CN107476291A - Tension nut sunk type prefabricated pile - Google Patents

Tension nut sunk type prefabricated pile Download PDF

Info

Publication number
CN107476291A
CN107476291A CN201710700655.3A CN201710700655A CN107476291A CN 107476291 A CN107476291 A CN 107476291A CN 201710700655 A CN201710700655 A CN 201710700655A CN 107476291 A CN107476291 A CN 107476291A
Authority
CN
China
Prior art keywords
tension nut
pile body
tension
pile
sunk type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710700655.3A
Other languages
Chinese (zh)
Other versions
CN107476291B (en
Inventor
周兆弟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=54027980&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN107476291(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Priority to CN201710700655.3A priority Critical patent/CN107476291B/en
Publication of CN107476291A publication Critical patent/CN107476291A/en
Application granted granted Critical
Publication of CN107476291B publication Critical patent/CN107476291B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to building trade prefabricated component technical field, is related to a kind of tension nut sunk type prefabricated pile.Solves the technical problem that the nut of prior art connection is easily damaged.It includes pile body, steel reinforcement cage is provided with pile body, described steel reinforcement cage includes some longitudinal reinforcements and the helical spiral reinforcement being fixedly connected with longitudinal reinforcement, described pile body both ends are respectively fixed with some one-to-one tension nuts so that the both ends of every longitudinal reinforcement tense a tension nut respectively, and described tension nut is sunk to inside pile body so that forming horn-like connector between the end of tension nut and the end of pile body.The tension nut of the present invention is sunk in pile body, not easily damaged, improves the success rate of connection.

Description

Tension nut sunk type prefabricated pile
The application is " tension nut sunk type prefabricated pile (application number:201510313980.5;The applying date: 2015.06.09) " divisional application.
Technical field
The invention belongs to building trade prefabricated component technical field, is related to a kind of prefabricated pile, more particularly to a kind of tension nut Sunk type prefabricated pile.
Background technology
Because the quality stability of driven cast-in-place pile is relatively poor, in recent years, precast prestressed concrete stake obtains swift and violent Development., be according to the different stakes for needing to select different length during piling, this is just needed between stake and stake by mutual Connect to form the pile body of long length.
Connecting through between existing pile body sets metal end plate at the both ends of pile body, when two pile bodies need to connect When, it is attached by the end plate for welding two pile bodies, welding job is wasted time and energy, and connection is inconvenient, in addition, weld is easy By the chlorine salt corrosion in soil, the junction fastness of pile body is caused to be damaged.
People are although constantly explore, it is proposed that various solutions, as Chinese patent literature discloses one kind Mechanical connection prestressed solid square pile [application number:201420316038.5], including foundation pile, connection stake and be vertically provided at Reinforcing bar inside foundation pile and connection stake, connection stake are correspondingly arranged above foundation pile, and the cross section of foundation pile and connection stake is rectangle, base Stake upper end and connection stake lower end are provided with annular clips, upper fastener, lower fastener and keeper, and the lower fastener is uniformly set Put in foundation pile top, the foundation pile it is end reinforced be provided with the first card article, the first card article is socketed in lower fastener etc..Should Having the technical effect that for scheme is easy to connect firm.But after carefully studying, it has been found that the position of upper fastener and lower fastener Design is very unreasonable, and upper fastener and lower fastener are concordant with pile body end face, in pile body transport, carrying and connection procedure In, if pile body end face collides fastener and lower fastener when meeting with friction, hitting, upper fastener and lower fastener Port can be deformed or lose, so as to cause connection failure.Because the connection procedure of pile body needs to employ substantial amounts of equipment, because This, is changed once upper fastener and lower fastener are damaged, it is necessary to employ substantial amounts of manpower and materials, very inconvenient.
The applicant is in entitled " cutting-free fast tearing sleeve couple and the interfacing part " [Granted publication applied before this Number:CN101519876B] patent in mention a kind of connector, top pull nut and tensioning nut therein are used to tense longitudinal steel Muscle, the program are equally used for the connection between prefabricated component such as pile body.But in embodiment and accompanying drawing not by top pull nut and The position of tensioning nut is limited, and causes that top pull nut and tensioning nut are impaired when in use can also be present.
The content of the invention
A kind of regarding the issue above, the present invention provides tension nut sunk type that connection is reliable, not easily damaged Prefabricated pile.
To reach above-mentioned purpose, present invention employs following technical proposal:A kind of tension nut sunk type prefabricated pile, including Pile body, is provided with steel reinforcement cage in pile body, and described steel reinforcement cage is including some longitudinal reinforcements and what is be fixedly connected with longitudinal reinforcement is in spiral shell The spiral reinforcement of shape is revolved, described pile body both ends are respectively fixed with some one-to-one tension nuts so that every longitudinal steel The both ends of muscle tense a tension nut respectively, and described tension nut is sunk to inside pile body so that the end of tension nut Horn-like connector is formed between the end of pile body.
In a kind of above-mentioned tension nut sunk type prefabricated pile, the cross section of described connector is from the end of tension nut The direction of portion toward pile body end becomes larger.
In a kind of above-mentioned tension nut sunk type prefabricated pile, described connector is in round tapered.
In a kind of above-mentioned tension nut sunk type prefabricated pile, the both ends of described longitudinal reinforcement are provided with external diameter more than vertical To the pier nose of reinforcing bar, the bottom of described tension nut reduces the chuck to be formed and can block pier nose.
In a kind of above-mentioned tension nut sunk type prefabricated pile, the end of described tension nut has the first chamfering, And the first described chamfering is located on tension nut inner wall.
In a kind of above-mentioned tension nut sunk type prefabricated pile, the bottom of described tension nut and in the both sides of chuck There is the second chamfering and the 3rd chamfering respectively, the second described chamfering and the 3rd chamfering are located on the inwall of tension nut.
In a kind of above-mentioned tension nut sunk type prefabricated pile, described pile body both ends are enclosed with angle protection cover.
Compared with prior art, the advantage of the invention is that:
1st, tension nut sinks to inside pile body and makes to be formed between the end of tension nut and the end of pile body so as to be formed Hollow connector, plays cushioning and protection, ensure that tension nut will not be by during transport, mobile and connection etc. To shock and breakage, it ensure that whole pile body can realize quick connection.
2nd, angle protection cover strengthens the intensity of junction, further increases the service life of bonding strength and pile body.
Brief description of the drawings
Fig. 1 is structural representation provided by the invention;
Fig. 2 is another structural representation provided by the invention;
Fig. 3 is enlarged drawing at Fig. 1 B;
Fig. 4 is the structural representation for pulling nut;
Fig. 5 is Fig. 1 A direction views;
Fig. 6 is Fig. 1 another A direction views.
In figure:Pile body 10, angle protection cover 11, heavy in section stake 12, small bore stake 13, slope 14, non-uniform pile 15, steel reinforcement cage 20th, longitudinal reinforcement 21, transverse steel 22, pier nose 23, tension nut 30, connector 31, chuck 32, the first chamfering 33, second fall Angle 34, the 3rd chamfering 35, concavo-convex chuck mechanism 40, concave station 41, boss 42, hollow structure 50.
Embodiment
The present invention will be further described in detail with reference to the accompanying drawings and detailed description.
As shown in figures 1 and 3, a kind of tension nut sunk type prefabricated pile, including pile body 10, the cross section of pile body 10 is not Limit, can be circle, direction, regular polygon etc., steel reinforcement cage 20 is provided with pile body 10, if described steel reinforcement cage 20 includes Dry longitudinal reinforcement 21 and the transverse steel 22 being fixedly connected with longitudinal reinforcement 21, it is preferable that transverse steel 22 is spiral wound On the surface of longitudinal reinforcement 21, so as to form steel reinforcement cage 20, the described both ends of pile body 10 be respectively fixed with it is some correspondingly by Drawing nut 30, described tension nut 30 is sunk to so that the both ends of every longitudinal reinforcement 21 tense a tension nut 30 respectively To the inside of pile body 10 so that forming connector 31, the guarantor of connector 31 between the end of tension nut 30 and the end of pile body 10 Tension nut 30 is demonstrate,proved inside pile body 10, during transport, mobile and connection pile body 10, tension nut 30 is located all the time In with exterior object contactless state, therefore will not lose, ensure that and connection is realized between pile body in future, connector 31 is same When can also play buffer protection, namely when two pile bodies 10 connect, on two different pile bodies 10 of junction both sides Tension nut 30 will not hit.
Preferred scheme, connector 31 is in horn-like, and the cross section of connector 31 is from the end of tension nut 30 toward pile body 10 The direction of end becomes larger, and is easy to plug connector to insert.It is highly preferred that connector 31 is in round tapered.
As shown in figure 3, the both ends of longitudinal reinforcement 21 are provided with the pier nose 23 that external diameter is more than longitudinal reinforcement 21, described tension spiral shell The bottom of mother 30 reduces to form the chuck 32 that can block pier nose 23.
In conjunction with shown in Fig. 4, the end of tension nut 30 has the first chamfering 33, and the first described chamfering 33 be located at by Draw on the inwall of nut 30, the bottom of tension nut 30 and there is the second chamfering 34 and the 3rd chamfering respectively in the both sides of chuck 32 35, the second described chamfering 34 and the 3rd chamfering 35 are located on the inwall of tension nut 30, wherein the surface of the second chamfering 34 with The surface of pier nose 23 is engaged, and when pier nose 23 is snapped onto in chuck 32, the second chamfering 24 and pier nose 23 are brought into close contact.
As depicted in figs. 1 and 2, the both ends of pile body 10 are additionally provided with concavo-convex chuck mechanism 40, when two adjacent pile bodies 10 are mutual When close, two pile bodies 10 can be allowed to be engaged by clamping for described concavo-convex chuck mechanism 40 so that two pile bodies 10 are connected with each other.
Concavo-convex chuck mechanism 40 includes being arranged on the one end of pile body 10 and to the concave station 41 of the inner recess of pile body 10, in addition to It is arranged on the other end of pile body 10 and to the boss 42 protruded outside pile body 10, shape, the size of described concave station 41 and boss 42 Match, when two pile bodies 10 are close to each other, the boss 42 on a pile body 10 can be inserted into recessed on another pile body 10 It is engaged by clamping in platform 41 so as to be formed.The both ends of pile body 10 are enclosed with angle protection cover 11, and pile body 10 has the shield on the one end of concave station 41 Angle covers the depth that 11 width are more than concave station 41.Boss 42 and bumps 41 are preferably truncated cone or cube rod or just more Side shape post, or other strip columns.
As shown in Figure 5 and Figure 6, tension nut 30 surround the 42 evenly spaced distribution of concave station 41 or boss, and tension nut 30 are integrally located inside pile body 10.
Preferred scheme, as depicted in figs. 1 and 2, described pile body 10 are alternateed by heavy in section stake 12 and small bore stake 13 Composition, described heavy in section stake 12 are connected with the junction of small bore stake 13 by the transition of non-uniform pile 15 with slope 14. Above-mentioned heavy in section stake 12 or small bore stake 13 can while or be independently each circular stake, oval stake, rectangular pile, triangle Shape stake, polygonal pile, quincunx stake or the stake of other shapes.When the surface of heavy in section stake 12 or small bore stake 13 can also be preferred Chamfered transition is used, so that surface is more smooth, it is non-breakable.The gradient on slope 14 can made according to the difference of soil property As when do corresponding adjustment, slope 14 is linearly, is easy to make and lower stake, certain slope 14 can also make negative camber or outer into Curved surface or spiral shape etc..
As shown in Fig. 2 being additionally provided with hollow structure 50 in described pile body 10, described hollow structure 50 includes filling out being located at stake Gas tank or hollow pipe inside body 10.The hollow structure 50 by the closed at both ends of pile body 10 or connect pile body 10 both ends, Hollow structure 50 can also fill out the gas tank or hollow pipe being located inside pile body 10, and gas tank can also use the elastomeric material of sealing to replace Generation, and injecting compressed air forms the gas tank of tubulose inside elastomeric material, hollow tube can use pvc pipe or PP pipes or steel pipe Etc., either gas tank or hollow tube can form fixed shape, so that pile body 10 is internally formed hollow structure 50.In a pile body 10, hollow structure 50 can be one or multiple.
Specific embodiment described herein is only to spirit explanation for example of the invention.Technology belonging to the present invention is led The technical staff in domain can be made various modifications or supplement to described specific embodiment or be replaced using similar mode Generation, but without departing from the spiritual of the present invention or surmount scope defined in appended claims.
Although pile body 10, angle protection cover 11, heavy in section stake 12, small bore stake 13, slope 14, change has more been used to cut herein Face stake 15, steel reinforcement cage 20, longitudinal reinforcement 21, transverse steel 22, pier nose 23, tension nut 30, connector 31, chuck 32, first The terms such as chamfering 33, the second chamfering 34, the 3rd chamfering 35, concavo-convex chuck mechanism 40, concave station 41, boss 42, hollow structure 50, but It is not precluded from the possibility using other terms.It is used for the purpose of more easily describing and explaining the present invention's using these terms Essence;Any additional limitation is construed as all to disagree with spirit of the present invention.

Claims (7)

1. a kind of tension nut sunk type prefabricated pile, including pile body (10), pile body (10) is interior to be provided with steel reinforcement cage (20), described steel Muscle cage (20) includes some longitudinal reinforcements (21) and the transverse steel (22) being fixedly connected with longitudinal reinforcement (21), and its feature exists In described pile body (10) both ends are respectively fixed with some one-to-one tension nuts (30), so that every longitudinal reinforcement (21) both ends tense a tension nut (30) respectively, and described tension nut (30) sinks to pile body (10) inside, so as to Make to form connector (31) between the end of tension nut (30) and the end of pile body (10).
A kind of 2. tension nut sunk type prefabricated pile according to claim 1, it is characterised in that described connector (31) Cross section become larger from the end of tension nut (30) toward the direction of pile body (10) end.
A kind of 3. tension nut sunk type prefabricated pile according to claim 1 or 2, it is characterised in that described connector (31) it is in round tapered.
A kind of 4. tension nut sunk type prefabricated pile according to claim 1 or 2, it is characterised in that described longitudinal steel The both ends of muscle (21) are provided with the pier nose (23) that external diameter is more than longitudinal reinforcement (21), and the bottom of described tension nut (30) reduces shape Into the chuck (32) that can block pier nose (23).
A kind of 5. tension nut sunk type prefabricated pile according to claim 1 or 2, it is characterised in that described tension spiral shell The end of female (30) has the first chamfering (33), and described the first chamfering (33) is located on tension nut (30) inwall.
A kind of 6. tension nut sunk type prefabricated pile according to claim 4, it is characterised in that described tension nut (30) bottom and there is the second chamfering (34) and the 3rd chamfering (35), the second described chamfering respectively in the both sides of chuck (32) (34) it is located at the 3rd chamfering (35) on the inwall of tension nut (30).
A kind of 7. tension nut sunk type prefabricated pile according to claim 1, it is characterised in that described pile body (10) two End is enclosed with angle protection cover (11).
CN201710700655.3A 2015-06-09 2015-06-09 Tension nut sinking type precast pile Active CN107476291B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710700655.3A CN107476291B (en) 2015-06-09 2015-06-09 Tension nut sinking type precast pile

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510313980.5A CN104895050A (en) 2015-06-09 2015-06-09 Tension nut sunken type prefabricated pile
CN201710700655.3A CN107476291B (en) 2015-06-09 2015-06-09 Tension nut sinking type precast pile

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201510313980.5A Division CN104895050A (en) 2015-06-09 2015-06-09 Tension nut sunken type prefabricated pile

Publications (2)

Publication Number Publication Date
CN107476291A true CN107476291A (en) 2017-12-15
CN107476291B CN107476291B (en) 2020-12-01

Family

ID=54027980

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510313980.5A Pending CN104895050A (en) 2015-06-09 2015-06-09 Tension nut sunken type prefabricated pile
CN201710700655.3A Active CN107476291B (en) 2015-06-09 2015-06-09 Tension nut sinking type precast pile

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510313980.5A Pending CN104895050A (en) 2015-06-09 2015-06-09 Tension nut sunken type prefabricated pile

Country Status (1)

Country Link
CN (2) CN104895050A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103498468A (en) * 2013-08-27 2014-01-08 周兆弟 Single-joint pile without end plate strong pulling and components
CN103556624A (en) * 2013-11-01 2014-02-05 建华建材(中国)投资有限公司 Connecting sleeve, prefabricated part comprising same as well as production method and connecting method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57173112A (en) * 1981-04-20 1982-10-25 Asahi Chemical Ind Pc pile and its manufacture
CN103266595B (en) * 2013-06-03 2016-02-24 建华建材(中国)投资有限公司 A kind of rigid pile for complex ground treatment and production method thereof
CN203904976U (en) * 2014-04-22 2014-10-29 杨众 Two-section rectangular support pile with grooves
CN104358253B (en) * 2014-10-14 2016-02-17 周兆弟 The concavo-convex stake of variable cross-section
CN204780864U (en) * 2015-06-09 2015-11-18 周兆弟 Drawn nut formula precast pile that sinks

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103498468A (en) * 2013-08-27 2014-01-08 周兆弟 Single-joint pile without end plate strong pulling and components
CN103556624A (en) * 2013-11-01 2014-02-05 建华建材(中国)投资有限公司 Connecting sleeve, prefabricated part comprising same as well as production method and connecting method thereof

Also Published As

Publication number Publication date
CN104895050A (en) 2015-09-09
CN107476291B (en) 2020-12-01

Similar Documents

Publication Publication Date Title
WO2017107960A1 (en) Connection device for use in vertical uplift resistance load of pre-buried foundation pile
CN105040685B (en) Prefabricated component with hollow structure
CN202466569U (en) Integrated solid-hollow concrete pile
WO2021042764A1 (en) Concrete variable cross-section prefabricated square pile
CN203891007U (en) Precast reinforced concrete hollow plum blossom pile
CN105040678B (en) Prefabricated pile with concave-convex chuck
CN203684072U (en) Energy-dissipation-shell-plate-embedded box-shaped steel bridge pier
CN109235413B (en) Device for reinforcing soft soil foundation by transverse reinforced rigid-flexible composite piles and construction method
CN204385727U (en) Spiral grouting preformed pile
CN208329021U (en) Miniature steel pipe pile for foundation stabilization
CN204780864U (en) Drawn nut formula precast pile that sinks
CN103967167B (en) Steel pipe concrete frame and shear wall vertical composition surface attachment structure and construction method
CN104278690B (en) A kind of novel high-pressure iron tower of power transmission line pile foundation
CN204780880U (en) There is variable cross section stake of end plate
CN201190290Y (en) Buried water meter pool
CN107476291A (en) Tension nut sunk type prefabricated pile
CN104895068A (en) Variable-cross-section pile with end plates
CN206052758U (en) The attachment structure of a small-sized clump of piles and cushion cap
CN112012195B (en) Construction method of precast pile anticorrosion hoisting structure
CN107740408A (en) A kind of Prefabricated concrete-filled steel tube stake
CN208346973U (en) Concrete-filled steel tubular hollow steel structure technique and steel construction
CN202031092U (en) Pile forming device used for cast-in-place concrete
CN204151816U (en) A kind of novel high-pressure iron tower of power transmission line pile foundation
CN212896976U (en) To wearing bolt multicavity steel pipe-concrete earthquake-resistant wall
CN203821631U (en) Vertical joint face connecting structure of steel tube concrete frame and shear wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant