CN107542981A - Fast pipe buckle structure - Google Patents

Fast pipe buckle structure Download PDF

Info

Publication number
CN107542981A
CN107542981A CN201610863392.3A CN201610863392A CN107542981A CN 107542981 A CN107542981 A CN 107542981A CN 201610863392 A CN201610863392 A CN 201610863392A CN 107542981 A CN107542981 A CN 107542981A
Authority
CN
China
Prior art keywords
foregoing
buckling
concave arc
fulcrum
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610863392.3A
Other languages
Chinese (zh)
Inventor
郑福耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Piping & Corrosion Proof Industrial Co
Original Assignee
First Piping & Corrosion Proof Industrial Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Piping & Corrosion Proof Industrial Co filed Critical First Piping & Corrosion Proof Industrial Co
Publication of CN107542981A publication Critical patent/CN107542981A/en
Pending legal-status Critical Current

Links

Landscapes

  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)

Abstract

The invention relates to a quick pipe buckle structure, which is characterized in that a support shaft is arranged on the outer side of a first element to be arranged in a shaft groove of a second element, one ends of the first element and the second element are mutually combined to form a one-way opening shape, a leakage stopping element is arranged at a connecting end after the two pipe fittings are mutually connected, the outer side of the leakage stopping element is covered by the first element and the second element, the other ends of the first element and the second element are buckled by a buckling element, the two connected pipe fittings can be connected, liquid leakage in the pipe fittings is prevented by the leakage stopping element, accumulated dirt in the pipe fittings can be quickly cleaned by one person only through operation, the smoothness in the pipe fittings is kept, and the maintenance labor is saved.

