CN107563591A - A kind of regional distribution network based on unit style builds priority computational methods - Google Patents

A kind of regional distribution network based on unit style builds priority computational methods Download PDF

Info

Publication number
CN107563591A
CN107563591A CN201710635836.2A CN201710635836A CN107563591A CN 107563591 A CN107563591 A CN 107563591A CN 201710635836 A CN201710635836 A CN 201710635836A CN 107563591 A CN107563591 A CN 107563591A
Authority
CN
China
Prior art keywords
power supply
supply unit
distribution network
unit
regional distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710635836.2A
Other languages
Chinese (zh)
Inventor
王建春
叶雪峰
刘刚
徐子鲲
王轩
赵哲源
张飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
HuaiAn Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
HuaiAn Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, HuaiAn Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710635836.2A priority Critical patent/CN107563591A/en
Publication of CN107563591A publication Critical patent/CN107563591A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of regional distribution network based on unit style to build priority computational methods, comprises the following steps:Step 1: regional distribution network to be built is divided into several power supply units;Step 2: the significant coefficient index system and construction demand coefficient index system of power supply unit are built respectively;Step 3: significant coefficient index weights and construction demand coefficient index weights using AHP analytic hierarchy process (AHP)s, respectively determination power supply unit;Utilize the significant coefficient index score and construction demand coefficient index score of membership function, respectively calculating power supply unit;Step 4: significant coefficient I and construction demand coefficient D according to respective index weights and index score, respectively calculating power supply unit;Step 5: the construction priority factor P of power supply unit is calculated according to below equation.Combining unit prcgramming ideas of the present invention, using unit as object, the evaluation system of a set of power supply unit is established, the priority of quantitative analysis unit, substantially increases power distribution network precision construction investment level.

