame;74th, ventilation blower;75th, Air Filter;76th, fixed card slot; 77th, fixing bolt;8th, opposite opened sliding door.
Embodiment
The present invention is described further below in conjunction with accompanying drawing:
Embodiment:
As shown in accompanying drawing 1 to accompanying drawing 4
The present invention provides a kind of multi-functional laser melting coating processing factory building, including factory building 1, solar power supply apparatus 2, driving 3, laser melting coating process equipment 4, side door 5, waste material collection device 6, radiation ventilator 7 and opposite opened sliding door 8, it is described too Positive energy electric supply installation 2 is welded on the top of factory building 1;Described driving 3 is arranged on the inner upper of factory building 1;Described laser melts Cover the bosom position that process equipment 4 is arranged on factory building 1;Described side door 5 is arranged on the right side of factory building 1;Described waste material Collection device 6 is arranged on the left side that described radiation ventilator 7 is welded on factory building 1;Described opposite opened sliding door 8 is arranged on The front portion of factory building 1;Described waste material collection device 6 includes base 61, chute 62, garbage collection bucket 63, carries web plate 64, baffle plate 65, handle 66, liquid discharge pipe 67 and regulating valve 68, described chute 62 are laterally opened in the bosom position of base 61; Described garbage collection bucket 63 is plugged in chute 62;Described baffle plate 65 is welded on the right-hand member of garbage collection bucket 63;Described Liquid discharge pipe 67 is opened in the lower right side of garbage collection bucket 63.
In above-described embodiment, specifically, described solar power supply apparatus 2 includes solar panel 21, cell panel branch Frame 22, protective frame 23, battery 24 and photovoltaic controller 25, described battery board bracket 22 are arranged on solar panel 21 At left and right sides of bottom;Described protective frame 23 is arranged on the middle and lower part of solar panel 21;Described battery 24 and photovoltaic Controller 25 is separately mounted to the inside of protective frame 23;Described solar panel 21 is electrically connected with photovoltaic controller 25; Described photovoltaic controller 25 is electrically connected with battery 24.
In above-described embodiment, specifically, described radiation ventilator 7 includes fixed frame 71, fixed plate 72, blower fan frame 73, ventilation blower 74, Air Filter 75, fixed card slot 76 and fixing bolt 77, described fixed plate 72 are welded on the upper of fixed frame 71 Lower both sides;Described blower fan frame 73 is plugged in fixed frame 71;Described ventilation blower 74 is arranged on the inner right side of blower fan frame 73; Described Air Filter 75 is arranged on the left side of blower fan frame 73.
In above-described embodiment, specifically, described battery board bracket 22 uses two-stage stainless steel stent.
In above-described embodiment, specifically, described blower fan frame 73 is fixed on by the plugged and fixed neck 76 of fixing bolt 77 The inner side of fixed plate 72.
In above-described embodiment, specifically, described carrying web plate 64 uses stainless steel web plate, described carrying web plate 64 welds It is connected on the top of base 61.
In above-described embodiment, specifically, described regulating valve 68 is arranged on liquid discharge pipe 67.
In above-described embodiment, specifically, described handle 66 is welded on the right side of garbage collection bucket 63.
Operation principle
The present invention in the course of the work, in use, absorbing solar energy using solar panel 21, then utilizes photovoltaic control Device 25 processed converts light energy into electric energy, and stores to battery 24, to provide power supply to ventilation blower 74, utilizes ventilation blower 74 To being aerated in factory building 1, the dust in factory building 1, if liquid, can open regulation by dropping into garbage collection bucket 63 Valve 68 discharges liquid in liquid discharge pipe 67.
Using technical solutions according to the invention, or those skilled in the art is under the inspiration of technical solution of the present invention, Similar technical scheme is designed, and reaches above-mentioned technique effect, is to fall into protection scope of the present invention.

