CN107601255A - A kind of built-in hanger, shield machine and development machine - Google Patents

A kind of built-in hanger, shield machine and development machine Download PDF

Info

Publication number
CN107601255A
CN107601255A CN201710680299.3A CN201710680299A CN107601255A CN 107601255 A CN107601255 A CN 107601255A CN 201710680299 A CN201710680299 A CN 201710680299A CN 107601255 A CN107601255 A CN 107601255A
Authority
CN
China
Prior art keywords
hanger
shackle
built
hanger body
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710680299.3A
Other languages
Chinese (zh)
Other versions
CN107601255B (en
Inventor
梁兴生
徐涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Heavy Industry Group Co Ltd
Original Assignee
China Railway Construction Heavy Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Heavy Industry Group Co Ltd filed Critical China Railway Construction Heavy Industry Group Co Ltd
Priority to CN201710680299.3A priority Critical patent/CN107601255B/en
Publication of CN107601255A publication Critical patent/CN107601255A/en
Application granted granted Critical
Publication of CN107601255B publication Critical patent/CN107601255B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of built-in hanger, shield machine and development machine.Built-in hanger, including hanger body, lifting rope and shackle, the hanger body are installed on the madial wall for treating hanging device, and the lifting rope is connected with the shackle, and described unload is connected when being buckled in lifting with the hanger body.Shield machine includes shield body shell and built-in hanger described above, and the hanger body is installed on the madial wall of the shield body shell.Development machine includes driving housing and above-mentioned built-in hanger, and hanger body is installed on the madial wall of the driving housing.The present invention has that simple to operate, operating efficiency is high, and the advantages that installation reliability is high.

Description

A kind of built-in hanger, shield machine and development machine
Technical field
The present invention relates to lifting field, more particularly to a kind of built-in hanger, shield machine and development machine.
Background technology
With the quickening of modernization, it is more and more to be largely used to engineering construction, the sophisticated equipment of tunnel excavation, its machine Tool and automaticity increasingly improve, and structure also becomes increasingly complex.At present, manufacture, assembling and the transportation of large scale equipment Generally use hanger is realized.The process such as lifting and upset is more to ensure that the effective measure of safety in production using hanger.
Based on present society development of civilization degree and scientific and technological level, existing shield machine hanger mainly uses two kinds of sides Formula:A kind of mode is that hanger is installed in shield machine shield body case by bolt, can easily be torn open after shield machine is completed The bolt hole on shield body shell is sealed except hanger, while using the sealing bearing pin with waterproof grommet, it can be realized The Fast Installation dismounting of hanger and reuse, but bolt is after a number of uses, screw thread easily top load effect and it is other not Determine to damage under factor, bolt reuse easily reaches fatigue limit and broken, and causes the generation of contingency.Meanwhile use Sealing bearing pin carries out the process such as sealing to bolt hole, causes tedious process, labor intensive and time.Another way is welded for hanger It is connected on shield body shell, shield body is lifted, it needs to be dismantled after the completion of lifting, then needs to weld again when lifting again Connect, its complex procedures, operating efficiency are low, less economical.
The content of the invention
The technical problem to be solved in the present invention is overcome the deficiencies in the prior art, there is provided a kind of simple to operate, operating efficiency Height, and built-in hanger, shield machine and development machine reliable, that have higher economy are installed.
In order to solve the above technical problems, technical scheme proposed by the present invention is:
A kind of built-in hanger, including hanger body, lifting rope and shackle, the hanger body, which is installed on, treats hanging device On madial wall, the lifting rope is connected with the shackle, and described unload is connected when being buckled in lifting with the hanger body.
Further improvement as above-mentioned technical proposal:
The shackle includes shackle lock pin and button, and the shackle lock pin is installed in the hanger body, the button It is connected in lifting through hanger body with the shackle lock pin.
Also include main shackle plate, the main shackle plate is provided with axially extending bore, and the shackle lock pin is axially movable installation In in the axially extending bore.
The hanger body is provided with the accommodating component for being used for that suspension shaft to be placed when shackle lock pin departs from axially extending bore, institute Accommodating component is stated on the axial movement stroke of the suspension shaft;The accommodating component includes accommodating cylinder and cover plate, described One end of accommodating cylinder is connected with hanger body, and the other end of the accommodating cylinder is connected with cover plate.
The hanger body includes four blocks of side plates and bottom plate, and four blocks of side plates enclose with bottom plate and unload padlock described in placement The placement space of pin.
The hanger body also includes top plate, and when the shackle departs from the hanger body, the top plate is covered on institute State on side plate.
The bottom plate is fixed with plate-side plate welding, and the top plate is mounted on the side plate.
A kind of shield machine, including shield body shell, in addition to built-in hanger described above, the hanger body are installed on On the madial wall of the shield body shell.
Further improvement as above-mentioned technical proposal:
The shield body shell is provided with the through hole passed through for lifting rope or joining shackle;The hanger body includes top plate, When the lifting rope departs from suspension shaft, the top plate is installed in the through hole.
A kind of development machine, including driving housing, in addition to built-in hanger described above, the hanger body are installed on On the madial wall of the driving housing.
Compared with prior art, the advantage of the invention is that:
The hanger body of the present invention is installed on the madial wall for treating hanging device, and in lifting, shackle connects with hanger body Pick up to hang and treat hanging device, its is simple in construction, easy to operate.Meanwhile hanger body is located at and treated in hanging device, treats hanging device Interference will not be produced with miscellaneous part at work so that hanger completes that follow-up work can be carried out without dismounting after lifting, and keeps away Exempted from the problem of hanger need to be dismantled repeatedly in lifting and work, its process is simple, operating efficiency is high, effectively reduce manpower into This, and avoids the generation of the contingency such as bolt failure in hanger unloading process, its economy, safe.The present invention's Shield machine, development machine equally have above-mentioned advantage.
Brief description of the drawings
The invention will be described in more detail below based on embodiments and refering to the accompanying drawings.Wherein:
Fig. 1 is the dimensional structure diagram of hanger of the present invention.
Fig. 2 is the main sectional view of hanger of the present invention.
Fig. 3 is the structural representation (lifting state) of shield machine of the present invention.
Fig. 4 is the structural representation (not lifting state) of shield machine of the present invention.
Fig. 5 is the structural representation that the present invention is placed or taken out shackle lock pin.
Each label represents in figure:
1st, hanger;11st, hanger body;111st, side plate;112nd, bottom plate;113rd, placement space;114th, top plate;12nd, lifting rope; 13rd, shackle;131st, shackle lock pin;132nd, button;14th, main shackle plate;141st, axially extending bore;2nd, component is housed;21st, cylinder is housed Body;22nd, cover plate;3rd, shield body shell.
Embodiment
Under will combine Figure of description and specific embodiment the present invention will be described in further details, but therefore do not limit Protection scope of the present invention processed.
As depicted in figs. 1 and 2, the built-in hanger of the present embodiment, including hanger body 11, lifting rope 12 and shackle 13.Its In, hanger body 11 is installed on the madial wall for treating hanging device, treat hanging device can be shield machine, development machine or other need to hang The large scale equipment of dress;Lifting rope 12 is connected with shackle 13, and shackle 13 is connected in lifting with the hanger body 11.The present invention's hangs Ear body 11 is installed on the madial wall for treating hanging device, and in lifting, shackle 13 is connected to lift by crane with hanger body 11 and waits to lift Equipment, its is simple in construction, easy to operate.Meanwhile hanger body 11 is located at and treated in hanging device, treats hanging device at work not Interference can be produced with miscellaneous part so that hanger 1 completes that follow-up work can be carried out without dismounting after lifting, and avoids hanger 1 The problem of need to being dismantled repeatedly in lifting and work, its process is simple, operating efficiency is high, effectively reduces human cost, and keep away The generation of the contingency such as bolt failure in the unloading process of hanger 1 is exempted from, its security reliability is high.
In the present embodiment, shackle 13 includes shackle lock pin 131 and button 132, and shackle lock pin 131 is installed on hanger body 11 Interior, button 132 is connected in lifting through hanger body 11 with shackle lock pin 131.Its hoisting structure is simple and convenient to operate.
In the present embodiment, built-in hanger 1 also includes main shackle plate 14, and main shackle plate 14 is welded in hanger body 11. In the present embodiment, main shackle plate 14 is provided with axially extending bore 141, and shackle lock pin 131 is axially movable in axially extending bore 141. When that need to lift, first button 132 is put into hanger body 11, the axial movement of shackle lock pin 131 insertion button 132 and axial direction are logical Hole 141, now shackle lock pin 131 and 132 spacing cooperation of button, then lifting rope 12 is connected with button 132, realizes lifting;Hanging After the completion of dress, the axial movement of shackle lock pin 131 is separated with button 132, then button 132 is removed into hanger body by lifting rope 12 11, the shackle lock pin 131 in hanger body 11 is taken out afterwards, its is simple to operate.
In the present embodiment, hanger body 11 is provided with accommodating component 2.Axial direction shifting of the accommodating component 2 located at shackle lock pin 131 On dynamic stroke, for placing shackle lock pin 131 when shackle lock pin 131 departs from axially extending bore 141, this avoid shackle lock pin 131 produce movement in equipment working state, ensure that equipment property safe and reliable to operation.
In the present embodiment, housing component 2 includes accommodating cylinder 21 and cover plate 22.Wherein, one end of cylinder 21 is housed with hanging Ear body 11 is connected, and hole is communicated with hanger body 11, and shackle lock pin 131 is positioned in accommodating cylinder 21 through intercommunicating pore; The other end of accommodating cylinder 21 is connected with cover plate 22.In the present embodiment, accommodating cylinder 21 is welded and fixed with hanger body 11, cover plate 22 are welded and fixed with accommodating cylinder 21.
In the present embodiment, hanger body 11 includes four blocks of side plates 111 and bottom plate 112, and four blocks of side plates 111 enclose with bottom plate 112 The placement space 113 of shackle lock pin 131 is placed in synthesis.In the present embodiment, hanger body 11 also includes top plate 114, in shackle 13 When departing from hanger body 11, top plate 114 is covered on side plate 111, forms the accommodation space of sealing.Using the design of body structure It not only effectively prevent extraneous muddy water and enter device interior, also improve the bulk strength of hanger 1, ensure that the safety of lifting can By property.
It is to be welded and fixed in the present embodiment, between side plate 111 and side plate 111 and side plate 111 and bottom plate 112;Top plate 114 It is mounted at by fastener on side plate 111 so that the top plate 114 when being put into taking-up of shackle 13 can be torn open easily and fast Unload.
Fig. 3 to Fig. 5 shows the embodiment of shield machine of the present invention, and shield machine includes shield body shell 3 and described above hung Ear 1, the hanger body 11 of hanger 1 are installed on the madial wall of shield body shell 3.In the present embodiment, hanger body 11 is located at shield body In shell 3, shield machine will not produce interference during set of tunneling construction so that hanger 1 is after completing to lift without dismounting Follow-up work can be carried out, after appearing also can lift up rapidly, avoid that hanger 1 need to dismantle repeatedly in lifting and work asks Topic, its process is simple, operating efficiency is high, effectively reduces human cost, and avoids bolt failure etc. in the unloading process of hanger 1 The generation of contingency, its security reliability are high.
In the present embodiment, shield body shell 3 is provided with the through hole passed through for shackle 13.After the disengaging of shackle 13, top plate 114 It is installed in through hole, and is connected with hanger body 11, forms sealing accommodation space.
A kind of embodiment of development machine, including driving housing and hanger 1 described above, the hanger body 11 of hanger 1 are pacified On madial wall loaded on driving housing.In the present embodiment, hanger body 11 in driving housing, in tunnel piercing apply by development machine Interference will not be produced during work so that hanger 1 can carry out follow-up work after completing to lift without dismounting, after appearing Can lift up rapidly, avoid the problem of hanger 1 need to be dismantled repeatedly in lifting and work, its process is simple, operating efficiency is high, has Effect reduces human cost, and avoids the generation of the contingency such as bolt failure in the unloading process of hanger 1, its security reliability It is high.
Although by reference to preferred embodiment, invention has been described, is not departing from the situation of the scope of the present invention Under, various improvement can be carried out to it and part therein can be replaced with equivalent.Especially, as long as being rushed in the absence of structure Prominent, the every technical characteristic being previously mentioned in each embodiment can combine in any way.The invention is not limited in text Disclosed in specific embodiment, but all technical schemes including falling within the scope of the appended claims.

Claims (10)

1. a kind of built-in hanger, it is characterised in that including hanger body, lifting rope and shackle, the hanger body, which is installed on, to be treated On the madial wall of hanging device, the lifting rope is connected with the shackle, and described unload is connected when being buckled in lifting with the hanger body.
2. built-in hanger according to claim 1, it is characterised in that the shackle includes shackle lock pin and button, institute State shackle lock pin to be installed in the hanger body, the button connects in lifting through hanger body and the shackle lock pin Connect.
3. built-in hanger according to claim 2, it is characterised in that also including main shackle plate, on the main shackle plate Provided with axially extending bore, the shackle lock pin, which is axially movable, to be installed in the axially extending bore.
4. built-in hanger according to claim 3, it is characterised in that the hanger body, which is provided with, to be used to unload padlock Pin places the accommodating component of suspension shaft when departing from axially extending bore, the accommodating component is located at the axial movement stroke of the suspension shaft On;The accommodating component includes accommodating cylinder and cover plate, one end of the accommodating cylinder are connected with hanger body, the accommodating cylinder The other end of body is connected with cover plate.
5. the built-in hanger according to Claims 1-4 any one, it is characterised in that the hanger body includes four Block side plate and bottom plate, four blocks of side plates enclose the placement space for placing the shackle lock pin with bottom plate.
6. built-in hanger according to claim 5, it is characterised in that the hanger body also includes top plate, described When shackle departs from the hanger body, the top plate is covered on the side plate.
7. built-in hanger according to claim 6, it is characterised in that the bottom plate is fixed with plate-side plate welding, the top Plate is mounted on the side plate.
8. a kind of shield machine, including shield body shell, it is characterised in that also include in as described in claim 1 to 7 any one Formula hanger is put, the hanger body is installed on the madial wall of the shield body shell.
9. shield machine according to claim 8, it is characterised in that the shield body shell is provided with and supplies lifting rope or joining shackle The through hole passed through;The hanger body includes top plate, and when the lifting rope departs from suspension shaft, the top plate is installed in described pass through In through hole.
10. a kind of development machine, including driving housing, it is characterised in that also include as described in claim 1 to 7 any one Built-in hanger, the hanger body are installed on the madial wall of the driving housing.
CN201710680299.3A 2017-08-10 2017-08-10 Built-in lifting lug, shield tunneling machine and tunneling machine Active CN107601255B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710680299.3A CN107601255B (en) 2017-08-10 2017-08-10 Built-in lifting lug, shield tunneling machine and tunneling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710680299.3A CN107601255B (en) 2017-08-10 2017-08-10 Built-in lifting lug, shield tunneling machine and tunneling machine

Publications (2)

Publication Number Publication Date
CN107601255A true CN107601255A (en) 2018-01-19
CN107601255B CN107601255B (en) 2020-04-14

Family

ID=61064977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710680299.3A Active CN107601255B (en) 2017-08-10 2017-08-10 Built-in lifting lug, shield tunneling machine and tunneling machine

Country Status (1)

Country Link
CN (1) CN107601255B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111874792A (en) * 2020-07-31 2020-11-03 中国十九冶集团有限公司 Hoisting roadbed box device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202346580U (en) * 2011-12-05 2012-07-25 重庆川东船舶重工有限责任公司 Concealed lifting lug assembly
CN203568661U (en) * 2013-10-31 2014-04-30 中石化第十建设有限公司 Built-in tail-sliding lifting lug
CN203667789U (en) * 2013-11-25 2014-06-25 辽宁石油机械制造有限公司 Hidden type hoisting tool
CN203889870U (en) * 2014-04-30 2014-10-22 中冶天工集团有限公司 Specific lifting device for cylinder module of large flotation machine
CN104236399A (en) * 2014-09-17 2014-12-24 江西洪都航空工业集团有限责任公司 Folding missile lifting lug structure
CN204871958U (en) * 2015-08-03 2015-12-16 南通润邦海洋工程装备有限公司 Portable weight box
CN207346974U (en) * 2017-08-10 2018-05-11 中国铁建重工集团有限公司 A kind of built-in lifting lug, shield machine and development machine

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202346580U (en) * 2011-12-05 2012-07-25 重庆川东船舶重工有限责任公司 Concealed lifting lug assembly
CN203568661U (en) * 2013-10-31 2014-04-30 中石化第十建设有限公司 Built-in tail-sliding lifting lug
CN203667789U (en) * 2013-11-25 2014-06-25 辽宁石油机械制造有限公司 Hidden type hoisting tool
CN203889870U (en) * 2014-04-30 2014-10-22 中冶天工集团有限公司 Specific lifting device for cylinder module of large flotation machine
CN104236399A (en) * 2014-09-17 2014-12-24 江西洪都航空工业集团有限责任公司 Folding missile lifting lug structure
CN204871958U (en) * 2015-08-03 2015-12-16 南通润邦海洋工程装备有限公司 Portable weight box
CN207346974U (en) * 2017-08-10 2018-05-11 中国铁建重工集团有限公司 A kind of built-in lifting lug, shield machine and development machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111874792A (en) * 2020-07-31 2020-11-03 中国十九冶集团有限公司 Hoisting roadbed box device

Also Published As

Publication number Publication date
CN107601255B (en) 2020-04-14

Similar Documents

Publication Publication Date Title
CN106290035A (en) Extra deep shaft drum winding steel wire rope fretting corrosion fatigue damage detection device and method
CN202186831U (en) Hanger
CN207346974U (en) A kind of built-in lifting lug, shield machine and development machine
CN107601255A (en) A kind of built-in hanger, shield machine and development machine
CN202265311U (en) Hoisting jig with water-cooling wall
CN204897143U (en) Wheel crane counter weight special lifting device
CN201873464U (en) Baseplate frame lifting appliance
CN110482395A (en) A kind of shield body auxiliary turning-over device
CN106185597B (en) A kind of large size Analytic Tower merogenesis special hanger for hoisting and hanging method
CN205816797U (en) A kind of ladle is with turning over bag apparatus
CN203248599U (en) Counterweight self-detached structure of rotary drilling rig and rotary drilling rig
CN207313050U (en) A kind of frock for aiding in installation shackle
CN201809029U (en) Lifting lever
CN203199949U (en) Dedicated accessory for detaching and installing containers for forklift truck
CN213294401U (en) Lifting appliance for hoisting steel lining plate of ore pass
CN215558356U (en) Building engineering construction material lifts by crane fixing device
CN202766061U (en) Tank-falling prevention device of skip bucket
CN206029352U (en) Winch brake band processing frock
CN102431887A (en) Simple hanger
CN214216505U (en) Transportation bracket and anti-deformation device for steel containment vessel of nuclear power plant
CN205603060U (en) Anchor clamps are lifted by crane in slewing bearing assembly
CN209193441U (en) Vertical shaft simple lifting appliance
CN204778410U (en) Bogie of bridge crane
CN206396641U (en) A kind of access bridge hoisting mechanism of stepping type self movable trestle
CN218434608U (en) Double-beam portal type hoisting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 410100 No. 88 East 7 Line, Changsha Economic and Technological Development Zone, Hunan Province

Applicant after: China Railway Construction Heavy Industry Co.,Ltd.

Address before: 410100 No. 88 Dongqi Road, Jingkai District, Changsha City, Hunan Province

Applicant before: China Railway Construction Heavy Industry Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant