CN107388611A - A kind of method that rock salt bittern is preheated with directional-butted well - Google Patents

A kind of method that rock salt bittern is preheated with directional-butted well Download PDF

Info

Publication number
CN107388611A
CN107388611A CN201710858724.3A CN201710858724A CN107388611A CN 107388611 A CN107388611 A CN 107388611A CN 201710858724 A CN201710858724 A CN 201710858724A CN 107388611 A CN107388611 A CN 107388611A
Authority
CN
China
Prior art keywords
well
directional
straight
main pipeline
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710858724.3A
Other languages
Chinese (zh)
Inventor
张乐
樊传忠
肖文科
尹科明
周志刚
续培信
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Original Assignee
CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd filed Critical CHINA SALT PROSPECTING DESIGN INSTITUTE Co Ltd
Priority to CN201710858724.3A priority Critical patent/CN107388611A/en
Publication of CN107388611A publication Critical patent/CN107388611A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24TGEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
    • F24T10/00Geothermal collectors
    • F24T10/10Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24TGEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
    • F24T10/00Geothermal collectors
    • F24T2010/50Component parts, details or accessories
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/10Geothermal energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention discloses a kind of method that rock salt bittern is preheated with directional-butted well, is being easy to the drilling well position of construction at salt manufacturing workshop selection two;A drilling well opening position construction straight well wherein, the drilling depth of straight well is 2500m ~ 5000m, and the formation temperature of straight well bottom is 75 DEG C ~ 140 DEG C, the setting of casing Cheng Jing into straight well;In another drilling well opening position construction directional well, directional well is connected with the bottom of straight well, orientation downhole end sets inclination section, into directional well into well at setting of casing to the target spot being docked and connected with straight well;Directional well upper end is connected with the first halogen transportation main pipeline, straight well upper end is connected with the second halogen transportation main pipeline, first halogen transportation main pipeline, directional well, straight well and the second halogen transportation main pipeline collectively form a closed halogen transportation passage, and salt manufacturing workshop is delivered to after the rock salt bittern that exploitation obtains is preheated by halogen transportation passage.This method can effectively reduce the production cost of salt making enterprises, and technique is simple.

Description

A kind of method that rock salt bittern is preheated with directional-butted well
Technical field
The present invention relates to geothermal energy utilization and rock salt production technical field, and in particular to a kind of to preheat rock with directional-butted well The method of bittern water.
Background technology
Salt mine is typically exploited using drilling solution method, and the product for exploiting to obtain is bittern, then that bittern is defeated It is sent to vacuum salt making facility and explosive evaporation crystallization is carried out to bittern using steam, that is, solid salt is made.Existing salt making enterprises generation Bittern used in solid salt is not generally first preheated, directly enters vacuum salt making facility after bittern purifying from mine.For mineral deposit Shallower mine is buried, the brine temperature that drilling solution method is produced is relatively low, typically at 30 DEG C or so, in salt manufacturing production process In need to consume substantial amounts of steam(Steam generally use coal-fired heating is made, it is necessary to consume a large amount of fire coals), high energy consumption is coal-fired to take With the nearly half for accounting for production cost.Therefore, how to reduce combustion the consumption of coal is the most important of salt making enterprises control cost A ring.
Geothermal energy resources have the features such as widely distributed, to be easy to exploitation as a kind of novel energy mineral products.China has good Geothermal energy resources condition, at present China's geothermal energy resources Land use systems to heat, bathing, plantation etc. based on, geothermal energy utilization Conversion ratio it is also very low.
Drilling engineering technology is found broad application in the mineral explorations such as oil, natural gas, rock salt exploitation, and China's deep-well bores Well technology has reached the depth of 8000m ultradeep wells in field use field, and extended reach directional well technology bottom hole displacement even can To reach thousands of rice to a myriametre.
The content of the invention
It is an object of the present invention to overcome the shortcomings of to mention in background above technology and defect, there is provided one kind can effectively drop The method that low production cost, technique simply preheat rock salt bittern with directional-butted well.
In order to solve the above technical problems, technical scheme proposed by the present invention is:
A kind of method that rock salt bittern is preheated with directional-butted well, comprises the following steps:
S1, it is being easy to the drilling well position of construction at salt manufacturing workshop selection two, this need to expire the distance between drilling well position at two The construction requirement of sufficient directional-butted well;
S2, the straight well of drilling well opening position construction wherein, the drilling depth of the straight well are 2500m ~ 5000m, straight well bottom Formation temperature be 75 DEG C ~ 140 DEG C, the setting of casing Cheng Jing into straight well;
S3, another drilling well opening position construct directional well, the directional well is connected with the bottom of straight well, under directional well End is provided with inclination section, into directional well into well at setting of casing to the target spot being docked and connected with straight well;
S5, the upper end of directional well is connected with the first halogen transportation main pipeline, the upper end of straight well is connected with the second halogen transportation main pipeline Connect, the first halogen transportation main pipeline, directional well, straight well and the second halogen transportation main pipeline collectively form a closed halogen transportation passage, will open The rock salt bittern for adopting to obtain is delivered to salt manufacturing workshop after being preheated by the halogen transportation passage and further handled.
It is the problem of for existing salt making enterprises high energy consumption, of the invention by setting directional-butted well near salt manufacturing workshop, Straight well and directional well are drilled into deep formation(2500m~5000m), make full use of the geothermal energy resources of deep formation to carry out bittern Preheating.Before entering salt manufacturing workshop and carrying out condensing crystallizing salt manufacturing, first bittern is preheated, bittern is in directional well and straight well After carrying out abundant thermal energy exchange with deep formation, its temperature greatly improves, it is preheated after bittern have into vacuum salt making facility The energy consumption of salt-making process is reduced to effect, the consumption of coal resources is significantly reduced, has saved production cost.Certainly, bittern Flowing through directional-butted well needs to increase the lift of brine transportation pump, but increased lift just corresponds to 10km or so brine pipeline Road length frictional head loss, the consumption of its increased electric power resource is less, still can generally substantially reduce the life of enterprise Produce cost.In addition, the generation of pipeline scale can be reduced after bittern flow velocity is accelerated by the method for the present invention, after substantially reducing The maintenance cost of phase.Directional-butted well is positioned close to the position in salt manufacturing workshop, avoids bittern after directional-butted well comes out Temperature declines excessive.
The above-mentioned method that rock salt bittern is preheated with directional-butted well, it is preferred that in the step S3, the inclination section Arc radius is 300m ~ 600m.If inclination section radius is too small to increase the difficulty and risk of construction, and reduces pre-heat effect;Make Oblique section radius is excessive and can increase operating expenses.The present invention considers above-mentioned factor, and the arc radius of inclination section is arranged to 300m ~ 600m, it both ensure that pre-heat effect, reduced difficulty of construction, and reduced operating expenses again, and met orientation down-hole casing and consolidate The requirement of well.
The above-mentioned method that rock salt bittern is preheated with directional-butted well, it is preferred that the second halogen transportation main pipeline it is another End is connected with salt manufacturing workshop, and bittern conveys via the first halogen transportation main pipeline, directional well, straight well and the second halogen transportation main pipeline successively To salt manufacturing workshop.The present invention is using the directional-butted well structure of a straight well and a directional well, and the cost of directional well is than straight Well is high, and construction cost can be saved using a straight well, a directional well.The present invention is injected bittern by directional well defeated by straight well Go out, advantageously reduce the drop mistake of brine temperature after preheating, also, the possibility blocked by the way of bittern is exported by straight well Property it is smaller, even if occurring blocking scale problems, straight well also more preferably handles.
The above-mentioned method that rock salt bittern is preheated with directional-butted well, it is preferred that between the step S3 and step S5 Also step S4, the step S4 including carrying out well-flushing to the straight well and directional well are specially:Well-flushing medium is set by infusion It is standby to be injected from straight well or directional well, the polluter in straight well and directional well is carried to ground.By well-flushing, bittern is improved Purity, it is ensured that the product quality of gained rock salt.
The above-mentioned method that rock salt bittern is preheated with directional-butted well, it is preferred that in the step S1, drilling well position at two The distance between be 600m ~ 1000m.The distance of two mouthfuls of wells should meet the execution conditions at the requirement and scene for orienting well construction, if Drilling well positional distance is excessive at two, can cause the distance increase of directional well horizontal segment, and then increase operating expenses and difficulty of construction;If Drilling well positional distance is too small at two, will be unfavorable for the construction of directional well.The distance between drilling well position at two(I.e. directional well is horizontal Segment length)It is associated parameter with drilling depth.Drilling depth can accordingly reduce if horizontal segment length, if horizontal segment is short The depth of drilling well can be increased to ensure bittern preheating section length.
Compared with prior art, the advantage of the invention is that:The present invention near salt manufacturing workshop by setting orientation docking Well, the rock salt bittern for entering salt manufacturing workshop is preheated using the geothermal energy resources of deep formation.The average geothermic gradient of the earth's crust It it is about 75 DEG C ~ 140 DEG C in deep 2500m ~ 5000m directional-butted well bottom formation temperature about per 25 DEG C of km.By halogen Water is passed through directional-butted well, and bittern fully carries out heat exchange with stratum, improves the temperature of bittern, enter back into vacuum salt making facility system Salt, greatly reduce energy consumption, reduce the coal resources consumption of salt making enterprises.For the little salt of mineral deposit buried depth Ore deposit, salt making enterprises production cost can substantially be reduced using the method for the present invention.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are the present invention Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis These accompanying drawings obtain other accompanying drawings.
Fig. 1 is the structural representation of halogen transportation passage used in method of the invention.
Marginal data:
1st, straight well;2nd, directional well;3rd, target spot;4th, the first halogen transportation main pipeline;5th, the second halogen transportation main pipeline;21st, inclination section.
Embodiment
For the ease of understanding the present invention, the present invention is made below in conjunction with Figure of description and preferred embodiment more complete Face, meticulously describe, but protection scope of the present invention is not limited to embodiment in detail below.
It should be strongly noted that when a certain element, to be described as " be fixed on, be fixed in, be connected to or be communicated in " another When on element, it can be directly fixed, affixed, connection or connect on another element or by connecting among other Fitting is indirectly fixed, affixed, connection or connection are on another element.
Unless otherwise defined, the implication that all technical terms used hereinafter are generally understood that with those skilled in the art It is identical.Technical term used herein is intended merely to describe the purpose of specific embodiment, is not intended to the limitation present invention Protection domain.
Embodiment:
A kind of method of the invention that rock salt bittern is preheated with directional-butted well, the structure of halogen transportation passage used is such as in this method Shown in Fig. 1.By taking certain rock salt manufacturing enterprise as an example, 400 meters of its mineral deposit buried depth, drilling solution method produces brine temperature on 30 DEG C of left sides It is right.The ore deposit production scale is 4,000,000 sides/year, produces 1,200,000 tons/year of solid salt.
It is being easy to the drilling well position of construction at salt manufacturing workshop selection two, the ground distance at two between drilling well position For 600m;The straight well 1 of drilling well opening position construction wherein, the drilling depth of the straight well 1 are 3500m, the bottomland layer depth of straight well 1 Formation temperature is 95 DEG C in degree, the setting of casing Cheng Jing into straight well 1;
In another drilling well opening position construction directional well 2, directional well 2 is connected with the bottom of straight well 1, the lower end of directional well 2 Provided with inclination section 21, the arc radius of the inclination section 21 is 500m, and into directional well 2, setting of casing is extremely docked and connected with straight well 1 Into well at target spot 3;
Well-flushing water is injected by pumping-in equipment from straight well 1, the polluter in straight well 1 and directional well 2 is carried to ground;Will The upper end of directional well 2 is connected with the first halogen transportation main pipeline 4, and the upper end of straight well 1 is connected with the second halogen transportation main pipeline 5;The One halogen transportation main pipeline 4, directional well 2, the halogen transportation main pipeline 5 of straight well 1 and second collectively form a closed halogen transportation passage;Will exploitation Obtained rock salt bittern is sent into directional well 2 from the first halogen transportation main pipeline 4, and bittern has directional well 2 to flow into straight well 1, then defeated through second Halogen main pipeline 5 is delivered to salt manufacturing workshop and is further processed.Rock salt bittern enters salt manufacturing after directional-butted well preheats and filled Temperature when putting is promoted to 75 DEG C or so.
Coal index experience is consumed under different brine temperatures according to related salt making enterprises, 75 DEG C of bittern salt manufacturing comprehensive energy consumptions are 74Kg marks coal/t, and 30 DEG C of bittern salt manufacturing comprehensive energy consumptions are that 140Kg marks coal/t.Thus, mark can be saved by producing 1,200,000 tons of solid salts 7.92 ten thousand tons of coal.Market according to 510 yuan/ton of mark coals calculate, and the rock salt manufacturing enterprise amounts to every year can about save 4000 Wan Yuan.Bittern probably needs more increase 60m pump head, 1 year electricity for newly increasing 400,000 yuan or so by directional-butted well Take.The operating expenses of a pair of 3500m depth directional-butted wells probably withdraws in 40,000,000 or so, about one years cans and is constructed into This, the income in later stage is considerable.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (5)

1. a kind of method that rock salt bittern is preheated with directional-butted well, comprises the following steps:
S1, it is being easy to the drilling well position of construction at salt manufacturing workshop selection two, this need to expire the distance between drilling well position at two The construction requirement of sufficient directional-butted well;
S2, wherein a drilling well opening position construction straight well(1), the straight well(1)Drilling depth be 2500m ~ 5000m, directly Well(1)The formation temperature of bottom is 75 DEG C ~ 140 DEG C, to straight well(1)Middle setting of casing Cheng Jing;
S3, another drilling well opening position construct directional well(2), by the directional well(2)With straight well(1)Bottom be connected, Directional well(2)Lower end be provided with inclination section(21), to directional well(2)Middle setting of casing to and straight well(1)The target spot being docked and connected(3) Place is into well;
S5, by directional well(2)Upper end and the first halogen transportation main pipeline(4)It is connected, by straight well(1)Upper end and the second halogen transportation master Pipeline(5)It is connected, the first halogen transportation main pipeline(4), directional well(2), straight well(1)With the second halogen transportation main pipeline(5)Collectively form One closed halogen transportation passage, salt manufacturing workshop is delivered to after the rock salt bittern that exploitation obtains is preheated by the halogen transportation passage Further processing.
2. according to the method for claim 1, it is characterised in that:In the step S3, the inclination section(21)Circular arc half Footpath is 300m ~ 600m.
3. according to the method for claim 1, it is characterised in that:The second halogen transportation main pipeline(5)The other end and salt manufacturing Workshop is connected, and bittern is successively via the first halogen transportation main pipeline(4), directional well(2), straight well(1)With the second halogen transportation main pipeline(5) It is delivered to salt manufacturing workshop.
4. according to the method for claim 1, it is characterised in that:Also include between the step S3 and step S5 to described Straight well(1)And directional well(2)Carry out well-flushing step S4, the step S4 be specially:By well-flushing medium by pumping-in equipment from straight Well(1)Or directional well(2)Injection, by straight well(1)And directional well(2)Interior polluter is carried to ground.
5. the method according to any one of claim 1 ~ 4, it is characterised in that:In the step S1, drilling well position at two The distance between be 600m ~ 1000m.
CN201710858724.3A 2017-09-21 2017-09-21 A kind of method that rock salt bittern is preheated with directional-butted well Pending CN107388611A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710858724.3A CN107388611A (en) 2017-09-21 2017-09-21 A kind of method that rock salt bittern is preheated with directional-butted well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710858724.3A CN107388611A (en) 2017-09-21 2017-09-21 A kind of method that rock salt bittern is preheated with directional-butted well

Publications (1)

Publication Number Publication Date
CN107388611A true CN107388611A (en) 2017-11-24

Family

ID=60350649

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710858724.3A Pending CN107388611A (en) 2017-09-21 2017-09-21 A kind of method that rock salt bittern is preheated with directional-butted well

Country Status (1)

Country Link
CN (1) CN107388611A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016991A (en) * 2021-09-16 2022-02-08 西安交通大学 Method for determining well body structure of butt joint well based on geothermal field distribution characteristics
CN114922576A (en) * 2022-05-23 2022-08-19 国投新疆罗布泊钾盐有限责任公司 Sectional type well washing process for horizontal well

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1241676A (en) * 1999-05-15 2000-01-19 洪泽县化工(集团)总公司 Mirabilite exploiting water-dissolution process with two wells communicated by horizontal hole
US6301894B1 (en) * 2000-05-12 2001-10-16 Albert H. Halff Geothermal power generator
CN1415841A (en) * 2002-12-01 2003-05-07 化学工业部连云港设计研究院 Drilling method for exploiting soluble salt mine through dissolution method
CN103644673A (en) * 2013-12-11 2014-03-19 中盐勘察设计院有限公司 Exploitation method for geothermal energy in salt mineral deposit
CN106196233A (en) * 2016-07-15 2016-12-07 西安交通大学 A kind of medium and deep geothermal energy heating system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1241676A (en) * 1999-05-15 2000-01-19 洪泽县化工(集团)总公司 Mirabilite exploiting water-dissolution process with two wells communicated by horizontal hole
US6301894B1 (en) * 2000-05-12 2001-10-16 Albert H. Halff Geothermal power generator
CN1415841A (en) * 2002-12-01 2003-05-07 化学工业部连云港设计研究院 Drilling method for exploiting soluble salt mine through dissolution method
CN103644673A (en) * 2013-12-11 2014-03-19 中盐勘察设计院有限公司 Exploitation method for geothermal energy in salt mineral deposit
CN106196233A (en) * 2016-07-15 2016-12-07 西安交通大学 A kind of medium and deep geothermal energy heating system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016991A (en) * 2021-09-16 2022-02-08 西安交通大学 Method for determining well body structure of butt joint well based on geothermal field distribution characteristics
CN114016991B (en) * 2021-09-16 2022-10-21 西安交通大学 Method for determining well body structure of butt joint well based on geothermal field distribution characteristics
CN114922576A (en) * 2022-05-23 2022-08-19 国投新疆罗布泊钾盐有限责任公司 Sectional type well washing process for horizontal well
CN114922576B (en) * 2022-05-23 2023-10-20 国投新疆罗布泊钾盐有限责任公司 Sectional well flushing process for horizontal well

Similar Documents

Publication Publication Date Title
CN103362442B (en) Drilling well multiple spot communication loop gathers geothermal method
CN1875168B (en) Hydrocarbon recovery from impermeable oil shales
CN105863568A (en) Method for exploring dry-hot-rock geotherm through underground heat siphon self-circulation
CN105909214A (en) Method for exploiting compact dry heat rock geothermal energy by utilizing long horizontal well self-circulation structure
CN101881151B (en) Rapid solution construction method for rock salt cavity
JP2018537620A (en) Geothermal recovery device
CN102434141A (en) Method for mining sylvite in underground carnallite ore
CN105178963B (en) A kind of drill well water mixeding mining method of novel sylvite deposit
CN103939071A (en) Horizontal well steam flooding well network structure and steam flooding method
CN107388611A (en) A kind of method that rock salt bittern is preheated with directional-butted well
CN106593368B (en) A kind of preprocess method improving SAGD development effectiveness
CN111043780A (en) Hydrothermal multi-branch directional mining and grouting geothermal well and construction method
CN206803542U (en) A kind of porous geothermal well system of large span
CN104975826A (en) Method for improving recovery ratio of super heavy oil reservoir
CN111608624B (en) Method for exploiting heavy oil reservoir by utilizing terrestrial heat
CN107060642A (en) Horizontal well track control method being connected trona deep-thin layer more
CN111561304B (en) Short-well-distance heat exchange method suitable for hot dry rock
CN212508250U (en) Well body structure
Yang et al. Application of well factory drilling technology in shale gas development in the Sichuan basin
CN208765297U (en) A kind of mid-deep strata underground pipe horizontal well heat exchange structure
Xuezhong The hot water oil expulsion technique for geothermal resources
CN206290241U (en) Underground heat horizontal well mining system
CN102278116A (en) Device and method for manufacturing underground frozen wall in cold areas in winter
CN103644673A (en) Exploitation method for geothermal energy in salt mineral deposit
CN104594904B (en) Same well site directional-butted well group salt well accident method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171124

RJ01 Rejection of invention patent application after publication