CN107575926A - A kind of method of work of dual heat supply workshop heating system - Google Patents

A kind of method of work of dual heat supply workshop heating system Download PDF

Info

Publication number
CN107575926A
CN107575926A CN201710869136.XA CN201710869136A CN107575926A CN 107575926 A CN107575926 A CN 107575926A CN 201710869136 A CN201710869136 A CN 201710869136A CN 107575926 A CN107575926 A CN 107575926A
Authority
CN
China
Prior art keywords
water
water inlet
radiator
pipe
heating system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710869136.XA
Other languages
Chinese (zh)
Inventor
王李剑
蒋三
蒋三一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou 31 Heating And Cooling Engineering Co Ltd
Original Assignee
Suzhou 31 Heating And Cooling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou 31 Heating And Cooling Engineering Co Ltd filed Critical Suzhou 31 Heating And Cooling Engineering Co Ltd
Priority to CN201710869136.XA priority Critical patent/CN107575926A/en
Publication of CN107575926A publication Critical patent/CN107575926A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]

Landscapes

  • Steam Or Hot-Water Central Heating Systems (AREA)

Abstract

The invention discloses a kind of method of work of dual heat supply workshop heating system, comprise the following steps:1)The solar panels and boiler of solar energy heating system respectively heat water;2)Heat storage water tank and boiler provide hot water to radiator;3)The first water inlet pipe magnetic valve, the first main water inlet tube magnetic valve and the first main water return tube magnetic valve are opened successively;4)Radiator enters hot water, heating;5)Controller receives the data of first flow sensor and temperature display adjusting means;6)Temperature display adjusting means sets heating temperature, and controller adjusts the inflow of the first water inlet pipe magnetic valve;7)The hot water of heat storage water tank and boiler enters radiator by the first main water inlet tube, water collecting and diversifying device, tie point water inlet pipe, radiator water inlet pipe;8)Hot water enters heat storage water tank or boiler from radiator return pipe, tie point return pipe, water collecting and diversifying device and the first main water return tube;9)Heat continuous repeat step 4)‑8).