Claims (8)

  1. A kind of 1. multi-functional laser melting coating processing factory building, it is characterised in that the multi-functional laser melting coating processing factory building, including Factory building (1), solar power supply apparatus (2), drive a vehicle (3), laser melting coating process equipment (4), side door (5), waste material collection device (6), radiation ventilator (7) and opposite opened sliding door (8), described solar power supply apparatus (2) are welded on the upper of factory building (1) Portion;Described driving (3) is arranged on the inner upper of factory building (1);Described laser melting coating process equipment (4) is arranged on factory building (1) bosom position;Described side door (5) is arranged on the right side of factory building (1);Described waste material collection device (6) installation The left side of factory building (1) is welded in described radiation ventilator (7);Described opposite opened sliding door (8) is arranged on factory building (1) Front portion;Described waste material collection device (6) includes base (61), chute (62), garbage collection bucket (63), carries web plate (64), baffle plate (65), handle (66), liquid discharge pipe (67) and regulating valve (68), described chute (62) are laterally opened in bottom The bosom position of seat (61);Described garbage collection bucket (63) is plugged in chute (62);Described baffle plate (65) welding Right-hand member in garbage collection bucket (63);Described liquid discharge pipe (67) is opened in the lower right side of garbage collection bucket (63).
  2. 2. multi-functional laser melting coating processing factory building as claimed in claim 1, it is characterised in that described solar powered dress Putting (2) includes solar panel (21), battery board bracket (22), protective frame (23), battery (24) and photovoltaic controller (25), described battery board bracket (22) is arranged at left and right sides of the bottom of solar panel (21);Described protective frame (23) it is arranged on the middle and lower part of solar panel (21);Described battery (24) and photovoltaic controller (25) is separately mounted to The inside of protective frame (23);Described solar panel (21) is electrically connected with photovoltaic controller (25);Described photovoltaic control Device (25) processed is electrically connected with battery (24).
  3. 3. multi-functional laser melting coating processing factory building as claimed in claim 1, it is characterised in that described radiation ventilator (7) include fixed frame (71), fixed plate (72), blower fan frame (73), ventilation blower (74), Air Filter (75), fixed card slot (76) and Fixing bolt (77), described fixed plate (72) are welded on the both sides up and down of fixed frame (71);Described blower fan frame (73) grafting In fixed frame (71);Described ventilation blower (74) is arranged on the inner right side of blower fan frame (73);Described Air Filter (75) peace Mounted in the left side of blower fan frame (73).
  4. 4. multi-functional laser melting coating processing factory building as claimed in claim 2, it is characterised in that described battery board bracket (22) two-stage stainless steel stent is used.
  5. 5. multi-functional laser melting coating processing factory building as claimed in claim 3, it is characterised in that described blower fan frame (73) is logical Cross the inner side that fixing bolt (77) plugged and fixed neck (76) is fixed on fixed plate (72).
  6. 6. multi-functional laser melting coating processing factory building as claimed in claim 1, it is characterised in that described carrying web plate (64) Using stainless steel web plate, described carrying web plate (64) is welded on the top of base (61).
  7. 7. multi-functional laser melting coating processing factory building as claimed in claim 1, it is characterised in that described regulating valve (68) peace On liquid discharge pipe (67).
  8. 8. multi-functional laser melting coating processing factory building as claimed in claim 1, it is characterised in that described handle (66) welding On the right side of garbage collection bucket (63).
CN201711153970.5A 2017-11-20 2017-11-20 A kind of multi-functional laser melting coating processing factory building Pending CN107675175A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711153970.5A CN107675175A (en) 2017-11-20 2017-11-20 A kind of multi-functional laser melting coating processing factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711153970.5A CN107675175A (en) 2017-11-20 2017-11-20 A kind of multi-functional laser melting coating processing factory building

Publications (1)

Publication Number Publication Date
CN107675175A true CN107675175A (en) 2018-02-09

Family

ID=61149732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711153970.5A Pending CN107675175A (en) 2017-11-20 2017-11-20 A kind of multi-functional laser melting coating processing factory building

Country Status (1)

Country Link
CN (1) CN107675175A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4209222A (en) * 1977-05-03 1980-06-24 Bernardo Raimann Installation for utilizing solar energy with wavelength selective reflector
CN201883147U (en) * 2010-12-08 2011-06-29 杭州中科新松光电有限公司 Crystallizer laser reproducing complete equipment
CN102373814A (en) * 2010-08-15 2012-03-14 孙善骏 Ventilating generation system plant of steel-structure building
CN103840122A (en) * 2012-11-26 2014-06-04 黄信 Laser cutting automatic production line for polar plate
CN204040548U (en) * 2014-07-22 2014-12-24 上海金萃激光技术有限公司 A kind of laser melting coating processing factory building
CN104989130A (en) * 2015-07-10 2015-10-21 成都亨通兆业精密机械有限公司 Energy-saving and environment-friendly production workshop factory building device
CN105545026A (en) * 2015-12-16 2016-05-04 青岛智享专利技术开发有限公司 Automatic heating plant

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4209222A (en) * 1977-05-03 1980-06-24 Bernardo Raimann Installation for utilizing solar energy with wavelength selective reflector
CN102373814A (en) * 2010-08-15 2012-03-14 孙善骏 Ventilating generation system plant of steel-structure building
CN201883147U (en) * 2010-12-08 2011-06-29 杭州中科新松光电有限公司 Crystallizer laser reproducing complete equipment
CN103840122A (en) * 2012-11-26 2014-06-04 黄信 Laser cutting automatic production line for polar plate
CN204040548U (en) * 2014-07-22 2014-12-24 上海金萃激光技术有限公司 A kind of laser melting coating processing factory building
CN104989130A (en) * 2015-07-10 2015-10-21 成都亨通兆业精密机械有限公司 Energy-saving and environment-friendly production workshop factory building device
CN105545026A (en) * 2015-12-16 2016-05-04 青岛智享专利技术开发有限公司 Automatic heating plant

Similar Documents

Publication Publication Date Title
CN205062101U (en) Carbon -free system iron device
CN106623398A (en) Ferric salt strengthened electrokinetic remediation device for heavy metal pollution in e-waste dismantling place
CN107287591A (en) A kind of laser melting coating metal dust storage device sensed with capacity
CN108212332A (en) A kind of Solid construction refuse disposal installation
CN202045125U (en) Continuous microwave soil restoring device
CN107675175A (en) A kind of multi-functional laser melting coating processing factory building
CN111809132B (en) High-efficiency heat absorption device for hot galvanizing pot
CN209501791U (en) A kind of waste treatment device of aluminium metallurgy anode material
CN206947462U (en) A kind of battery recycling device
CN211216834U (en) Slag treatment structure of garbage incinerator
CN207192004U (en) A kind of mosquito-proof dustbin of intelligence for being easy to safeguard
CN213363423U (en) Smelting furnace waste heat recovery utilizes device
CN205940016U (en) Special drying device of tin copper gold and silver waste material comprehensive recovery
CN110803424B (en) Garbage disposal station with pre-compression function
CN108723075A (en) A kind of heavy metal polluted soil solar energy electric prosthetic device
CN205309588U (en) Laser cutting machine ware people's garbage collection cooling device
CN206760687U (en) A kind of honey concentrator
CN206041617U (en) Plain type solar energy spray set
CN206974154U (en) A kind of superior copper alloy smelting furnace of feature of environmental protection
CN207743242U (en) A kind of equipment reprocessed for double-sided glass battery component
CN206001890U (en) A kind of indoor heavy oil stove mechanism heating for blank
CN206812293U (en) A kind of energy-efficient environment-friendly type engineering plastics crush drying and processing equipment
CN206334952U (en) A kind of house refuse recycle device
CN210481473U (en) Energy-saving smelting equipment for silicon-manganese alloy
CN216557358U (en) Heat supply unit with overlapping formula heating function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180209

RJ01 Rejection of invention patent application after publication