CN107575929B - A kind of gas-heating heat-storage heating equipment - Google Patents

A kind of gas-heating heat-storage heating equipment Download PDF

Info

Publication number
CN107575929B
CN107575929B CN201710999797.4A CN201710999797A CN107575929B CN 107575929 B CN107575929 B CN 107575929B CN 201710999797 A CN201710999797 A CN 201710999797A CN 107575929 B CN107575929 B CN 107575929B
Authority
CN
China
Prior art keywords
oil
water
heat
gas
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710999797.4A
Other languages
Chinese (zh)
Other versions
CN107575929A (en
Inventor
刘祥宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Tianai Environmental Protection Technology Development Co ltd
Original Assignee
Tianjin Love Of Environmental Protection Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Love Of Environmental Protection Technology Development Co Ltd filed Critical Tianjin Love Of Environmental Protection Technology Development Co Ltd
Priority to CN201710999797.4A priority Critical patent/CN107575929B/en
Publication of CN107575929A publication Critical patent/CN107575929A/en
Application granted granted Critical
Publication of CN107575929B publication Critical patent/CN107575929B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

The invention discloses a kind of gas-heating heat-storage heating equipment, including phase-change material heat storage box, heater box, water tank, fuel reserve tank and heating heat exchange box;Conduction oil heat exchanger tube is equipped in phase-change material heat storage box;Water heater, oil heater and gas-operated thermal bath facility are equipped in heater box;Water heater is connected to by water circulation pipe with water tank;The fluid outlet of fuel reserve tank passes sequentially through conduction oil and goes out oil circulating pipe to be connected with the liquid feeding end of heat conduction oil circulating pipe;Conduction oil heat exchanger tube inlet communication of the outlet end of heat conduction oil circulating pipe after oil heater with phase-change material heat storage box;The conduction oil heat transfer tube outlet of phase-change material heat storage box is connected to heating heat exchange box;It is connected to by conduction oil heat exchanger tube between the import of conduction oil heat exchanger tube and conduction oil heat transfer tube outlet;Heating heat exchange box is connected to by conduction oil oil return circulation pipe with fuel reserve tank;Forced circulation pump is installed, heat conduction oil circulating pipe or conduction oil go out on oil circulating pipe to be equipped with conduction oil main circulation pump in water circulation pipe.

Description

A kind of gas-heating heat-storage heating equipment
Technical field
The present invention relates to heating equipment technical fields, more particularly to a kind of gas-heating heat-storage heating equipment.
Background technology
In recent years, with society fast development, the continuous improvement of human living standard, in northern China city, heating Central heating has become the thing popularized very much during people's life and work, currently, what traditional heating mainly used It is coal heating either electrical heating heating, it is well known that coal heating solves the problems, such as heating to a certain extent, still Since coal heating will produce greatly environmental hazard, in recent years, with increasingly serious, the electric energy confession of environmental problem Heat has gradually replaced coal heating, it appears that having for electric energy is also greatly to be generated electricity using coal, Pollution sources are only removed big city by these measures, but are directed to the remote location of coal power generation, and pollution still remains, institute With how to design and develop a kind of gas-heating heat-storage heating equipment that can be solved the above problems then seems it is particularly important.
Invention content
The technical problem to be solved by the present invention is to:A kind of gas-heating heat-storage heating equipment is provided;The gas-heating accumulation of heat Heating equipment is based on phase-change material heat storage box, is heated as main energy source using combustion gas, while by extra thermal energy It is stored in phase-change thermal storage case, when Interior Temperature Environment changes, can be realized by adjusting the flow control valve of different location The adjusting of heat supply.
The present invention is adopted the technical scheme that solve technical problem present in known technology:
A kind of gas-heating heat-storage heating equipment, includes at least:
Inside is equipped with the phase-change material heat storage box (30) of phase-change material, and heat conduction is equipped in the phase-change material heat storage box (30) Oily heat exchanger tube (26);
Heater box, the heater box is interior to be equipped with water heater (16), oil heater (13) and gas-operated thermal bath facility;
Water tank (50), fuel reserve tank (41) and heating heat exchange box (29);Wherein:
The water heater (16) is connected to by water circulation pipe with water tank (50);The fuel reserve tank (41) is equipped with fluid Outlet and fluid entrance;Fluid outlet pass sequentially through conduction oil go out oil circulating pipe (33) and heat conduction oil circulating pipe (20) into Liquid end connects;The outlet end of the heat conduction oil circulating pipe (20) pass through oil heater (13) afterwards with phase-change material heat storage box (30) Conduction oil heat exchanger tube import (21) is connected to;The conduction oil heat transfer tube outlet (27) of the phase-change material heat storage box (30) passes through high temperature Fluid pipeline is connected to heating heat exchange box (29);The conduction oil heat exchanger tube import (21) and conduction oil heat transfer tube outlet (27) it Between pass through conduction oil heat exchanger tube (26) be connected to;The heating heat exchange box (29) passes through conduction oil oil return circulation pipe (32) and fuel reserve tank (41) fluid entrance connection;Forced circulation pump (48) is installed in the water circulation pipe, in the heat conduction oil circulating pipe (20) or conduction oil goes out on oil circulating pipe (33) to be equipped with conduction oil main circulation pump (18).
In order to preferably solve the technical problem in background technology, this patent additionally uses following technical characteristic:
Further:Second flow is installed in the heat conduction oil circulating pipe (20) or conduction oil go out on oil circulating pipe (33) Control valve (38);4th oil flow control valve (40) is installed in the high-temperature oil liquid pipeline.
Further:The liquid feeding end of the heat conduction oil circulating pipe (20) passes through branch line and high-temperature oil liquid pipeline connection; Conduction oil pair circulating pump (42), the first oil flow control valve (37) and the control of third oil stream amount are installed in the branch line Valve (39).
Further:The heater box includes gas-tight silo (2), and the water heater (16) and oil heater (13) are positioned at close It seals in storehouse (2), the gas-operated thermal bath facility includes burner (11), provides the fuel gas pipeline of combustion gas for burner (11);Institute It states and gas control valve (10), the first gas control valve (8) and the second gas control valve (9) is installed in fuel gas pipeline.
Further:The inner wall of the gas-tight silo (2) is equipped with fire-retardant heat insulation layer (3), is opened up at the top of the gas-tight silo (2) There is exhaust outlet, enclosure (4), exhaust blower (24) and exhaust pipe (5) are installed in the vent position.
Further:The water tank (50) connect with one end of water supply pipe (53);It is equipped on the water supply pipe (53) Water compensating valve (55);The other end of the water supply pipe (53) by triple valve respectively with the water outlet of running water pipe, cold water pipe (56) One end connection;The other end of the cold water pipe (56) passes sequentially through cold water regulating valve (57), hot-water line (54) and water tank (50) it is connected to;The cold water regulating valve (57) is two into one logical three-way control valves;The cold water pipe (56) and hot-water line (54) It is connect with the entrance of cold water regulating valve (57).