Description

A kind of method of work of dual heat supply workshop heating system
Technical field
The invention belongs to heating technology field, more particularly to a kind of method of work of dual heat supply workshop heating system.
Background technology
The winter either north or south, most area are in cold, and factory floor is even more to be in one Kind is similar to outdoor working environment, the employee of shopwork, it is also often desirable to carry the workpiece such as metalwork, therefore often go out The situation of existing frostbite, when serious, workshop can not normally be produced, due to the working environment of supercooling, and its lubricating oil reach Less than assigned temperature, it is impossible to ensure the service behaviour of machine, but heating needs to consume mass energy on a large scale in workshop, This gives the increased very heavy production cost of enterprise again, therefore it is urgently to be resolved hurrily to provide a energy-efficient workshop heating system Problem.
The content of the invention
Goal of the invention:In order to overcome the above insufficient, it is an object of the invention to provide a kind of dual heat supply workshop heating system Method of work, this method of work set independent radiator and inlet and outlet pipe in each workbench, can both be closed with subregion Heating can also individually close some radiator, and the controller and temperature control system of setting, using flexible is simple to operate, be adapted to Large-scale workshop, heating area and temperature can be adjusted flexibly, be adapted to factory floor to use, while save resource again, use this side Method can save resource.
Technical scheme:A kind of dual heat supply workshop heating system, the device of the method for work include radiator, control Device, first flow sensor, the first water inlet pipe magnetic valve, power supply, temperature display adjusting means, the first water outlet pipe valve, diversity water Device, the first main water inlet tube magnetic valve, the first main water return tube magnetic valve, boiler, the first main water inlet tube, the first main water return tube, first Branch road water inlet pipe, tie point return pipe, radiator water inlet pipe, radiator return pipe, workshop and workbench, the controller with First flow sensor and the first water inlet pipe magnetic valve are electrically connected with, the power supply and temperature display adjusting means and controller electricity Property connection, the water inlet of the radiator is connected with radiator water inlet pipe, and radiator water inlet pipe is provided with first flow sensing Device and the first water inlet pipe magnetic valve, the delivery port of the radiator is connected with radiator return pipe, and is set on radiator return pipe There is the first water outlet pipe valve, the radiator water inlet pipe connects with tie point water inlet pipe, the radiator return pipe and first Road return pipe connection, the tie point water inlet pipe and tie point return pipe are connected with the water side of water collecting and diversifying device respectively, institute The water inlet end for stating water collecting and diversifying device is connected with the first main water inlet tube and the first main water return tube, and first main water inlet tube passes through the first master The delivery port of water inlet pipe magnetic valve and boiler connects, and first main water return tube passes through the first main water return tube magnetic valve and boiler Water return outlet connects;Wherein, one group of workbench is provided with the workshop, the workbench is correspondingly provided with radiator;Wherein, dual confession Hot shop heating system also includes solar energy heating system, and the solar energy heating system includes solar panels, heat exchanger and storage Boiler, the heat storage water tank are connected with the first main water inlet tube and the first main water return tube, and the heat exchanger is connected with heat storage water tank, The heat exchanger connects with solar panels;
The method of work of the dual heat supply workshop heating system, comprises the following steps:
1)The solar panels and boiler of solar energy heating system respectively heat water;
2)Heat storage water tank and boiler provide hot water to radiator;
3)The first water inlet pipe magnetic valve, the first main water inlet tube magnetic valve and the first main water return tube magnetic valve are opened successively;
4)Radiator enters hot water, heating;
5)Controller receives the data of first flow sensor and temperature display adjusting means;
6)Temperature display adjusting means sets heating temperature, and controller adjusts the inflow of the first water inlet pipe magnetic valve;
7)The hot water of heat storage water tank and boiler is intake by the first main water inlet tube, water collecting and diversifying device, tie point water inlet pipe, radiator Pipe enters radiator;
8)Hot water from radiator return pipe, tie point return pipe, water collecting and diversifying device and the first main water return tube enter heat storage water tank or Person's boiler;
9)Heat continuous repeat step 4)-8).
The method of work of the energy-saving workshop heating system of the present invention, single radiator is provided with each workbench, Can be that workbench heats, and each radiator can be switched individually, when workbench does not work, can be stopped supplying by heating It is warm, resource is saved, while flow sensor and temperature display adjusting means are provided with each radiator, it can be adjusted flexibly every The temperature of piece radiator, so as to carry out the reasonable distribution of resource, avoid waste of resource, the solar heating of setting of the invention System, in the area that southern winter is warmer, will not in the case of bursting by freezing solar energy system, available solar energy to heating, Not only environmental protection but also saving resource, this method of work, controller can be according to the temperature adjustment hot water inflow of setting, flexible adjustment side Just, it can accurately set, while different temperature can be set according to different operating positions, adapting to multiple workbench individually makes With, two independent heating systems of solar energy and boiler, solar heating can be individually carried out, save resource, solar heating Introduce, reduce the use of boiler heating.
Further, the method for work of the dual heat supply workshop heating system, it is further comprising the steps of:
10)In heating process, when the enough workshops of heat storage water tank hot water of solar energy heating system are in use, close boiler;
11)When the workbench in workshop does not work, radiator corresponding to the workbench can be closed.
Each workbench is separately provided heating, for the workshop spread the work, can close the radiator of the workbench, so Resource can be saved, only with solar heating, both environmentally friendly and can saved resource.
Further, above-mentioned dual heat supply workshop heating system, the radiator return pipe sense provided with second flow Device.Flow sensor is set in the return pipe of radiator, the flow of return pipe can be monitored, avoids causing backwater to make more than water inlet There is no hot water in into radiator, influence to heat.
Further, above-mentioned dual heat supply workshop heating system, the boiler are provided with temperature controller.The temperature of setting The temperature that controller can adjust boiler is spent, so as to the temperature of integrally-regulated hot water, has the function that to control heating heating.
Further, above-mentioned dual heat supply workshop heating system, the second main water inlet tube and are additionally provided with the boiler Two main water return tubes.Other group of water inlet pipe and return pipe set, can be that factory provides hot water, such as hand washing sink elsewhere.
Further, above-mentioned dual heat supply workshop heating system, second main water inlet tube and the second main water return tube with Workshop hand washing sink connection.In order to further improve the working environment of shopwork employee, hot water can be provided to hand washing sink, avoided Washed one's hands with cold water, so as to greatly improve the comfort level of staff.
Further, above-mentioned dual heat supply workshop heating system, the radiator water inlet pipe are provided with automatic blow off valve valve air relief. The automatic blow off valve valve air relief of setting can be deflated automatically according to the temperature in radiator, avoid gas mistake in radiator or water pipe It is more, influence the heating effect of heating.
Further, above-mentioned dual heat supply workshop heating system, the radiator, the first main water inlet tube, first are led back Water pipe, tie point water inlet pipe, tie point return pipe, the outer surface of radiator water inlet pipe and radiator return pipe scribble anti- Rust paint.In order to ensure the attractive in appearance of radiator while prevent radiator surface from, for a long time using being corroded, being set anti-in workshop Rust paint.
Further, above-mentioned dual heat supply workshop heating system, on the solar panels, heat exchanger and heat storage water tank It is connected with water pump.The water pump of setting can enter the transmission of water-filling, ensure delivery into heating pipeline.
Above-mentioned technical proposal can be seen that the present invention and have the advantages that:Dual heat supply workshop of the present invention The method of work of heating system, automaticity is high, more enough temperature for individually adjusting radiator in real time, according to different workbench Different heating temperatures is set, most of resource can be saved, using flexible, overall heating is avoided, some areas overheat, cause whole Body workshop is uneven in temperature, influences working effect, and used method of work is easy to operate, adapts to factory floor and uses, work side Method is reasonable in design, easy to utilize.
Brief description of the drawings
Fig. 1 is the structural representation of dual heat supply workshop heating system of the present invention;
Fig. 2 is the workshop radiator layout of dual heat supply workshop heating system of the present invention.
In figure:1 radiator, 2 controllers, 3 first flow sensors, 4 first water inlet pipe magnetic valves, 5 power supplys, 6 temperature show Show adjusting means, 7 second flow sensors, 8 first water outlet pipe valves, 9 water collecting and diversifying devices, 10 first main water inlet tube magnetic valves, 11 One main water return tube magnetic valve, 12 boilers, 13 temperature controllers, 14 first main water inlet tubes, 15 first main water return tubes, 16 tie points Water inlet pipe, 17 tie point return pipes, 18 radiator water inlet pipes, 19 radiator return pipes, 20 second main water inlet tubes, 21 second masters Return pipe, 22 workshop hand washing sinks, 23 heat storage water tanks, 24 heat exchangers, 25 solar panels, 100 workshops, 200 workbench.
Embodiment
Embodiments of the invention are described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning to end Same or similar label represents same or similar element or the element with same or like function.Below with reference to attached The embodiment of figure description is exemplary, it is intended to for explaining the present invention, and is not considered as limiting the invention.
In the description of the invention, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", " on ", " under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " clockwise ", " inverse The orientation or position relationship of the instructions such as hour hands " are based on orientation shown in the drawings or position relationship, are for only for ease of description originally Invent and simplify description, rather than the device or element of instruction or hint meaning there must be specific orientation, with specific side Position construction and operation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or hint relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can be expressed or Implicitly include one or more this feature.In the description of the invention, unless otherwise indicated, " multiple " are meant that two Individual or two or more, limited unless otherwise clear and definite.
In the present invention, unless otherwise clearly defined and limited, term " installation ", " connected ", " connection ", " fixation " etc. Term should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;It can be machine Tool connects or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary, can be two members Connection inside part.For the ordinary skill in the art, above-mentioned term can be understood in this hair as the case may be Concrete meaning in bright.
In the present invention, unless otherwise clearly defined and limited, fisrt feature second feature it " on " or it " under " Can directly it be contacted including the first and second features, it is not directly to contact but pass through it that can also include the first and second features Between other characterisation contact.Moreover, fisrt feature second feature " on ", " top " and " above " to include first special Sign is directly over second feature and oblique upper, or is merely representative of fisrt feature level height and is higher than second feature.Fisrt feature exists Second feature " under ", " lower section " and " following " fisrt feature that includes are immediately below second feature and obliquely downward, or be merely representative of Fisrt feature level height is less than second feature.
Embodiment
Dual heat supply workshop heating system as shown in Figure 1, including radiator 1, controller 2, first flow sensor 3, First water inlet pipe magnetic valve 4, power supply 5, temperature display adjusting means 6, the first water outlet pipe valve 8, water collecting and diversifying device 9, the first main water inlet Pipe magnetic valve 10, the first main water return tube magnetic valve 11, boiler 12, the first main water inlet tube 14, the first main water return tube 15, tie point Water inlet pipe 16, tie point return pipe 17, radiator water inlet pipe 18, radiator return pipe 19, workshop 100 and workbench 200, institute State controller 2 to be electrically connected with the water inlet pipe magnetic valve 4 of first flow sensor 3 and first, the power supply 5 and temperature display regulation Device 6 is electrically connected with controller 2, and water inlet and the radiator water inlet pipe 18 of the radiator 1 are connected, and radiator water inlet pipe 18 are provided with the water inlet pipe magnetic valve 4 of first flow sensor 3 and first, delivery port and the radiator return pipe of the radiator 1 19 connections, and radiator return pipe 19 is provided with the first water outlet pipe valve 8, the radiator water inlet pipe 18 and tie point water inlet pipe 16 connections, the radiator return pipe 19 and tie point return pipe 17 connect, the tie point water inlet pipe 16 and first Water side of the road return pipe 17 respectively with water collecting and diversifying device 9 is connected, the water inlet end of the water collecting and diversifying device 9 and the first main water inlet tube 14 and First main water return tube 15 connects, the delivery port that first main water inlet tube 14 passes through the first main water inlet tube magnetic valve 10 and boiler 12 Connection, first main water return tube 15 are connected by the first main water return tube magnetic valve 11 with the water return outlet of boiler 12, and radiator returns Water pipe 19 is provided with second flow sensor 7;Wherein, one group of workbench 200 is provided with the workshop 100, the workbench 200 is right Radiator 1 should be provided with;In addition, wherein, dual heat supply workshop heating system also includes solar energy heating system, the solar energy supplies Heating system includes solar panels 25, heat exchanger 24 and heat storage water tank 23, the main water inlet tube 14 of heat storage water tank 23 and first and One main water return tube 15 is connected, and the heat exchanger 24 is connected with heat storage water tank 23, and the heat exchanger 24 and solar panels 25 connect, and Water pump is respectively connected with solar panels 25, heat exchanger 24 and heat storage water tank 23.The dual heating system set, in solar energy system On the premise of heating enough can be carried out, boiler 12 is closed, saves resource.Further, in order to improve shopwork environment, The second main water inlet tube 20 and the second main water return tube 21, and the second main water inlet tube 20 and the second main water return tube 21 are additionally provided with boiler 12 It is connected with workshop hand washing sink 22, when being easy to the winter staff to wash one's hands, water will not be subcooled, and cause finger frostbite.Further, institute State boiler 12 and be provided with temperature controller 13, for showing temperature of the boiler 12 altogether to hot water, be convenient for temperature control.Enter one Step, the radiator water inlet pipe 18 is provided with automatic blow off valve valve air relief, in addition, in order to keep attractive in appearance and anti-corrosion, radiator 1, first Main water inlet tube 14, the first main water return tube 15, tie point water inlet pipe 16, tie point return pipe 17, the and of radiator water inlet pipe 18 The outer surface of radiator return pipe 19 scribbles anticorrosive paint.
A kind of method of work of dual heat supply workshop heating system, it is characterised in that:Comprise the following steps:
1)The solar panels 25 and boiler 12 of solar energy heating system respectively heat water;
2)Heat storage water tank 23 and boiler 12 provide hot water to radiator 1;
3)The first water inlet pipe magnetic valve 4, the first main water inlet tube magnetic valve 10 and the first main water return tube magnetic valve 11 are opened successively;
4)Radiator 1 enters hot water, heating;
5)Controller 2 receives the data of first flow sensor 3 and temperature display adjusting means 6;
6)Temperature display adjusting means 6 sets heating temperature, and controller 2 adjusts the inflow of the first water inlet pipe magnetic valve 4;
7)The hot water of heat storage water tank 23 and boiler 12 by the first main water inlet tube 14, water collecting and diversifying device 9, tie point water inlet pipe 16, Radiator water inlet pipe 18 enters radiator 1;
8)Hot water enters heat accumulation from radiator return pipe 19, tie point return pipe 17, the main water return tube 15 of water collecting and diversifying device 9 and first Water tank 23 or boiler 12;
9)Heat continuous repeat step 4)-8).
A kind of method of work of dual heat supply workshop heating system as shown in Figure 2, it is characterised in that:Also include following step Suddenly:
10)In heating process, when the enough workshops of the hot water of heat storage water tank 23 of solar energy heating system are in use, close boiler 12;
11)When the workbench 200 in workshop 100 does not work, radiator 1 corresponding to the workbench 200 can be closed.
In the heating system of workshop, boiler 12 is combined the confession that can ensure to provide the larger workshop of area with solar energy heating system It is warm, ensure heating effect.In addition, solar heating bonded boiler heats, when the heat of solar heating is enough, it is not necessary to make With the boiler heating being connected with boiler, both environmentally friendly and can saved resource, so as to save cost, the method can flexible operating, can Boiler 12 is closed at any time.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, under the premise without departing from the principles of the invention, some improvement can also be made, these improvement also should be regarded as the present invention's Protection domain.

Claims (9)

  1. A kind of 1. method of work of dual heat supply workshop heating system, it is characterised in that:The device of the method for work includes warm Gas piece(1), controller(2), first flow sensor(3), the first water inlet pipe magnetic valve(4), power supply(5), temperature display regulation Device(6), the first water outlet pipe valve(8), water collecting and diversifying device(9), the first main water inlet tube magnetic valve(10), the first main water return tube magnetic valve (11), boiler(12), the first main water inlet tube(14), the first main water return tube(15), tie point water inlet pipe(16), tie point return Water pipe(17), radiator water inlet pipe(18), radiator return pipe(19), workshop(100)And workbench(200), the controller (2)With first flow sensor(3)With the first water inlet pipe magnetic valve(4)It is electrically connected with, the power supply(5)Adjusted with temperature display Device(6)With controller(2)It is electrically connected with, the radiator(1)Water inlet and radiator water inlet pipe(18)Connect, and heating Piece water inlet pipe(18)It is provided with first flow sensor(3)With the first water inlet pipe magnetic valve(4), the radiator(1)Water outlet Mouth and radiator return pipe(19)Connection, and radiator return pipe(19)It is provided with the first water outlet pipe valve(8), the radiator enters Water pipe(18)With tie point water inlet pipe(16)Connection, the radiator return pipe(19)With tie point return pipe(17)Even Connect, the tie point water inlet pipe(16)With tie point return pipe(17)Respectively with water collecting and diversifying device(9)Water side connection, institute State water collecting and diversifying device(9)Water inlet end and the first main water inlet tube(14)With the first main water return tube(15)Connection, the first main water inlet Pipe(14)Pass through the first main water inlet tube magnetic valve(10)With boiler(12)Delivery port connection, first main water return tube(15)It is logical Cross the first main water return tube magnetic valve(11)With boiler(12)Water return outlet connection;Wherein, the workshop(100)Inside it is provided with one group of work Make platform(200), the workbench(200)It is correspondingly provided with radiator(1);
    Wherein, dual heat supply workshop heating system also includes solar energy heating system, and the solar energy heating system includes the sun Can plate(25), heat exchanger(24)And heat storage water tank(23), the heat storage water tank(23)With the first main water inlet tube(14)With the first master Return pipe(15)Connection, the heat exchanger(24)With heat storage water tank(23)Connection, the heat exchanger(24)And solar panels(25) Connection;
    The method of work of the dual heat supply workshop heating system, comprises the following steps:
    1)The solar panels of solar energy heating system(25)And boiler(12)Water is heated respectively;
    2)Heat storage water tank(23)And boiler(12)To radiator(1)Hot water is provided;
    3)The first water inlet pipe magnetic valve is opened successively(4), the first main water inlet tube magnetic valve(10)With the first main water return tube magnetic valve (11);
    4)Radiator(1)Into hot water, heating;
    5)Controller(2)Receive first flow sensor(3)With temperature display adjusting means(6)Data;
    6)Temperature display adjusting means(6)Heating temperature, controller are set(2)Adjust the first water inlet pipe magnetic valve(4)Water inlet Amount;
    7)Heat storage water tank(23)And boiler(12)Hot water pass through the first main water inlet tube(14), water collecting and diversifying device(9), tie point enters Water pipe(16), radiator water inlet pipe(18)Into radiator(1);
    8)Hot water is from radiator return pipe(19), tie point return pipe(17), water collecting and diversifying device(9)With the first main water return tube(15) Into heat storage water tank(23)Or boiler(12);
    9)Heat continuous repeat step 4)-8).
  2. 2. the method for work of dual heat supply workshop heating system according to claim 1, it is characterised in that:Also include following Step:
    10)In heating process, when the heat storage water tank of solar energy heating system(23)The enough workshops of hot water are in use, close boiler (12);
    11)Workshop(100)Workbench(200), can be by the workbench when not working(200)Corresponding radiator(1)Close.
  3. 3. dual heat supply workshop heating system according to claim 1, it is characterised in that:The radiator return pipe(19) Provided with second flow sensor(7).
  4. 4. dual heat supply workshop heating system according to claim 1, it is characterised in that:The boiler(12)It is provided with temperature Spend controller(13).
  5. 5. dual heat supply workshop heating system according to claim 3, it is characterised in that:The boiler(12)On be additionally provided with Second main water inlet tube(20)With the second main water return tube(21).
  6. 6. dual heat supply workshop heating system according to claim 1, it is characterised in that:Second main water inlet tube(20) With the second main water return tube(21)With workshop hand washing sink(22)Connection.
  7. 7. dual heat supply workshop heating system according to claim 1, it is characterised in that:The radiator water inlet pipe(18) It is provided with automatic blow off valve valve air relief.
  8. 8. dual heat supply workshop heating system according to claim 6, it is characterised in that:The radiator(1), first master Water inlet pipe(14), the first main water return tube(15), tie point water inlet pipe(16), tie point return pipe(17), radiator water inlet Pipe(18)With radiator return pipe(19)Outer surface scribble anticorrosive paint.
  9. 9. dual heat supply workshop heating system according to claim 1, it is characterised in that:The solar panels(25), change Hot device(24)And heat storage water tank(23)On be respectively connected with water pump.
CN201710869136.XA 2017-09-22 2017-09-22 A kind of method of work of dual heat supply workshop heating system Pending CN107575926A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710869136.XA CN107575926A (en) 2017-09-22 2017-09-22 A kind of method of work of dual heat supply workshop heating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710869136.XA CN107575926A (en) 2017-09-22 2017-09-22 A kind of method of work of dual heat supply workshop heating system

Publications (1)

Publication Number Publication Date
CN107575926A true CN107575926A (en) 2018-01-12

Family

ID=61039749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710869136.XA Pending CN107575926A (en) 2017-09-22 2017-09-22 A kind of method of work of dual heat supply workshop heating system

Country Status (1)

Country Link
CN (1) CN107575926A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019095194A1 (en) * 2017-11-16 2019-05-23 苏州三一冷暖工程有限公司 Adjustable heating system for double heating workshop

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201126208Y (en) * 2007-10-10 2008-10-01 戴民 Solar energy radiator
CN201836987U (en) * 2010-10-23 2011-05-18 徐德钦 Automatic controller for heating equipment
CN103256654A (en) * 2013-04-18 2013-08-21 北京三能达科技有限公司 Heating radiator set
CN104864448A (en) * 2015-05-29 2015-08-26 河南中烟工业有限责任公司 Energy-saving hot water supply system
CN106582918A (en) * 2017-02-20 2017-04-26 成都科创谷科技有限公司 Multifunctional worktable

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201126208Y (en) * 2007-10-10 2008-10-01 戴民 Solar energy radiator
CN201836987U (en) * 2010-10-23 2011-05-18 徐德钦 Automatic controller for heating equipment
CN103256654A (en) * 2013-04-18 2013-08-21 北京三能达科技有限公司 Heating radiator set
CN104864448A (en) * 2015-05-29 2015-08-26 河南中烟工业有限责任公司 Energy-saving hot water supply system
CN106582918A (en) * 2017-02-20 2017-04-26 成都科创谷科技有限公司 Multifunctional worktable

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019095194A1 (en) * 2017-11-16 2019-05-23 苏州三一冷暖工程有限公司 Adjustable heating system for double heating workshop

Similar Documents

Publication Publication Date Title
CN205573836U (en) Car as a house energy -saving equipment
CN204043939U (en) Ptc heater test board
CN107477645A (en) A kind of adjustable dual heat supply workshop heating system
CN205593408U (en) Car as a house water heater
CN107575926A (en) A kind of method of work of dual heat supply workshop heating system
CN107477648A (en) A kind of method of work for the heating system that can carry out wireless monitor in real time
CN107504546A (en) A kind of workshop heating system that can carry out wireless monitor
CN2826234Y (en) Improved solar hot-water supply device
CN207231806U (en) Solar energy ground-source heat pump system analogue test platform
CN206724288U (en) Electric accumulation of heat intelligent warming device
CN111365747A (en) Multi-energy complementary heating system and heating method
CN206001687U (en) A kind of heat storage electric boiler system
CN101915437A (en) Hydro-thermal recovery system in shower
CN106091476B (en) The association system of closed-loop ground source heat pump and electric hot water storage tank
CN107559925A (en) A kind of energy-saving workshop heating system and its method of work
CN209386397U (en) A kind of graphene electric heating system based on solar energy auxiliary heating
WO2019095194A1 (en) Adjustable heating system for double heating workshop
CN208936561U (en) Additional hot water storage tank formula solid heat storage electric heating system
CN209229837U (en) A kind of low temperature double stage heat pump unit
CN206944443U (en) Water heater
KR20120092238A (en) Heating system of the boiler which economizes an energy
CN207162688U (en) A kind of boiler heating system
CN207317290U (en) A kind of intelligence heat reservoir
CN204535154U (en) Solar energy integrated optimization hot-water heating system
CN203797759U (en) Low-temperature hot-water floor radiation warming system by air energy and solar energy integrated energy source

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180112