Description

A kind of regional distribution network based on unit style builds priority computational methods
Technical field
The present invention relates to distribution network construction technical field, and in particular to a kind of regional distribution network based on unit style is built excellent First level computational methods.
Background technology
At present, distribution network construction investment carries out Investment Allocation by the way of plate is divided, and lacks the foundation of science, easily makes Into investment waste.Develop new situations in face of power distribution network, it is necessary to power distribution network investment is optimized, to improve the warp of power grid enterprises Ji benefit.
The content of the invention
The invention discloses a kind of regional distribution network based on unit style to build priority computational methods, can be that power network is looked forward to The distribution network construction of industry provides the foundation of science, improves the economic benefit of power grid enterprises.
The present invention is achieved through the following technical solutions:
A kind of regional distribution network based on unit style builds priority computational methods, comprises the following steps:
Step 1: regional distribution network to be built is divided into several power supply units;
Step 2: the significant coefficient index system and construction demand coefficient index system of power supply unit are built respectively;
Step 3: significant coefficient index weights and construction demand coefficient using AHP analytic hierarchy process (AHP)s, respectively determination power supply unit Index weights;Utilize the significant coefficient index score and construction demand coefficient index of membership function, respectively calculating power supply unit Score;
Step 4: significant coefficient I and construction demand according to respective index weights and index score, respectively calculating power supply unit Coefficient D;
Step 5: the construction priority factor P of power supply unit is calculated according to below equation:
P=α × D+ β × I,
Alpha+beta=1,
Wherein, α is the destination layer weight of construction demand coefficient, and β is the destination layer weight of significant coefficient.
The further scheme of the present invention is that step 1 is advised in detail according to region and distant view yearly peak load result, specifies power transformation Stand supply district, target net, regional distribution network to be built is divided into several power supply units by reference unit division principle.
The further scheme of the present invention is that the dividing elements principle includes:
A. each power supply unit at least has two power supply points, and power supply point is nearest from power supply unit;
B. demarcate along Regional Road Network or planned road network or naturally and divided;
C. circuit returns number less than or equal to 12 times in power supply unit.
Step 1 is by after the regional distribution network built is divided into several power supply units, according to phase also in power supply unit The power supply quality demand answered builds target net form, and the rule of middle transition year and recent rack are carried out according to target net Draw, draw the project table in units of group.
The further scheme of the present invention is that power supply unit significant coefficient index system covers social influence and warp in step 2 Help two datum layers of benefit, and wherein social influence includes three load density, unit area number of users and responsible consumer ratio fingers Layer is marked, economic benefit includes delivery and average electricity price level two indices layer.
The further scheme of the present invention is that power supply unit construction demand coefficient index system covers power network power supply in step 2 Four quality, technical equipment, operation level and power supply safety datum layers;The grid supply quality includes power supply reliability and electricity Qualification rate two indices layer is pressed, technical equipment, which includes, matches somebody with somebody from coverage rate, cable rate, insulation rate and old equipment ratio four Indicator layer, operation level includes circuit Rate of average load, circuit overloads ratio again and circuit three fingers of average attaching capacity of distribution transform Layer is marked, power supply safety includes one indicator layer of circuit " N-1 " percent of pass.
The further scheme of the present invention is that the index weights of step 3 and step 4 include datum layer weight and indicator layer is weighed Weight.
The present invention compared with prior art the advantages of be:
First, combining unit prcgramming ideas, using unit as object, the evaluation system of a set of power supply unit, quantitative analysis list are established The priority of member, substantially increase power distribution network precision construction investment level;
2nd, districts and cities are applicable, the unit of county's company power distribution mesh mark space truss project preferably distributes with construction;On the one hand to this area The significance level of each unit, construction demand are evaluated, and ginseng is provided for this area electric company distribution network construction, Investment Allocation Examine, the scientific and reasonable arrangement distribution network construction project in the case of limited investment amount, avoid the blindness of distribution network construction Investment, guide the high-quality fast development of power distribution network;On the other hand, the closed loop management flow of distribution network planning work is improved, by local area The strategic objective that domain electric company builds " intelligence, efficiently, reliable, green, economic " power network is decomposed and quantified to tangible micro- Index is seen, so as to improve the development level of this area power distribution network, realizes that the construction of power distribution network is changed from extensive style to intensive style, Corporate economy's benefit is improved under the requirement of new electric reshaping gesture.
Brief description of the drawings
Fig. 1 is the flow chart that power supply unit is divided in the present invention.
Fig. 2 is the significant coefficient index system figure of power supply unit in the present invention.
Fig. 3 is the construction demand coefficient index system figure of power supply unit in the present invention.
Embodiment
A kind of regional distribution network based on unit style builds priority computational methods, comprises the following steps:
Step 1: as shown in figure 1, advised in detail according to region and distant view yearly peak load result, transformer station's supply district, target are specified Rack, regional distribution network to be built is divided into several power supply units by reference unit division principle, then in power supply unit Target net form is built according to corresponding power supply quality demand, middle transition year and recent rack are carried out according to target net Planning, draw the project table in units of group;The dividing elements principle includes:
A. each power supply unit at least has two power supply points, and power supply point is nearest from power supply unit;
B. demarcate along Regional Road Network or planned road network or naturally and divided;
C. circuit returns number less than or equal to 12 times in power supply unit.
Step 2: the significant coefficient index system of power supply unit as shown in Figure 2 and construction as shown in Figure 3 are built respectively Service demand factor index system;
Power supply unit significant coefficient index system covers two datum layers of social influence and economic benefit, and wherein social influence includes Three load density, unit area number of users and responsible consumer ratio indicator layers, economic benefit include delivery and average electricity price Horizontal two indices layer;
Power supply unit construction demand coefficient index system covers grid supply quality, technical equipment, operation level and power supply safety Four datum layers;The grid supply quality includes power supply reliability and rate of qualified voltage two indices layer, technical equipment include With from coverage rate, cable rate, insulation four indicator layers of rate and old equipment ratio, operation level includes circuit average load Rate, circuit overload ratio and average attaching three indicator layers of capacity of distribution transform of circuit again, and power supply safety includes circuit " N-1 " percent of pass One indicator layer.
Step 3: significant coefficient index weights and construction demand using AHP analytic hierarchy process (AHP)s, respectively determination power supply unit Coefficient index weights, index weights include datum layer weight and indicator layer weight;
The significant coefficient index weights of certain power supply unit are:
The construction demand coefficient index weights of the power supply unit are:
Membership function is recycled, the significant coefficient index score of power supply unit is calculated respectively and construction demand coefficient index obtains Point;
The significant coefficient index of the power supply unit is scored at:
Illustrate index scoring process by taking load density as an example:
It is fitted using the linear membership function of trapezoidal profile, it is first determined the bound of index, i.e.,:Degree of membership threshold values, provides phase Parameter is answered, such as:
Load density(MW/km²) 0 0.1 1 6 15
Score 0 20 40 80 100
Determine that the linear membership function formula of trapezoidal profile is further according to parameter:
,
Wherein f is score, and x is load density target;
When the load density of the power supply unit is 11.4MW/km2When, it is 92 points that corresponding scoring, which can be calculated,.
The construction demand coefficient index of the power supply unit is scored at:
Step 4: significant coefficient I and construction demand according to respective index weights and index score, respectively calculating power supply unit Coefficient D;
The significant coefficient I of the power supply unit of the present embodiment is:
0.5*(0.24*92+0.17*83+0.19*80)+0.5*(0.28*87+0.12*84)=36.415;
Construction demand coefficient D is:
0.2*(0.5*85+0.5*96)+0.3*(0.3*97+0.15*82+0.25*80+0.3*77)+0.3*(0.35*84+0.4* 73+0.25*81)+0.2*79=82.905;
Step 5: the construction priority factor P of power supply unit is calculated according to below equation:
P=α × D+ β × I,
Alpha+beta=1,
Wherein, α is the destination layer weight of construction demand coefficient, and β is the destination layer weight of significant coefficient, and α, β value are by expertise Given, between α values preferably take 0.2 ~ 0.3, β value is preferably taken between 0.7 ~ 0.8.

Claims (7)

1. a kind of regional distribution network based on unit style builds priority computational methods, it is characterised in that comprises the following steps:
Step 1: regional distribution network to be built is divided into several power supply units;
Step 2: the significant coefficient index system and construction demand coefficient index system of power supply unit are built respectively;
Step 3: significant coefficient index weights and construction demand coefficient using AHP analytic hierarchy process (AHP)s, respectively determination power supply unit Index weights;Utilize the significant coefficient index score and construction demand coefficient index of membership function, respectively calculating power supply unit Score;
Step 4: significant coefficient I and construction demand according to respective index weights and index score, respectively calculating power supply unit Coefficient D;
Step 5: the construction priority factor P of power supply unit is calculated according to below equation:
P=α × D+ β × I,
Alpha+beta=1,
Wherein, α is the destination layer weight of construction demand coefficient, and β is the destination layer weight of significant coefficient.
2. a kind of regional distribution network based on unit style as claimed in claim 1 builds priority computational methods, its feature exists In:Step 1 is advised in detail according to region and distant view yearly peak load result, specifies transformer station's supply district, target net, with reference to single Regional distribution network to be built is divided into several power supply units by first division principle.
3. a kind of regional distribution network based on unit style as claimed in claim 2 builds priority computational methods, its feature exists In:The dividing elements principle includes:
A. each power supply unit at least has two power supply points, and power supply point is nearest from power supply unit;
B. demarcate along Regional Road Network or planned road network or naturally and divided;
C. circuit returns number less than or equal to 12 times in power supply unit.
4. a kind of regional distribution network based on unit style as claimed in claim 1 or 2 builds priority computational methods, its feature It is:Step 1 is by after the regional distribution network built is divided into several power supply units, and foundation is corresponding also in power supply unit Power supply quality demand build target net form, the planning of middle transition year and recent rack is carried out according to target net, Draw the project table in units of group.
5. a kind of regional distribution network based on unit style as claimed in claim 1 builds priority computational methods, its feature exists In:Power supply unit significant coefficient index system covers two datum layers of social influence and economic benefit in step 2, wherein society Influence comprising load density, three indicator layers of unit area number of users and responsible consumer ratio, economic benefit include delivery and The horizontal two indices layer of average electricity price.
6. a kind of regional distribution network based on unit style as claimed in claim 1 builds priority computational methods, its feature exists In:Power supply unit construction demand coefficient index system covers grid supply quality, technical equipment, operation level and confession in step 2 Four datum layers of electric safety;The grid supply quality includes power supply reliability and rate of qualified voltage two indices layer, technology dress It is standby comprising with being put down from coverage rate, cable rate, insulation four indicator layers of rate and old equipment ratio, operation level comprising circuit Equal load factor, circuit overload ratio and average attaching three indicator layers of capacity of distribution transform of circuit again, and power supply safety includes circuit " N-1 " One indicator layer of percent of pass.
7. a kind of regional distribution network based on unit style as claimed in claim 1 builds priority computational methods, its feature exists In:The index weights of step 3 and step 4 include datum layer weight and indicator layer weight.
CN201710635836.2A 2017-07-31 2017-07-31 A kind of regional distribution network based on unit style builds priority computational methods Withdrawn CN107563591A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710635836.2A CN107563591A (en) 2017-07-31 2017-07-31 A kind of regional distribution network based on unit style builds priority computational methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710635836.2A CN107563591A (en) 2017-07-31 2017-07-31 A kind of regional distribution network based on unit style builds priority computational methods

Publications (1)

Publication Number Publication Date
CN107563591A true CN107563591A (en) 2018-01-09

Family

ID=60974126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710635836.2A Withdrawn CN107563591A (en) 2017-07-31 2017-07-31 A kind of regional distribution network based on unit style builds priority computational methods

Country Status (1)

Country Link
CN (1) CN107563591A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108694527A (en) * 2018-08-09 2018-10-23 河海大学常州校区 A kind of power distribution network evaluation method
CN109711750A (en) * 2019-01-09 2019-05-03 国网宁夏电力有限公司 A kind of power grid investment benefit Whole Process Simulation method and system
CN111724025A (en) * 2020-04-26 2020-09-29 国网福建省电力有限公司 High-voltage distribution network frame planning method based on power supply unit optimized division

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930482A (en) * 2012-11-30 2013-02-13 河北省电力公司电力科学研究院 Investment effect evaluation method for county power distribution networks
CN105303259A (en) * 2015-11-06 2016-02-03 国网上海市电力公司 Gridding concept based power distribution network planning management method
CN105335810A (en) * 2015-06-12 2016-02-17 国家电网公司 Method for evaluating investment benefits of power distribution network individual projects
CN106503919A (en) * 2016-11-03 2017-03-15 国家电网公司 A kind of power distribution network evaluation methodology based on power supply zone characteristic

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930482A (en) * 2012-11-30 2013-02-13 河北省电力公司电力科学研究院 Investment effect evaluation method for county power distribution networks
CN105335810A (en) * 2015-06-12 2016-02-17 国家电网公司 Method for evaluating investment benefits of power distribution network individual projects
CN105303259A (en) * 2015-11-06 2016-02-03 国网上海市电力公司 Gridding concept based power distribution network planning management method
CN106503919A (en) * 2016-11-03 2017-03-15 国家电网公司 A kind of power distribution network evaluation methodology based on power supply zone characteristic

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108694527A (en) * 2018-08-09 2018-10-23 河海大学常州校区 A kind of power distribution network evaluation method
CN108694527B (en) * 2018-08-09 2021-07-13 河海大学常州校区 Power distribution network evaluation method
CN109711750A (en) * 2019-01-09 2019-05-03 国网宁夏电力有限公司 A kind of power grid investment benefit Whole Process Simulation method and system
CN111724025A (en) * 2020-04-26 2020-09-29 国网福建省电力有限公司 High-voltage distribution network frame planning method based on power supply unit optimized division

Similar Documents

Publication Publication Date Title
CN108122068A (en) A kind of power distribution network risk-averse retailer method and system
CN103514570B (en) A kind of power distribution network Expansion Planning comprehensive optimization method containing distributed power source
CN107038530A (en) A kind of power distribution network overall planning method and system
CN102609792B (en) A kind of extra-high voltage alternating current-direct current power transmission mode is suitable for system of selection and device thereof
CN105761161A (en) AC and DC power distribution network power supply mode evaluation method
CN105375461B (en) Active distribution network power supply capacity real time evaluating method based on Predicting Technique
CN101930491A (en) Method for comprehensively evaluating measures for limiting short-circuit current
CN109598377B (en) AC/DC hybrid power distribution network robust planning method based on fault constraint
CN108985602B (en) Power grid classification project input and output evaluation method and system considering risks
CN103093391A (en) City power distribution network arranging method
CN107563591A (en) A kind of regional distribution network based on unit style builds priority computational methods
CN104699959A (en) Similar line-loss division method based on K-MEANS algorithm
Huanna et al. Flexible‐regulation resources planning for distribution networks with a high penetration of renewable energy
Wang et al. Unified strategy for electric vehicles participate in voltage and frequency regulation with active power in city grid
Moradi-Sepahvand et al. Coordinated expansion planning of transmission and distribution systems integrated with smart grid technologies
Yi et al. Optimal co-planning of ESSs and line reinforcement considering the dispatchability of active distribution networks
CN110808600B (en) Method and system for calculating access battery energy storage station in transformer substation
CN103020729A (en) Comprehensive evaluation method for short-circuit current limitation of Gansu power grid
CN105244874B (en) A kind of meter and failure risk and the power distribution network Optimal reactive power model of cost
CN108665133A (en) A kind of construction method and system of distribution system operational efficiency evaluation model
CN113610359A (en) Photovoltaic access power distribution network adaptability evaluation method based on quantitative hierarchical index system
Abapour et al. Maximizing penetration level of distributed generations in active distribution networks
Li et al. Determination of optimal opening scheme for electromagnetic loop networks based on fuzzy analytic hierarchy process
CN102315646A (en) Maximum power capability based power distribution network communication validity and communication simplifying method
CN105701735A (en) Loss reduction potential estimation method and device for power distribution network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180109