CN107448688A - Pipe support - Google Patents
Pipe support Download PDFInfo
- Publication number
- CN107448688A CN107448688A CN201710658399.6A CN201710658399A CN107448688A CN 107448688 A CN107448688 A CN 107448688A CN 201710658399 A CN201710658399 A CN 201710658399A CN 107448688 A CN107448688 A CN 107448688A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- bottom plate
- pipe support
- supporter
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/16—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets with special provision allowing movement of the pipe
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/24—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets with a special member for attachment to profiled girders
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Sewage (AREA)
Abstract
The invention provides a kind of pipe support.The pipe support includes:With the adjustable bottom plate being connected in pipeline foundation position;The bottom plate upper end is arranged at, for placing the supporter of pipeline.In the present invention, by the way that pipeline is positioned on the supporter being connected with bottom plate upper end, further by adjusting position of the bottom plate relative to pipeline foundation, the adjustment of pipeline location is realized.With needing to remove original bearing in the prior art, then reinstall the new bearing of welding and compared with adjusting the technical scheme of pipeline location, reduce construction cost, considerably increase the convenience of pipeline location regulation, improve operating efficiency.
Description
Technical field
The present invention relates to construction engineering technical field, in particular to a kind of pipe support.
Background technology
At present, in the construction of Urban Underground pipe gallery, pipe support is welded on pipeline foundation built-in fitting in pipeline cabin,
Because duct length is longer, pipeline caused error in installation process is segmented causes off-centring so that pipeline docks the line of apsides
It is not conllinear, it is necessary to adjust docking pipeline height and right position, if bearing is directly welded on built-in fitting, needing will be original
Bearing is removed, then is reinstalled and welded new bearing, could be adjusted the height and right position of docking pipeline, therefore, be added
Construction cost and delay construction speed.
China Patent Publication No.:CN106015754A application for a patent for invention, a kind of adjustable pipeline bearing is disclosed, and
Specifically disclose including bottom plate, external support board is installed on bottom plate, inner support plate is provided with the inside of external support board, inner support plate top is set
Pipe clamp is put, skewed slot regulating positioning device is correspondingly arranged between external support board and inner support plate, connecting pole is through skewed slot regulation positioning
Device, fastened between connecting pole and skewed slot regulating positioning device by fastener., will using aid when adjusting duct height
Pipeline is adjusted to require height, and relative displacement occurs for the skewed slot of external support board and inner support plate, locking stud can external support board with
Inner support plate overlap skewed slot in slide so that the adjustable height of pipeline can external support board, inner support plate eight words it is oblique
Freely adjusted in the range of groove height.
In above-mentioned technical proposal, relative displacement is occurred by external support board and the skewed slot of inner support plate so that locking stud
It can be slided in the skewed slot that external support board overlaps with inner support plate to adjust the height of pipeline and need to match somebody with somebody by aid
Closing material can be adjusted.
The content of the invention
In consideration of it, the present invention proposes a kind of pipe support, it is intended to solves in duct segments installation process in the prior art
The problem of pipeline location inconvenience regulation.
On one side, the present invention proposes a kind of pipe support, including:With the adjustable bottom being connected in pipeline foundation position
Plate;The bottom plate upper end is arranged at, for placing the supporter of pipeline.
Further, in above-mentioned pipe support, offer to adjust the bottom plate on the bottom plate relative to the pipe
The regulating tank of the position on road basis.
Further, in above-mentioned pipe support, the regulating tank at least two, also, each regulating tank is on institute
Supporter is stated to be symmetrical arranged.
Further, in above-mentioned pipe support, the regulating tank is kidney slot.
Further, in above-mentioned pipe support, the supporter upper end offers to place the passage of the pipeline.
Further, in above-mentioned pipe support, the passage is semicircular arc.
Further, in above-mentioned pipe support, the vias inner walls are provided with rubber blanket.
Further, in above-mentioned pipe support, the supporter is concrete structure, also, the supporter with it is described
Bottom plate is connected by anchor bar.
Further, in above-mentioned pipe support, the bottom plate passes through the bolt for being arranged in the regulating tank and the pipeline
Base position is adjustable to be connected.
Further, in above-mentioned pipe support, it is provided between the bottom plate and the pipeline foundation and is arranged in the spiral shell
Bolt, to adjust the pad of the bottom plate heights.
Pipe support provided by the invention, by the way that pipeline is positioned on the supporter being connected with bottom plate upper end, enter one
Step realizes the adjustment of pipeline location by adjusting position of the bottom plate relative to pipeline foundation.With need in the prior art will be original
Bearing is removed, then is reinstalled the new bearing of welding and compared with adjusting the technical scheme of pipeline location, reduces construction cost, greatly
The big convenience for adding pipeline location regulation, improves operating efficiency.
Brief description of the drawings
By reading the detailed description of hereafter preferred embodiment, it is various other the advantages of and benefit it is common for this area
Technical staff will be clear understanding.Accompanying drawing is only used for showing the purpose of preferred embodiment, and is not considered as to the present invention
Limitation.And in whole accompanying drawing, identical part is denoted by the same reference numerals.In the accompanying drawings:
Fig. 1 is the front view of support of pipelines provided in an embodiment of the present invention;
Fig. 2 is the top view of support of pipelines provided in an embodiment of the present invention;
Fig. 3 is the side view of support of pipelines provided in an embodiment of the present invention.
Embodiment
The exemplary embodiment of the disclosure is more fully described below with reference to accompanying drawings.Although the disclosure is shown in accompanying drawing
Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here
Limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure
Completely it is communicated to those skilled in the art.It should be noted that in the case where not conflicting, embodiment in the present invention and
Feature in embodiment can be mutually combined.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
Refering to Fig. 1, the pipe support of the embodiment of the present invention includes:Bottom plate 2 and supporter 3;Wherein, bottom plate 2 and pipeline base
The position of plinth 1 is adjustable to be connected, and supporter 3 is arranged at the upper end of bottom plate 2, for placing pipeline 5.
Specifically, bottom plate 2 can be steel plate, and plate size and thickness can be determined according to actual conditions.Bottom plate 2
Connected mode with pipeline foundation 1 can be bolt connection.
Supporter 3 can be steel construction, concrete structure etc..When supporter 3 is steel construction, bottom plate 2 can with supporter 3
To weld together;When supporter 3 is concrete structure, bottom plate 2 can be connected with supporter 3 by anchor bar 7, be had
Beneficial to the stability of increase pipe support.The section of supporter 3 can be inverted trapezoidal, square etc., and the present embodiment is not appointed to it
What is limited.
The upper end of supporter 3 offers to place the passage 31 of pipeline 5, and shape, the size of passage 31 can be according to reality
Situation is determined.Preferably, passage 31 is semicircular arc.The opening radius of passage 31 can carry out true according to actual requirement
It is fixed, to increase the contact surface of pipeline 5 and passage 31, reduce the stress of the contact surface of pipeline 5, prevent pipeline 5 from being led because stress is concentrated
The deformation of cause.It is further preferred that the inwall of passage 31 can be provided with rubber blanket 6, such as can be in the inwall of passage 31 and pipe
One or more layers rubber blanket 6 is laid on the contact surface in road 5, with collision of the buffering pipe 5 in installation process between supporter 3
Power, while reduce the stress of the contact surface of pipeline 5, prevent pipeline 5 to be damaged.
When it is implemented, bottom plate 2 and supporter 3 can be prefabricated in factory, it is not necessary to make, reduce live light
Pollute, greatly save the engineering time, and the accurate of the size of pipe support using unified Mold Making, can be ensure that
Degree, be advantageous to more accurately adjust the position of pipeline.In addition, reinforcing bar leftover pieces can also be utilized when making, resource saved, protected
Environment is protected.
Pipe support that is above-mentioned obviously to draw, being provided in the present embodiment, by the way that pipeline is positioned over and bottom plate upper end
On the supporter being connected, further by adjusting position of the bottom plate relative to pipeline foundation, the adjustment of pipeline location is realized,
Operation is simple, with needing to remove original bearing in the prior art, then reinstalls and welds new bearing to adjust pipeline position
The technical scheme put is compared, and reduces construction cost, considerably increases the convenience of pipeline location regulation, improves operation effect
Rate.
With reference to Fig. 1 and Fig. 2, the regulating tank relative to the position of pipeline foundation 1 to regulating base board 2 is offered on bottom plate 2
4, bottom plate 2 is by being arranged in the bolt 9 of regulating tank 4 and the position of pipeline foundation 1 is adjustable is connected.
Specifically, regulating tank 4 at least two, also, each regulating tank 4 is symmetrical arranged on supporter 3.Regulating tank 4
It can be kidney slot.Such as four kidney slots can be opened up on a base plate 2, wherein, it is symmetrically distributed in two-by-two in four kidney slots
The both sides of supporter 3.
The first end (lower end in Fig. 1) of bolt 9 can be embedded in pipeline foundation 1 in advance, and the second end (upper end in Fig. 1) is worn
If overregulating groove 4, so as to which now bottom plate 2 will be arranged on pipeline foundation 1, the stability of pipe support is added.
When it is implemented, first the first end of bolt 9 is embedded in concrete foundation, coagulation is stretched out at the second end of bolt 9
Earth foundation surface, then bottom plate 2 is mounted directly by bolt 9 and is fixed on pipeline foundation 1, finally in the horizontal direction (such as
Left and right directions) the overall position with adjustment bolt 9 in kidney slot that forms of movable base plate 2 and supporter 3, until by supporter
The pipeline 5 placed on 3 is adjusted to position to be installed, and the second end of bolt 9 is fixed on into bottom plate 2 by nut.
Obviously it can draw, be engaged by regulating tank 4 and bolt 9, the pipe that bottom plate 2 and supporter 3 form can be adjusted
The overall position in the horizontal direction of road bearing, so as to have adjusted the position of pipeline 5 in the horizontal direction, constructing operation is simple, is easy to
Workmen's rapid construction.
With reference to Fig. 2 and Fig. 3, it is provided between bottom plate 2 and pipeline foundation 1 and is arranged in bolt 9, to the height of regulating base board 2
Pad 8.
Specifically, pad 8 can be steel disc, and its shape, thickness can be determined according to actual conditions.On pad 8
It is provided with the through hole for wearing bolt 9.Preferably, the opening being connected with through hole is offered on pad 8, in order to tearing open after
Unload.
Obviously it can draw, by setting pad 8 between the lower end of bottom plate 2 and pipeline foundation 1, pipe support can be adjusted
Height, it is simple in construction, operation it is easy.
To sum up, the pipe support provided in example of the present invention, by the way that pipeline is positioned over into the support being connected with bottom plate upper end
On body, further by adjusting position of the bottom plate relative to pipeline foundation, the adjustment of pipe level position and height is realized, is grasped
Make simple and easy, improve operating efficiency.In addition, pipe support mainly uses concrete material, batch lower than bridle iron cost
Using reducing cost of manufacture.
Obviously, those skilled in the art can carry out the essence of various changes and modification without departing from the present invention to the present invention
God and scope.So, if these modifications and variations of the present invention belong to the scope of the claims in the present invention and its equivalent technologies
Within, then the present invention is also intended to comprising including these changes and modification.
Claims (10)
- A kind of 1. pipe support, it is characterised in that including:With the adjustable bottom plate (2) being connected in pipeline foundation (1) position;The bottom plate (2) upper end is arranged at, for placing the supporter (3) of pipeline (5).
- 2. pipe support according to claim 1, it is characterised in that offer to adjust on the bottom plate (2) described Bottom plate (2) relative to the position of the pipeline foundation (1) regulating tank (4).
- 3. pipe support according to claim 2, it is characterised in that the regulating tank (4) at least two, also, respectively The regulating tank (4) is symmetrical arranged on the supporter (3).
- 4. pipe support according to claim 3, it is characterised in that the regulating tank (4) is kidney slot.
- 5. pipe support according to any one of claim 1 to 4, it is characterised in that supporter (3) upper end opens up There is the passage (31) for placing the pipeline (5).
- 6. pipe support according to claim 5, it is characterised in that the passage (31) is semicircular arc.
- 7. pipe support according to claim 6, it is characterised in that passage (31) inwall is provided with rubber blanket (6).
- 8. pipe support according to any one of claim 1 to 4, it is characterised in that the supporter (3) is concrete Structure, also, the supporter (3) is connected with the bottom plate (2) by anchor bar (7).
- 9. pipe support according to claim 2, it is characterised in that the bottom plate (2) is by being arranged in the regulating tank (4) bolt (9) with the pipeline foundation (1) position is adjustable is connected.
- 10. pipe support according to claim 9, it is characterised in that the bottom plate (2) and the pipeline foundation (1) it Between be provided with and be arranged in the bolt (9), to adjust the pad (8) of the bottom plate (2) height.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710658399.6A CN107448688A (en) | 2017-08-04 | 2017-08-04 | Pipe support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710658399.6A CN107448688A (en) | 2017-08-04 | 2017-08-04 | Pipe support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107448688A true CN107448688A (en) | 2017-12-08 |
Family
ID=60490268
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710658399.6A Pending CN107448688A (en) | 2017-08-04 | 2017-08-04 | Pipe support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107448688A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08178135A (en) * | 1994-12-26 | 1996-07-12 | Ishikawajima Harima Heavy Ind Co Ltd | Piping supporting structure |
CN101063286A (en) * | 2006-04-30 | 2007-10-31 | 上海磁浮交通工程技术研究中心 | Track structure of magnetic floating traffic and manufacturing method therefor |
CN201368263Y (en) * | 2008-12-30 | 2009-12-23 | 张明亮 | No-negative pressure water supplying facility by-pass pipe fine-adjustable support |
CN204828955U (en) * | 2015-07-29 | 2015-12-02 | 江苏德威节能有限公司 | Support is maked somebody a mere figurehead to earth anchor sleeve pipe socket joint |
CN205479743U (en) * | 2016-02-22 | 2016-08-17 | 天津市祥盛达五金制品有限公司 | Pipeline support convenient to adjust |
-
2017
- 2017-08-04 CN CN201710658399.6A patent/CN107448688A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08178135A (en) * | 1994-12-26 | 1996-07-12 | Ishikawajima Harima Heavy Ind Co Ltd | Piping supporting structure |
CN101063286A (en) * | 2006-04-30 | 2007-10-31 | 上海磁浮交通工程技术研究中心 | Track structure of magnetic floating traffic and manufacturing method therefor |
CN201368263Y (en) * | 2008-12-30 | 2009-12-23 | 张明亮 | No-negative pressure water supplying facility by-pass pipe fine-adjustable support |
CN204828955U (en) * | 2015-07-29 | 2015-12-02 | 江苏德威节能有限公司 | Support is maked somebody a mere figurehead to earth anchor sleeve pipe socket joint |
CN205479743U (en) * | 2016-02-22 | 2016-08-17 | 天津市祥盛达五金制品有限公司 | Pipeline support convenient to adjust |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018028087A1 (en) | Box-type pipeline with circumferential obtuse angle connection | |
CN104878852A (en) | Frictional energy dissipation self-centering shear wall structure with easily restored bottom | |
CN201896365U (en) | Installing and fixing device for flat plate pre-embedded piece on surface of concrete | |
CN207227968U (en) | T beam beams bottom steel plate supertronic device | |
CN107022947A (en) | A kind of pre-buried shaped steel carvel joint bolt type connection locator of the prefabricated arch rib of concrete segment and its construction method | |
CN105649648A (en) | Segment connecting structure of quasi rectangular shield tunnel and construction method thereof | |
CN107448688A (en) | Pipe support | |
JP2015105569A (en) | Pump | |
CN103848361B (en) | The support beam of tower crane wall-attaching equipment | |
CN211113740U (en) | Prestressed steel cylinder concrete pipe with base | |
CN110397081B (en) | Method for fixing middle-buried rubber waterstop and steel reinforcement framework structure | |
CN204435361U (en) | Arc iron and adopt the stake reinforcement installation structure of this arc iron | |
CN103821281A (en) | Steel bar connecting body for prefabricated reinforced concrete structure as well as manufacturing method and construction method of steel bar connecting body | |
CN203878718U (en) | Joint structure of cover plate of trench and pipe trench | |
CN205369280U (en) | Pressure -bearing precipitation tubular well | |
KR101683616B1 (en) | Apparatus for Connecting Steel Pile and Concrete Base, and Connecting Structure using such Apparatus | |
CN204715362U (en) | A kind of deep foundation ditch embedded column base bracing frame | |
CN203905306U (en) | Steel bar connection adjustment member between prefabricated reinforced concrete members | |
CN102416667B (en) | Production method of socket and spigot joint reinforcement concrete pipe | |
CN204455855U (en) | A kind of pressure rackwork of sections pier shaft docking | |
JP7079166B2 (en) | Tunnel internal structure and its construction method | |
CN102155242B (en) | Shield segment mold | |
CN203716056U (en) | Gate structure of casting machine | |
CN107254887A (en) | City integrated piping lane, which is poured, uses outer side mold guider | |
CN104196213B (en) | A kind of decorative thread ten thousand ties up rotating connector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171208 |