Description

Quick pipe thread structure
Technical field
The present invention sets fulcrum on quick pipe thread structure, espespecially one kind in the first member outboard, thinks the axle of the second element Groove is set, and allows one end of the first element and the second element to be first combined with each other to form unidirectional openning shape, and overlapped in two pipe fittings Afterwards, leakproof element is set in cohesive end, then be coated on foregoing first element and the second element on the outside of leakproof element, and to fasten Element fastens the other end of foregoing first element and the second element, you can two pipe fittings being mutually connected engaged, and by leak-stopping Element prevents the fluid seepage in pipe fitting, as long as one man operation, you can the accumulation dirt in quick-replaceable cleaning pipe fitting, to keep It is unimpeded in pipe fitting, save the quick pipe thread structure of maintenance manpower.
Background technology
As shown in Fig. 1 and 2, it is existing pipe thread, includes the groups such as the first element A0, the second element A1 and leakproof element B Into wherein the first element A and the second element B one end system form axle with a fulcrum A3 sets end A30, allowing the first element A0 and second Element A1 is able to produce the function being unidirectionally opened and closed, and sets element A4 bolts in the first element A and the second element B other end with a bolt If forming bolt sets end A40 so that the existing pipe thread is able to the external diameter for coordinating all kinds of pipe fitting C, can be connected two pipe fitting bolts admittedly. And its shortcoming is arranged in leakproof element B for the cohesive end C0 as two pipe fitting C, and just it is located at foregoing first element A and second yuan Part B axle sets the position that end A30 sets end A40 with bolt, and the external diameter such as pipe fitting C is tied just greater than the first element A0 and the second element A1 Minimum diameter after conjunction, the first element A0 for being combined with each other and the second element A1 axles will be caused to set end A30 and set with bolt in the A40 of end Side produces the first gap A31 and the second gap A41, in this way, when pipe fitting is as flow pipe, liquid can be in the linking from two pipe fittings C0 position is held, leaks into leakproof element B, now, the pressure of the liquid can extrude positioned at the first gap A31 and second automatically Gap A41 leakproof element B, leakproof element B is caused to be deformed (such as according to the first gap A31 and the second gap A41 shape Fig. 1), through after a period of time, leakproof element B i.e. can since at deformation breakage, cause fluid seepage to come out.
Therefore, present inventor, the shortcomings that for the prior art, the product research and development of Related product and manufacturing experience for many years, And invention this case, fully to solve the shortcomings that prior art and problem.
The content of the invention
It is an object of the invention to provide a kind of simple structure, and it is narrow to be addressed building pipe fitting, water-supply-pipe installation site Narrow, manpower is constructed the problem of inconvenient, with few manpower, is not necessary to hand-held tool, you can with the pipe fitting that quick-replaceable is damaged, and can be quick Two pipe fittings being mutually connected are pulled down, to remove the accumulation dirt in pipe fitting, keep unimpeded in pipe fitting, and through experiment, than existing skill Fast more than 5 times of the speed of application of art, and manpower is reduced more than half, so as to speed speed of application, saves manpower Quick pipe thread structure innovation.
Quick pipe thread structure of the present invention sets the first element and the second element, and foregoing first element and the second element are equal Engaging collar, is able to be sticked in the slot for two pipe fittings being mutually connected corresponding to being set in medial surface, in foregoing engaging collar Inner side sets concave arc groove, thinks that leakproof element is set.
First member outboard one end of the present invention sets fulcrum, thinks that the axial trough of the second element is set, foregoing first yuan Part buckling groove corresponding with the other end of the second element, after the first element and the second element jointly clamping pipe fitting, it is able to foregoing Buckling element is fastened on the respective buckling groove of foregoing first element and the second element, you can two pipe fittings being mutually connected combined, and The fluid seepage in pipe fitting is prevented with leakproof element, and with the accumulation dirt in quick-replaceable cleaning pipe fitting, is kept in pipe fitting It is unimpeded, save maintenance manpower person.
Quick pipe thread structure of the present invention, is to set fastening end in one end of the concave arc groove of the first element, the other end is then If engaging area, running is combined with each other with the setting in engaging area and fastening end corresponding to the second element, to prevent leakproof element By the pressure that the liquid of two pipe fitting cohesive end seepages extrudes, the cohesive end in the first element and the second element deforms, and causes Make fluid seepage.
