CN107526633A - Energy-saving control method, device, energy conserving system and the storage medium of electrical equipment - Google Patents
Energy-saving control method, device, energy conserving system and the storage medium of electrical equipment Download PDFInfo
- Publication number
- CN107526633A CN107526633A CN201710664422.2A CN201710664422A CN107526633A CN 107526633 A CN107526633 A CN 107526633A CN 201710664422 A CN201710664422 A CN 201710664422A CN 107526633 A CN107526633 A CN 107526633A
- Authority
- CN
- China
- Prior art keywords
- electrical equipment
- load
- power supply
- energy
- saving control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 69
- 238000003860 storage Methods 0.000 title claims abstract description 16
- 230000005611 electricity Effects 0.000 claims description 36
- 238000004891 communication Methods 0.000 claims description 21
- 238000004134 energy conservation Methods 0.000 abstract description 10
- 238000004378 air conditioning Methods 0.000 description 12
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 238000010586 diagram Methods 0.000 description 3
- 238000005406 washing Methods 0.000 description 3
- 238000001514 detection method Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000003287 optical effect Effects 0.000 description 2
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000001133 acceleration Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000005314 correlation function Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000009527 percussion Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for program control, e.g. control units
- G06F9/06—Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
- G06F9/46—Multiprogramming arrangements
- G06F9/48—Program initiating; Program switching, e.g. by interrupt
- G06F9/4806—Task transfer initiation or dispatching
- G06F9/4843—Task transfer initiation or dispatching by program, e.g. task dispatcher, supervisor, operating system
- G06F9/4881—Scheduling strategies for dispatcher, e.g. round robin, multi-level priority queues
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/042—Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/4185—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by the network communication
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02D—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
- Y02D10/00—Energy efficient computing, e.g. low power processors, power management or thermal management
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Automation & Control Theory (AREA)
- Health & Medical Sciences (AREA)
- Economics (AREA)
- Software Systems (AREA)
- General Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- General Health & Medical Sciences (AREA)
- Water Supply & Treatment (AREA)
- Manufacturing & Machinery (AREA)
- Quality & Reliability (AREA)
- Public Health (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The invention discloses a kind of energy-saving control method of electrical equipment, the energy-saving control method of the electrical equipment comprises the following steps:The power supply priority of the electrical equipment is determined according to the use information of the electrical equipment, the power supply priority is the power supply grade of the electrical equipment;The first present load is obtained, first present load is the total load for the electrical equipment for being currently completely in working condition, judges whether first present load is more than the first default load;If first present load is more than the described first default load, the electrical equipment of working condition is currently completely according to the power supply two priority classes.The invention also discloses a kind of energy-saving control device of electrical equipment, energy conserving system and storage medium.The present invention sets the power supply priority of electrical equipment according to the service condition of electrical equipment, by the purpose for being turned on and off reaching energy-conservation for intelligently controlling electrical equipment.
Description
Technical field
The present invention relates to Event tourism control field, more particularly to the energy-saving control method of electrical equipment, device, energy-conservation system
System and storage medium.
Background technology
With the arrival in electrification epoch, increasing enterprise, family rely on electrical equipment and carry out production and living.
There is different electrical equipments in existing each enterprise, family, various electrical equipments are during work
Power consumption is quite a few, and the electricity consumption of normal electrical equipment is unblamable, but is still existed, due to the use of electrical equipment
Person for close in time and caused by electric energy waste, park mode is provided with existing part electrical equipment, with according to user
The situation of operation, carries out the energy consumption of the reduction electrical equipment of intelligent control, but part home appliance still be present and do not have intelligence
The program that can be controlled, it is impossible to carry out intelligent open and close.
The above is only used for auxiliary and understands technical scheme, does not represent and recognizes that the above is existing skill
Art.
The content of the invention
It is a primary object of the present invention to provide a kind of energy-saving control method of electrical equipment, device, energy conserving system and deposit
Storage media, it is intended to according to the service condition of electrical equipment, be turned on and off reaching energy-conservation by intelligently control electrical equipment
Purpose.
To achieve the above object, the present invention provides a kind of energy-saving control method of electrical equipment, the section of the electrical equipment
Energy control method comprises the following steps:
The power supply priority of the electrical equipment, the power supply priority are determined according to the use information of the electrical equipment
It is the power supply grade of the electrical equipment;
The first present load is obtained, first present load is currently to be completely in the electrical equipment of working condition
Total load, judge whether first present load is more than the first default load;
It is currently complete according to the power supply two priority classes if first present load is more than the described first default load
The in running order electrical equipment in portion.
Alternatively, the use information according to the electrical equipment determines the step of the power supply priority of the electrical equipment
Suddenly, specifically include:
By in preset time period, frequency of use, usage time and/or the power consumption of the electrical equipment are as the electricity consumption
The use information of equipment;
The use information of the electrical equipment is obtained, and the use information is calculated by default weight, to obtain
The use parameter of the electrical equipment;
According to the power supply priority that the electrical equipment is determined using parameter.
Alternatively, the use information according to the electrical equipment determines the step of the power supply priority of the electrical equipment
After rapid, methods described also includes:
The classification of the power supply priority is set, according to electrical equipment described in the classification setting of the power supply priority
Closing flow path.
Alternatively, the first present load of the acquisition, first present load are be completely in working condition described
The total load of electrical equipment, after judging the step of whether first present load is more than the first default load, methods described
Also include:
If first present load keeps the current work of the electrical equipment no more than the described first default load
State, and first present load is detected in real time.
Alternatively, it is preferential according to the power supply if first present load is more than the described first default load
The step of level control is currently completely in the electrical equipment of working condition, specifically includes:
If first present load is more than the described first default load, the current institute for being completely in working condition is obtained
State the power supply priority of electrical equipment and corresponding classification;
According to the power supply priority and the corresponding classification, the current use for being completely in working condition is closed in control
Powered in electric equipment the elementary electrical equipment.
Alternatively, it is described to close according to the power supply priority and the corresponding classification, control and be currently completely in work
After the step of elementary electrical equipment of being powered in the electrical equipment of state, methods described also includes:
S1:The second present load is obtained, second present load is currently to be completely in the electricity consumption of working condition
The total load of equipment, judges whether second present load is more than the described first default load, if second present load
More than the described first default load, then work is currently completely according to the power supply priority and the corresponding classification, closing
Powered in the electrical equipment of state the elementary electrical equipment;
Circulation performs S1, until second present load is no more than the described first default load.
Alternatively, it is described to judge whether second present load was more than after described first default the step of loading, institute
Stating method also includes:
If second present load judges whether second present load is big no more than the described first default load
In the second default load;
If second present load is more than the described second default load, the work shape of presently described electrical equipment is kept
State;
If second present load is no more than the described second default load, according to the described second power supply priority, control
System opens electrical equipment described in grade highest of being powered in the electrical equipment being turned off.
Alternatively, it is preferential according to the power supply if first present load is more than the described first default load
After the step of level control is currently completely in the electrical equipment of working condition, methods described also includes:
When detecting that user triggers the start-up command of the electrical equipment, based on the use corresponding to the start-up command
The load of electric equipment and first present load, judge whether to need to close other the described electricity consumptions for being currently at working condition
Equipment..
To achieve the above object, the present invention also provides a kind of energy-saving control device of electrical equipment, the electrical equipment
Energy-saving control device includes:Electric quantity acquisition module, communication module, memory, processor and it is stored on the memory and can
The Energy Saving Control program for the electrical equipment run on the processor, wherein:
The electric quantity acquisition module, for gathering the use information of electrical equipment and obtaining the load of the electrical equipment,
The load includes currently being completely in point of the total load of the electrical equipment of working condition and each electrical equipment
Load;
The communication module, for receiving control instruction;
When the Energy Saving Control program of the electrical equipment is by the computing device, the section of electrical equipment described above is realized
The step of energy control method.
To achieve the above object, the present invention also provides a kind of energy conserving system, and the energy conserving system includes:Above-mentioned electricity consumption is set
Standby energy-saving control device.
In addition, to achieve the above object, the present invention also provides a kind of storage medium.
The Energy Saving Control program of electrical equipment, the Energy Saving Control program of the electrical equipment are stored with the storage medium
The step of energy-saving control method of electrical equipment as described above is realized when being executed by processor.
A kind of energy-saving control method for electrical equipment that the embodiment of the present invention proposes, comprises the following steps:According to the use
The use information of electric equipment determines the power supply priority of the electrical equipment, and the power supply priority is the confession of the electrical equipment
Electric grade;The first present load is obtained, first present load is currently to be completely in the electrical equipment of working condition
Total load, judge whether first present load is more than the first default load;If first present load is more than described
First default load, then the electrical equipment of working condition is currently completely according to the power supply two priority classes.This hair
The bright use information by detecting electrical equipment, and according to the power supply priority of use information setting electrical equipment, detecting
Multiple electrical equipments work when causing circuit load excessive simultaneously, by combine electrical equipment power supply priority and circuit it is current
Load, control are closed the relatively low electrical equipment of part power supply priority, with the switch by intelligently controlling electrical equipment, reached
The Energy Saving Control of electrical equipment.
Brief description of the drawings
Fig. 1 is the apparatus structure schematic diagram for the hardware running environment that scheme of the embodiment of the present invention is related to;
Fig. 2 is the schematic flow sheet of the embodiment of energy-saving control method one of electrical equipment of the present invention;
Fig. 3 is the refinement schematic flow sheet of the step S10 of the energy-saving control method of electrical equipment in Fig. 2;
Fig. 4 is the refinement schematic flow sheet of the step S30 of the energy-saving control method of electrical equipment in Fig. 2;
Fig. 5 is the schematic flow sheet of another embodiment of energy-saving control method of electrical equipment of the present invention;
Fig. 6 is the schematic flow sheet that each embodiment of energy-saving control method of electrical equipment of the present invention combines;
Fig. 7 is the concrete scene schematic diagram of the specific method of the Energy Saving Control of electrical equipment of the present invention.
The realization, functional characteristics and advantage of the object of the invention will be described further referring to the drawings in conjunction with the embodiments.
Embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The primary solutions of the embodiment of the present invention are:Electric quantity acquisition mould is installed in total lock part that independent circuit controls
Block, communication module;Electric quantity acquisition module, for taking use information (use information i.e., the electricity consumption of various electrical equipments in circuit
The information such as the frequency of use of a period of time of equipment, electrical power, usage time) and according to corresponding use information using related
Power supply priority is calculated, and the relatively low electrical equipment of power supply priority is closed in control when the load of circuit is larger;Communication
Module, for receiving control information, and realize the electrical signal communication between a variety of electrical equipments.
It is turned on and off because prior art part electrical appliance can be controlled intelligently, but and in the absence of total according to circuit
Load control circuit in all electrical appliances operation technical scheme.
As shown in figure 1, Fig. 1 is the apparatus structure schematic diagram for the hardware running environment that scheme of the embodiment of the present invention is related to.
Device of the embodiment of the present invention can be PC or smart mobile phone, tablet personal computer, integrate different electronic components
Intelligent control chip, pocket computer etc. have the packaged type appliance arrangement of display function, and the present invention is applied to described in Fig. 1
Device, present apparatus installation are lived at total lock with circuit control, carry out the electricity control of electrical equipment, or the present apparatus is divided into two portions
Part, a part are arranged on the total lock part of power supply, and for the control of circuit power, another part is arranged in mobile terminal, just
In artificially controlling, communicated to connect between two parts;With reference to Fig. 7, as shown in Figure 7, information connects between each electrical equipment
Logical, electric quantity acquisition module communicates to connect with communication module and mobile phone terminal, can remotely control opening for electrical equipment with user
Machine or closing reach the purpose of energy-conservation.
As shown in figure 1, the device can include:Processor 1001, such as CPU, network interface 1004, user interface
1003, memory 1005, communication bus 1002.Wherein, communication bus 1002 is used to realize the connection communication between these components.
User interface 1003 can include display screen (Display), input block such as keyboard (Keyboard), optional user interface
1003 can also include wireline interface, the wave point of standard.Network interface 1004 can optionally connect including the wired of standard
Mouth, wave point (such as WI-FI interfaces).Memory 1005 can be high-speed RAM memory or stable memory
(non-volatile memory), such as magnetic disk storage.Memory 1005 optionally can also be independently of aforementioned processor
1001 storage device.
