CN107654762A - A kind of anchor ear and its construction method - Google Patents

A kind of anchor ear and its construction method Download PDF

Info

Publication number
CN107654762A
CN107654762A CN201710762866.XA CN201710762866A CN107654762A CN 107654762 A CN107654762 A CN 107654762A CN 201710762866 A CN201710762866 A CN 201710762866A CN 107654762 A CN107654762 A CN 107654762A
Authority
CN
China
Prior art keywords
anchor ear
projection
weld groove
present
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710762866.XA
Other languages
Chinese (zh)
Inventor
回光林
陆海英
生振杰
孙爱华
罗旭东
隗合新
罗亮
张锐鹏
王伟朋
王欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Installation Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Installation Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201710762866.XA priority Critical patent/CN107654762A/en
Publication of CN107654762A publication Critical patent/CN107654762A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L13/00Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints
    • F16L13/02Welded joints
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups

Abstract

The invention discloses a kind of anchor ear, it is made up of anchor ear body and multiple projections to stretch out is equidistantly provided with the anchor ear body, a weld groove is provided between the projection, the invention cost is low, strong applicability and with fixing function hood type pipeline welding device.

Description

A kind of anchor ear and its construction method
Technical field
The present invention relates to a kind of pipeline welding device, is to be related to a kind of anchor ear in particular.
Background technology
At present, the frock weak point of most of pipeline welding devices is:1. bulky, cost is high;It is 2. empty to operation Between require high;3. without fixing function;4. low precision.
The content of the invention
The invention aims to overcome deficiency of the prior art, there is provided a kind of low manufacture cost, strong applicability And with fixing function hood type pipeline welding device.
The purpose of the present invention is achieved through the following technical solutions:
A kind of anchor ear, it is made up of anchor ear body and multiple projections to stretch out, institute is equidistantly provided with the anchor ear body State and be provided with a weld groove between projection.
The length that the projection stretches out is in 5cm~10cm;Its thickness is between 10cm~30cm.
The floor projection length of described weld groove is in 10cm~15cm;Its width is in 3cm~8cm
The anchor ear body includes the first anchor ear and the second anchor ear, the first anchor ear both ends and the two of second anchor ear Terminal bolt connects.
Technical problem be present to solve prior art, the present invention can also adopt the following technical scheme that:
Step 1, the first anchor ear body and the second anchor ear body are close to pipeline junction respectively, using on anchor ear body Projection is calibrated to the first anchor ear and the second anchor ear;
Step 2, the both ends of the first anchor ear and the second anchor ear after step 1 is calibrated carry out bolt connection;
Step 3, pipeline junction is welded using a weld groove.
Beneficial effect
Compared with prior art, beneficial effect caused by technical scheme is:
(1) in the present invention, split type anchor ear can be fixed by bolt, and flexible tune can be carried out according to the size of barrier Section, save space, strong applicability;
(2) hooping structure of the present invention is simple, easy to disassemble, assembling;
(3) in the present invention, the projection on anchor ear body can realize the fixation of object horizontal direction;Improve installation precision;
(4) in the present invention, anchor ear body is provided with multiple weld grooves and can fixed according to pipe welding port progress spot welding, adapts to energy Power is stronger.
(5) present invention is simple in construction, is easy to make, and plant equipment and human input are less during making, makes material therefor Secondary returning high income, therefore also there is the advantages of cost is low.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the three-dimensional isometric figure of single anchor ear device in the present invention.
Reference:1 anchor ear body, 2 projection, 3 bolts hole of 4 bolt of weld groove 5
The anchor ear of 11 first anchor ear 12 second
Embodiment
The present invention will be further described below in conjunction with the accompanying drawings:
As shown in figure 1, the present invention provides a kind of anchor ear, it is made up of anchor ear body 1, the anchor ear body includes the first anchor ear 11 and second anchor ear 12, the both ends of the first anchor ear 11 are connected with the bolts at two ends of second anchor ear 12.As shown in Fig. 2 institute The junction for stating the both ends of the first anchor ear 11 and the both ends of the second anchor ear 12 is equipped with bolt hole 5, and bolt 4 is real by bolt hole 4 Existing first anchor ear 11 is connected with the second anchor ear 12.
As shown in figure 1, multiple projections 2 to stretch out, the projection are equidistantly provided with the anchor ear body (11,12) 2 length to stretch out are in 5cm~10cm;Its thickness is between 10cm~30cm;A weld groove 3 is provided between the projection 2; The floor projection length of described weld groove 3 is in 10cm~15cm;Its width is in 3cm~8cm.
The present invention can also adopt the following technical scheme that:
Step 1, the first anchor ear body and the second anchor ear body are close to pipeline junction respectively, using on anchor ear body Projection is calibrated to the first anchor ear and the second anchor ear;
Step 2, the both ends of the first anchor ear and the second anchor ear after step 1 is calibrated carry out bolt connection;
Step 3, pipeline junction is welded using a weld groove.
Although the preferred embodiments of the present invention are described above in conjunction with accompanying drawing, the invention is not limited in upper The embodiment stated, above-mentioned embodiment is only schematical, be not it is restricted, this area it is common Technical staff in the case of present inventive concept and scope of the claimed protection is not departed from, may be used also under the enlightenment of the present invention By make it is many in the form of, these are belonged within protection scope of the present invention.

Claims (7)

1. a kind of anchor ear, it is made up of split type anchor ear body, it is characterised in that:Equidistantly be provided with the anchor ear body it is multiple to The projection of outer extension, a weld groove is provided between the projection.
A kind of 2. anchor ear according to claim 1, it is characterised in that:The length that the projection stretches out 5cm~ 10cm;Its thickness is between 10cm~30cm.
A kind of 3. anchor ear according to claim 1, it is characterised in that:The floor projection length of described weld groove 10cm~ 15cm;Its width is in 3cm~8cm.
A kind of 4. anchor ear according to claim 1, it is characterised in that:The anchor ear body includes the first anchor ear and second armful Hoop, the first anchor ear both ends are connected with the bolts at two ends of second anchor ear.
A kind of 5. anchor ear according to claim 2, it is characterised in that:The floor projection length 10cm of described weld groove~ 15cm;Its width is in 3cm~8cm.
A kind of 6. anchor ear according to claim 5, it is characterised in that:The anchor ear body includes the first anchor ear and second armful Hoop, the first anchor ear both ends are connected with the bolts at two ends of second anchor ear.
7. a kind of anchor ear construction method using as described in power 1, it is characterised in that comprise the following steps:
Step 1, the first anchor ear body and the second anchor ear body are close to pipeline junction respectively, utilize the projection on anchor ear body First anchor ear and the second anchor ear are calibrated;
Step 2, the both ends of the first anchor ear and the second anchor ear after step 1 is calibrated carry out bolt connection;
Step 3, pipeline junction is welded using a weld groove.
CN201710762866.XA 2017-08-30 2017-08-30 A kind of anchor ear and its construction method Pending CN107654762A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710762866.XA CN107654762A (en) 2017-08-30 2017-08-30 A kind of anchor ear and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710762866.XA CN107654762A (en) 2017-08-30 2017-08-30 A kind of anchor ear and its construction method

Publications (1)

Publication Number Publication Date
CN107654762A true CN107654762A (en) 2018-02-02

Family

ID=61128785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710762866.XA Pending CN107654762A (en) 2017-08-30 2017-08-30 A kind of anchor ear and its construction method

Country Status (1)

Country Link
CN (1) CN107654762A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113635231A (en) * 2021-06-25 2021-11-12 国营芜湖机械厂 Auxiliary clamp for vibration test of aviation plunger pump
CN114808927A (en) * 2022-05-27 2022-07-29 广东品建基础工程有限公司 Prestressed pipe pile and construction method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0740084A (en) * 1993-07-27 1995-02-10 Tokyo Gas Co Ltd Centering jig for welding of piping
JPH11267888A (en) * 1998-03-20 1999-10-05 Nippon Steel Corp Alignment ring jig for steel pipe welding
JP2002066788A (en) * 2000-08-22 2002-03-05 Hitachi Plant Eng & Constr Co Ltd Pipe groove matching jig
JP2006142340A (en) * 2004-11-22 2006-06-08 Jfe Koken Corp Tube centering tool
CN202155698U (en) * 2011-07-16 2012-03-07 中国十七冶集团有限公司 Labor-saving shaft coiling device
CN202418912U (en) * 2012-01-16 2012-09-05 宁波建工股份有限公司 Bearing support for heat insulation and preservation vertical tube
CN203265983U (en) * 2012-12-19 2013-11-06 中国核工业第五建设有限公司 Pairing tool for main cooling agent main pipelines of nuclear power station
CN104191126A (en) * 2014-08-20 2014-12-10 来宾华锡冶炼有限公司 Hoop used for clamping spray gun main body and spray gun head of Ausmelt furnace during welding
CN204183172U (en) * 2014-10-20 2015-03-04 五冶集团上海有限公司 A kind of hood type round steel pipe docking adjustment fixture
CN205600219U (en) * 2016-05-10 2016-09-28 中国能源建设集团安徽电力建设第一工程有限公司 Light -duty pipeline is to mouthpart based on large pipe welding
CN205776183U (en) * 2016-05-30 2016-12-07 中国建筑土木建设有限公司路桥分公司 Pile tube connects with welding anchor ear
CN207161916U (en) * 2017-08-30 2018-03-30 中建六局安装工程有限公司 A kind of anchor ear

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0740084A (en) * 1993-07-27 1995-02-10 Tokyo Gas Co Ltd Centering jig for welding of piping
JPH11267888A (en) * 1998-03-20 1999-10-05 Nippon Steel Corp Alignment ring jig for steel pipe welding
JP2002066788A (en) * 2000-08-22 2002-03-05 Hitachi Plant Eng & Constr Co Ltd Pipe groove matching jig
JP2006142340A (en) * 2004-11-22 2006-06-08 Jfe Koken Corp Tube centering tool
CN202155698U (en) * 2011-07-16 2012-03-07 中国十七冶集团有限公司 Labor-saving shaft coiling device
CN202418912U (en) * 2012-01-16 2012-09-05 宁波建工股份有限公司 Bearing support for heat insulation and preservation vertical tube
CN203265983U (en) * 2012-12-19 2013-11-06 中国核工业第五建设有限公司 Pairing tool for main cooling agent main pipelines of nuclear power station
CN104191126A (en) * 2014-08-20 2014-12-10 来宾华锡冶炼有限公司 Hoop used for clamping spray gun main body and spray gun head of Ausmelt furnace during welding
CN204183172U (en) * 2014-10-20 2015-03-04 五冶集团上海有限公司 A kind of hood type round steel pipe docking adjustment fixture
CN205600219U (en) * 2016-05-10 2016-09-28 中国能源建设集团安徽电力建设第一工程有限公司 Light -duty pipeline is to mouthpart based on large pipe welding
CN205776183U (en) * 2016-05-30 2016-12-07 中国建筑土木建设有限公司路桥分公司 Pile tube connects with welding anchor ear
CN207161916U (en) * 2017-08-30 2018-03-30 中建六局安装工程有限公司 A kind of anchor ear

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113635231A (en) * 2021-06-25 2021-11-12 国营芜湖机械厂 Auxiliary clamp for vibration test of aviation plunger pump
CN114808927A (en) * 2022-05-27 2022-07-29 广东品建基础工程有限公司 Prestressed pipe pile and construction method thereof
CN114808927B (en) * 2022-05-27 2023-09-26 广东品建基础工程有限公司 Prestressed pipe pile and construction method thereof

Similar Documents

Publication Publication Date Title
CN107654762A (en) A kind of anchor ear and its construction method
CN107386759A (en) A kind of bamboo shape steel tower bracing means
CN102979185A (en) Variable-beam depth H-beam and rectangular steel tube column assembly type node and construction method thereof
CN207161916U (en) A kind of anchor ear
CN203475422U (en) Concrete tubular pile extension device
CN103982077A (en) Universal wrapping board type joint of lattice type concrete filled steel tube wind power tower
CN106948477B (en) A kind of oblique grid system node
CN202064646U (en) Special appliance used for arranging steel truss folding line
CN203795936U (en) Reinforced electric transmission line angle steel tower main material structure
CN203983518U (en) Substation equipment ground structure
CN206917382U (en) A kind of bamboo shape steel tower bracing means
CN201890730U (en) Pin
DE112006000537B4 (en) Exhaust manifold for exhaust gases
CN205369970U (en) Reinforcing apparatus of no collar tie beam grange
CN104612454B (en) Main material breaking joint for cross section of filler-plate-free four-combination angle steel of transmission tower
CN204946659U (en) The hybrid core construction of Transformer
CN103790241B (en) A kind of Bolted angle connection method of H type steel flanged beam beam and laced of battened compression member
CN206426261U (en) A kind of tensioning equipment for U-shaped sheet pile
CN207194147U (en) A kind of new quadrate steel pipe column and the full assembled connecting node of H profile steel beam
CN202736637U (en) Air guide device used for ascending seat of transformer
CN206770121U (en) A kind of large diameter combined pylon
CN207195886U (en) A kind of double pipe structure connected using outward flange
CN205992568U (en) Collector plate and electrokinetic cell
CN206636295U (en) A kind of movably connected electric power bar of bottom plate
CN105568842A (en) Steel pipe weight reduction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180202