Quick pipe thread structure of the present invention, it is to set engaging area in one end of the concave arc groove of the second element, the other end is then If fastening end, combination is operated mutually with engaging area with the fastening end for foregoing first element.
Quick pipe thread structure of the present invention, can set the engaging area of invaginated type in the both ends of the concave arc groove of the first element, Corresponding with two fastening ends corresponding to the second element combines running.
Quick pipe thread structure of the present invention, can set to extension respectively in the both ends of the bottom wall of the concave arc groove of the first element The fastening end stretched, operated with engaging the setting in area corresponding to the two of the second element.
Brief description of the drawings
It is of the invention from the point of view of the following description to the purport and its preferred embodiments and drawings used of the explanation present invention Above and other objects, features and advantages will be apparent, in the accompanying drawings:
Fig. 1 is the use state figure of prior art.
Fig. 2 is the sectional view of prior art.
Fig. 3 is the decomposition view of the embodiment of the present invention one.
Fig. 4 is the decomposition view of the embodiment of the present invention two.
Fig. 5 is the action view of combination first of the present invention.
Fig. 6 is the action view of combination second of the present invention.
Fig. 7 is the zoomed-in view of part A in Fig. 6.
Fig. 8 is the zoomed-in view of part B in Fig. 6.
Fig. 9 is the action view of combination the 3rd of the present invention.
Figure 10 is the zoomed-in view of C portion in Fig. 9.
Figure 11 is the zoomed-in view of D parts in Fig. 9.
Figure 12 is the sectional view after the completion of present invention combination.
Figure 13 is the zoomed-in view of E parts in Figure 12.
Figure 14 is the zoomed-in view of F parts in Figure 12.
Figure 15 is the view after the completion of present invention combination.
Figure 16 is along the sectional view of line A-A in Figure 15.
Figure 17 is use state view of the present invention.
Figure 18 is the three-dimensional view of use state of the present invention.
【Main element symbol description】
First element 1
Engage the concave arc groove 11 of collar 10
The axle bed 120 of fulcrum 12
The extending seat 130 of buckling groove 13
Fastening end 140 engages area 141
Second element 2
Engage the concave arc groove 21 of collar 20
The axial trough seat 220 of axial trough 22
The extending seat 230 of buckling groove 23
Fastening end 240 engages area 241
Leakproof element 3
The inclined plane 31 of outer surface 30
The mesopore 33 of gap 32
Pipe fitting 4a, 4b
Buckling element 5
Pulling piece 50
Fulcrum 500 pulls face 501
The engagement groove 502a activity spaces 503 of combined hole 502
Pull part 51
The upper connecting piece 512 of 510 times fulcrums of fulcrum 511
Contact gap 60,61
Embodiment
The present invention is further understood that to allow the public to be able to, it is as follows hereby to depend on schema explanation:
As shown in figs. 3 and 4, the present invention comprises at least:First element 1, engaging collar 10, foregoing snap rings are set in medial surface The shape for enclosing 10 the first elements of cooperation 1 is formed in one, obtain using it is foregoing engaging collar 10 be sticked in mutually be connected two pipe fitting 4a, 4b surface (as shown in figure 17), the inner side of foregoing engaging collar 10 simultaneously set concave arc groove 11, think that leakproof element 3 is set.It is foregoing First element 1 sets fulcrum 12, and to be arranged at the axial trough 22 of the second element 2, the system of fulcrum 12 of foregoing first element 1 is by an axle bed 120 is integral with the first element 1.Foregoing first element 1 sets buckling groove 13, thinks that buckling element 5 is fastened (such as the institute of Fig. 5~15 Show), foregoing buckling groove 13 is disposed on the lower section of extending seat 130, and foregoing extending seat 130 is formed in one with the first element 1 And stretch out.One end of the concave arc groove 11 of foregoing first element 1 is provided with from the fastening end that the bottom wall of concave arc groove 11 stretches out 140, the other end of the concave arc groove 11 of foregoing first element 1 then sets the engaging area 141 of invaginated type (as schemed in the bottom wall of concave arc groove 11 Shown in 3), it corresponds to the setting in the engaging area 241 of the second element 2 and fastening end 240 and operated, to prevent leakproof element 3 By the pressure that the liquid of two pipe fitting cohesive end seepages extrudes, the cohesive end in the first element 1 and the second element 2 deforms Cause fluid seepage.Or as shown in figure 4, can in the both ends of concave arc groove 11 of foregoing first element 1 respectively at concave arc groove 11 bottom wall If the engaging area 141 of invaginated type, it corresponds to the setting running of two fastening ends 240 of the second element 2, to prevent leak-stopping member The pressure that part 3 is extruded by the liquid of two pipe fitting cohesive end seepages, and occur in the cohesive end of the first element 1 and the second element 2 Deformation causes fluid seepage.Certainly also can in the both ends of concave arc groove 11 of foregoing first element 1 respectively at concave arc groove 11 bottom wall to Outer extension forms fastening end 140, with corresponding to the second element 2 two engage areas 241 setting operate, also without can not, end regard in fact Border demand.
As shown in figs. 3 and 4, the present invention sets the second element 2, and it is corresponding each other with foregoing first element 1, be able to it is foregoing The combination of first element 1 forms ring-type, and the medial surface of foregoing second element 2 sets engaging collar 20, with corresponding to foregoing first element 1 Engaging collar 10, be able to be sticked in two pipe fitting 4a, 4b being mutually connected surface (as shown in figure 17), in foregoing engaging collar 20 Side sets concave arc groove 21, with the concave arc groove 11 corresponding to foregoing first element 1, thinks that leakproof element 3 is set (such as the institute of Fig. 4~16 Show).One end of foregoing second element 2 sets axial trough 22, to coordinate the fulcrum 12 of foregoing first element 1 to set, foregoing second element 2 Axial trough 22 be arranged at the top of axial trough seat 220, and be formed in one with the second element 2.The other end of foregoing second element 2, which is set, to be buckled Groove 23 is closed, thinks that buckling element 5 fastens (as shown in Fig. 4~15), the buckling groove 23 of foregoing second element 2 is then disposed on extending The top of seat 230, and stretch out from foregoing second element 2, and be formed in one with the second element 2.Foregoing second element 2 it is recessed One end of arc groove 21 sets the engaging area 241 of invaginated type in the bottom wall of concave arc groove 11, and the other end of foregoing concave arc groove 21 is then in concave arc The bottom wall of groove 11 stretches out the fastening end 240 (as shown in Figure 3) to be formed.Or the as shown in figure 4, concave arc of foregoing second element 2 The both ends of groove 21 set the fastening end 240 to be formed that stretches out in the bottom wall of concave arc groove 11, to coordinate the correspondence of the first element to set Put, therefore, however it is not limited to the corresponding method disclosed in description of the invention accompanying drawing.When buckling element 5 is not yet by the first element 1 Before being combined with the second element 2, it is able to the fastening end in the engaging area 241 of foregoing second element 2, the element 1 of fastening end 240 and first 140th, engaging area 141 is combined with each other, or two fastening ends 240 of foregoing second element 2 are engaged into area 141 with the 2 of the first element 1 Be combined with each other, you can the first element 1 and the second element 2 are produced into the initial effect for combining positioning, so as to avoid the first element 1 with Second element 2 or so is offset, and allows buckling element 5 to be able to more rapidly, more accurately buckle the first element 1 and the second element 2 admittedly.Its It is secondary, when this quick pipe thread is employed for water delivery pipe fitting, because the liquid flowing in water delivery pipe fitting can produce certain pressure, hydraulic pressure Most weak part in pipe fitting can be attacked, the leakproof element flexibility material of the quick pipe thread of such as pipe fitting joining place that is, can be by water The attack of pressure and deform, or even damaged, the present invention by fastening end 240 and can engage the combination in area 241, allow the first element 1 The element 2 of concave arc groove 11 and second concave arc groove 21 produce closing effect, it is sufficient to support and come from attacking for liquid in pipe pressure Hit leakproof element 3, the deformation of prevention leakproof element 3 and breakage (as seen in figs. 15-17).
As shown in figs. 3 and 4, the present invention sets leakproof element 3, is that ring is made by the material for possessing elasticity and having sealing effectiveness Shape body, foregoing leakproof element 3 set outer surface 30, are able to be set into foregoing first element 1 and second yuan using aforementioned external surfaces 30 The ring concave arc groove that the concave arc groove 11,21 of part 2 is formed, you can leakproof element 3 is arranged in the first element 1 and the second element 2 Portion (as shown in Fig. 5~15).The inner side of foregoing leakproof element 3 sets inclined plane 31, and gap 32 is set between inclined plane 31, is able to The joint (as shown in figure 17) for two pipe fitting 4a, 4b being mutually connected is closed with foregoing leakproof element 3, you can generation prevents liquid from oozing The effect of leakage.Foregoing leakproof element 3 sets mesopore 33, is the mesopore 33 that leakproof element 3 is first passed through with a pipe fitting during installation, then will Leakproof element 3 is sheathed on two pipe fitting 4a, 4b cohesive end, then the concave arc groove with the element 2 of concave arc groove 11 and second of the first element 1 Set wherein for leakproof element 3, after the first element is combined with the second element, you can by leakproof element 3 to prevent two pipe fittings Cohesive end leak.
As shown in figs. 3 and 4, buckling element 5 of the present invention sets pulling piece 50, and foregoing pulling piece 50 sets fulcrum 500, obtained To be arranged at the buckling groove 13 of foregoing first element 1 with foregoing fulcrum 500.Foregoing pulling piece 50 sets the face of pulling 501, foregoing to pull Face 501 and the interior combination angle of foregoing fulcrum 500 are less than 90 degree, and downward condensed state is presented, more easy to be laborsaving in operation, and The solid effect of enhancing button.Pulling face 501 between two groups of fulcrums 500 and forming activity space 503 for foregoing pulling piece 50, it is convenient Pull the setting of part 51.Foregoing pulling piece 50, which is located on rear side of fulcrum, is respectively arranged with combined hole 502 and engagement groove 502a, positioned at pulling The dynamic inner side of face 501, is set and is positioned with the lower fulcrum 511 of Convenient button moving part 51.Foregoing buckling element 5, which is set, pulls part 51, foregoing Pull part 51 and set fulcrum 510 and lower fulcrum 511, the link of camber sheet is set between foregoing upper fulcrum 510 and lower fulcrum 511 Piece 512, both sides are to be recessed in foregoing upper fulcrum 510 and lower fulcrum 511 both sides, are allowed by the connecting piece 512 of camber sheet Buckling groove 23 of the upper fulcrum 510 exactly with the second element 2 fastens.
As shown in Fig. 5~14, buckling element 5 of the present invention is intended to before being combined with the first element 1 and the second element 2, is The combined hole 502 and engagement groove of foregoing pulling piece 50 are first arranged at the lower fulcrum 511 for pulling part 51 of foregoing buckling element 5 In 502a, then the upper fulcrum 510 of foregoing pulling piece 50 is arranged to the buckling groove 13 of foregoing first element 1, and pulled with foregoing The upper fulcrum 510 of part 51 is fastened on the buckling groove 23 of the second element 2, then firmly pulls foregoing pulling piece 50 downwards, will be downward Pull it is foregoing pull part 51, and the opening of the first element 1 and the second element 2 is closed, completes two be mutually connected with pipe thread engagement Pipe fitting 4a, 4b (as shown in figure 17).
As shown in Fig. 6~14, after adjacent two pipe fittings 4a, 4b overlap, i.e., with the foregoing element of first element 1 and second 2 engaging collar 20 is sticked in pipe fitting 4a, 4b outer surface, then with foregoing buckling element 5 by the first element 1 and the second element 2 It is fixed, you can to utilize common clamping two pipe fitting of pipe thread, you can two pipe fittings being mutually connected fully are combined, and by leakproof element 3 Two pipe fitting 4a, 4b joining place leak fluid is prevented, is not necessary to any hand-held tool, you can disassembled and assembled freely pipe thread, and have no screw spiral shell Got rusty after the permanent use of cap, it is not easy to remove the problem of, there is quick-replaceable pipe fitting, the accumulation dirt cleared up in pipe fitting, to keep It is unimpeded in pipe fitting, save maintenance manpower person.
As seen in figs. 15-17, when pipe thread of the present invention is fastened on two pipe fitting 4a, 4b cohesive end 4c, two pipe Part 4a, 4b cohesive end 4c only by leakproof element 3 as, to prevent fluid seepage, for water delivery pipe fitting, might have quick broken The problem of damaging seepage produces, and this is that meeting is in the first element 1 and second because after the first element 1 and the second element 2 are combined with each other Element 2 produces two contact gaps 60,61, and aforementioned contact gap 60,61 may be sealed shape, superfine small, even very big, and end regards pipe Depending on marriage relation between button and pipe fitting, when the cohesive end 4c for having liquid from two pipe fitting 4a, 4b is leaked into inside leakproof element 3 When, the liquid can increase as pipe fitting conveys the pressure of liquid, now, then can be by the concave arc groove 11 of foregoing first element 1 Set fastening end 140, engaging area 141 are combined with each other with engaging area 241, the fastening end 240 of the second element 2, or with foregoing the Engaging area 141 and two fastening ends 240 of the second element 2 set by the concave arc groove 11 of one element 1 are combined with each other, and contact is filled up in generation The effect in gap 60,61, allow by the concave arc groove 11 of foregoing first element 1 and combining to form for the concave arc groove 11 of the second element 2 Complete arc groove is supported in the side wall of leakproof element 3 whole to support completely, it is sufficient to prevents leakproof element 3 and is held in the mouth by two pipe fittings Connect the pressure of the liquid extruding of end seepage and the cohesive end in the first element 1 and the second element 2 deforms and causes fluid seepage, Leakproof element 3 never deforms, to lift the structure effectiveness of pipe thread.
To sum up refer to old, pipe thread of the present invention, be able to the fast of cohesive end as the pipe fitting of water-supply-pipe or sewage pipe etc. two Speed fastens and can prevent the function of cohesive end leak, and because with fast fastening in the function of the cohesive end of two pipe fittings, is able to Lifting pipe fitting matches somebody with somebody pipe construction, or the purposes of dismounting cleaning or maintenance pipe fitting, to save construction cost and manpower, and can prevent Leakproof element 3 is attacked by the fluid seepage of the cohesive end of two pipe fittings, avoids breakage, reduces maintenance frequency, the sequitur present invention Really possess progressive and practicality, be the composition of this case, as previous embodiment or accompanying drawing and non-limiting aspect of the invention Or occupation mode, the appropriate change or modification of any those of ordinary skill in the art, it all should be regarded as not departing from this The patent category of invention.

Claims (7)

1. a kind of quick pipe thread structure, it is characterised in that comprise at least:
First element, engaging collar is set in medial surface, be able to be sticked in the surface for the pipe fitting being mutually connected, it is foregoing to engage the interior of collar Side sets concave arc groove, obtains and is set for leakproof element, and one end of foregoing first member outboard sets integrally formed fulcrum, and with axle bed with First element connects, and thinks that the axial trough of the second element is set, the other end of foregoing first member outboard sets buckling groove, thinks fastening Element fastens;One end of the concave arc groove of foregoing first element sets fastening end, and the other end then sets engaging area, with corresponding to the second element Engaging area and the setting of fastening end be combined with each other running, to prevent liquid of the leakproof element by two pipe fitting cohesive end seepages The pressure of extruding and the cohesive end in the first element and the second element deforms, cause fluid seepage;
Second element, corresponding to foregoing first element, engaging collar is set in medial surface, be able to be sticked in another pipe fitting being mutually connected Outer surface, it is foregoing engaging collar on the inside of set concave arc groove, obtain for leakproof element set, one end of foregoing second member outboard sets axle Groove, it is disposed on above axial trough seat, and is integrally formed with axial trough seat and the second element, thinks that the fulcrum of foregoing first element is set Put, the foregoing second member outboard other end then sets buckling groove, in the first element and the second element two pipes that clamping phase is connected jointly After part, it is able to buckling element and is fastened on the respective buckling groove of foregoing first element and the second element, you can two pipes that will be mutually connected Part combines;One end of the concave arc groove of foregoing second element sets engaging area, and the other end then sets fastening end, with corresponding to foregoing first yuan The fastening end of part operates mutually combination with engaging area;
Buckling element, if pulling piece, foregoing pulling piece sets integrally formed fulcrum, pulls face, combined hole and engagement groove, be able to The fulcrum of foregoing pulling piece is arranged at the buckling groove of foregoing first element, and the foregoing face of pulling is provided above foregoing fulcrum, foregoing Combined hole and engagement groove are on the inside of face of pulling, and think that the lower fulcrum for pulling part is set, foregoing pulling piece pulls face and branch The interior combination angle of axle is less than 90 degree, is able to the running of more convenient force operation pulling piece, and foregoing pulling piece pulls face in two Activity space, the setting and running of Convenient button moving part are formed between group fulcrum;Foregoing buckling element, which is set, pulls part, foregoing to pull part If integrally formed upper and lower fulcrum and connecting piece, foregoing connecting piece is camber sheet, allows the part of pulling of buckling element to be able to accurately Be interlocked with the buckling groove of the second element, foregoing connecting piece is provided between foregoing upper and lower fulcrum, and be recessed in it is foregoing it is upper, Lower fulcrum both sides.
2. quick pipe thread structure as claimed in claim 1, it is characterised in that buckling element and the first element and the second element knot It is the combined hole and engagement groove that pulling piece is first arranged at the lower fulcrum for pulling part of buckling element before conjunction, then by pulling piece Fulcrum is arranged at the buckling groove of the first element, and is fastened on buckleing for the second element with the upper fulcrum for pulling part of foregoing buckling element Groove is closed, then firmly pulls pulling piece downwards, while pull pulls part downwards, and the opening of the first element and the second element is tight Close.
3. quick pipe thread structure as claimed in claim 1, it is characterised in that the ring after the first element is combined with the second element Concave arc groove sets leakproof element, and foregoing ring concave arc groove is formed by the concave arc groove of the first element and the concave arc groove of the second element, And leakproof element cladding is arranged to the cohesive end of two pipe fittings.
4. quick pipe thread structure as claimed in claim 1, it is characterised in that set in the both ends of the concave arc groove of the first element recessed The engaging area of shape, corresponding with two fastening ends corresponding to the second element combine running.
5. quick pipe thread structure as claimed in claim 4, it is characterised in that in the both ends of the bottom wall of the concave arc groove of the first element The fastening end to stretch out is set respectively, is operated with engaging the setting in area corresponding to the two of the second element.
6. quick pipe thread structure as claimed in claim 1, it is characterised in that the bottom wall both ends difference of the concave arc groove of the second element If the fastening end to stretch out, to coordinate the two of the first element the corresponding of engaging area to operate.
7. pipe thread structure as claimed in claim 1 quick, it is characterised in that be able to the fastening end of the first element, engaging area with Engaging area, the fastening end of second element are combined with each other;It is or mutual with two engaging areas of the first element and two fastening ends of the second element It is combined, you can the first element and the second element are produced and initially combine positioning action, avoids the first element and the second element left Right avertence is moved, and allows buckling element to be able to more rapidly accurately buckle the first element with the second element and consolidate.
CN201610863392.3A 2016-06-27 2016-09-29 Fast pipe buckle structure Pending CN107542981A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
TW105120142A TW201800692A (en) 2016-06-27 2016-06-27 Quick pipe buckle structure
TW105120142 2016-06-27

Publications (1)

Publication Number Publication Date
CN107542981A true CN107542981A (en) 2018-01-05

Family

ID=60965624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610863392.3A Pending CN107542981A (en) 2016-06-27 2016-09-29 Fast pipe buckle structure

Country Status (2)

Country Link
CN (1) CN107542981A (en)
TW (1) TW201800692A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201391704Y (en) * 2009-03-24 2010-01-27 上海瑞孚管路系统有限公司 Quick pipeline connector
CN202884306U (en) * 2012-11-19 2013-04-17 王伟亮 Pipeline fastener
CN103115210A (en) * 2011-11-16 2013-05-22 第一防蚀管业有限公司 Pipe joint structure
US20130187379A1 (en) * 2012-01-20 2013-07-25 Mueller International, Llc Slip-on coupling
CN203880270U (en) * 2014-05-23 2014-10-15 河南中泽新材料有限公司 Pipe clamp

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201391704Y (en) * 2009-03-24 2010-01-27 上海瑞孚管路系统有限公司 Quick pipeline connector
CN103115210A (en) * 2011-11-16 2013-05-22 第一防蚀管业有限公司 Pipe joint structure
US20130187379A1 (en) * 2012-01-20 2013-07-25 Mueller International, Llc Slip-on coupling
CN202884306U (en) * 2012-11-19 2013-04-17 王伟亮 Pipeline fastener
CN203880270U (en) * 2014-05-23 2014-10-15 河南中泽新材料有限公司 Pipe clamp

Also Published As

Publication number Publication date
TW201800692A (en) 2018-01-01

Similar Documents

Publication Publication Date Title
CN101660637B (en) Pressure hose for use in water-guiding system
JP2010139062A (en) Connection structure for waveform synthetic resin pipe, waveform synthetic resin pipe used for connection structure, and manufacturing method thereof
CN204829051U (en) Hose coupling
CN202972303U (en) Hoop of steel belt helical bellows
CN107542981A (en) Fast pipe buckle structure
JPS5913430Y2 (en) pipe fittings
CN203656389U (en) Novel double-wall corrugated pipe provided with square outside and round inside
JP2009047302A (en) Connection structure of metal-resin composite pipes and metal-resin composite pipe for use in the connection structure
CN202215868U (en) Barb type connection structure for steel-plastic composite pipe
CN106051325B (en) The composite reinforced pipe of overall steel-plastic and its processing method
CN205745818U (en) The union elbow being convenient to clean
CN204127538U (en) Pipe end socket type groove quick joint
CN210770800U (en) PVC tubular product with fastening flaring structure
CN210397968U (en) Impact-resistant pipe fitting
JP2011511914A5 (en)
CN206347913U (en) A kind of upper plate sealing structure of air-air type heat exchanger
CN215445525U (en) Socket joint coupling mechanism of polygon double-walled corrugated pipe
KR101743672B1 (en) Single-sided split construction Medium to large diameter pipeline Unscraped interior repair method
CN204922309U (en) Resistance to plucking takes off hydraulic hose assembly
US20090021005A1 (en) Connection structure of metal-resin composite pipes and metal-resin composite pipe for use in the connection structure
CN204437515U (en) A kind of reinforced steel-band double-wall corrugated pipeline
CN204345138U (en) Hose coupling anti-deforming sealing configuration
CN213040008U (en) Telescopic PE manages connecting piece
CN217736599U (en) Sewer pipe connecting structure
CN208719599U (en) A kind of steel-plastics composite pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180105