A kind of cooling system emergency failure recovery method of large size based on Local cooling equipment
Technical field
It is exactly a kind of based on the big of Local cooling equipment the present invention relates to a kind of cooling system failure countermeasure
Type cooling system is met an urgent need failure recovery method.
Background technology
At present in daily production and living, large-scale cooling system has extremely wide application, and makes to meet
With needs, current large-scale cooling system is often made of more integrated distributions or the synchronous operation of the cooling equipment of discrete distribution
, due to the factors such as equipment operating environment difference and equipment oneself factor difference, more coolings for constituting large-scale cooling system are set
One or several is often occurred in which in standby because failure is unable to operate normally or needs to reduce operation Power operation, therefore final
The operation stability for resulting in large-scale cooling system is severely impacted, simultaneously because the volume of each cooling equipment is larger, and
Cost is also relatively high, causes to cause in actual use large-scale cooling system often without corresponding failure stand-by equipment, because
This is caused currently after going out first equipment fault in large-scale cooling system, and there are larger scarce for refrigerating capacity when large size cooling system operation
Mouthful, and the other effective replies of object and remedial measure, and with the development and popularization of local cooling system technology, since part is cold
But running efficiency of system is high, and compact is flexible and convenient to use, therefore using local cooling system to large-scale cooling system failure
Urgent remedy is possibly realized, but still lacks in practical operation and effectively carried out to large-scale cooling system using Local cooling equipment
The specific implementation method remedied, therefore the promotion and application of this technology are seriously limited, for this present situation, there is an urgent need to open
The cooling system emergency failure recovery method of large size for sending out a kind of based on Local cooling equipment, to meet the need that actual production uses
It wants.
Invention content
A kind of large-scale cooling system based on Local cooling equipment is provided the object of the present invention is to provide the utility model to answer
Anxious failure recovery method.
In order to achieve the above object, the present invention provides the following technical solutions:
A kind of cooling system emergency failure recovery method of large size based on Local cooling equipment, includes the following steps:
The first step determines cooling system failure source and influence, former to the failure of the large-scale cooling system to break down first
Because being analyzed, at the same calculate the system failure it is out of service after caused by whole cooling system refrigerating capacity vacancy value;
Second step, Preliminary design remedy solutions for refrigeration, and the relevant information obtained according to the first step is tentatively selected for mending
The installation site for the partial cooling equipment rescued, the mode of operation power and the whole cooling system of access and position;
Third walks, and the operation of Local cooling equipment according to the calculated value of the first step, and combines the scheme specified by second step,
The installation positioning of Local cooling equipment is carried out first, and Local cooling equipment is connected to whole cooling system then, is finally started
Partial cooling equipment brings into operation, and gradually replaces the large-scale cooling system to break down, while the large size to break down is cooling
System-down is overhauled online;
4th step, fault recovery start the cooling system first after complete paired fault cools down maintenance of equipment or replaces,
And make its normal operation, it is then shut off Local cooling equipment, and disconnect the connection of Local cooling equipment and whole cooling system, most
Local cooling equipment is recycled afterwards.
5th step, equipment maintenance carry out whole maintenance to Local cooling equipment of the 4th step after operation and recycling, and
Repair and replacement are carried out to its vulnerable part and close to fault extreme parts, in case running again.
Further, it in the first step, when large-scale cooling system is because of failure partial loss of function, but remains to reduce work(
When rate is run, then still with cooling system situation out of service calculate and as second step when calculating refrigerating capacity vacancy value
The foundation of work, while cooling system refrigerating capacity missing values caused by failure loss of function part need to be separately calculated, and with this
Calculated value instructs the foundation of Local cooling equipment operation power as third step.
Further, in the 4th step, when carrying out fault recovery, the cooling system operation refrigeration of large size after repair
It is 1 to measure output power amplification and Local cooling equipment downtime refrigerating capacity amount of decrease ratio:1—5:1.
Operating method of the present invention is simple and practicable, versatility and highly practical, the effective specification large size cooling system of one side
On the other hand the quick means to save the situation of equipment fault efficiently can easily realize the exclusion to cooling system failure and remedy, have
Help improve the operation stability and reliability under cooling system is nonserviceabled.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
Obtain other attached drawings according to these attached drawings.
Fig. 1 is present invention specific implementation flow chart.
Specific implementation mode
Technical scheme of the present invention is clearly and completely described below in conjunction with the attached drawing of the present invention, it is clear that retouched
The embodiment stated is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, originally
The every other embodiment that field those of ordinary skill is obtained without creative efforts, belongs to the present invention
The range of protection.
A kind of cooling system emergency failure recovery method of large size based on Local cooling equipment as shown in Figure 1, including such as
Lower step:
The first step determines cooling system failure source and influence, former to the failure of the large-scale cooling system to break down first
Because being analyzed, at the same calculate the system failure it is out of service after caused by whole cooling system refrigerating capacity vacancy value;
Second step, Preliminary design remedy solutions for refrigeration, and the relevant information obtained according to the first step is tentatively selected for mending
The installation site for the partial cooling equipment rescued, the mode of operation power and the whole cooling system of access and position;
Third walks, and the operation of Local cooling equipment according to the calculated value of the first step, and combines the scheme specified by second step,
The installation positioning of Local cooling equipment is carried out first, and Local cooling equipment is connected to whole cooling system then, is finally started
Partial cooling equipment brings into operation, and gradually replaces the large-scale cooling system to break down, while the large size to break down is cooling
System-down is overhauled online;
4th step, fault recovery start the cooling system first after complete paired fault cools down maintenance of equipment or replaces,
And make its normal operation, it is then shut off Local cooling equipment, and disconnect the connection of Local cooling equipment and whole cooling system, most
Local cooling equipment is recycled afterwards.
5th step, equipment maintenance carry out whole maintenance to Local cooling equipment of the 4th step after operation and recycling, and
Repair and replacement are carried out to its vulnerable part and close to fault extreme parts, in case running again.
In the present embodiment, in the first step, when large-scale cooling system is because of failure partial loss of function, but remain to reduce
When Power operation, then still with cooling system situation out of service calculate and as second when calculating refrigerating capacity vacancy value
The foundation of work is walked, while need to separately calculate cooling system refrigerating capacity missing values caused by failure loss of function part, and with
This calculated value instructs the foundation of Local cooling equipment operation power as third step.
In the present embodiment, in the 4th step, when carrying out fault recovery, the cooling system operation system of large size after repair
Cold output power amplification and Local cooling equipment downtime refrigerating capacity amount of decrease ratio are 1:1—5:1.
Operating method of the present invention is simple and practicable, versatility and highly practical, the effective specification large size cooling system of one side
On the other hand the quick means to save the situation of equipment fault efficiently can easily realize the exclusion to cooling system failure and remedy, have
Help improve the operation stability and reliability under cooling system is nonserviceabled.
Operating method of the present invention is simple and practicable, versatility and highly practical, on the one hand can efficiently and effectively carry out and promptly send
On the other hand wind operation can targetedly be adjusted the air themperature of air-supply, humidity and gas ingredients, reach in time,
Purpose that is efficient and accurately carrying out emergency ventilation, to provide necessary support and side for personnel rescuing and dangerous situation exclusion etc.
It helps, and helps to improve the efficiency of rescue work.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any
Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain
Lid is within protection scope of the present invention.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.