CN107553419A - One kind building monitoring mark installation auxiliary bore hole device - Google Patents

One kind building monitoring mark installation auxiliary bore hole device Download PDF

Info

Publication number
CN107553419A
CN107553419A CN201710895610.6A CN201710895610A CN107553419A CN 107553419 A CN107553419 A CN 107553419A CN 201710895610 A CN201710895610 A CN 201710895610A CN 107553419 A CN107553419 A CN 107553419A
Authority
CN
China
Prior art keywords
rotating shaft
car body
gear
bore hole
slide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710895610.6A
Other languages
Chinese (zh)
Inventor
易宇情
陈思蓉
杨周
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710895610.6A priority Critical patent/CN107553419A/en
Publication of CN107553419A publication Critical patent/CN107553419A/en
Pending legal-status Critical Current

Links

Landscapes

  • Processing Of Stones Or Stones Resemblance Materials (AREA)

Abstract

The present invention relates to building monitoring field, more particularly to a kind of building monitoring mark installation auxiliary bore hole device.The technical problem to be solved in the present invention is to provide one kind to build monitoring mark installation auxiliary bore hole device.In order to solve the above-mentioned technical problem, the invention provides such a building monitoring mark installation auxiliary bore hole device, wheel, car body, slide rail etc. are included;The bottom of car body is provided with wheel, and the top right-hand member of car body is provided with pushing hands, and the top left of car body is provided with slide rail, the top of slide rail is provided with sliding block, and the top of sliding block is provided with installing frame, drive mechanism is provided with installing frame, the left end of drive mechanism is connected with drill bit, and the top right side of car body is provided with pushing mechanism.Invention achieves convenient drilling and the effect of airborne dust can be reduced, device can make dust pass through the absorption and filtering for the treatment of fluid, and last clean air is discharged by escape pipe, and can expand the scope of dust absorbing, the efficiency absorbed is improved, and then improves the environmentally friendly degree of device.

Description

One kind building monitoring mark installation auxiliary bore hole device
Technical field
The present invention relates to building monitoring field, more particularly to a kind of building monitoring mark installation auxiliary bore hole device.
Background technology
Building mark is the mark that worker is used for showing a certain features in construction site.It is with simple, notable, easy knowledge Other image, figure or letter symbol are visual language, except represent what, instead of what in addition to, also with expression and significance, emotion With instruction action etc. effect.
Monitoring processing for building, generally artificially installation monitoring indicates on building wall, generally requires in a pre-installation Drilled on building wall, and current drilling is generally accomplished manually, and is extremely wasted time and energy, and can be kicked up in drilling Dust, air is not only polluted, also staff's health is impacted, therefore needed a kind of convenient drilling of research and development badly and can reduce The building monitoring mark installation auxiliary bore hole device of airborne dust.
The content of the invention
(1)Technical problems to be solved
In order to overcome the monitoring for building to handle, generally artificially installation monitoring indicates the present invention on building wall, is installing Before generally require and drilled on building wall, and current drilling is generally accomplished manually, and is extremely wasted time and energy, and boring Kong Shihui kicks up dust, not only pollutes air, the shortcomings that also being impacted to staff's health, the invention solves technology Problem is to provide a kind of building monitoring mark installation auxiliary bore hole device.
(2)Technical scheme
In order to solve the above-mentioned technical problem, the invention provides such a building monitoring mark installation auxiliary bore hole device, bag Wheel, car body, slide rail, sliding block, pushing hands, pushing mechanism, drive mechanism, installing frame and drill bit are included, the bottom of car body is provided with car Wheel, the top right-hand member of car body are provided with pushing hands, and the top left of car body is provided with slide rail, and the top of slide rail is provided with sliding block, the top of sliding block Portion is provided with installing frame, is provided with drive mechanism in installing frame, the left end of drive mechanism is connected with drill bit, and the top right side of car body is provided with Pushing mechanism, pushing mechanism are connected with installing frame right wall, and car body is hollow structure.
Preferably, pushing mechanism includes gear, upper rack, lower rack, lower gear, vertical rotating shaft and the first motor, The first motor is installed on the right side of car body top, vertical rotating shaft is connected with the top of the first motor, vertical rotating shaft is provided with gear And lower gear, gear are located at the top of lower gear, installing frame right wall front end is respectively equipped with upper rack and lower rack in both sides up and down, Upper rack and lower rack are respectively arranged on the rear of gear and lower gear, and gear engages with upper rack, lower gear and lower rack Engagement.
Preferably, drive mechanism includes first bearing seat, first rotating shaft, the first belt pulley, flat belt, the second belt Wheel, the second rotating shaft and the second motor, both sides are separately installed with first bearing seat and the second motor to installing frame inner right wall up and down, and second The second rotating shaft is connected with the left of motor, the left end of the second rotating shaft is provided with the first belt pulley, and is provided with first bearing seat One rotating shaft, the first belt pulley is installed in first rotating shaft, flat belt, installing frame are wound between the first belt pulley and the second belt pulley Perforation is provided with the upside of left wall, first rotating shaft is connected through perforation, the left end of first rotating shaft with drill bit.
Preferably, ash-sucking cover, hard tube, air pump, 7 shape pipes, treatment box and escape pipe are also included, car body inner bottom part is provided with place Case is managed, right-hand member is connected with escape pipe at the top for the treatment of box, and air pump is provided with the left of car body inner top, 7 shape pipes are connected with the right side of air pump, 7 shape pipes are stretched in treatment box, hard tube are connected with the left of air pump, hard tube is through car body top left side, and hard tube is before slide rail Side, ash-sucking cover is connected with the top of hard tube, ash-sucking cover is located at the front lower place of drill bit.
Preferably, the first installing plate and the second installing plate are also included, the right-hand member of drill bit is provided with the first installing plate, the first peace Bilateral type is provided with the first mounting hole to loading board up and down, and the left end of first rotating shaft is provided with the second installing plate, on the second installing plate Lower bilateral type is provided with the second mounting hole, and the first mounting hole is corresponding with the second mounting hole.
Preferably, first bevel gear, second bevel gear, horizontal rotating shaft, cam, elastic component, guide plate, second are also included Bearing block, support plate, flexible pipe, pilot hole, elevating lever and contact projection, first bevel gear, the first cone tooth are installed in vertical rotating shaft Wheel is located between gear and lower gear, and support plate is provided with the left of car body top, and support plate is located at the front side of slide rail, the top peace of support plate Equipped with second bearing seat, horizontal rotating shaft being installed in second bearing seat, the right-hand member of horizontal rotating shaft is provided with second bevel gear, and second Bevel gear engages with first bevel gear, and the left end of horizontal rotating shaft is provided with cam, and the top of second bearing seat is provided with guide plate, led Pilot hole is provided with to plate, elastic component is connected with left and right sides of the top of guide plate, the top and ash-sucking cover bottom of elastic component are left Right both sides are connected, and elevating lever is provided among ash-sucking cover bottom, and elevating lever passes through pilot hole, and it is convex that elevating lever bottom is provided with contact Rise, contact projection coordinates with cam contact, and flexible pipe is communicated between hard tube top on the left of ash-sucking cover.
Preferably, object storage mechanism is also included, right side is provided with object storage mechanism in car body, and object storage mechanism includes handle, storage Thing frame, roller and mounting groove, car body right side are provided with opening, and right side is provided with mounting groove, the mounting groove inner bottom part left and right sides in car body Neck is provided with, storage is placed with mounting groove, the bottom of storage is provided with roller, and roller is corresponding with neck, the right side of storage Wall is provided with handle.
