CN107486382A - Armouring anti-corrosion process for protecting method - Google Patents

Armouring anti-corrosion process for protecting method Download PDF

Info

Publication number
CN107486382A
CN107486382A CN201710712203.7A CN201710712203A CN107486382A CN 107486382 A CN107486382 A CN 107486382A CN 201710712203 A CN201710712203 A CN 201710712203A CN 107486382 A CN107486382 A CN 107486382A
Authority
CN
China
Prior art keywords
brush
brushing
time
brushed
less
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710712203.7A
Other languages
Chinese (zh)
Inventor
卢瑞福
肖河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xin Ruiji Energy Technology Co Ltd
Original Assignee
Beijing Xin Ruiji Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Xin Ruiji Energy Technology Co Ltd filed Critical Beijing Xin Ruiji Energy Technology Co Ltd
Priority to CN201710712203.7A priority Critical patent/CN107486382A/en
Publication of CN107486382A publication Critical patent/CN107486382A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05DPROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05D7/00Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
    • B05D7/14Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials to metal, e.g. car bodies
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05DPROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05D7/00Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
    • B05D7/50Multilayers
    • B05D7/56Three layers or more
    • B05D7/58No clear coat specified
    • B05D7/584No clear coat specified at least some layers being let to dry, at least partially, before applying the next layer

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Wood Science & Technology (AREA)
  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

The invention discloses a kind of armouring anti-corrosion process for protecting method, comprise the following steps:Protection body is treated to be pre-processed;Treat that protection body is completed repeatedly to brush by the way of round brush to pretreated, and after multiple brush, kept for the drying time not less than 7 days to realize that armouring anti-corrosion is protected.This method solve conventional art in work progress and after the completion of disaster hidden-trouble be present;Construction technology is cumbersome, environmental requirement is harsh, personnel qualifications are high;Easily leave cracking, play the defects of drum, anticorrosion ability is poor;Long construction period, pre-processed by treating protection body, and treat that protection body completes four brushings by the way of round brush to pretreated, and after four times are brushed, kept for the drying time not less than 7 days to realize that armouring anti-corrosion is protected, wide in range property, the simplicity, high efficiency used and the flexibility with application.

Description

Armouring anti-corrosion process for protecting method
Technical field
The present invention relates to engineer equipment technical field, more particularly to a kind of armouring anti-corrosion process for protecting method.
Background technology
Existing aseptic production, such as glass flake etc. and construction technology have the disadvantages that:Work progress and after the completion of deposit In disaster hidden-trouble;Construction technology is cumbersome, environmental requirement is harsh, personnel qualifications are high;Easily leave cracking, play the defects of drum, prevent Corrosive effect is poor;Long construction period.As can be seen here, how to help user to solve the raising of anticorrosion ability in conventional art to use The limitation of pattern and complicated inefficiencies are a urgent problems to be solved.
The content of the invention
Based on this, it is necessary to the problem of existing for conventional art, there is provided a kind of armouring anti-corrosion process for protecting method, can Solve conventional art in work progress and after the completion of disaster hidden-trouble be present;Construction technology is cumbersome, environmental requirement is harsh, peopleware It is it is required that high;Easily leave cracking, play the defects of drum, anticorrosion ability is poor;Long construction period, located in advance by treating protection body Reason, and treat that protection body completes four brushings by the way of round brush to pretreated, and after four times are brushed, keep being not less than The drying time of 7 days to realize that armouring protects, wide in range property, the simplicity, high efficiency used and the flexibility with application.
In a first aspect, the embodiments of the invention provide a kind of armouring anti-corrosion process for protecting method, including:Protection body is treated to enter Row pretreatment;To it is pretreated it is described treat that protection body is completed repeatedly to brush by the way of round brush, and after multiple brush, protect The drying time not less than 7 days is held to realize that armouring anti-corrosion is protected.
In one of the embodiments, described to treat that protection body is metal, the pretreatment includes:To the metallic surface By corrosion, skin is stuck up, come off and complete grinding process, greasy dirt or other chemicals caused by metal covering attachment are completed at chemistry Reason, and cleaned;
In one of the embodiments, described repeatedly brush includes:To it is pretreated it is described treat protection body brushing rust go out Agent living, basis of formation layer, and kept for the drying time no less than 4 hours brushed for the first time to realize.
In one of the embodiments, described repeatedly brush also includes:On the basis of being brushed based on the first time, brush Macromolecule protection isolation ester, and kept for the drying time no less than 3 hours realize second of brushing.
In one of the embodiments, described repeatedly brush also includes:On the basis of being brushed based on described second, complete The brushing for the combination that ester isolate in the protection of carborundum and macromolecule forms structure sheaf, and keep being no less than drying time of 3 hours with Realize that third time is brushed.
In one of the embodiments, described repeatedly brush also includes:On the basis of the third time brushing, complete The brushing for the combination that brushing graphite isolates ester with macromolecule protection forms enhancement layer, and is kept for the drying time no less than 3 hours To realize the 4th brushing.
In one of the embodiments, described to treat that protection body is concrete, the pretreatment includes:Concrete surface is led to Cross giant or sandblasting mode by the dust of cement-based surface, dirt completion handle, then by mica cream ester repair leak with And crackle, polished after to be dried round and smooth;Or
Described to treat that protection body is Wood surface, the pretreatment includes:Wood surface dirt, dust are removed by sand paper, If there is oil stain on surface, and the scouring of surface and oil contaminant is completed with No. 200 gasoline.
In one of the embodiments, described repeatedly brush includes:Described protection body brushing is treated to pretreated Macromolecule protection isolation ester, basis of formation layer, and kept for the drying time no less than 4 hours brushed for the first time to realize;
In one of the embodiments, described repeatedly brush includes:On the basis of being brushed based on the first time, stone is completed Ink isolates the brushing of the combination of ester with macromolecule protection, forms structure sheaf, and kept for the drying time no less than 3 hours realize Second of brushing.
In one of the embodiments, described repeatedly brush includes:On the basis of being brushed based on described second, complete high The brushing of molecule protection isolation ester, forms enhancement layer, and is kept for the drying time no less than 3 hours to realize that third time is brushed.
In one of the embodiments, the mode of the round brush can select spraying method or brush mode.
Armouring anti-corrosion process for protecting method provided by the invention, treats protection body and is pre-processed;Treated to pretreated Protection body completes four brushings by the way of round brush, and after four times are brushed, is kept for the drying time not less than 7 days realize Armouring protects.This method solve conventional art in work progress and after the completion of disaster hidden-trouble be present;Construction technology is cumbersome, environment is wanted Seek harsh, personnel qualifications height;Easily leave cracking, play the defects of drum, anticorrosion ability is poor;Long construction period, by treating Protection body is pre-processed, and treats that protection body completes four brushings by the way of round brush to pretreated, and in four paintings After brush, keep not less than 7 days drying time with realize armouring protect, have application wide in range property, use it is simplicity, efficient Property and flexibility.
Brief description of the drawings
Fig. 1 is a kind of schematic flow sheet of armouring anti-corrosion process for protecting method in one embodiment of the invention;And
Fig. 2 is a kind of Structure Mechanism figure of armouring anti-corrosion process for protecting method in one embodiment of the invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, below in conjunction with drawings and Examples pair Armouring anti-corrosion process for protecting method of the present invention is further elaborated.It should be appreciated that specific embodiment described herein Only to explain the present invention, it is not intended to limit the present invention.
As shown in figure 1, be a kind of schematic flow sheet of armouring anti-corrosion process for protecting method in one embodiment, specific bag Include following steps:
Step 102, protection body is treated to be pre-processed.
In the present embodiment, if treating, protection body is metal, and pretreatment includes:To metallic surface by corrosion, stick up skin, come off Complete grinding process;Chemical treatment is completed to greasy dirt or other chemicals caused by metal covering attachment, and cleaned.
If in addition, treating that protection body is concrete, pretreatment also includes:Then pass through giant or sandblasting side to coagulating native surface Formula handles the dust of cement-based surface, dirt completion;Leak and crackle are repaired by mica cream ester again, polished after to be dried It is round and smooth.
If in addition, treating that protection body is Wood surface, pretreatment also includes:Wood surface dirt, ash are then removed by sand paper There is oil stain on dirt, surface and the scouring of surface and oil contaminant are completed with No. 200 gasoline.
Step 104, treat that protection body is completed repeatedly to brush by the way of round brush to pretreated, and repeatedly brushing Afterwards, the drying time not less than 7 days is kept to realize that armouring protects.Wherein, the mode of round brush can select spraying method or brush Painting mode.Thus, the multi-selection for choosing round brush mode is improved.
In one of the embodiments, if treating, protection body is metal, treats that protection body uses the side of round brush to pretreated Formula, which completes four brushings, to be included:Treat that protection body brushing becomes rusty inactivator, basis of formation layer, and holding no less than 4 to pretreated The drying time of hour is brushed for the first time with realizing.
Further, described treat that protection body is completed four brushings by the way of round brush and included to pretreated:It is based on On the basis of brushing for the first time, brushing macromolecule protection isolation ester, and kept for the drying time no less than 3 hours realize second Secondary brushing;On the basis of being brushed based on second, the brushing formation for completing the combination that carborundum isolates ester with macromolecule protection is tied Structure layer, and kept for the drying time no less than 3 hours to realize that third time is brushed;On the basis of being brushed based on third time, complete The brushing for the combination that brushing graphite isolates ester with macromolecule protection forms enhancement layer, and is kept for the drying time no less than 3 hours To realize the 4th brushing.
In one of the embodiments, if described treat that protection body is concrete or Wood surface, wait to prevent to pretreated Watch box complete to brush three times by the way of round brush including:Protection body brushing macromolecule protection isolation ester is treated to pretreated, Basis of formation layer, and kept for the drying time no less than 4 hours brushed for the first time to realize.
Further, to it is pretreated treat protection body complete to brush three times by the way of round brush including:Based on first On the basis of secondary brushing, the brushing that graphite isolates the combination of ester with macromolecule protection is completed, forms structure sheaf, and keep being no less than The drying time of 3 hours is to realize second of brushing;On the basis of being brushed based on second, macromolecule protection isolation ester is completed Brush, form enhancement layer, and kept for the drying time no less than 3 hours to realize that third time is brushed.
It should be noted that armouring anti-corrosion protective mechanism is implanted into Organic fluoride 201, organosilicon 202 in the main chain 200 of resin. Specifically, as shown in Fig. 2 the fluorine silicon resin of macromolecular is degraded into small molecule in order to permeate, then passed through based on fluorine silicon resin Active gene 204 adds isocyanates (NCO) group 203 plus activity, then pre-buried catalyst, can quickly hand in atmosphere Connection reaction forms interpenetrating networks (PIN) and solidified.I.e. it includes basal layer, structure sheaf and enhancement layer.Basal layer is with active The matrix protective layer of the rust inactivator conversion of ion, structure sheaf are embedded carborundum and macromolecule protection isolation ester perfect combinations Separation layer, enhancement layer are that graphite isolates the protective layer that the combination of ester prevents the external world from corroding with macromolecule protection.
In summary, method proposed by the present invention is macromolecule protection isolation ester and the organic knot of rust inactivator with rust antirust Close, be a kind of brand-new construction process, construction process can be increased and decreased according to the operating mode of anti-corrosion medium.With following characteristic:Apply Work technique is simple, not high to environmental requirement, can be combined with matrix strength, good toughness, not expanded with heat and contract with cold and ftractureed by matrix, With good fire resistance;Used by this flow and method product contain it is homemade there is wetting and infiltration function material, can be with Penetrate into inside rusty scale, form parcel, while can also carry rust inactivator, it is reacted with rust, make reaction than conventional method more Add thoroughly;Used by this flow and method product contain acidic materials can well with unstable iron rust composition (γ- Fe2O3) react, convert it into complex steady in a long-term, rust inactivator can carry out complex reaction again to rust and form stabilization Compound, play dual rust transformation function;Contained organic compound resin in product used by this flow and method, in homemade tool Have under wetting and the effect of infiltration function material, closely combined with iron rust, the iron rust material for inactivator conversion of becoming rusty is wrapped up, after solidification Row prevents the generation of corrosion reaction into stable coating;All resin components of product finally all enter used by this flow and method Row crosslinking, forms three-dimensional-structure, has good sealing process, prevent the intrusion of water and corrosive deposit, reach anti-corrosion purpose.
A kind of armouring anti-corrosion process for protecting method provided by the invention, treats protection body and is pre-processed;After pretreatment Treat that protection body is completed repeatedly to brush by the way of round brush, and after multiple brush, keep drying time not less than 7 days with Realize that armouring anti-corrosion is protected.This method solve conventional art in work progress and after the completion of disaster hidden-trouble be present;Construction technology is numerous It is trivial, environmental requirement is harsh, personnel qualifications are high;Easily leave cracking, play the defects of drum, anticorrosion ability is poor;Long construction period, Pre-processed by treating protection body, and treat that protection body completes four brushings by the way of round brush to pretreated, and After four times are brushed, kept for the drying time not less than 7 days to realize that armouring protects, there is the wide in range property of application, the letter used Victory, high efficiency and flexibility.
Further, armouring anti-corrosion process for protecting method proposed by the present invention changes traditional pretreatment mode, solution The problem of having determined inside active factors into rust, shortens the derusting duration;Unique armouring anti-corrosion process for protecting method, reduces rust The motion of active factors;It is formulated using flake graphite, carborundum, quartz sand etc., strengthens the adhesive force of aging layer, with high-strength Degree, high weather resisteant and wear-resistant feature;Flow and method is protected using armouring anti-corrosion, has prevented the condition of electrochemical corrosion, to gold Belong to the protection that matrix implements armor formula in terms of physics and chemistry two to matrix.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, the scope that this specification is recorded all is considered to be.
Embodiment described above only expresses the several embodiments of the present invention, and its description is more specific and detailed, but simultaneously Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the guarantor of the present invention Protect scope.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (10)

1. a kind of armouring anti-corrosion process for protecting method, including:
Protection body is treated to be pre-processed;
To it is pretreated it is described treat that protection body is completed repeatedly to brush by the way of round brush, and after multiple brush, keep not Drying time less than 7 days is to realize that armouring anti-corrosion is protected.
2. according to the method for claim 1, wherein, described to treat that protection body is metal, the pretreatment includes:To the gold The surface of category by corrosion, stick up skin, come off and complete grinding process, greasy dirt or other chemicals caused by metal covering attachment are completed Chemical treatment, and cleaned.
3. according to the method for claim 2, wherein, described repeatedly brush includes:Described protection body is treated to pretreated Rust inactivator, basis of formation layer are brushed, and is kept for the drying time no less than 4 hours brushed for the first time to realize.
4. according to the method for claim 3, wherein, described repeatedly brush also includes:The base brushed based on the first time On plinth, brushing macromolecule protection isolation ester, and kept for the drying time no less than 3 hours realize second of brushing.
5. according to the method for claim 4, wherein, described repeatedly brush also includes:Based on second of base brushed On plinth, the brushing for completing the combination that carborundum isolates ester with macromolecule protection forms structure sheaf, and keeps dry no less than 3 hours The dry time is brushed for the third time with realizing.
6. according to the method for claim 5, wherein, described repeatedly brush also includes:Base based on the third time brushing On plinth, the brushing for completing the combination that brushing graphite isolates ester with macromolecule protection forms enhancement layer, and keeps no less than 3 hours Drying time is brushed with realizing the 4th time.
7. according to the method for claim 1, wherein, described to treat that protection body is concrete, the pretreatment includes:To coagulation Native surface is handled the dust of cement-based surface, dirt completion by giant or sandblasting mode, then is repaiied by mica cream ester Plug a hole and crackle, rear polishing to be dried are round and smooth;Or
Described to treat that protection body is Wood surface, the pretreatment includes:Wood surface dirt, dust are removed by sand paper, if There is oil stain on surface, and the scouring of surface and oil contaminant is completed with No. 200 gasoline.
8. according to the method for claim 7, wherein, described repeatedly brush includes:Described wait to prevent to pretreated Watch box brushing macromolecule protection isolation ester, basis of formation layer, and kept for the drying time no less than 4 hours applied for the first time to realize Brush.
9. according to the method for claim 8, wherein, described repeatedly brush includes:The basis brushed based on the first time On, the brushing that graphite isolates the combination of ester with macromolecule protection is completed, forms structure sheaf, and keep the drying no less than 3 hours Time is to realize second of brushing.
10. according to the method for claim 9, wherein, described repeatedly brush includes:Based on second of basis brushed On, the brushing of macromolecule protection isolation ester is completed, forms enhancement layer, and is kept for the drying time no less than 3 hours to realize the Brush three times.
CN201710712203.7A 2017-08-18 2017-08-18 Armouring anti-corrosion process for protecting method Pending CN107486382A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710712203.7A CN107486382A (en) 2017-08-18 2017-08-18 Armouring anti-corrosion process for protecting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710712203.7A CN107486382A (en) 2017-08-18 2017-08-18 Armouring anti-corrosion process for protecting method

Publications (1)

Publication Number Publication Date
CN107486382A true CN107486382A (en) 2017-12-19

Family

ID=60646661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710712203.7A Pending CN107486382A (en) 2017-08-18 2017-08-18 Armouring anti-corrosion process for protecting method

Country Status (1)

Country Link
CN (1) CN107486382A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101613563A (en) * 2009-07-23 2009-12-30 东南大学 A kind of preparation method of anti-graffiti coating for rail train carriage
CN103642373A (en) * 2013-11-21 2014-03-19 中国石油化工股份有限公司 Corrosion-resistant crude oil pipeline coating material and coating process thereof
US20160009971A1 (en) * 2013-03-04 2016-01-14 Liang Wang Anti-Icing Composite
CN105623504A (en) * 2016-03-21 2016-06-01 苏州天键衡电子信息科技有限公司 Heat-dissipation anti-corrosive paint for ships
CN105694696A (en) * 2016-03-29 2016-06-22 上海麦加涂料有限公司 Modified fluorocarbon varnish and application thereof
CN106117449A (en) * 2016-07-12 2016-11-16 合众(佛山)化工有限公司 A kind of fluorinated silicone modified aqueous alkide resin and preparation method thereof
CN106189639A (en) * 2016-07-12 2016-12-07 合众(佛山)化工有限公司 A kind of fluorinated silicone modified alkyd resin water paint
CN106903029A (en) * 2017-03-31 2017-06-30 叶云川 A kind of steel construction and equipment paint renovation coating process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101613563A (en) * 2009-07-23 2009-12-30 东南大学 A kind of preparation method of anti-graffiti coating for rail train carriage
US20160009971A1 (en) * 2013-03-04 2016-01-14 Liang Wang Anti-Icing Composite
CN103642373A (en) * 2013-11-21 2014-03-19 中国石油化工股份有限公司 Corrosion-resistant crude oil pipeline coating material and coating process thereof
CN105623504A (en) * 2016-03-21 2016-06-01 苏州天键衡电子信息科技有限公司 Heat-dissipation anti-corrosive paint for ships
CN105694696A (en) * 2016-03-29 2016-06-22 上海麦加涂料有限公司 Modified fluorocarbon varnish and application thereof
CN106117449A (en) * 2016-07-12 2016-11-16 合众(佛山)化工有限公司 A kind of fluorinated silicone modified aqueous alkide resin and preparation method thereof
CN106189639A (en) * 2016-07-12 2016-12-07 合众(佛山)化工有限公司 A kind of fluorinated silicone modified alkyd resin water paint
CN106903029A (en) * 2017-03-31 2017-06-30 叶云川 A kind of steel construction and equipment paint renovation coating process

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
仓理: "《涂料工艺》", 31 August 2005, 北京:化学工业出版社 *
孙连捷等: "《安全科学技术百科全书》", 30 June 2003, 中国劳动社会保障出版社 *
惠文华等: "《摩擦学与耐磨性设计》", 30 November 1993, 东南大学出版社 *
李肇强: "《现代涂料的生产及应用 第2版》", 31 March 2017, 上海科学技术文献出版社 *
武卫莉: "《电线电缆加工工艺学》", 31 October 2014, 哈尔滨:哈尔滨工业大学出版社 *
童忠良: "《功能涂料及其应用》", 30 September 2007, 北京:中国纺织出版社 *

Similar Documents

Publication Publication Date Title
Weldon Failure analysis of paints and coatings
US7737195B2 (en) Anti-graffiti coating
CN103182725B (en) Wood product surface embrocates the method for wood wax oil
CN102168244B (en) Steel sleeper and zinc impregnation processing method thereof
CN105254332B (en) One kind carries out armored concrete method of inhibiting corrosion with nano silicon
CN107199167A (en) A kind of underwater steel construction compound protective coating and preparation method
KR20090039701A (en) Ultra-weatherability antipollution process over ceramics of nonflammable materials and fluorine
CN102816486B (en) Rust-removing-free environment-friendly acrylic acid zinc phosphate organic composite ceramic anticorrosive paint and preparation method thereof
US8877088B2 (en) Mono- and bi-component formulations in the form of a paint, varnish and water-emulsified base, processes for preparing the same and applications thereof
CN107486382A (en) Armouring anti-corrosion process for protecting method
JP5993799B2 (en) High corrosion resistance coating composition using Sn ions
US6248403B1 (en) Environmental wipe solvent processes
US20210102077A1 (en) Moisture and Ultraviolet Light Barrier Composition
JP5075402B2 (en) Coating composition
CN105088949A (en) Steel strand inhaul cable filled or coated with polyurea protective material and manufacturing method of steel strand inhaul cable
JP5400633B2 (en) Temperature rise control method for railroad rail
KR102449723B1 (en) Coating method with surface treatment process for steel material structure
CN215152654U (en) Rubber bonding structure
McNamara et al. Analysis of bacterial community composition in concretions formed on the USS Arizona, Pearl Harbor, HI
CN103397317B (en) Coloring rust-proof test solution for bronze sculpture and coloring method thereof
CN106893380A (en) A kind of Jing Yin anti-skidding superthin layer terrace investment precoat of high abrasion and preparation method thereof
US10030310B1 (en) Methods for removal of reaction sites on metal surfaces and application of a nanotube containing protecting coating
JP2019099723A (en) Release agent composition
KR101418863B1 (en) MMA resin coating structure
CN108554754A (en) A kind of steel structure surface protection technique

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171219

RJ01 Rejection of invention patent application after publication