Alternatively, device can also include electric quantity acquisition module, communication module, camera, RF (Radio Frequency,
Radio frequency) circuit, sensor, voicefrequency circuit, WiFi module etc..Wherein, electric quantity acquisition module is used for each electricity consumption in Acquisition Circuit
The use information of the electricity of equipment;Communication module, passed for receiving control information, and by the use information of each electrical equipment
Pass;Sensor ratio such as optical sensor, motion sensor and other sensors.Specifically, optical sensor may include that ambient light passes
Sensor and proximity transducer, wherein, ambient light sensor can adjust the brightness of display screen according to the light and shade of ambient light, approach
Sensor can close display screen and/or backlight when device is moved in one's ear.As one kind of motion sensor, gravity accelerates
The size that sensor can detect in all directions (generally three axles) acceleration is spent, size and the side of gravity are can detect that when static
To application (such as horizontal/vertical screen switching, dependent game, magnetometer pose calibrating), Vibration identification available for identification device posture
Correlation function (such as pedometer, percussion) etc.;Certainly, device can also configure gyroscope, barometer, hygrometer, thermometer, infrared
The other sensors such as line sensor, will not be repeated here.
It will be understood by those skilled in the art that the restriction of the apparatus structure shown in Fig. 1 not structure twin installation, can be wrapped
Include than illustrating more or less parts, either combine some parts or different parts arrangement.
As shown in figure 1, as a kind of storage medium, storage medium be stored with electrical equipment Energy Saving Control program it is hard
Part, it can be read and run by computer or other-end;Memory 1005 in can include operating system, network service
The Energy Saving Control program of module, Subscriber Interface Module SIM and electrical equipment.
In the device shown in Fig. 1, network interface 1004 is mainly used in connecting background server, is carried out with background server
Data communicate;User interface 1003 is mainly used in connecting client (user terminal), enters row data communication with client;And processor
1001 can be used for calling the Energy Saving Control program of electrical equipment stored in memory 1005, and perform following operate:
The power supply priority of the electrical equipment, the power supply priority are determined according to the use information of the electrical equipment
It is the power supply grade of the electrical equipment;
The first present load is obtained, first present load is currently to be completely in the electrical equipment of working condition
Total load, judge whether first present load is more than the first default load;
It is currently complete according to the power supply two priority classes if first present load is more than the described first default load
The in running order electrical equipment in portion.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
The use information according to the electrical equipment determines the step of power supply priority of the electrical equipment, specifically
Including:
By in preset time period, frequency of use, usage time and/or the power consumption of the electrical equipment are as the electricity consumption
The use information of equipment;
The use information of the electrical equipment is obtained, and the use information is calculated by default weight, to obtain
The use parameter of the electrical equipment;
According to the power supply priority that the electrical equipment is determined using parameter.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
After the use information according to the electrical equipment determines the step of power supply priority of the electrical equipment,
Methods described also includes:
The classification of the power supply priority is set, according to electrical equipment described in the classification setting of the power supply priority
Closing flow path.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
The first present load of the acquisition, first present load is to be completely in the electrical equipment of working condition
Total load, after judging the step of whether first present load is more than the first default load, methods described also includes:
If first present load keeps the current work of the electrical equipment no more than the described first default load
State, and first present load is detected in real time.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
If first present load is more than the described first default load, worked as according to the power supply two priority classes
Before the step of being completely in the electrical equipment of working condition, specifically include:
If first present load is more than the described first default load, the current institute for being completely in working condition is obtained
State the power supply priority of electrical equipment and corresponding classification;
According to the power supply priority and the corresponding classification, the current use for being completely in working condition is closed in control
Powered in electric equipment the elementary electrical equipment.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
It is described that the current institute for being completely in working condition is closed according to the power supply priority and the corresponding classification, control
After stating the step of elementary electrical equipment is powered in electrical equipment, methods described also includes:
S1:The second present load is obtained, second present load is currently to be completely in the electricity consumption of working condition
The total load of equipment, judges whether second present load is more than the described first default load, if second present load
More than the described first default load, then work is currently completely according to the power supply priority and the corresponding classification, closing
Powered in the electrical equipment of state the elementary electrical equipment;
Circulation performs S1, until second present load is no more than the described first default load.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
Described to judge whether second present load was more than after described first default the step of loading, methods described is also
Including:
If second present load judges whether second present load is big no more than the described first default load
In the second default load;
If second present load is more than the described second default load, the work shape of presently described electrical equipment is kept
State;
If second present load is no more than the described second default load, according to the described second power supply priority, control
System opens electrical equipment described in grade highest of being powered in the electrical equipment being turned off.
Further, processor 1001 can call the Energy Saving Control program of the electrical equipment stored in memory 1005,
Also perform following operate:
If first present load is more than the described first default load, worked as according to the power supply two priority classes
Before after the step of being completely in the electrical equipment of working condition, methods described also includes:
When detecting that user triggers the start-up command of the electrical equipment, based on the use corresponding to the start-up command
The load of electric equipment and first present load, judge whether to need to close other the described electricity consumptions for being currently at working condition
Equipment.
Reference picture 2, in an a kind of embodiment of the energy-saving control method of electrical equipment of the present invention, the section of the electrical equipment
Energy control method includes:
Step S10, the power supply priority of the electrical equipment, the confession are determined according to the use information of the electrical equipment
Electric priority is the power supply grade of the electrical equipment.
Controlled in enterprise or house current and electric quantity acquisition module is set at total lock, utilize electric quantity acquisition module Acquisition Circuit
In each electrical equipment electricity use information, and according to the use information (use information of electrical equipment:Preset time period makes
With number, frequency of use, usage time and electric quantity consumption), i.e. electric quantity acquisition module can be set preset time period and gather each use
The electricity use information of electric equipment, and each electrical equipment is determined by corresponding computation rule according to the use information collected
Power supply priority.
Step S20, obtains the first present load, and first present load is currently to be completely in the described of working condition
The total load of electrical equipment, judges whether first present load is more than the first default load.
Load (the load of circuit of circuit when obtaining electrical equipment work:Can to the electric current that is interpreted as in circuit or
The specifying information for each electrical equipment power consumption that person's general power is used in indication circuit), and will be total negative in the circuit got
Load is used as the first present load, compares the magnitude relationship of the first present load and the first default load, and judges that first is current negative
Carry and whether be more than first default load (the first default load:According to the quantity of the electrical equipment connected in circuit, electrical equipment
The actual conditions of the electricity consumptions such as usage time interval are configured;That is, the use electric loading that enterprise's work hours section is set is larger, during rest
Between the load that sets of section it is relatively low, when the use load of reality is more than default load, illustrate that business electrical is abnormal, during enterprise's rest
Between section set default load be 0W, if being not turned off electrical equipment in time of having a rest section company personnel, automatic pass can be controlled
Close, if the load of the setting of upper plate period is 5000W, when load is higher than 5000W, part electrical equipment is closed in control).