Operation principle:When worker need will building mark be arranged on it is architectural before, the present apparatus is pushed into properly by worker first Position, then starts pushing mechanism and drive mechanism is started working, and pushing mechanism drives drill bit movement, and drive mechanism drives drill bit Rotate, drill bit is rotated while going deep into building wall, and after the completion of drilling, drill bit sets back, and worker closes pushing mechanism And drive mechanism, you can carry out the installation operation of follow-up building mark.
Because pushing mechanism includes gear, upper rack, lower rack, lower gear, vertical rotating shaft and the first motor, car body Top right side is provided with the first motor, and vertical rotating shaft is connected with the top of the first motor, and vertical rotating shaft is provided with gear with Gear, gear are located at the top of lower gear, and installing frame right wall front end is respectively equipped with upper rack and lower rack, upper tooth in both sides up and down Bar and lower rack are respectively arranged on the rear of gear and lower gear, and gear engages with upper rack, and lower gear engages with lower rack, So worker starts the work of the first motor, the first motor rotates, and drives gear and lower gear to rotate, can drive upper rack and Lower rack moves left and right together, so as to drive drill bit to move left and right, is easy to its drilling with exiting.
Because drive mechanism includes first bearing seat, first rotating shaft, the first belt pulley, flat belt, the second belt pulley, Two rotating shafts and the second motor, installing frame inner right wall are separately installed with first bearing seat and the second motor, the second motor in both sides up and down Left side be connected with the second rotating shaft, the left end of the second rotating shaft is provided with the first belt pulley, first turn is provided with first bearing seat Axle, the first belt pulley is installed in first rotating shaft, flat belt, installing frame left wall are wound between the first belt pulley and the second belt pulley Upside is provided with perforation, and first rotating shaft is connected through perforation, the left end of first rotating shaft with drill bit, so worker starts the second motor Work, second the second axis of rotation of motor driven, by the machine driving of the first belt pulley and the second belt pulley, drill bit is driven to turn It is dynamic, facilitate drill bit to carry out drilling operation, after drilling terminates, worker closes the second motor.
Because also including ash-sucking cover, hard tube, air pump, 7 shape pipes, treatment box and escape pipe, car body inner bottom part is provided with processing Case, right-hand member is connected with escape pipe at the top for the treatment of box, and air pump is provided with the left of car body inner top, is connected with 7 shape pipes on the right side of air pump, and 7 Shape pipe is stretched in treatment box, hard tube is connected with the left of air pump, hard tube is through car body top left side, and hard tube is before slide rail Side, ash-sucking cover is connected with the top of hard tube, ash-sucking cover is located at the front lower place of drill bit, and treatment box is built with treatment fluid, so worker Booster air pump, dust caused by drilling are sucked by ash-sucking cover, are passed through by 7 shape pipes in treatment fluid, and dust is by treatment fluid Absorb and filtering, last clean air are discharged by escape pipe.
Because also including the first installing plate and the second installing plate, the right-hand member of drill bit is provided with the first installing plate, the first installation Bilateral type is provided with the first mounting hole to plate up and down, and the left end of first rotating shaft is provided with the second installing plate, above and below the second installing plate Bilateral type is provided with the second mounting hole, and the first mounting hole is corresponding with the second mounting hole, so bolt is inserted first by worker Mounting hole and the second mounting hole, then fixed with nut and can install drill bit, when a bit replacement is required, worker unloads bolt spiral shell Mother can easily be changed.
Because also include first bevel gear, second bevel gear, horizontal rotating shaft, cam, elastic component, guide plate, the second axle Bearing, support plate, flexible pipe, pilot hole, elevating lever and contact projection, first bevel gear, first bevel gear are installed in vertical rotating shaft Between gear and lower gear, support plate is provided with the left of car body top, support plate is located at the front side of slide rail, the top installation of support plate There is second bearing seat, horizontal rotating shaft is installed in second bearing seat, the right-hand member of horizontal rotating shaft is provided with second bevel gear, the second cone Gear engages with first bevel gear, and the left end of horizontal rotating shaft is provided with cam, and the top of second bearing seat is provided with guide plate, is oriented to Pilot hole is provided with plate, elastic component, the top and ash-sucking cover bottom of elastic component or so are connected with left and right sides of the top of guide plate Both sides are connected, and elevating lever is provided among ash-sucking cover bottom, and elevating lever passes through pilot hole, and elevating lever bottom is provided with contact projection, Contact projection coordinates with cam contact, and flexible pipe is communicated between hard tube top on the left of ash-sucking cover, so in bit bore, erects Straight axis of rotation drives first bevel gear to rotate, and then drives cam rotation, drives ash-sucking cover to move up and down, so as to expand dust The scope of absorption, the efficiency of absorption is improved, and then improve the environmentally friendly degree of device, reduced the pollution to environment, avoid to worker's body Body has undesirable effect.
Because also including object storage mechanism, right side is provided with object storage mechanism in car body, and object storage mechanism includes handle, storing Frame, roller and mounting groove, car body right side are provided with opening, and right side is provided with mounting groove in car body, is opened at left and right sides of mounting groove inner bottom part There is neck, storage is placed with mounting groove, the bottom of storage is provided with roller, and roller is corresponding with neck, the right wall of storage Provided with handle, so building mark and instrument etc. can be placed in storage by worker, usually roller is stuck in neck, when need When taking thing, worker takes out storage by shaking hands, very convenient.
The control mode of the present invention is automatically controlled by controller, the skill that the control circuit of controller passes through this area Art personnel simple programming can be achieved, and belong to the common knowledge of this area, and the present invention is mainly used to protect mechanical device, institute Control mode is not explained with the present invention to connect with circuit.
(3)Beneficial effect
Invention achieves convenient drilling and the effect of airborne dust can be reduced, device can make dust by treatment fluid absorption with Filtering, last clean air is discharged by escape pipe, and can expand the scope of dust absorbing, improves the efficiency of absorption, And then the environmentally friendly degree of device is improved, the pollution to environment is reduced, avoids having undesirable effect worker's body.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is the main structure diagram of pushing mechanism of the present invention.
Fig. 3 is the main structure diagram of drive mechanism of the present invention.
Fig. 4 is second of main structure diagram of the present invention.
Fig. 5 is the first part main structure diagram of the present invention.
Fig. 6 is second of part main structure diagram of the present invention.
Fig. 7 is the third part main structure diagram of the present invention.
Fig. 8 is the main structure diagram of object storage mechanism of the present invention.
Mark in accompanying drawing for:1- building walls, 2- wheels, 3- ground, 4- car bodies, 5- slide rails, 6- sliding blocks, 7- pushing hands, 8- Pushing mechanism, 80- gears, 81- upper racks, rack under 82-, 83- lower gears, the vertical rotating shafts of 84-, the motors of 85- first, 9- drive Motivation structure, 90- first bearing seats, 91- first rotating shafts, 92- perforation, the belt pulleys of 93- first, 94- flat belts, the belts of 95- second Wheel, the rotating shafts of 96- second, the motors of 97- second, 10- installing frames, 11- drill bits, 12- ash-sucking covers, 13- hard tubes, 14- air pumps, 15-7 shapes Pipe, 16- treatment boxes, 17- escape pipes, the installing plates of 18- first, the installing plates of 19- second, the mounting holes of 20- second, 21- first are installed Hole, 22- first bevel gears, 23- second bevel gears, 24- horizontal rotating shafts, 25- cams, 26- elastic components, 27- guide plates, 28- Two bearing bracket, 29- support plates, 30- flexible pipes, 31- pilot holes, 32- elevating levers, 33- contact projections, 34- object storage mechanisms, 340- are drawn Hand, 341- openings, 342- storages, 343- necks, 344- rollers, 345- mounting grooves.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
One kind building monitoring mark installation auxiliary bore hole device, as shown in figures 1-8, includes wheel 2, car body 4, slide rail 5, sliding block 6th, pushing hands 7, pushing mechanism 8, drive mechanism 9, installing frame 10 and drill bit 11, the bottom of car body 4 are provided with wheel 2, the top of car body 4 Right-hand member is provided with pushing hands 7, and the top left of car body 4 is provided with slide rail 5, and the top of slide rail 5 is provided with sliding block 6, and the top of sliding block 6 is provided with peace Frame up 10, is provided with drive mechanism 9 in installing frame 10, the left end of drive mechanism 9 is connected with drill bit 11, and the top right side of car body 4 is set There is pushing mechanism 8, pushing mechanism 8 is connected with the right wall of installing frame 10, and car body 4 is hollow structure.
Embodiment 2
One kind building monitoring mark installation auxiliary bore hole device, as shown in figures 1-8, includes wheel 2, car body 4, slide rail 5, sliding block 6th, pushing hands 7, pushing mechanism 8, drive mechanism 9, installing frame 10 and drill bit 11, the bottom of car body 4 are provided with wheel 2, the top of car body 4 Right-hand member is provided with pushing hands 7, and the top left of car body 4 is provided with slide rail 5, and the top of slide rail 5 is provided with sliding block 6, and the top of sliding block 6 is provided with peace Frame up 10, is provided with drive mechanism 9 in installing frame 10, the left end of drive mechanism 9 is connected with drill bit 11, and the top right side of car body 4 is set There is pushing mechanism 8, pushing mechanism 8 is connected with the right wall of installing frame 10, and car body 4 is hollow structure.
Pushing mechanism 8 includes gear 80, upper rack 81, lower rack 82, lower gear 83, the electricity of vertical rotating shaft 84 and first Machine 85, the top right side of car body 4 are provided with the first motor 85, and the top of the first motor 85 is connected with vertical rotating shaft 84, vertical rotating shaft 84 are provided with gear 80 and lower gear 83, and gear 80 is two above and below the top of lower gear 83, the right wall front end of installing frame 10 Side is respectively equipped with upper rack 81 and lower rack 82, after upper rack 81 and lower rack 82 are respectively arranged on gear 80 and lower gear 83 Side, gear 80 engage with upper rack 81, and lower gear 83 engages with lower rack 82.
Embodiment 3
One kind building monitoring mark installation auxiliary bore hole device, as shown in figures 1-8, includes wheel 2, car body 4, slide rail 5, sliding block 6th, pushing hands 7, pushing mechanism 8, drive mechanism 9, installing frame 10 and drill bit 11, the bottom of car body 4 are provided with wheel 2, the top of car body 4 Right-hand member is provided with pushing hands 7, and the top left of car body 4 is provided with slide rail 5, and the top of slide rail 5 is provided with sliding block 6, and the top of sliding block 6 is provided with peace Frame up 10, is provided with drive mechanism 9 in installing frame 10, the left end of drive mechanism 9 is connected with drill bit 11, and the top right side of car body 4 is set There is pushing mechanism 8, pushing mechanism 8 is connected with the right wall of installing frame 10, and car body 4 is hollow structure.
Pushing mechanism 8 includes gear 80, upper rack 81, lower rack 82, lower gear 83, the electricity of vertical rotating shaft 84 and first Machine 85, the top right side of car body 4 are provided with the first motor 85, and the top of the first motor 85 is connected with vertical rotating shaft 84, vertical rotating shaft 84 are provided with gear 80 and lower gear 83, and gear 80 is two above and below the top of lower gear 83, the right wall front end of installing frame 10 Side is respectively equipped with upper rack 81 and lower rack 82, after upper rack 81 and lower rack 82 are respectively arranged on gear 80 and lower gear 83 Side, gear 80 engage with upper rack 81, and lower gear 83 engages with lower rack 82.
Drive mechanism 9 includes first bearing seat 90, first rotating shaft 91, the first belt pulley 93, flat belt 94, the second belt Take turns the 95, second rotating shaft 96 and the second motor 97, both sides are separately installed with first bearing seat 90 and the to the inner right wall of installing frame 10 up and down Two motors 97, the left side of the second motor 97 are connected with the second rotating shaft 96, and the left end of the second rotating shaft 96 is provided with the first belt pulley 93, First rotating shaft 91 is installed in first bearing seat 90, the first belt pulley 93 is installed in first rotating shaft 91, the first belt pulley 93 with Flat belt 94 is wound between second belt pulley 95, perforation 92 is provided with the upside of the left wall of installing frame 10, first rotating shaft 91 passes through perforation 92, The left end of first rotating shaft 91 is connected with drill bit 11.
Embodiment 4
One kind building monitoring mark installation auxiliary bore hole device, as shown in figures 1-8, includes wheel 2, car body 4, slide rail 5, sliding block 6th, pushing hands 7, pushing mechanism 8, drive mechanism 9, installing frame 10 and drill bit 11, the bottom of car body 4 are provided with wheel 2, the top of car body 4 Right-hand member is provided with pushing hands 7, and the top left of car body 4 is provided with slide rail 5, and the top of slide rail 5 is provided with sliding block 6, and the top of sliding block 6 is provided with peace Frame up 10, is provided with drive mechanism 9 in installing frame 10, the left end of drive mechanism 9 is connected with drill bit 11, and the top right side of car body 4 is set There is pushing mechanism 8, pushing mechanism 8 is connected with the right wall of installing frame 10, and car body 4 is hollow structure.
Pushing mechanism 8 includes gear 80, upper rack 81, lower rack 82, lower gear 83, the electricity of vertical rotating shaft 84 and first Machine 85, the top right side of car body 4 are provided with the first motor 85, and the top of the first motor 85 is connected with vertical rotating shaft 84, vertical rotating shaft 84 are provided with gear 80 and lower gear 83, and gear 80 is two above and below the top of lower gear 83, the right wall front end of installing frame 10 Side is respectively equipped with upper rack 81 and lower rack 82, after upper rack 81 and lower rack 82 are respectively arranged on gear 80 and lower gear 83 Side, gear 80 engage with upper rack 81, and lower gear 83 engages with lower rack 82.
Drive mechanism 9 includes first bearing seat 90, first rotating shaft 91, the first belt pulley 93, flat belt 94, the second belt Take turns the 95, second rotating shaft 96 and the second motor 97, both sides are separately installed with first bearing seat 90 and the to the inner right wall of installing frame 10 up and down Two motors 97, the left side of the second motor 97 are connected with the second rotating shaft 96, and the left end of the second rotating shaft 96 is provided with the first belt pulley 93, First rotating shaft 91 is installed in first bearing seat 90, the first belt pulley 93 is installed in first rotating shaft 91, the first belt pulley 93 with Flat belt 94 is wound between second belt pulley 95, perforation 92 is provided with the upside of the left wall of installing frame 10, first rotating shaft 91 passes through perforation 92, The left end of first rotating shaft 91 is connected with drill bit 11.
Also include ash-sucking cover 12, hard tube 13, air pump 14,7 shape pipes 15, treatment box 16 and escape pipe 17, the inner bottom part of car body 4 Provided with treatment box 16, the top right-hand member for the treatment of box 16 is connected with escape pipe 17, and air pump 14, air pump are provided with the left of the inner top of car body 4 14 right sides are connected with the shape pipe 15 of 7 shape pipe 15,7 and stretched in treatment box 16, and the left side of air pump 14 is connected with hard tube 13, and hard tube 13 passes through The top left side of car body 4, hard tube 13 are located at the front side of slide rail 5, and the top of hard tube 13 is connected with ash-sucking cover 12, and ash-sucking cover 12 is positioned at brill First 11 front lower place.
Also including the first installing plate 18 and the second installing plate 19, the right-hand member of drill bit 11 is provided with the first installing plate 18, and first Installing plate about 18 bilateral type be provided with the first mounting hole 21, the left end of first rotating shaft 91 is provided with the second installing plate 19, Two installing plates about 19 bilateral type be provided with the second mounting hole 20, the first mounting hole 21 is corresponding with the second mounting hole 20.
Also include first bevel gear 22, second bevel gear 23, horizontal rotating shaft 24, cam 25, elastic component 26, guide plate 27th, second bearing seat 28, support plate 29, flexible pipe 30, pilot hole 31, elevating lever 32 and contact projection 33, install in vertical rotating shaft 84 There is first bevel gear 22, first bevel gear 22 is located between gear 80 and lower gear 83, and the top left side of car body 4 is provided with support plate 29, support plate 29 is located at the front side of slide rail 5, and the top of support plate 29 is provided with second bearing seat 28, is provided with second bearing seat 28 Horizontal rotating shaft 24, the right-hand member of horizontal rotating shaft 24 are provided with second bevel gear 23, and second bevel gear 23 engages with first bevel gear 22, The left end of horizontal rotating shaft 24 is provided with cam 25, and the top of second bearing seat 28 is provided with guide plate 27, is provided with and leads on guide plate 27 To hole 31, elastic component 26, the top and the bottom of ash-sucking cover 12 of elastic component 26 or so are connected with left and right sides of the top of guide plate 27 Both sides are connected, and are provided with elevating lever 32 among the bottom of ash-sucking cover 12, elevating lever 32 passes through pilot hole 31, and the bottom of elevating lever 32 is provided with Contact projection 33, contact projection 33 are engaged with cam 25, and flexible pipe is communicated between the left side of ash-sucking cover 12 and the top of hard tube 13 30。
Also include object storage mechanism 34, right side is provided with object storage mechanism 34 in car body 4, object storage mechanism 34 include handle 340, Storage 342, roller 344 and mounting groove 345, the right side of car body 4 are provided with opening 341, and right side is provided with mounting groove 345 in car body 4, pacifies Neck 343 is provided with left and right sides of the inner bottom part of tankage 345, storage 342 is placed with mounting groove 345, the bottom of storage 342 is set There is roller 344, roller 344 is corresponding with neck 343, and the right wall of storage 342 is provided with handle 340.
Operation principle:When worker need will building mark be arranged on it is architectural before, the present apparatus is pushed into properly by worker first Position, then start pushing mechanism 8 and drive mechanism 9 is started working, pushing mechanism 8 drives drill bit 11 to move, the band of drive mechanism 9 Dynamic drill bit 11 is rotated, and drill bit 11 is rotated while going deep into building wall 1, and after the completion of drilling, drill bit 11 sets back, worker Close pushing mechanism 8 and drive mechanism 9, you can carry out the installation operation of follow-up building mark.
Because pushing mechanism 8 includes gear 80, upper rack 81, lower rack 82, lower gear 83, vertical rotating shaft 84 and One motor 85, the top right side of car body 4 are provided with the first motor 85, and the top of the first motor 85 is connected with vertical rotating shaft 84, vertically Rotating shaft 84 is provided with gear 80 and lower gear 83, and gear 80 is on the top of lower gear 83, the right wall front end of installing frame 10 Lower both sides are respectively equipped with upper rack 81 and lower rack 82, and upper rack 81 and lower rack 82 are respectively arranged on gear 80 and lower gear 83 Rear, gear 80 engages with upper rack 81, and lower gear 83 engages with lower rack 82, so worker starts the work of the first motor 85 Make, the first motor 85 rotates, and drives gear 80 and lower gear 83 to rotate, upper rack 81 and lower rack 82 can be driven left together Move right, so as to drive drill bit 11 to move left and right, be easy to its drilling with exiting.
Because drive mechanism 9 includes first bearing seat 90, first rotating shaft 91, the first belt pulley 93, flat belt 94, second Belt pulley 95, the second rotating shaft 96 and the second motor 97, the inner right wall of installing frame 10 are separately installed with first bearing seat 90 in both sides up and down With the second motor 97, the left side of the second motor 97 is connected with the second rotating shaft 96, and the left end of the second rotating shaft 96 is provided with the first belt 93 are taken turns, first rotating shaft 91 is installed in first bearing seat 90, the first belt pulley 93, the first belt pulley are installed in first rotating shaft 91 93 and second are wound with flat belt 94 between belt pulley 95, are provided with perforation 92 on the upside of the left wall of installing frame 10, first rotating shaft 91 is worn Hole 92, the left end of first rotating shaft 91 are connected with drill bit 11, so worker starts the second motor 97 and worked, the second motor 97 drives Second rotating shaft 96 rotates, and by the machine driving of the first belt pulley 93 and the second belt pulley 95, drives drill bit 11 to rotate, convenient to bore First 11 carry out drilling operation, and after drilling terminates, worker closes the second motor 97.
Because also including ash-sucking cover 12, hard tube 13, air pump 14,7 shape pipes 15, treatment box 16 and escape pipe 17, in car body 4 Bottom is provided with treatment box 16, and the top right-hand member for the treatment of box 16 is connected with escape pipe 17, air pump 14 is provided with the left of the inner top of car body 4, The right side of air pump 14 is connected with the shape pipe 15 of 7 shape pipe 15,7 and stretched in treatment box 16, and the left side of air pump 14 is connected with hard tube 13, hard tube 13 Through the top left side of car body 4, hard tube 13 is located at the front side of slide rail 5, and the top of hard tube 13 is connected with ash-sucking cover 12, ash-sucking cover 12 In the front lower place of drill bit 11, treatment box 16 is built with treatment fluid, so worker's booster air pump 14, dust caused by drilling passes through suction The suction of ash cover 12, is passed through in treatment fluid by 7 shape pipes 15, and dust passes through the absorption and filtering for the treatment of fluid, last clean air Discharged by escape pipe 17.
Because also including the first installing plate 18 and the second installing plate 19, the right-hand member of drill bit 11 is provided with the first installing plate 18, First installing plate about 18 bilateral type be provided with the first mounting hole 21, the left end of first rotating shaft 91 is provided with the second installing plate 19, the second installing plate about 19 bilateral type be provided with the second mounting hole 20, the first mounting hole 21 is relative with the second mounting hole 20 Should, so bolt is inserted the first mounting hole 21 and the second mounting hole 20 by worker, then fixed with nut and can install drill bit 11, When needing more bit change 11, worker unloads bolt and nut and can easily changed.
Because also include first bevel gear 22, second bevel gear 23, horizontal rotating shaft 24, cam 25, elastic component 26, guiding Plate 27, second bearing seat 28, support plate 29, flexible pipe 30, pilot hole 31, elevating lever 32 and contact projection 33, pacify in vertical rotating shaft 84 Equipped with first bevel gear 22, first bevel gear 22 is located between gear 80 and lower gear 83, and the top left side of car body 4 is provided with support plate 29, support plate 29 is located at the front side of slide rail 5, and the top of support plate 29 is provided with second bearing seat 28, is provided with second bearing seat 28 Horizontal rotating shaft 24, the right-hand member of horizontal rotating shaft 24 are provided with second bevel gear 23, and second bevel gear 23 engages with first bevel gear 22, The left end of horizontal rotating shaft 24 is provided with cam 25, and the top of second bearing seat 28 is provided with guide plate 27, is provided with and leads on guide plate 27 To hole 31, elastic component 26, the top and the bottom of ash-sucking cover 12 of elastic component 26 or so are connected with left and right sides of the top of guide plate 27 Both sides are connected, and are provided with elevating lever 32 among the bottom of ash-sucking cover 12, elevating lever 32 passes through pilot hole 31, and the bottom of elevating lever 32 is provided with Contact projection 33, contact projection 33 are engaged with cam 25, and flexible pipe is communicated between the left side of ash-sucking cover 12 and the top of hard tube 13 30, so when drill bit 11 drills, vertical rotating shaft 84, which rotates, drives first bevel gear 22 to rotate, and then is rotated with moving cam 25, Drive ash-sucking cover 12 to move up and down, so as to expand the scope of dust absorbing, improve the efficiency of absorption, and then improve the environmental protection of device Degree, reduces the pollution to environment, avoids having undesirable effect worker's body.
Because also including object storage mechanism 34, right side is provided with object storage mechanism 34 in car body 4, and object storage mechanism 34 includes handle 340th, storage 342, roller 344 and mounting groove 345, the right side of car body 4 are provided with opening 341, and right side is provided with mounting groove in car body 4 345, the inner bottom part of mounting groove 345 left and right sides is provided with neck 343, and storage 342 is placed with mounting groove 345, storage 342 Bottom is provided with roller 344, and roller 344 is corresponding with neck 343, and the right wall of storage 342 is provided with handle 340, so worker can be with Building mark and instrument etc. are placed in storage 342, usually roller 344 is stuck in neck 343, when needing to take thing, work People takes out storage 342 by handle 340, very convenient.
The control mode of the present invention is automatically controlled by controller, the skill that the control circuit of controller passes through this area Art personnel simple programming can be achieved, and belong to the common knowledge of this area, and the present invention is mainly used to protect mechanical device, institute Control mode is not explained with the present invention to connect with circuit.
Embodiment described above only expresses the preferred embodiment of the present invention, and its description is more specific and detailed, but simultaneously Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these belong to this hair Bright protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (7)

1. one kind building monitoring mark installation auxiliary bore hole device, it is characterised in that include wheel(2), car body(4), slide rail (5), sliding block(6), pushing hands(7), pushing mechanism(8), drive mechanism(9), installing frame(10)And drill bit(11), car body(4)Bottom Portion is provided with wheel(2), car body(4)Top right-hand member be provided with pushing hands(7), car body(4)Top left be provided with slide rail(5), slide rail (5)Top be provided with sliding block(6), sliding block(6)Top be provided with installing frame(10), installing frame(10)It is interior to be provided with drive mechanism(9), Drive mechanism(9)Left end be connected with drill bit(11), car body(4)Top right side be provided with pushing mechanism(8), pushing mechanism(8) With installing frame(10)Right wall is connected, car body(4)For hollow structure.
A kind of 2. building monitoring mark installation auxiliary bore hole device according to claim 1, it is characterised in that pushing mechanism (8)Include gear(80), upper rack(81), lower rack(82), lower gear(83), vertical rotating shaft(84)With the first motor (85), car body(4)Top right side is provided with the first motor(85), the first motor(85)Top be connected with vertical rotating shaft(84), Vertical rotating shaft(84)It is provided with gear(80)And lower gear(83), gear(80)Located at lower gear(83)Top, installation Frame(10)Right wall front end is respectively equipped with upper rack in both sides up and down(81)With lower rack(82), upper rack(81)With lower rack(82)Point She Yu not gear(80)And lower gear(83)Rear, gear(80)With upper rack(81)Engagement, lower gear(83)With under Rack(82)Engagement.
A kind of 3. building monitoring mark installation auxiliary bore hole device according to claim 2, it is characterised in that drive mechanism (9)Include first bearing seat(90), first rotating shaft(91), the first belt pulley(93), flat belt(94), the second belt pulley (95), the second rotating shaft(96)With the second motor(97), installing frame(10)Inner right wall is separately installed with first bearing seat in both sides up and down (90)With the second motor(97), the second motor(97)Left side be connected with the second rotating shaft(96), the second rotating shaft(96)Left end peace Equipped with the first belt pulley(93), first bearing seat(90)On first rotating shaft is installed(91), first rotating shaft(91)On be provided with One belt pulley(93), the first belt pulley(93)With the second belt pulley(95)Between be wound with flat belt(94), installing frame(10)Left wall Upside is provided with perforation(92), first rotating shaft(91)Through perforation(92), first rotating shaft(91)Left end and drill bit(11)It is connected.
4. a kind of building monitoring mark installation auxiliary bore hole device according to claim 3, it is characterised in that also include Ash-sucking cover(12), hard tube(13), air pump(14), 7 shape pipes(15), treatment box(16)And escape pipe(17), car body(4)Inner bottom part is set There is treatment box(16), treatment box(16)Top right-hand member is connected with escape pipe(17), car body(4)Air pump is installed on the left of inner top (14), air pump(14)Right side is connected with 7 shape pipes(15), 7 shape pipes(15)Stretch to treatment box(16)It is interior, air pump(14)Left side connects There is hard tube(13), hard tube(13)Through car body(4)Top left side, hard tube(13)Located at slide rail(5)Front side, hard tube(13)Top Portion is connected with ash-sucking cover(12), ash-sucking cover(12)Positioned at drill bit(11)Front lower place.
5. a kind of building monitoring mark installation auxiliary bore hole device according to claim 4, it is characterised in that also include First installing plate(18)With the second installing plate(19), drill bit(11)Right-hand member be provided with the first installing plate(18), the first installing plate (18)Upper and lower bilateral type is provided with the first mounting hole(21), first rotating shaft(91)Left end the second installing plate is installed(19), Second installing plate(19)Upper and lower bilateral type is provided with the second mounting hole(20), the first mounting hole(21)With the second mounting hole(20) It is corresponding.
6. a kind of building monitoring mark installation auxiliary bore hole device according to claim 5, it is characterised in that also include First bevel gear(22), second bevel gear(23), horizontal rotating shaft(24), cam(25), elastic component(26), guide plate(27), Two bearing bracket(28), support plate(29), flexible pipe(30), pilot hole(31), elevating lever(32)And contact projection(33), vertical rotating shaft (84)On first bevel gear is installed(22), first bevel gear(22)Located at gear(80)With lower gear(83)Between, car body (4)Top left side is provided with support plate(29), support plate(29)Located at slide rail(5)Front side, support plate(29)Top the second axle is installed Bearing(28), second bearing seat(28)On horizontal rotating shaft is installed(24), horizontal rotating shaft(24)Right-hand member the second cone tooth is installed Wheel(23), second bevel gear(23)With first bevel gear(22)Engagement, horizontal rotating shaft(24)Left end cam is installed(25), the Two bearing bracket(28)Top be provided with guide plate(27), guide plate(27)On be provided with pilot hole(31), guide plate(27)Top The left and right sides is connected with elastic component(26), elastic component(26)Top and ash-sucking cover(12)It is connected at left and right sides of bottom, inhales ash Cover(12)Elevating lever is provided among bottom(32), elevating lever(32)Through pilot hole(31), elevating lever(32)Bottom is provided with contact It is raised(33), contact projection(33)With cam(25)It is engaged, ash-sucking cover(12)Left side and hard tube(13)Connected between top There is flexible pipe(30).
7. a kind of building monitoring mark installation auxiliary bore hole device according to claim 6, it is characterised in that also include Object storage mechanism(34), car body(4)Interior right side is provided with object storage mechanism(34), object storage mechanism(34)Include handle(340), storage (342), roller(344)And mounting groove(345), car body(4)Right side is provided with opening(341), car body(4)Interior right side is provided with mounting groove (345), mounting groove(345)Neck is provided with left and right sides of inner bottom part(343), mounting groove(345)Inside it is placed with storage(342), Storage(342)Bottom be provided with roller(344), roller(344)With neck(343)It is corresponding, storage(342)Right wall be provided with Handle(340).
CN201710895610.6A 2017-09-28 2017-09-28 One kind building monitoring mark installation auxiliary bore hole device Pending CN107553419A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710895610.6A CN107553419A (en) 2017-09-28 2017-09-28 One kind building monitoring mark installation auxiliary bore hole device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710895610.6A CN107553419A (en) 2017-09-28 2017-09-28 One kind building monitoring mark installation auxiliary bore hole device

Publications (1)

Publication Number Publication Date
CN107553419A true CN107553419A (en) 2018-01-09

Family

ID=60983240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710895610.6A Pending CN107553419A (en) 2017-09-28 2017-09-28 One kind building monitoring mark installation auxiliary bore hole device

Country Status (1)

Country Link
CN (1) CN107553419A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108202417A (en) * 2018-02-26 2018-06-26 曹立梅 Construction top beam plate drilling device
CN108590508A (en) * 2018-03-21 2018-09-28 张晓婷 A kind of drilling device for building monitoring
CN108656233A (en) * 2018-03-30 2018-10-16 湖州虹君机械有限公司 A kind of dowel hole structure
CN111347077A (en) * 2020-04-27 2020-06-30 福清市利恒科技有限公司 Over-and-under type automatic drilling machine
CN113442308A (en) * 2021-07-01 2021-09-28 张彩静 Wall drilling device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205848451U (en) * 2016-06-29 2017-01-04 林志龙 A kind of gardens plant pesticide high efficient sprinkling device
CN106476146A (en) * 2016-12-15 2017-03-08 赵文林 A kind of efficiently accurate perforating device of wallboard
CN106522144A (en) * 2016-12-01 2017-03-22 朱雪梅 Construction site dust removing device used for preventing fog and haze

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205848451U (en) * 2016-06-29 2017-01-04 林志龙 A kind of gardens plant pesticide high efficient sprinkling device
CN106522144A (en) * 2016-12-01 2017-03-22 朱雪梅 Construction site dust removing device used for preventing fog and haze
CN106476146A (en) * 2016-12-15 2017-03-08 赵文林 A kind of efficiently accurate perforating device of wallboard

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108202417A (en) * 2018-02-26 2018-06-26 曹立梅 Construction top beam plate drilling device
CN108590508A (en) * 2018-03-21 2018-09-28 张晓婷 A kind of drilling device for building monitoring
CN108590508B (en) * 2018-03-21 2019-09-24 湖北德纳建设有限公司 It is a kind of for build monitoring drilling device
CN108656233A (en) * 2018-03-30 2018-10-16 湖州虹君机械有限公司 A kind of dowel hole structure
CN111347077A (en) * 2020-04-27 2020-06-30 福清市利恒科技有限公司 Over-and-under type automatic drilling machine
CN113442308A (en) * 2021-07-01 2021-09-28 张彩静 Wall drilling device

Similar Documents

Publication Publication Date Title
CN107553419A (en) One kind building monitoring mark installation auxiliary bore hole device
CN107900043A (en) A kind of food inspection test tube cleaning drying device
CN105170589B (en) A kind of vertical storage tank shell body cleaning equipment
CN105798347B (en) A kind of industrial drilling equipment
CN107813427A (en) A kind of impact drill servicing unit
CN107524411A (en) One kind building monitoring mark auxiliary installing device
CN207267113U (en) A kind of laser marking machine
CN116159784A (en) Meteorological equipment maintenance equipment
CN207747643U (en) A kind of wood-worker engraving machine
CN113199063A (en) Drilling equipment for blank plate jig and using method thereof
CN203508477U (en) Throwing and rotating device of hydrocarbon cleaning machine
CN206561344U (en) Automatic polishing machine
CN109442579A (en) Self-cleaning aeration device
CN215144881U (en) Panel processing drilling equipment convenient to remove
CN210937219U (en) Drilling machine with dust absorption function
CN103551331B (en) Throwing and rotating device in hydrocarbon cleaning machine
CN209181180U (en) A air speed regulator for new fan
CN210791557U (en) Perforating device for construction
CN207669538U (en) A kind of multiple degrees of freedom Cutting platform
CN209520402U (en) A kind of drilling machine for facilitating coolant liquid to recycle
CN208830793U (en) A kind of intelligent parking system applied to parking lot
CN218802855U (en) Board positioning and drilling device for base wood workpiece
CN212762256U (en) Building drilling device capable of guaranteeing perpendicularity
CN220880602U (en) Multi-surface processing equipment for processing aluminum profile
CN211225596U (en) Feeding device for wood furniture processing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180109