Further:Water shortage sensor (52) is installed in the water tank (50), in the phase-change material heat storage box (30) material temperature sensor (47) is installed in, water temperature sensor (17) is installed in the water circulation pipe, and water temperature senses Device (17) is located at the outlet side of water heater (16), and oil temperature sensor (15) is equipped in the heat conduction oil circulating pipe (20); Flame-out feedback probe (59) is installed on the burner (11);The gas-heating heat-storage heating equipment further includes:
Control the first controller (60) and the 5th controller (62) of gas-operated thermal bath facility working condition;First control The signal input port of device (60) is electrically connected with oil temperature sensor (15) and flame-out feedback probe (59) respectively;First control The signal output port of device (60) is electrically connected with the control terminal of the first gas control valve (8) respectively;5th controller (62) signal input port is electrically connected with water temperature sensor (17), the signal output port difference of the 5th controller (62) It is electrically connected with combustion controller, forced circulation pump (48);
Control the second controller (61) of water compensating valve (55) working condition, the ports I/O point of the second controller (61) It is not electrically connected with water shortage sensor (52) and water compensating valve (55);
Room temperature creep for measuring room temperature;
The third controller (63) and the 4th controller (64) being electrically connected with room temperature creep, wherein:
The ports I/O of the third controller (63) respectively with heating water-circulating pump (43), the second oil flow control valve (38), the 4th oil flow control valve (40) and conduction oil main circulation pump (18) electrical connection;
The ports I/O of 4th controller (64) respectively with conduction oil pair circulating pump (42), the first oil flow control valve (37), third oil flow control valve (39) is electrically connected.
Further:It is provided with guard shield (1) outside the gas-tight silo (2);The bottom of the water tank (50) opens up There is soil cleaning port (51);The water tank (50), fuel reserve tank (41) and heating heat exchange box (29) inner wall of at least one are equipped with and protect Warm layer.
Further:At least one is equipped with heat transmission fin in the oil heater (13) and/or water heater (16) (14)。
Further:The heat conduction oil circulating pipe (20) includes:Positioned at oil heater (13) entrance side access oil pipe and Oil pipe is picked out positioned at oil heater (13) outlet side;The both ends for picking out oil pipe are rectilinear tubes (18-1), described to pick out oil The intermediate ends of pipe are bending tube (18-2), and the bending tube (18-2) is located at the top of gas-operated thermal bath facility.
Further:At least one is hollow cavity for the oil heater (13) and water heater (16), in hollow cavity Side wall is opened up there are two interface.
Further:The bending tube (18-2) is hollow rectangle structure, is installed at the top of the bending tube (18-2) There is hot-air spoiler (18-3).
Further:The heat transmission fin (14) is to be made of multiple heat transmission fins parallel to each other;In the oil heating It is also equipped with the heat conduction baffle vertical with heat transmission fin (14) (16-1) in device (13) and/or water heater (16).
Further:The partition board being equipped in the bending tube (18-2) in multiple horizontal directions.
The invention has the advantages and positive effects that:
By using above-mentioned technical proposal, the invention firstly uses clean energy resource combustion gas as main energy sources, utilizes combustion gas The thermal energy of generation is that water and oil are heated, and then, the high temperature oil after heating is changed by entering heating after phase-change material heat storage box Hot tank heats heating water source;In the process, high temperature oil is that phase-change material heating carries out heat accumulation;When the temperature of high temperature oil When insufficient, phase-change material heat storage box will feed back thermal energy to high temperature oil, ensure the demand of heating;Due to being heated to water in this patent When, heating water cooperation tap water can be utilized to realize the control of daily life water temperature.
Description of the drawings
Fig. 1 is the structural schematic diagram of the preferred embodiment of the present invention;
Fig. 2 is heater section first embodiment structure chart in the preferred embodiment of the present invention;
Fig. 3 is heater section second embodiment structure chart in the preferred embodiment of the present invention;
Fig. 4 is heater section 3rd embodiment structure chart in the preferred embodiment of the present invention;
Fig. 5 is heater section fourth embodiment structure chart in the preferred embodiment of the present invention;
Fig. 6 is the circuit diagram in the preferred embodiment of the present invention.
Wherein:1, guard shield;2, gas-tight silo;3, flame resistant protective layer;4, enclosure;5, ventilation pipe;6, firm banking;7、 Combustion gas is taken over;8, the first gas control valve;9, the second gas control valve;10, gas control valve;11, burner;12, ignition electrode; 13, oil heater;14, heat transmission fin;15, oil temperature sensor;16, water heater;17, water temperature sensor;18, conduction oil master follows Ring pumps;19, heat conduction water-circulating pipe;20, heat conduction oil circulating pipe;21, conduction oil heat exchanger tube import;22, oral siphon is recycled;23, it follows Ring outlet pipe;24, exhaust blower;25, blast switch;26, conduction oil heat exchanger tube;27, conduction oil heat transfer tube outlet;28, heating is changed Hot tank oil inlet;29, heat heat exchange box;30, phase-change material heat storage box;31, heat heat exchange box oil export;32, conduction oil oil return Circulation pipe;33, conduction oil goes out oil circulating pipe;34, charge door;35, feed lid;36, hopper gas vent;37, the first oil stream amount Control valve;38, the second oil flow control valve;39, third oil flow control valve;40, the 4th oil flow control valve;41, fuel reserve tank; 42, conduction oil pair circulating pump;43, heating water-circulating pump;44, heat outlet pipe;45, heating water return pipe;46, heat exchange box is vented Valve;47, material temperature sensor;48, forced circulation pump;49, water tank gas vent;50, water tank;51, soil cleaning port;52, water shortage senses Device;53, water supply pipe;54, hot-water line;55, water compensating valve;56, cold water pipe;57, cold water regulating valve;58, room temperature creep;59, it puts out Fiery feedback probe;60, the first controller;61, second controller;62, the 5th controller;63, third controller;64, the 4th control Device processed.
Specific implementation mode
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing Detailed description are as follows:
It please refers to Fig.1 to Fig. 6, a kind of gas-heating heat-storage heating equipment, including:
Inside is equipped with the phase-change material heat storage box 30 of phase-change material, is changed equipped with conduction oil in the phase-change material heat storage box 30 Heat pipe 26;The top of phase-change material heat storage box 30 offers charge door 34, and charging lid 35 is equipped in the position of charge door 34, Hopper gas vent 36 is offered in charging lid 35;
Heater box, the heater box is interior to be equipped with water heater 16, oil heater 13 and gas-operated thermal bath facility;
Water tank 50, fuel reserve tank 41 and heating heat exchange box 29;Wherein:
The water heater 16 is connected to by water circulation pipe with water tank 50;The water circulation pipe includes:Heat-conductive water Circulation pipe 19, cycle oral siphon 22 and recycling outlet 23;One end of recycling outlet 23 is connect with the water outlet of water tank 50, One end of cycle oral siphon 22 is connect with the water inlet of water tank 50, the both ends of heat conduction water-circulating pipe 19 respectively with recycling outlet 23 other end, the other end connection for recycling oral siphon 22;
The fuel reserve tank 41 is equipped with fluid outlet and fluid entrance;The fluid outlet passes sequentially through the fuel-displaced cycle of conduction oil Pipe 33 is connected with the liquid feeding end of heat conduction oil circulating pipe 20;The outlet end of the heat conduction oil circulating pipe 20 pass through oil heater 13 after with The conduction oil heat exchanger tube import 21 of phase-change material heat storage box 30 is connected to;The conduction oil heat exchanger tube of the phase-change material heat storage box 30 goes out Mouth 27 is connect by high-temperature oil liquid pipeline with the heating heat exchange box oil inlet 28 of heating heat exchange box 29;The conduction oil heat exchanger tube into Pass through conduction oil heat exchanger tube 26 between mouth 21 and conduction oil heat transfer tube outlet 27 to be connected to;The heating heat exchange of the heating heat exchange box 29 Case oil export 31 is connected to by conduction oil oil return circulation pipe 32 with the fluid entrance of fuel reserve tank 41;Pacify in the water circulation pipe Equipped with forced circulation pump 48, go out on oil circulating pipe 33 to be equipped with conduction oil major cycle in the heat conduction oil circulating pipe 20 or conduction oil Pump 18.The heating outlet pipe 44 being connect with heating loop and heating water return pipe 45 are offered on heating heat exchange box 29;
In order to ensure safety, heat exchange box air bleeding valve 46 is offered at the top of heating heat exchange box 29;In water tank 50 Top offers water tank gas vent 49;
Preferably, on the basis of above preferred embodiment:
In order to which the accurate adjustment of heating temperature is better achieved, in the heat conduction oil circulating pipe 20 or the fuel-displaced cycle of conduction oil Second flow control valve 38 is installed on pipe 33;The 4th oil flow control valve 40 is installed in the high-temperature oil liquid pipeline.
The liquid feeding end of the heat conduction oil circulating pipe 20 passes through branch line and high-temperature oil liquid pipeline connection;In the branched pipe Conduction oil pair circulating pump 42, the first oil flow control valve 37 and third oil flow control valve 39 are installed in road.
The heater box includes gas-tight silo 2, and the water heater 16 and oil heater 13 are located in gas-tight silo 2, the combustion Gas heating device includes burner 11, provides the fuel gas pipeline of combustion gas for burner 11;Combustion is installed in the fuel gas pipeline Gas regulating valve 10, the first gas control valve 8 and the second gas control valve 9.Above-mentioned fuel gas pipeline is the combustion gas take over 7 in Fig. 2; Ignition electrode 12 is located at the gas outlet position of burner 11;
The inner wall of the gas-tight silo 2 is equipped with fire-retardant heat insulation layer 3, and the top of the gas-tight silo 2 offers exhaust outlet, described Vent position is equipped with enclosure 4, exhaust blower 24, exhaust pipe 5 and blast switch 25, and blast switch 25 makes with exhaust blower 24 It can terminal electrical connection.Start exhaust blower 24 in time when wind pressure is excessive, reduces the wind pressure in gas-tight silo 2, prevent trouble before it happens.
The water tank 50 is connect with one end of water supply pipe 53;Water compensating valve 55 is installed on the water supply pipe 53;The benefit The other end of water pipe 53 is connected to one end of the water outlet of running water pipe, cold water pipe 56 respectively by triple valve;The cold water pipe 56 other end passes sequentially through cold water regulating valve 57, hot-water line 54 is connected to water tank 50;The cold water regulating valve 57 be two into One logical three-way control valve;The cold water pipe 56 and hot-water line 54 are connect with the entrance of cold water regulating valve 57.
Water shortage sensor 52 is installed in the water tank 50, material temperature is installed in the phase-change material heat storage box 30 Sensor 47 is equipped with water temperature sensor 17 in the water circulation pipe, and water temperature sensor 17 is located at water heater 16 Outlet side is equipped with oil temperature sensor 15 in the heat conduction oil circulating pipe 20;Flame-out feedback is installed on the burner 11 Probe 59;The gas-heating heat-storage heating equipment further includes:
Control the first controller 60 and the 5th controller 62 of gas-operated thermal bath facility working condition;First controller 60 Signal input port be electrically connected respectively with material temperature sensor 47, oil temperature sensor 15 and flame-out feedback probe 59;Described first The signal output port of controller 60 is electrically connected with the control terminal of the first gas control valve 8, the second gas control valve 9 respectively; The signal input port of 5th controller 62 is electrically connected with water temperature sensor 17, the signal output of the 5th controller 62 Port is electrically connected with combustion controller, forced circulation pump 48 respectively;It is described
Control the second controller 61 of 55 working condition of water compensating valve, the ports I/O of the second controller 61 respectively with lack Water sensor 52 and water compensating valve 55 are electrically connected;
Room temperature creep 58 for measuring room temperature;
The third controller 63 and the 4th controller 64 being electrically connected with room temperature creep, wherein:
The ports I/O of the third controller 63 respectively with heating water-circulating pump 43, the second oil flow control valve the 38, the 4th Oil flow control valve 40 and conduction oil main circulation pump 18 are electrically connected;
The ports I/O of 4th controller 64 respectively with conduction oil pair circulating pump 42, the first oil flow control valve 37, Three oil flow control valves 39 are electrically connected.
Guard shield 1 is provided with outside the gas-tight silo 2, the bottom of guard shield 1 is provided with firm banking 6;The storage The bottom of water tank 50 offers soil cleaning port 51;The water tank 50, fuel reserve tank 41 and heating heat exchange box 29 at least one interior Wall is equipped with insulating layer.
At least one is equipped with heat transmission fin 14 in the oil heater 13 and/or water heater 16.
The heat conduction oil circulating pipe 20 includes:Positioned at the access oil pipe of 13 entrance side of oil heater and positioned at oil heater 13 Outlet side picks out oil pipe;The both ends for picking out oil pipe are rectilinear tubes 18-1, and the intermediate ends for picking out oil pipe are bending tube 18-2, the bending tube 18-2 are located at the top of gas-operated thermal bath facility.
At least one is hollow cavity for the oil heater 13 and water heater 16, opened up in the side wall of hollow cavity there are two Interface.
The bending tube 18-2 is hollow rectangle structure, and hot-air spoiler is equipped at the top of the bending tube 18-2 18-3。
The heat transmission fin 14 is to be made of multiple heat transmission fins parallel to each other;In the oil heater 13 and/or water The heat conduction baffle 16-1 vertical with heat transmission fin 14 is also equipped in heater 16.
The partition board being equipped in the bending tube 18-2 in multiple horizontal directions.
Heating part in above preferred embodiment, i.e. heater box can be fixed on phase-change material heat storage box outside or It is integrally fixed on wall, heater box includes mainly burner 11, ignition electrode 12, flame-out feedback probe 59, combustion gas take over 7, first Gas control valve 8, the second gas control valve 9, gas control valve 10;Gas control valve 10 is preferably proportion magnetic valve;Water adds Hot device 16, forced circulation pump 48, heat conduction water-circulating pipe 19, cycle oral siphon 22, recycling outlet 23 form water heat cycles system System;Enclosure 4 and exhaust blower 24 are installed in the top of water heater 16, the exhaust gas for generation of burning and the oxygen needed for burning are by changing Tracheae 5 is realized;The bottom of ventilation pipe 5 and the top of guard shield are tightly connected;Water after water heater 16 heats passes through cycle Oral siphon 22, recycling outlet 23, forced circulation pump 48 and water storage box 50 form the heating heat reservoir of domestic water;
Heating circulation system:When room temperature is higher than predetermined threshold value, high temperature signal is sent to third control by room temperature creep 58 63 and the 4th controller 64 of device processed, third controller 63 close conduction oil main circulation pump 18, heating water-circulating pump 43, the second oil stream Control valve 38 and the 4th oil flow control valve 40, while the 4th controller 64 opens conduction oil pair circulating pump 42, the first oil stream Control valve 37 and third oil flow control valve 39, at this point, the high temperature oil after heater box heating is phase-change thermal storage case heat supply, it will be hot It can be stored in the phase change material in phase-change thermal storage case;Oil at this time is partial circulating in the entire system;When room temperature is less than default When threshold value, low-temperature signal is sent to third controller 63 and the 4th controller 64 by room temperature creep 58, and third controller 63 is opened Conduction oil main circulation pump 18, heating water-circulating pump 43, the second oil flow control valve 38 and the 4th oil flow control valve 40 are opened, simultaneously 4th controller 64 closes conduction oil pair circulating pump 42, the first oil flow control valve 37 and third oil flow control valve 39, at this point, Heater box heating after high temperature oil both can be phase-change thermal storage case heat supply, also simultaneously for heating system by thermal energy, oil at this time It is systemic circulation in the entire system;
Storage heating system:First, real by the first gas control valve 8, the second gas control valve 9, gas control valve 10 The delivery rate of existing combustion gas accurately controls;Prevent that pressure is excessive and deflagration accident occurs;Then, burning is lighted by ignition electrode 12 The combustion gas that device 11 exports;It is heated for oil heater 13 by the thermal energy that fuel gas buring process generates, oil is after oil heater 13 Temperature increases, and subsequent high temperature oil, which enters in phase-change thermal storage case, to exchange heat, and after the completion of heat exchange, high temperature oil enters heating heat exchange box and is Heating system provides thermal energy, it is clear that in above-mentioned cyclic process, partial heat energy is distributed to phase-change thermal storage case and deposited by high temperature oil Storage uses remaining thermal energy supply heating system, in order to ensure that the abundant of oil heater 13 (water heater is similarly) adds The thermal efficiency, increasing in oil heater 13 has heat transmission fin 14 and then increases heat exchange area.When oil temperature sensor detects oil When temperature is excessively high, then the first controller 60 closes the second gas control valve 9 and burner 11, when oil temperature sensor detects oil temperature When normal, then the first controller 60 opens burner 11.Material temperature sensor 47 is measured in real time the temperature of phase-change material, and Testing result is sent to the first controller 60, when phase-change material when the temperature is excessively high, then the first controller 60 close first combustion Gas control valve 8 and burner 11, when the temperature of phase-change material is normal, then the first controller 60 opens the first gas control valve 8 With burner 11, conduction oil heat exchanger tube 26 heats for phase-change material.
Life water circulation system:When burner 11 works, water heater 16 can be heated, water heater 16 is to heat conduction Recirculated water in water-circulating pipe 19 is heated, and forced circulation pump 48 drives recirculated water to be recycled;Hot water is stored in water tank In 50, when the water temperature over-high in water storage box 50, the steam of generation is discharged in time by water tank gas vent 49, when being needed in life When hot water, ratio cooperation can be carried out to the hot water of the hot water or cold water pipe of tap water by cold water regulating valve 57, be finally reached Suitable temperature water.Lack sensor 52 to be detected the water level in water storage box 50, when water temperature is too low, then second controller 61 open water compensating valve 55 supplements water for water storage box, and water temperature sensor 17 is measured in real time the water temperature after heating, when water temperature mistake Gao Shi, then the unlatching of second controller 61 forced circulation pump 48, accelerates the cycle of water, when water temperature is normal, then closes forced circulation Pump 48.
Wheel leakage protective:When the flame of burner 11 is insufficient or extinguishes, the feedback probe 59 that stops working sends detection signal To the first controller, the first controller closes the first gas control valve 8 and burner in time, can again restore just after Awaiting Overhaul Often.
The embodiments of the present invention have been described in detail above, but content is only the preferred embodiment of the present invention, It should not be construed as limiting the practical range of the present invention.Any changes and modifications in accordance with the scope of the present application, It should all still fall within the scope of the patent of the present invention.

Claims (14)

1. a kind of gas-heating heat-storage heating equipment, it is characterised in that:It includes at least:
Inside is equipped with the phase-change material heat storage box (30) of phase-change material, is changed equipped with conduction oil in the phase-change material heat storage box (30) Heat pipe (26);
Heater box, the heater box is interior to be equipped with water heater (16), oil heater (13) and gas-operated thermal bath facility;
Water tank (50), fuel reserve tank (41) and heating heat exchange box (29);Wherein:
The water heater (16) is connected to by water circulation pipe with water tank (50);The fuel reserve tank (41) exports equipped with fluid With fluid entrance;The fluid outlet passes sequentially through the liquid feeding end that conduction oil goes out oil circulating pipe (33) and heat conduction oil circulating pipe (20) Connection;The outlet end of the heat conduction oil circulating pipe (20) passes through oil heater (13) heat conduction with phase-change material heat storage box (30) afterwards Oily heat exchanger tube import (21) connection;The conduction oil heat transfer tube outlet (27) of the phase-change material heat storage box (30) passes through high-temperature oil liquid Pipeline is connected to heating heat exchange box (29);Lead between the conduction oil heat exchanger tube import (21) and conduction oil heat transfer tube outlet (27) Cross conduction oil heat exchanger tube (26) connection;The heating heat exchange box (29) passes through conduction oil oil return circulation pipe (32) and fuel reserve tank (41) Fluid entrance connection;Forced circulation pump (48) is installed in the water circulation pipe, in the heat conduction oil circulating pipe (20) Or conduction oil goes out on oil circulating pipe (33) to be equipped with conduction oil main circulation pump (18).
2. gas-heating heat-storage heating equipment according to claim 1, it is characterised in that:In the heat conduction oil circulating pipe (20) or conduction oil go out on oil circulating pipe (33) in the second oil flow control valve (38) is installed;In the high-temperature oil liquid pipeline 4th oil flow control valve (40) is installed.
3. gas-heating heat-storage heating equipment according to claim 2, it is characterised in that:The heat conduction oil circulating pipe (20) Liquid feeding end pass through branch line and high-temperature oil liquid pipeline connection;Conduction oil pair circulating pump is installed in the branch line (42), the first oil flow control valve (37) and third oil flow control valve (39).
4. gas-heating heat-storage heating equipment according to claim 3, it is characterised in that:The heater box includes gas-tight silo (2), the water heater (16) and oil heater (13) are located in gas-tight silo (2), and the gas-operated thermal bath facility includes burner (11), it is the fuel gas pipeline of burner (11) offer combustion gas;Gas control valve (10), first are installed in the fuel gas pipeline Gas control valve (8) and the second gas control valve (9).
5. gas-heating heat-storage heating equipment according to claim 4, it is characterised in that:The inner wall of the gas-tight silo (2) Equipped with fire-retardant heat insulation layer (3), exhaust outlet is offered at the top of the gas-tight silo (2), smoke evacuation is installed in the vent position Cover (4), exhaust blower (24) and exhaust pipe (5).
6. gas-heating heat-storage heating equipment according to claim 5, it is characterised in that:The water tank (50) and moisturizing Manage one end connection of (53);Water compensating valve (55) is installed on the water supply pipe (53);The other end of the water supply pipe (53) passes through Triple valve is connected to one end of the water outlet of running water pipe, cold water pipe (56) respectively;The other end of the cold water pipe (56) is successively It is connected to water tank (50) by cold water regulating valve (57), hot-water line (54);The cold water regulating valve (57) is two into one logical Three-way control valve;The cold water pipe (56) and hot-water line (54) are connect with the entrance of cold water regulating valve (57).
7. gas-heating heat-storage heating equipment according to claim 6, it is characterised in that:The peace in the water tank (50) Equipped with water shortage sensor (52), material temperature sensor (47) is installed in the phase-change material heat storage box (30), is followed in the water Water temperature sensor (17) is installed, and water temperature sensor (17) is located at the outlet side of water heater (16) in endless tube road, described Oil temperature sensor (15) is installed in heat conduction oil circulating pipe (20);Flame-out feedback probe is installed on the burner (11) (59);The gas-heating heat-storage heating equipment further includes:
Control the first controller (60) and the 5th controller (62) of gas-operated thermal bath facility working condition;First controller (60) signal input port is electrically connected with oil temperature sensor (15) and flame-out feedback probe (59) respectively;First controller (60) signal output port is electrically connected with the control terminal of the first gas control valve (8) respectively;5th controller (62) Signal input port be electrically connected with water temperature sensor (17), the signal output port of the 5th controller (62) respectively with combustion Burning controller, forced circulation pump (48) electrical connection;
Control the second controller (61) of water compensating valve (55) working condition, the ports I/O of the second controller (61) respectively with Water shortage sensor (52) and water compensating valve (55) electrical connection;
Room temperature creep for measuring room temperature;
The third controller (63) and the 4th controller (64) being electrically connected with room temperature creep, wherein:
The ports I/O of the third controller (63) respectively with heating water-circulating pump (43), the second oil flow control valve (38), Four oil flow control valves (40) and conduction oil main circulation pump (18) electrical connection;
The ports I/O of 4th controller (64) respectively with conduction oil pair circulating pump (42), the first oil flow control valve (37), Third oil flow control valve (39) is electrically connected.
8. gas-heating heat-storage heating equipment according to claim 6, it is characterised in that:In the gas-tight silo (2) peripheral hardware It is equipped with guard shield (1);The bottom of the water tank (50) offers soil cleaning port (51);The water tank (50), fuel reserve tank (41) and heating heat exchange box (29) inner wall of at least one is equipped with insulating layer.
9. according to claim 1-8 any one of them gas-heating heat-storage heating equipment, it is characterised in that:The oil heater (13) and/or in water heater (16) at least one is equipped with heat transmission fin (14).
10. gas-heating heat-storage heating equipment according to claim 9, it is characterised in that:The heat conduction oil circulating pipe (20) include:Oil pipe is picked out positioned at the access oil pipe of oil heater (13) entrance side and positioned at oil heater (13) outlet side; The both ends for picking out oil pipe are rectilinear tubes (18-1), and the intermediate ends for picking out oil pipe are bending tube (18-2), the bending Pipe (18-2) is located at the top of gas-operated thermal bath facility.
11. gas-heating heat-storage heating equipment according to claim 10, it is characterised in that:The oil heater (13) and At least one is hollow cavity to water heater (16), is opened up there are two interface in the side wall of hollow cavity.
12. gas-heating heat-storage heating equipment according to claim 10, it is characterised in that:The bending tube (18-2) is Hollow rectangle structure is equipped with hot-air spoiler (18-3) at the top of the bending tube (18-2).
13. gas-heating heat-storage heating equipment according to claim 12, it is characterised in that:The heat transmission fin (14) is It is made of multiple heat transmission fins parallel to each other;Be also equipped in the oil heater (13) and/or water heater (16) with The vertical heat conduction baffle (16-1) of heat transmission fin (14).
14. gas-heating heat-storage heating equipment according to claim 12, it is characterised in that:At the bending tube (18-2) The partition board being inside equipped in multiple horizontal directions.
CN201710999797.4A 2017-10-24 2017-10-24 A kind of gas-heating heat-storage heating equipment Expired - Fee Related CN107575929B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710999797.4A CN107575929B (en) 2017-10-24 2017-10-24 A kind of gas-heating heat-storage heating equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710999797.4A CN107575929B (en) 2017-10-24 2017-10-24 A kind of gas-heating heat-storage heating equipment

Publications (2)

Publication Number Publication Date
CN107575929A CN107575929A (en) 2018-01-12
CN107575929B true CN107575929B (en) 2018-07-27

Family

ID=61038169

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710999797.4A Expired - Fee Related CN107575929B (en) 2017-10-24 2017-10-24 A kind of gas-heating heat-storage heating equipment

Country Status (1)

Country Link
CN (1) CN107575929B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194969A (en) * 2018-03-22 2018-06-22 天津天爱环保技术开发有限公司 A kind of heating heat storage electric stove
CN108194975A (en) * 2018-03-22 2018-06-22 李海燕 A kind of heating thermal storage equipment
CN108386896B (en) * 2018-03-22 2024-05-14 山东恒辉节能技术集团有限公司 Multi-stage heat exchange heating and heat storage equipment
CN108507000A (en) * 2018-04-16 2018-09-07 天津天爱环保科技开发有限公司 Electrical heating type heating plant
CN109654582B (en) * 2018-12-18 2023-10-10 北京中安金圣科技有限公司 Energy storage and heat supply equipment
CN111596705A (en) * 2020-05-29 2020-08-28 福州游标卡尺网络科技有限公司 Intelligent temperature control system of communication cabinet

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207407417U (en) * 2017-10-24 2018-05-25 天津天爱环保技术开发有限公司 A kind of gas-heating heat-storage heating equipment

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4067314A (en) * 1975-12-29 1978-01-10 Dwight L. Bollefer Solar energy collector system
US5054540A (en) * 1987-11-05 1991-10-08 Instatherm Company Thermal energy storage apparatus
CN100572973C (en) * 2003-10-31 2009-12-23 潘戈 The hot water supply of a kind of solar energy, the accumulation of heat of peak valley electricity and refrigeration set composite
CN202581509U (en) * 2012-04-23 2012-12-05 李军 Solar energy and condensation type gas wall-hanging stove combined heating system
CN203258736U (en) * 2013-05-20 2013-10-30 成都前锋电子有限责任公司 Multi-energy wall-hanging stove type heat supply heating system
CN106766167B (en) * 2017-01-17 2022-08-16 张青林 Combustion heating system of gas wall-mounted furnace and gas wall-mounted furnace

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207407417U (en) * 2017-10-24 2018-05-25 天津天爱环保技术开发有限公司 A kind of gas-heating heat-storage heating equipment

Also Published As

Publication number Publication date
CN107575929A (en) 2018-01-12

Similar Documents

Publication Publication Date Title
CN107575929B (en) A kind of gas-heating heat-storage heating equipment
CN106895576A (en) A kind of Far infrared electric wall-hung boiler
CN207407417U (en) A kind of gas-heating heat-storage heating equipment
CN206626816U (en) A kind of special heating tube of boiler
CN103604154B (en) Electrothermal heating unit
CN204923481U (en) Environment -friendly heat collector
CN209300772U (en) A kind of energy saving and environment friendly steamer
CN206001686U (en) Large-scale ring water direct heat-exchange solid heat storage electric furnace
CN206583091U (en) A kind of fuel gas energy-saving boiler
CN206387124U (en) A kind of intelligent water replenishing type solar water heater
CN206222681U (en) A kind of energy-conserving and environment-protective gas-heating and hot-water boiler
CN106678930A (en) Solar phase change heating plant
CN207849537U (en) A kind of heating thermal storage equipment of multi-stage heat exchanger
CN210035860U (en) Intelligent heating heat-preservation water storage tank
CN203177294U (en) Light panel solar energy and fuel gas combined type heat supply system
CN109668181B (en) Multifunctional fuel steam energy-saving stove
CN207622121U (en) A kind of heating thermal storage equipment
CN206001685U (en) Small-sized paddy electricity solid heat storage electric furnace
CN207622114U (en) A kind of heating heat storage electric stove
CN207298910U (en) A kind of biomass boiler flue gas recirculation overfire air device
CN206670035U (en) A kind of Far infrared electric wall-hung boiler
CN207081204U (en) A kind of solar water supply boiler
CN206669864U (en) A kind of novel household heating equipment
CN205897502U (en) Electric heating boiler
CN206222304U (en) A kind of automatic heating system suitable for production mould

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180314

Address after: 301700 -3 (central office), room 217, No. 66, dragon and Phoenix Avenue, Wuqing District, Tianjin

Applicant after: TIANJIN TIANAI ENVIRONMENTAL PROTECTION TECHNOLOGY DEVELOPMENT CO.,LTD.

Address before: No. 25, 2 row of 5 District, Cang Shang Village, Si Cun town, Tianjin City, Tianjin

Applicant before: Liu Xiangyu

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180727