Step S30, if first present load is more than the described first default load, according to the power supply priority control
The current electrical equipment for being completely in working condition of system.
Obtained the first present load is detected in circuit and is more than the first default load, in order to realize the purpose of energy-conservation, it is necessary to
(control instruction of control can be set according to the electrical equipment of control, i.e. the equipment such as air-conditioning, can use reduces electricity consumption for control
The equipment such as the frequency of equipment, refrigerator, water heater can use the instruction, computer etc. of pause using the instruction closed) some are in
The electrical equipment of working condition, according to the power supply priority obtained according to the setting of electrical equipment use information, and close current work
Make the minimum electrical equipment of priority of being powered under state, the low electrical equipment of power supply priority is in running order, but to
The use at family influences little electrical equipment (for example, the water heater that unmanned usage time is heated up water every the period;With reference to it is different when
Between section the priority of the electrical equipment corresponded to can be set, i.e. the priority of each electrical equipment is not fixed).Together
When the first default load can also be set it is larger, to prevent circuit from tripping, for example, in the first preset negative of family's electrical equipment
Carry and be likely to occur the larger circuit of circuit load for 5500W, load in 5500W circuit default more than first of the total load of household electricity
Temperature is higher to have fire risk, then obtains the power supply priority of all electrical equipments of work at present in circuit, and controls pass
The minimum electrical equipment of priority of powering is closed in work at present electrical equipment.
The present invention is by detecting the use information of electrical equipment in the present embodiment, and sets electricity consumption to set according to use information
Standby power supply priority, when detecting that multiple electrical equipments while work cause circuit load excessive, electrical equipment will be combined
Power supply priority and circuit present load, the relatively low electrical equipment of part power supply priority is closed in control, to pass through intelligence
Ground controls the switch of electrical equipment, reaches the Energy Saving Control of electrical equipment, and the big I of the first default load is accordingly first adjusted
It is whole, it also can reach the purpose of control circuit safety, will be total in the use information and circuit of each electrical equipment in the present invention
Load combines, can more accurately control circuit load, reach the purpose of Energy Saving Control.
Reference picture 3, in the step S10 of the energy-saving control method of electrical equipment of the present invention, the step S10 includes:
Step S11, by preset time period, frequency of use, usage time and/or the power consumption conduct of the electrical equipment
The use information of the electrical equipment.
First set the period (set the period can be adjusted, can also carry out interval time section it is accumulative situations such as)
Detection electrical equipment corresponds to frequency of use, usage time, access times and/or the power consumption of period to be made as electrical equipment
With information, for example, the frequency of use of one month or one all home-use each electrical equipment of detection, usage time, using secondary
Number and/or power consumption (power consumption:Because part electrical appliance is to be spaced work so can not be directly by the electric work of electrical equipment
Rate and switching on and shutting down time are directly calculated), and the data message obtained according to statistics corresponds to the service condition of electrical equipment.
Step S12, obtains the use information of the electrical equipment, and based on the use information carried out by default weight
Calculate, to obtain the use parameter of the electrical equipment.
The use information for the electrical equipment that electric quantity acquisition module obtains, and by according to the rule process use information of setting,
Obtain the use parameter of electrical equipment, for example, in household electricity electrical equipment have TV, refrigerator, washing machine, air-conditioning, water heater,
Micro-wave oven, electromagnetic oven, electric cooker and computer, count the information such as the access times of one week electrical equipment, usage time, power consumption
, and according to service condition set weight access times weight or other computation rules, such as weighted average or
The parameter collected add, subtracted, multiplication and division, square, the calculating of evolution etc., supplementary notes are that weight and computation rule can
To be formulated according to actual conditions, the calculating formula in the present invention does not do disclosure.
Step S13, according to the power supply priority that the electrical equipment is determined using parameter.
It will be associated between the use parameter of determination and power supply priority, and electricity consumption correspondingly obtained by the use parameter of determination
The power supply priority of equipment, can accordingly it be adjusted by adjusting the weight of the electrical equipment in use information in the present embodiment
Using parameter, so that the power supply priority of electrical equipment is also adjusted accordingly.It is determined that the power supply priority of electrical equipment
Be for the load according to whole circuit, carry out Energy Saving Control, or in circuit load excessive when, it is corresponding that to close power supply preferential
The relatively low electrical equipment of level, therefore the power supply priority of electrical equipment accordingly can be divided into two classes in the present embodiment, with root
According to the closing flow path of the classification setting electrical equipment of power supply priority, such as:The power supply of in running order electrical equipment is excellent
Higher three of first level are divided into the first kind, are divided into the second class remainingly, and the electrical equipment for being divided into first kind power supply priority is being controlled
, it is necessary to which user is confirmed when system is closed, the electrical equipment of the second class power supply priority is when controlling closing, it is only necessary to which prompting is used
Family is, it is necessary to which supplementary notes are that power supply priority can also can voluntarily be set with classification one-to-one corresponding and set electricity consumption by user
It is standby carried out with classification it is corresponding.
The use information of electrical equipment is obtained in the present embodiment, and use information setting weight is carried out that electricity consumption is calculated
The use parameter of equipment, the power supply priority using parameter and home appliance of electrical equipment is associated, can be power supply
Priority more science, and there is controllability, it is determined that after the power supply priority of electrical equipment, pass can also be correspondingly arranged
Close flow so that the control of electrical equipment is more intelligent, avoids and occurs when only electrical equipment is closed in control program control
Electrical equipment mistake close situation.
Reference picture 4, in the energy-saving control method step S30 of electrical equipment of the present invention, the step S30 includes:
Step S31, if first present load is more than the described first default load, acquisition is currently completely in work
The power supply priority of the electrical equipment of state and corresponding classification.
The first present load is more than first default load (the first default load in circuit:According to electrical equipment in circuit
Connection or circuit tripping operation load be configured, i.e. the tripping voltage that the first preset value can be set lower than circuit prevents
Circuit trips) when, classification corresponding to the power supply priority and power supply priority of current all work electrical equipment is obtained, it is necessary to mend
Fill explanation, the priority of electrical equipment can in above circuit all electrical equipments priority, existing circuit is one
The office of enterprise, electrical equipment include:Air-conditioning, water fountain, micro-wave oven, 50 computers, refrigerator, printer and electric light are some,
Preset the power supply priority of whole electrical equipments, when electrical equipment does not work in part, in running order electrical equipment
Priority can still uniquely determine, and be correspondingly arranged the classification of electrical equipment, the classification of electrical equipment and priority can be with
It is uncorrelated.
Step S32, according to the power supply priority and the corresponding classification, control is closed and is currently completely in working condition
The electrical equipment in power the elementary electrical equipment.
According to the classification of power supply priority and priority of powering, corresponding electrical equipment is closed in control, for example, existing circuit
For the circuit of household electricity, the first default load is 3500W in circuit, and now circuit load in circuit is 5000W, and electricity consumption is set
Standby is water heater, refrigerator, washing machine, air-conditioning, television set, micro-wave oven, to the power supply priority that should determine that and is categorized as:Water heater
Power supply 1 grade of 2 class of priority, the class of refrigerator power supply priority 3 level 1, washing machine power supply 2 grade of 1 class of priority, air-conditioning power supply priority 4
2 classes of level, television set power supply 5 grade of 1 class of priority, micro-wave oven power supply 6 grade of 2 class of priority, (power supply highest priority herein is 1
Level, minimum 6 grades) according to power supply priority the minimum micro-wave oven of priority of powering is first shut off, notice is used when micro-wave oven is closed
Family, and closing is automatically controlled, load after micro-wave oven is closed in circuit is changed into 4000W, still default more than first to load, then
Closing television machine power supply 5 grade of 2 class of priority is corresponded to according to power supply priority again, one is categorized as because television set is preferentially corresponding
Class, user is prompted to confirm that the electric quantity acquisition module in the communication module and circuit of the mobile phone of user (is carried out letter by closing television machine
Breath connection, user can control the opening and closing of electrical equipment by mobile phone remote, realize the Energy Saving Control of circuit), if
User's refusal closes then circuit acquisition module and sets closing air-conditioning, 4 grade of 2 class of power supply priority of air-conditioning, and air-conditioning is closed and led to
Know user.
Total load in the present embodiment in circuit is excessive, it is necessary to when carrying out Energy Saving Control, it is first determined electrical equipment
Power supply priority after classify, it is necessary to further determine that corresponding to electrical equipment (or power supply priority), can be controlled in energy-conservation
When processed, can more science, loaded in ensureing circuit it is relatively low in the case of, the specific feelings of each electrical equipment can also be taken into account
Condition, prevent electrical equipment from automatically controlling the situation closed and mistake closing occur.
Reference picture 5, in a kind of another embodiment of the energy-saving control method of electrical equipment of the present invention, the electrical equipment
Also include after energy-saving control method step S30:
Step S40, obtains the second present load, and second present load is currently to be completely in the described of working condition
The total load of electrical equipment, judges whether second present load is more than the described first default load.
Step S50, if second present load is more than the described first default load, according to the power supply priority and
The corresponding classification, closing are currently completely in the electrical equipment of working condition the elementary electricity consumption of powering and set
It is standby, until second present load is no more than the described first default load.
When closing in circuit, suspending and/or reduce by one electrical equipment of working frequency, the corresponding drop of load in circuit
It is low, using the load closed after an electrical equipment in circuit as the second present load, and the second present load and first is pre-
If value is compared, when present load is still more than the first default load in circuit, then continues to close currently whole work and use
Powered in electric equipment elementary electrical equipment, until second present load is no more than the described first default load;Need
To be remarked additionally, need to combine in the closing process of electrical equipment and divide corresponding to electrical equipment (or power supply priority)
Class, prevent electrical equipment mistake from closing.
Step S60, if second present load judges that described second is current negative no more than the described first default load
Carry and whether be more than the second default load;If second present load is more than the described second default load, keep presently described
The working condition of electrical equipment;If second present load supplies no more than the described second default load according to described second
Electrical equipment described in grade highest of being powered in the electrical equipment being turned off is opened in electric priority, control.
In the second present load no more than the first default load, i.e. the load in circuit meets that the requirement of Energy Saving Control makes,
Then determine whether the second present load is more than second default load (the second default load:Second default load is by first
Default load and the load of electrical equipment together decide on, and its purpose is to prevent from the open and close repeatedly of electrical equipment from shortening to use
The working life of electric equipment);If the second present load is more than the second default load, the working condition of current power equipment is kept
(specific flow combination Fig. 6, in figure 6 the judgment rule of preset value) for example, the first default load is 5000W, electrical equipment
Load be 1000W, it be 3000W that can be correspondingly arranged the second default load, if the load after electrical equipment closing in circuit is
4000W, then in holding circuit current power equipment working condition, make the load in circuit constant, if if electricity consumption is set in circuit
Load after standby closing in circuit is 2000W, then the electricity consumption for highest priority of being powered in the electrical equipment being turned off is opened in control
Equipment, control combine power supply priority and the classification of electrical appliance, specific step during opening:Circuit early stage is obtained first
The record for the electrical equipment that middle control is closed:6 grade of 2 class of micro-wave oven power supply priority, television set power supply priority 5 grade of 2 class, air-conditioning
4 grade of 2 class of power supply priority, it is necessary to first turn on air-conditioning and notify user when now electrical equipment is opened, can combine user's
Operation carries out the opening and closing of specific electrical equipment, it is necessary to which supplementary notes are:The control instruction of user can preferentially with setting
Control instruction, i.e. in the minimum electrical equipment of the manually opened power supply priority of user, now in order to prevent from being likely to occur
The minimum electrical equipment of power supply priority is closed in control instruction control, thus sets the manually opened electrical equipment of user can be
In the series for the electrical equipment for entering Energy Saving Control after unlatching half an hour.
Control electrical equipment is specifically illustrated in the present embodiment opens the relation disconnected between default load, Yong Huke
To set the default load of different time sections, use is accordingly controlled according to the power supply priority for the different electrical equipments being calculated
The intelligent control of energy-conservation is realized in the opening and closing of electric equipment, while ensures the degree of accuracy of control.
In the embodiment of the energy-saving control method of electrical equipment of the present invention, in addition to:When detect user triggering described in
It is currently negative based on the load of the electrical equipment corresponding to the start-up command and described first during the start-up command of electrical equipment
Carry, judge whether to need to close other the described electrical equipments for being currently at working condition.
It is less than the safe bearing load in circuit in the circuit total load that electrical equipment is set, in one electrical equipment of user,
User triggers the start-up command of electrical equipment, and electrical equipment is not opened directly, the circuit acquisition module of circuit, collects user's triggering
The load for electrical equipment of starting shooting, and the load of electrical equipment is added with the total load of current circuit to obtain what electrical equipment was opened
Circuit load, the circuit load that electrical equipment is opened is compared with the safe bearing load of circuit, if the circuit that electrical equipment is opened is born
The safe bearing load more than circuit is carried, then the equipment for being first shut off a work at present power supply for electrical equipment priority, is added again
Compare, until electrical equipment is opened less than being corresponded to again after the safe bearing load of circuit, if the circuit load that electrical equipment is opened is little
In the safe bearing load of circuit, then the electrical equipment that user triggers power-on command can be directly opened.For example, the tripping operation load of circuit
For 6600W, the circuit safety load of setting is 5600W, and the load of current circuit is 4500W, and user needs to open 2000W sky
Adjust, if directly opening 2000W air-conditioning, the circuit load 6500W that air-conditioning is opened, more than the safe bearing load of the circuit of setting
5600W, the minimum circuit arrangement of priority of being powered in current circuit, then corresponding unlatching user's start-up command pair can be first shut off
The electrical equipment answered.
Information communication between each electrical equipment in the present embodiment, circuit acquisition module can be with total in Acquisition Circuit
Load, while the load of each electrical equipment is also corresponding with electric quantity acquisition module, each electricity consumption is set in circuit acquisition module
It is standby to be controlled accordingly, while Energy Saving Control, can more intelligently easily in control circuit each electrical equipment it
Between opening and closing.
In addition, the embodiment of the present invention also proposes a kind of energy-saving control device of electrical equipment.
The energy-saving control device of the electrical equipment includes:Electric quantity acquisition module, communication module, memory, processor and
The Energy Saving Control program for the electrical equipment that can be run on the memory and on the processor is stored in, wherein:
The electric quantity acquisition module, for gathering the use information of electrical equipment and obtaining the load of the electrical equipment,
The load includes currently being completely in point of the total load of the electrical equipment of working condition and each electrical equipment
Load.
The communication module, for receiving control instruction, information between the communication module and circuit acquisition module in circuit
Connection, communication module can realize the information communication between other electrical equipments.
The section of electrical equipment described above is realized when the Energy Saving Control program of the electrical equipment is by the computing device
Can control method each embodiment the step of.
Wherein, the method realized when the energy-conservation program of electrical equipment is performed can refer to the energy-conservation of electrical equipment of the present invention
Each embodiment of method, here is omitted.
In a kind of embodiment of energy conserving system of the present invention;
The energy conserving system includes the energy-saving control device of above-mentioned electrical equipment.
Communicated to connect in the energy conserving system between the energy-saving control device of electrical equipment, the Energy Saving Control dress of electrical equipment
The Energy Saving Control program of electrical equipment is preserved in putting, is realized when the Energy Saving Control program of electrical equipment is by the computing device
The step of energy-saving control method of electrical equipment described above each embodiment.
Wherein, the method realized when the energy-conservation program of electrical equipment is performed can refer to the energy-conservation of electrical equipment of the present invention
Each embodiment of method, here is omitted
In addition, in a kind of embodiment of storage medium of the present invention.
The energy-conservation program of electrical equipment is stored with the storage medium, the energy-conservation program of the electrical equipment is by processor
The step in the power-economizing method such as electrical equipment is realized during execution.
Wherein, the method realized when the energy-conservation program of electrical equipment is performed can refer to the energy-conservation of electrical equipment of the present invention
Each embodiment of method, here is omitted.
It should be noted that herein, term " comprising ", "comprising" or its any other variant are intended to non-row
His property includes, so that process, method, article or system including a series of elements not only include those key elements, and
And also include the other element being not expressly set out, or also include for this process, method, article or system institute inherently
Key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that including this
Other identical element also be present in the process of key element, method, article or system.
The embodiments of the present invention are for illustration only, do not represent the quality of embodiment.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment side
Method can add the mode of required general hardware platform to realize by software, naturally it is also possible to by hardware, but in many cases
The former is more preferably embodiment.Based on such understanding, technical scheme is substantially done to prior art in other words
Going out the part of contribution can be embodied in the form of software product, and the computer software product is stored in one as described above
In storage medium (such as ROM/RAM, magnetic disc, CD), including some instructions to cause a table apparatus (can be mobile phone, calculate
Machine, server, air conditioner, or network equipment etc.) perform method described in each embodiment of the present invention.
The preferred embodiments of the present invention are these are only, are not intended to limit the scope of the invention, it is every to utilize this hair
The equivalent structure or equivalent flow conversion that bright specification and accompanying drawing content are made, or directly or indirectly it is used in other related skills
Art field, is included within the scope of the present invention.
Claims (11)
- A kind of 1. energy-saving control method of electrical equipment, it is characterised in that the energy-saving control method of the electrical equipment include with Lower step:The power supply priority of the electrical equipment is determined according to the use information of the electrical equipment, the power supply priority is institute State the power supply grade of electrical equipment;Obtain the first present load, first present load be currently be completely in working condition the electrical equipment it is total Load, judges whether first present load is more than the first default load;If first present load is more than the described first default load, currently all located according to the power supply two priority classes In the electrical equipment of working condition.
- 2. the energy-saving control method of electrical equipment as claimed in claim 1, it is characterised in that described according to the electrical equipment Use information the step of determining the power supply priority of the electrical equipment, specifically include:By in preset time period, frequency of use, usage time and/or the power consumption of the electrical equipment are as the electrical equipment Use information;The use information of the electrical equipment is obtained, and the use information is calculated by default weight, it is described to obtain The use parameter of electrical equipment;According to the power supply priority that the electrical equipment is determined using parameter.
- 3. the energy-saving control method of electrical equipment as claimed in claim 1 or 2, it is characterised in that described according to the electricity consumption After the use information of equipment determines the step of power supply priority of the electrical equipment, methods described also includes:The classification of the power supply priority is set, according to the pass of electrical equipment described in the classification setting of the power supply priority Close flow.
- 4. the energy-saving control method of electrical equipment as claimed in claim 1, it is characterised in that the acquisition first is currently negative Carry, first present load is the total load for the electrical equipment for being completely in working condition, judges that described first is current After the step of whether load is more than the first default load, methods described also includes:If first present load keeps the work shape that the electrical equipment is current no more than the described first default load State, and first present load is detected in real time.
- 5. the energy-saving control method of electrical equipment as claimed in claim 3, it is characterised in that if described first is current negative Carry and be more than the described first default load, then the electricity consumption of working condition is currently completely according to the power supply two priority classes The step of equipment, specifically include:If first present load is more than the described first default load, the current use for being completely in working condition is obtained The power supply priority of electric equipment and corresponding classification;According to the power supply priority and the corresponding classification, control is closed the current electricity consumption for being completely in working condition and set The standby middle elementary electrical equipment of power supply.
- 6. the energy-saving control method of electrical equipment as claimed in claim 5, it is characterised in that described preferential according to the power supply Level and the corresponding classification, control are closed and are currently completely in the electrical equipment of working condition elementary institute of powering After the step of stating electrical equipment, methods described also includes:S1:The second present load is obtained, second present load is currently to be completely in the electrical equipment of working condition Total load, judge whether second present load is more than the described first default load, if second present load is more than Described first default load, then working condition is currently completely according to the power supply priority and the corresponding classification, closing The electrical equipment in power the elementary electrical equipment;Circulation performs S1, until second present load is no more than the described first default load.
- 7. the energy-saving control method of electrical equipment as claimed in claim 3, it is characterised in that described to judge that described second is current After the step of whether load is more than the described first default load, methods described also includes:If second present load load default no more than described first, judge whether second present load is more than the Two default loads;If second present load is more than the described second default load, the working condition of presently described electrical equipment is kept;If second present load is no more than the described second default load, according to the described second power supply priority, control is opened Open electrical equipment described in grade highest of being powered in the electrical equipment being turned off.
- 8. the energy-saving control method of electrical equipment as claimed in claim 1, it is characterised in that if described first is current negative Carry and be more than the described first default load, then the electricity consumption of working condition is currently completely according to the power supply two priority classes After the step of equipment, methods described also includes:When detecting that user triggers the start-up command of the electrical equipment, set based on the electricity consumption corresponding to the start-up command Standby load and first present load, other the described electricity consumptions for judging whether to need closing to be currently at working condition are set It is standby.
- 9. a kind of energy-saving control device of electrical equipment, it is characterised in that the energy-saving control device of the electrical equipment includes:Electricity Amount acquisition module, communication module, memory, processor and it is stored on the memory and can runs on the processor The Energy Saving Control program of electrical equipment, wherein:The electric quantity acquisition module, it is described for gathering the use information of electrical equipment and obtaining the load of the electrical equipment Load includes point load for being currently completely in the total load of the electrical equipment of working condition and each electrical equipment;The communication module, for receiving control instruction;When the Energy Saving Control program of the electrical equipment is by the computing device, realize such as any one of claim 1 to 8 institute The step of energy-saving control method for the electrical equipment stated.
- 10. a kind of energy conserving system, it is characterised in that the energy conserving system includes:The energy-saving control device of electrical equipment as claimed in claim 9.
- 11. a kind of storage medium, it is characterised in that the Energy Saving Control program of electrical equipment, institute are stored with the storage medium State and realize that the electricity consumption as any one of claim 1 to 8 is set when the Energy Saving Control program of electrical equipment is executed by processor The step of standby energy-saving control method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710664422.2A CN107526633B (en) | 2017-08-04 | 2017-08-04 | Energy-saving control method and device for electric equipment, energy-saving system and storage medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710664422.2A CN107526633B (en) | 2017-08-04 | 2017-08-04 | Energy-saving control method and device for electric equipment, energy-saving system and storage medium |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107526633A true CN107526633A (en) | 2017-12-29 |
CN107526633B CN107526633B (en) | 2021-03-19 |
Family
ID=60680822
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710664422.2A Active CN107526633B (en) | 2017-08-04 | 2017-08-04 | Energy-saving control method and device for electric equipment, energy-saving system and storage medium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107526633B (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108363343A (en) * | 2018-05-17 | 2018-08-03 | 广东美的制冷设备有限公司 | Household electric appliance control method, system and computer storage media |
CN108490847A (en) * | 2018-05-17 | 2018-09-04 | 广东美的制冷设备有限公司 | Intelligent updating method, device and the readable storage medium storing program for executing for priority of rationing the power supply |
CN108762137A (en) * | 2018-05-17 | 2018-11-06 | 广东美的制冷设备有限公司 | Intelligent power-off method, device, intelligent socket and the storage medium of intelligent socket |
CN108931926A (en) * | 2018-08-27 | 2018-12-04 | 国网河北省电力有限公司沧州供电分公司 | A kind of household electricity power-economizing method, device and server |
CN109829360A (en) * | 2018-12-15 | 2019-05-31 | 深圳壹账通智能科技有限公司 | Electrical equipment control method, device, electrical equipment and storage medium |
CN110442032A (en) * | 2018-05-04 | 2019-11-12 | 青岛海尔洗衣机有限公司 | For the control method of household electricity equipment, control system and household electricity center |
CN111139620A (en) * | 2019-11-02 | 2020-05-12 | 珠海格力电器股份有限公司 | Control method for household appliances based on Internet of things |
CN112556104A (en) * | 2020-12-07 | 2021-03-26 | 珠海格力电器股份有限公司 | Load control method and device, electronic equipment and storage medium |
CN112797632A (en) * | 2020-12-18 | 2021-05-14 | 青岛经济技术开发区海尔热水器有限公司 | Control method of electric water heater and electric water heater |
CN113176736A (en) * | 2021-04-13 | 2021-07-27 | 宁波奥克斯电气股份有限公司 | Centralized driving device sharing control method and centralized driving device |
CN115036911A (en) * | 2022-05-26 | 2022-09-09 | 怀化建南机器厂有限公司 | Power grid concentrator for power system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101610005A (en) * | 2009-07-08 | 2009-12-23 | 浙江中控电子技术有限公司 | A kind of electrical control method and system |
CN103970089A (en) * | 2014-03-11 | 2014-08-06 | 杭州天丽科技有限公司 | Intelligent management system and method for domestic electrical load |
US20140229146A1 (en) * | 2013-02-08 | 2014-08-14 | Entic, Llc | In-situ optimization of chilled water plants |
CN104037774A (en) * | 2013-03-06 | 2014-09-10 | 珠海优特电力科技股份有限公司 | Method and system for controlling devices in micro grid based on priority |
CN104466951A (en) * | 2014-11-24 | 2015-03-25 | 珠海格力电器股份有限公司 | Control method and device for automatically detecting and adjusting loads |
CN105245472A (en) * | 2015-10-22 | 2016-01-13 | 国网安徽省电力公司 | Inheriting power supply information priority scheduling policy |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101611340B1 (en) * | 2015-09-22 | 2016-04-12 | 윤홍섭 | Devices for power efficiency control and electricity savings devices |
CN106602575B (en) * | 2015-10-14 | 2019-07-12 | 中国电力科学研究院 | A kind of customer charge device class combinatorial regulation method |
CN106444454B (en) * | 2016-11-02 | 2018-12-11 | 珠海格力电器股份有限公司 | The energy control method and control device of electricity system |
-
2017
- 2017-08-04 CN CN201710664422.2A patent/CN107526633B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101610005A (en) * | 2009-07-08 | 2009-12-23 | 浙江中控电子技术有限公司 | A kind of electrical control method and system |
US20140229146A1 (en) * | 2013-02-08 | 2014-08-14 | Entic, Llc | In-situ optimization of chilled water plants |
CN104037774A (en) * | 2013-03-06 | 2014-09-10 | 珠海优特电力科技股份有限公司 | Method and system for controlling devices in micro grid based on priority |
CN103970089A (en) * | 2014-03-11 | 2014-08-06 | 杭州天丽科技有限公司 | Intelligent management system and method for domestic electrical load |
CN104466951A (en) * | 2014-11-24 | 2015-03-25 | 珠海格力电器股份有限公司 | Control method and device for automatically detecting and adjusting loads |
CN105245472A (en) * | 2015-10-22 | 2016-01-13 | 国网安徽省电力公司 | Inheriting power supply information priority scheduling policy |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110442032A (en) * | 2018-05-04 | 2019-11-12 | 青岛海尔洗衣机有限公司 | For the control method of household electricity equipment, control system and household electricity center |
CN108490847A (en) * | 2018-05-17 | 2018-09-04 | 广东美的制冷设备有限公司 | Intelligent updating method, device and the readable storage medium storing program for executing for priority of rationing the power supply |
CN108762137A (en) * | 2018-05-17 | 2018-11-06 | 广东美的制冷设备有限公司 | Intelligent power-off method, device, intelligent socket and the storage medium of intelligent socket |
CN108363343A (en) * | 2018-05-17 | 2018-08-03 | 广东美的制冷设备有限公司 | Household electric appliance control method, system and computer storage media |
CN108363343B (en) * | 2018-05-17 | 2022-03-25 | 广东美的制冷设备有限公司 | Household appliance control method, system and computer storage medium |
CN108931926B (en) * | 2018-08-27 | 2021-08-17 | 国网河北省电力有限公司沧州供电分公司 | Household electricity energy-saving method and device and server |
CN108931926A (en) * | 2018-08-27 | 2018-12-04 | 国网河北省电力有限公司沧州供电分公司 | A kind of household electricity power-economizing method, device and server |
CN109829360A (en) * | 2018-12-15 | 2019-05-31 | 深圳壹账通智能科技有限公司 | Electrical equipment control method, device, electrical equipment and storage medium |
CN111139620A (en) * | 2019-11-02 | 2020-05-12 | 珠海格力电器股份有限公司 | Control method for household appliances based on Internet of things |
CN111206365A (en) * | 2019-11-02 | 2020-05-29 | 珠海格力电器股份有限公司 | Control method for household appliances based on Internet of things |
CN112556104A (en) * | 2020-12-07 | 2021-03-26 | 珠海格力电器股份有限公司 | Load control method and device, electronic equipment and storage medium |
CN112797632A (en) * | 2020-12-18 | 2021-05-14 | 青岛经济技术开发区海尔热水器有限公司 | Control method of electric water heater and electric water heater |
CN113176736A (en) * | 2021-04-13 | 2021-07-27 | 宁波奥克斯电气股份有限公司 | Centralized driving device sharing control method and centralized driving device |
CN115036911A (en) * | 2022-05-26 | 2022-09-09 | 怀化建南机器厂有限公司 | Power grid concentrator for power system |
Also Published As
Publication number | Publication date |
---|---|
CN107526633B (en) | 2021-03-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107526633A (en) | Energy-saving control method, device, energy conserving system and the storage medium of electrical equipment | |
US10298009B2 (en) | Monitoring and recoverable protection of switching circuitry for smart-home devices | |
US11385664B2 (en) | Methods and apparatus for achieving energy consumption goals through model-based simulations | |
US11709530B2 (en) | Electronic device and operation control method thereof | |
CN109084428A (en) | Air conditioner operating parameter update method, device and readable storage medium storing program for executing | |
CN107505974B (en) | Control method, device, house system and the storage medium of the anti-tripping of household electricity | |
US9949002B2 (en) | Apparatus control device and apparatus control method | |
JP2014087126A (en) | Power management device, method for controlling power management device, and control program for power management device | |
US10248092B2 (en) | Architecture for thermostat control during peak intervals | |
CN108572558A (en) | Intelligent home furnishing control method, device and computer readable storage medium | |
CN108427310A (en) | Intelligent home furnishing control method, device and computer readable storage medium | |
CN104009898A (en) | Household appliance and control method and device thereof | |
KR20170115802A (en) | Electronic apparatus and IOT Device Controlling Method thereof | |
CN108731185A (en) | Control method, device, electrical equipment and the readable storage medium storing program for executing of electrical equipment | |
CN107830607A (en) | Multi-online air-conditioning system and its energy-saving control method, device and storage medium | |
CN109489224A (en) | Electricity monitoring method, air regulator and the storage medium of household electrical appliance | |
KR20160096961A (en) | Method and apparatus for controlling battery charging of device | |
CN109780685A (en) | A kind of device energy conservation control method, device and household electrical appliance | |
CN107104478A (en) | A kind of information processing method and electronic equipment | |
CN112128952B (en) | Control method of air conditioner and air conditioner | |
CN109405189A (en) | The control method and device of air conditioner | |
CN105020849A (en) | Air conditioning control method and device | |
CN107577150A (en) | A kind of electric quantity controlling method, electronic equipment and computer-readable recording medium | |
WO2017149367A1 (en) | Multiple input power control system and power outlet device | |
CN108490847A (en) | Intelligent updating method, device and the readable storage medium storing program for executing for priority of rationing the power supply |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |